Summary
PRRES20245503
Building Permit - Residential
Certificate of Occupancy
NEW SINGLE FAMILY
NEW HOUSE - FINISHED AND UNFINISHED BASEMENT - COVERED PATIO STOP WORK ORDER generated on 02/26/2025 12:00 AM by username 'Dustin Agcopra'. STOP WORK ORDER removed on 02/27/2025 12:00 AM by username 'Dustin Agcopra'.
10/17/2024
10/25/2024
04/19/2025
04/17/2025
Locations
Contacts
ELEVATE DESIGN & BUILD LLC, Address:350 SW LONGVIEW BLVD, Phone:(816) 622-8826  
Elevate Design + Build , Address:350 Longview Blvd.   
SARA@ELEVATEDESIGNBUILDKC.COM  
5 STAR MECHANICAL, LLC, Address:PO BOX 793, Phone:(816) 679-0375  
ELECTRICAL CONNECTIONS, Address:20112 HOPS CREEK DR, Phone:(816) 838-6946  
S&B Plumbing, Inc., Address:PO Box 101, Phone:(913) 850-3445  
Reviews

There are no reviews for this permit application.

Fees
Paid Fees Amount Paid Owing Date Paid
8331507-Sanitary Sewer Development Fee $2,285.00 $2,285.00 Paid 10/25/2024
9110073-Right of Way Permit Fee $85.00 $85.00 Paid 10/25/2024
7232302-Residential License Tax Fee $1,022.72 $1,022.72 Paid 10/25/2024
8331401-Water Tap Fee $3,973.00 $3,973.00 Paid 10/25/2024
8350015-Water Meter Fee $748.03 $748.03 Paid 10/25/2024
9110078-Valuation Fee New Single Family $1,365.91 $1,365.91 Paid 10/25/2024
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Footing Inspection - Residential Passed 11/5/2024 11/5/2024 11/05/2024
Underslab Plumbing Inspection - Residential Not Ready 11/20/2024 11/20/2024 11/20/2024
Misc
Corrective Action Required
11/20/2024
NOT READY INSPECTION DENIDE NO PLUMBING
Erosion Control Inspection Residential Failed 11/20/2024 11/20/2024
Corrective Action Required
11/20/2024
- POST ADDRESS
Underslab Plumbing Inspection - Residential Passed 11/20/2024 11/20/2024
Misc
Resolved
11/20/2024
Sewer Service Inspection - R Passed 11/21/2024 11/21/2024 11/21/2024
Erosion Control Inspection Residential Partial 11/21/2024 11/21/2024
Miscellaneous Correction
Informational
11/21/2024
Erosion control is in place and must be properly maintained until CofO
Water Service Inspection - R Partial 11/22/2024 11/22/2024 11/22/2024
Misc
Corrective Action Required
11/22/2024
Partial, poly out of foundation and 10' of copper.
Water Service Inspection - R Passed 11/22/2024 11/22/2024 11/22/2024
Misc
Resolved
11/22/2024
Partial, poly out of foundation and 10' of copper.
All Rough Inspection - Residential Partial 12/6/2024 12/6/2024 12/06/2024
Misc
Informational
12/06/2024
Garage portal frame inspection only. Okay to cover.
All Rough Inspection - Residential Failed 12/23/2024 12/23/2024 12/23/2024
Misc
Resolved
12/23/2024
Garage portal frame inspection only. Okay to cover.
Misc
Corrective Action Required
12/23/2024
-provide Boca plate protection for dwv at laundry top and bottom plate -seal penetration in primary suite top plate near R/a -provide 3000# hold down per plans at rear door -provide floor joist at stairwell wall for floor joists in basement -provide Boca plate protection for dwv in wet bar area -seal penetrations in vertical to horizontal fire blocking every 10’ -complete panning in furr down for for R/A joist space -pack insulation in tightly and securely above window above basement bedroom -missing nails in hanger above basement bedroom
Electrical Service Inspection Failed 12/23/2024 12/23/2024 12/23/2024
Misc
Corrective Action Required
12/23/2024
Provide ufer connection
Gas Service Inspection - Residential Passed 12/23/2024 12/23/2024 12/23/2024
Electrical Service Inspection Failed 12/27/2024 12/27/2024 12/27/2024
Misc
Corrective Action Required
12/23/2024
Uncover and identify ufer connection each end
Electrical Service Inspection Failed 12/30/2024 12/30/2024 12/30/2024
Misc
Corrective Action Required
12/27/2024
Uncover and identify ufer connection each end ***( mark with green at both ends)***
All Rough Inspection - Residential Passed 12/30/2024 12/30/2024 12/30/2024
Misc
Resolved
12/30/2024
-provide Boca plate protection for dwv at laundry top and bottom plate -seal penetration in primary suite top plate near R/a -provide 3000# hold down per plans at rear door -provide floor joist at stairwell wall for floor joists in basement -provide Boca plate protection for dwv in wet bar area -seal penetrations in vertical to horizontal fire blocking every 10’ -complete panning in furr down for for R/A joist space in basement -pack insulation in tightly and securely above window basement bedroom -missing nails in hanger above basement bedroom
Electrical Service Inspection Passed 12/31/2024 1/3/2025 01/03/2025
Misc
Resolved
12/31/2024
Uncover and identify ufer connection each end ***( mark with green at both ends)***
Piers/Caissons Inspection - Residential Passed 2/4/2025 2/4/2025 02/04/2025
Driveway Inspection Failed 2/24/2025 2/24/2025 02/24/2025
Misc
Corrective Action Required
02/24/2025
2-24-25 Dustin A, DW has been formed and compacted. Their is standing water in approach and will need to be removed, recompacted and called back in for another pre pour inspection. Fail
Sidewalk Inspection Failed 2/24/2025 2/24/2025 02/24/2025
Misc
Corrective Action Required
02/24/2025
2-24-25 Dustin A, Sw is formed and slopes are in compliance. There is standing water, spots where aggregate is not deep enough as well as spots that are not compacted enough. Will need fixed and another pre pour called in. Fail.
Erosion Control Inspection Residential Failed 2/24/2025 2/24/2025 02/24/2025
Miscellaneous Correction
Informational
11/21/2024
Erosion control is in place and must be properly maintained until CofO
DCM3 ESC REQUIRED 2 DAY
Corrective Action Required
02/24/2025
2-24-25 Dustin A, Silt fence is down, Street needs cleaned of mud and gravel. EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS.
Erosion Control Inspection Residential Failed - Stop Work 2/27/2025 2/27/2025 02/26/2025
Miscellaneous Correction
Informational
02/24/2025
Erosion control is in place and must be properly maintained until CofO
DCM3 ESC REQUIRED 2 DAY
Corrective Action Required
02/24/2025
2-24-25 Dustin A, Silt fence is down, Street needs cleaned of mud and gravel. EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS. 2-26-25 Dustin A, Silt fence still down. Remove restroom from stormbox
Erosion Control Inspection Residential Partial 2/27/2025 2/27/2025 02/27/2025
Miscellaneous Correction
Informational
02/26/2025
Erosion control is in place and must be properly maintained until CofO
DCM3 ESC REQUIRED 2 DAY
Corrective Action Required
02/26/2025
2-24-25 Dustin A, Silt fence is down, Street needs cleaned of mud and gravel. EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS. 2-26-25 Dustin A, Silt fence still down. Remove restroom from stormbox 2-27-25 Dustin A, Silt fence is back up, restromed removed from storm box. Must maintain erosion control until vegetation is established
Driveway Inspection Partial 2/27/2025 2/27/2025 02/27/2025
Misc
Corrective Action Required
02/24/2025
2-24-25 Dustin A, DW has been formed and compacted. Their is standing water in approach and will need to be removed, recompacted and called back in for another pre pour inspection. Fail 2-27-25 Dustin A, Water removed. Approved to pour
Sidewalk Inspection Partial 2/27/2025 2/27/2025 02/27/2025
Misc
Corrective Action Required
02/24/2025
2-24-25 Dustin A, Sw is formed and slopes are in compliance. There is standing water, spots where aggregate is not deep enough as well as spots that are not compacted enough. Will need fixed and another pre pour called in. Fail. 2-27-25 Dustin A, Water removed. Aggregate has been corrected. Approved to pour
Sidewalk Inspection Passed 3/6/2025 3/6/2025 03/06/2025
Misc
Informational
03/06/2025
2-24-25 Dustin A, Sw is formed and slopes are in compliance. There is standing water, spots where aggregate is not deep enough as well as spots that are not compacted enough. Will need fixed and another pre pour called in. Fail. 2-27-25 Dustin A, Water removed. Aggregate has been corrected. Approved to pour 3-6-25 Dustin A, sw is poured to city specs. slopes are in compliance. PASS
Driveway Inspection Passed 3/6/2025 3/6/2025 03/06/2025
Misc
Informational
03/06/2025
2-24-25 Dustin A, DW has been formed and compacted. Their is standing water in approach and will need to be removed, recompacted and called back in for another pre pour inspection. Fail 2-27-25 Dustin A, Water removed. Approved to pour 3-6-25 Dustin A dw is poured to city specs. Slopes in compliance. PASS
Plot Plan Inspection Passed 4/1/2025 04/01/2025
Occupancy Inspection - Codes Residential Failed 4/14/2025 4/14/2025 04/14/2025
Misc
Corrective Action Required
04/14/2025
-install spark rings on outlets in kitchen backsplash outlets -remove dust covers from smoke detectors for inspection -missing arc fault protection on refrigerator and fireplace , afci protection required -all outlets in unfinished spaces to be gfci protected or single pull receptacle and labeled -Seal top ac disconnect -secure ac unit supply whip within 12” of disconnect -seal all exterior penetrations
Erosion Control Inspection Residential Passed 04/17/2025
Miscellaneous Correction
Resolved
04/17/2025
Erosion control is in place and must be properly maintained until CofO
DCM3 ESC REQUIRED 2 DAY
Resolved
04/17/2025
2-24-25 Dustin A, Silt fence is down, Street needs cleaned of mud and gravel. EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS. 2-26-25 Dustin A, Silt fence still down. Remove restroom from stormbox 2-27-25 Dustin A, Silt fence is back up, restromed removed from storm box. Must maintain erosion control until vegetation is established
Occupancy Inspection - Codes Residential Full C of O 4/17/2025 4/17/2025 04/17/2025
Misc
Resolved
04/17/2025
-install spark rings on outlets in kitchen backsplash outlets -remove dust covers from smoke detectors for inspection -missing arc fault protection on refrigerator and fireplace , afci protection required -all outlets in unfinished spaces to be gfci protected or single pull receptacle and labeled -Seal top ac disconnect -secure ac unit supply whip within 12” of disconnect -seal all exterior penetrations
Documents & Images
Date Uploaded File Type Document Name
10/17/2024 HP-24-10-14 HF177 Coronado~ab
10/17/2024 Application Form Permit Application-24-10-15
10/17/2024 PP-24-10-15-HF177-Staked
10/17/2024 Tax_Application-24-10-15
10/21/2024 Permit Codes Residential Plan Review
10/21/2024 PP-24-10-21-HF177-Changed MDP Elevations
10/21/2024 HP-24-10-21 HF177 Coronado~address update
10/21/2024 Approved Plans APPROVED PLANS
10/21/2024 Plot Plan APPROVED PLOT PLAN
10/21/2024 Permit Codes Residential Plan Review
10/25/2024 Permit DS Building Permit
10/25/2024 Receipt Receipt for transaction:2024-008577
11/05/2024 Letter INSPECTION SUMMARY
11/20/2024 Letter INSPECTION SUMMARY
11/20/2024 Letter INSPECTION SUMMARY
11/20/2024 Letter INSPECTION SUMMARY
11/21/2024 Letter INSPECTION SUMMARY
11/21/2024 Letter INSPECTION SUMMARY
11/22/2024 Letter INSPECTION SUMMARY
11/22/2024 Letter INSPECTION SUMMARY
12/06/2024 Letter INSPECTION SUMMARY
12/23/2024 Letter INSPECTION SUMMARY
12/23/2024 Letter INSPECTION SUMMARY
12/23/2024 Letter INSPECTION SUMMARY
12/27/2024 Letter INSPECTION SUMMARY
12/28/2024 LST STRAP HOLD DOWN
12/30/2024 Letter INSPECTION SUMMARY
12/30/2024 Letter INSPECTION SUMMARY
12/31/2024 Letter INSPECTION SUMMARY
01/03/2025 Letter INSPECTION SUMMARY
02/04/2025 Letter INSPECTION SUMMARY
02/24/2025 Letter INSPECTION SUMMARY
02/24/2025 Letter INSPECTION SUMMARY
02/24/2025 Letter INSPECTION SUMMARY
02/24/2025 Letter INSPECTION SUMMARY
02/24/2025 Letter INSPECTION SUMMARY
02/24/2025 Letter INSPECTION SUMMARY
02/26/2025 Letter Stop Work Order
02/26/2025 Letter Stop Work Order
02/27/2025 Letter INSPECTION SUMMARY
02/27/2025 Letter INSPECTION SUMMARY
02/27/2025 Letter INSPECTION SUMMARY
02/27/2025 Letter INSPECTION SUMMARY
03/06/2025 Letter INSPECTION SUMMARY
03/06/2025 Letter INSPECTION SUMMARY
03/06/2025 Letter INSPECTION SUMMARY
03/31/2025 177 Hook Farm As graded plot plan
03/31/2025 Plot Plan APPROVED AS GRADED PLOT PLAN
04/01/2025 Letter INSPECTION SUMMARY
04/14/2025 Letter INSPECTION SUMMARY
04/17/2025 Letter Codes Final Certificate of Occupancy
04/17/2025 Letter Field Certificate of Occupancy
04/17/2025 Letter INSPECTION SUMMARY
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home