Permit Application Status

PRRES20250097


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PRRES20250097
Building Permit - Residential
Issued
NEW SINGLE FAMILY
NEW HOUSE - UNFINISHED BASEMENT - COVERED DECK STOP WORK ORDER generated on 01/30/2025 12:00 AM by username 'Mitchell Schwarz'. STOP WORK ORDER removed on 01/31/2025 12:00 AM by username 'Kyle Beard'.
01/08/2025
01/10/2025
07/08/2025
Locations
Property
273274

Address
2221 SW CROWN DR, LEES SUMMIT, MO 64082

2221 SW Crown Dr, Lee's Summit MO 64082
Contacts
SAB CONSTRUCTION INC, Address:PO BOX 942, Phone:(816) 524-3855  
Joseph Matthew Schartz, Address:PO Box 942, Phone:(816) 524-3855  
JOE@SABHOMES.COM  
MIKE BRYANT HEATING & COOLING , Address:1711 E 123RD , Phone:(913) 441-7807  
TEAGUE ELECTRIC CONSTRUCTION INC, Address:12425 W 92ND ST, Phone:(913) 529-4600  
GARRISON PLUMBING, Address:15430 S MAHAFFIE ST STE 102, Phone:(913) 768-1311  
Reviews

There are no reviews for this permit application.

Fees
Paid Fees Amount Paid Owing Date Paid
8331507-Sanitary Sewer Development Fee $2,285.00 $2,285.00 Paid 01/10/2025
9110073-Right of Way Permit Fee $85.00 $85.00 Paid 01/10/2025
7232302-Residential License Tax Fee $1,022.72 $1,022.72 Paid 01/10/2025
8331401-Water Tap Fee $3,973.00 $3,973.00 Paid 01/10/2025
8350015-Water Meter Fee $748.03 $748.03 Paid 01/10/2025
9110078-Valuation Fee New Single Family $2,441.16 $2,441.16 Paid 01/10/2025
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Driveway Inspection Pending
Plot Plan Inspection Pending
Erosion Control Inspection Residential Pending
Electrical Service Inspection Pending
Gas Service Inspection - Residential Pending
All Rough Inspection - Residential Pending
Occupancy Inspection - Codes Residential Pending
Sewer Service Inspection - R Passed 1/30/2025 1/30/2025 01/30/2025
Footing Inspection - Residential Failed - Stop Work 1/30/2025 1/30/2025 01/30/2025
Misc
Corrective Action Required
01/30/2025
Footing poured without inspection stop work issued
Footing Inspection - Residential Passed 1/31/2025 1/31/2025 01/31/2025
Misc
Resolved
01/31/2025
Footing poured without inspection stop work issued
Underslab Plumbing Inspection - Residential Passed 2/7/2025 2/7/2025 02/07/2025
Water Service Inspection - R Passed 2/11/2025 2/11/2025 02/11/2025
Piers/Caissons Inspection - Residential Passed 2/25/2025 2/25/2025 02/25/2025
Documents & Images
Date Uploaded File Type Document Name
01/08/2025 HFR204 - Air Combustion Calcs
01/08/2025 HFR204 - Excise Tax Application
01/08/2025 HFR204 - Permit Application
01/09/2025 Permit Codes Residential Plan Review
01/09/2025 Approved Plans APPROVED PLANS
01/09/2025 Plot Plan APPROVED PLOT PLAN
01/09/2025 Permit Codes Residential Plan Review
01/10/2025 Permit DS Building Permit
01/10/2025 Receipt Receipt for transaction:2025-000152
01/30/2025 Letter INSPECTION SUMMARY
01/30/2025 Letter Stop Work Order
01/30/2025 Crose Foundations 2221 SW Crown Dr footing inspection 01-17-25
01/31/2025 Letter INSPECTION SUMMARY
02/07/2025 Letter INSPECTION SUMMARY
02/11/2025 Letter INSPECTION SUMMARY
02/25/2025 Letter INSPECTION SUMMARY
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide: