Permit Application Status

PRRES20243211


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PRRES20243211
Building Permit - Residential
Certificate of Occupancy
CMH PARKS INC
NEW SINGLE FAMILY
NEW HOUSE. UNFINISHED BASEMENT. UNCOVERED PATIO. ROOF TRUSSES.
06/24/2024
06/27/2024
05/08/2025
Locations
Contacts
CLAYTON PROPERTIES GROUP, INC, Address:10450 Holmes Rd Suite 100, Phone:(816) 246-6700  
CMH PARKS INC, Address:5000 CLAYTON RD  
Summit Homes, Address:120 SE 30th St, Phone:(816) 434-5074 Ext:320  
UNITED HEATING & COOLING, Address:301 DUCK RD, Phone:(816) 761-5262  
ARROW CIRCLE ELECTRIC, Address:1224 SE CENTURY DR, Phone:(816) 373-4888  
RELIABLE MECHANICAL SERVICES INC, Address:1025 W COUCHMAN DR, Phone:(816) 903-7674  
TREVOR@SUMMITHOMESKC.COM  
Reviews

There are no reviews for this permit application.

Fees
Paid Fees Amount Paid Owing Date Paid
Water Tap Fee $3,760.00 $3,760.00 Paid 06/27/2024
Water Meter Fee $680.46 $680.46 Paid 06/27/2024
Sanitary Sewer Development Fee $2,159.00 $2,159.00 Paid 06/27/2024
Right of Way Permit Fee $85.00 $85.00 Paid 06/27/2024
Residential Excise Tax Fee $1,022.72 $1,022.72 Paid 06/27/2024
Valuation Fee New Single Family $1,576.92 $1,576.92 Paid 06/27/2024
Not Ready Inspection Fee $75.00 $75.00 Paid 12/04/2024
Not Ready Inspection Fee $75.00 $75.00 Paid 12/04/2024
Not Ready Inspection Fee $75.00 $75.00 Paid 12/26/2024
Temporary Occupancy Fee $50.00 $50.00 Paid 12/26/2024
Temporary Occupancy Fee $50.00 $50.00 Paid 02/19/2025
Temporary Occupancy Fee $50.00 $50.00 Paid 03/13/2025
Temporary Occupancy Fee $50.00 $50.00 Paid 04/15/2025
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Footing Inspection - Residential Failed 7/22/2024 07/22/2024
Misc
Corrective Action Required
07/22/2024
Erosion control not in compliance inspection denied
Erosion Control Inspection Residential Failed 7/22/2024 07/22/2024
DCM3 ESC REQUIRED 2 DAY
Corrective Action Required
07/22/2024
EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS.
Sewer Service Inspection - R Passed 7/29/2024 07/29/2024
Water Service Inspection - R Passed 7/31/2024 07/31/2024
Underslab Plumbing Inspection - Residential Passed 8/6/2024 8/6/2024 08/06/2024
All Rough Inspection - Residential Not Ready 10/7/2024 10/7/2024 10/07/2024
Misc
Corrective Action Required
10/07/2024
Home still being worked on. No ready for inspection
Gas Service Inspection - Residential Passed 10/7/2024 10/7/2024 10/07/2024
Electrical Service Inspection Passed 10/7/2024 10/7/2024 10/07/2024
All Rough Inspection - Residential Failed 10/8/2024 10/8/2024 10/08/2024
Misc
Resolved
10/08/2024
Home still being worked on. No ready for inspection
Misc
Corrective Action Required
10/08/2024
NO FURTHER INSPECTIONS UNTIL EROSION CONTROL IS IN COMPLIANCE -Lib’s to be to length per plans -missing roof boots -nail plate under header at off to header per design -strap top plate at off where lapped less than 24” -nail GT above garage to plans -missing hold down device for GT in garage per plans -missing stud at hvac chase owners entry -seal dead space to ceiling space at primary bath -nail GT at dining room to plans -secure all wiring in truss space to code -missing window in bed3 -electrical not complete in basement. (Removed after passing electrical day before) -address joist cut for dev below primary bath -
Erosion Control Inspection Residential Failed 10/8/2024 10/08/2024
DCM3 ESC REQUIRED 2 DAY
Resolved
10/08/2024
EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS.
DCM1 ESC REQUIRED NO FURTHER INSP
Corrective Action Required
10/08/2024
EROSION CONTROL REQUIRED. NO FURTHER INSPECTIONS WILL BE PERFORMED UNTIL EROSION CONTROL IS INSTALLED AND IN COMPLIANCE.
DCM3 ESC REQUIRED 2 DAY
Corrective Action Required
10/08/2024
EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS. -maintain straw wattles -clean trash and debris from lot.
All Rough Inspection - Residential Failed 10/11/2024 10/11/2024 10/11/2024
Misc
Corrective Action Required
10/08/2024
INSPECTION DENIED EROSION CONTROL STILL NOT IN COMPLIANCE NO FURTHER INSPECTIONS UNTIL EROSION CONTROL IS IN COMPLIANCE -Lib’s to be to length per plans -missing roof boots -nail plate under header at off to header per design -strap top plate at off where lapped less than 24” -nail GT above garage to plans -missing hold down device for GT in garage per plans -missing stud at hvac chase owners entry -seal dead space to ceiling space at primary bath -nail GT at dining room to plans -secure all wiring in truss space to code -missing window in bed3 -electrical not complete in basement. (Removed after passing electrical day before) -address joist cut for dev below primary bath -
All Rough Inspection - Residential Failed 10/16/2024 10/16/2024 10/16/2024
Misc
Corrective Action Required
10/11/2024
-address joist cut for dev below primary bath { now provide joist hanger on header front side}
All Rough Inspection - Residential Not Ready 10/17/2024 10/17/2024 10/17/2024
Misc
Corrective Action Required
10/16/2024
Stairs removed no access to basement -address joist cut for dev below primary bath { now provide joist hanger on header front side}
All Rough Inspection - Residential Passed 10/18/2024 10/18/2024 10/18/2024
Misc
Resolved
10/18/2024
Stairs removed no access to basement -address joist cut for dev below primary bath { now provide joist hanger on header front side}
Miscellaneous Inspection Passed 10/25/2024 10/25/2024 10/25/2024
Sidewalk Inspection Partial 10/25/2024 10/25/2024 10/25/2024
Misc
Corrective Action Required
10/25/2024
10-25-24 Dustin A, Some of the SW is formed and is to city specs and compacted, Slopes are in compliance at this time. Section left of approach will not be poured due to ADA ramp needing replaced due to it being broke and missing section. I talked with Forrest and explained what needed to be done. Approve to pour the sections we talked about
Driveway Inspection Partial 10/25/2024 10/25/2024
Misc
Informational
10/25/2024
10-24-24 Dustin A, DW is formed and compacted, Approved to pour
Driveway Inspection Passed 11/1/2024 11/1/2024 11/01/2024
Misc
Informational
10/25/2024
10-24-24 Dustin A, DW is formed and compacted, Approved to pour 11-1-24 Dustin A, DW poured to city specs. Passed
Sidewalk Inspection Partial 11/1/2024 11/1/2024 11/01/2024
Misc
Corrective Action Required
10/25/2024
10-25-24 Dustin A, Some of the SW is formed and is to city specs and compacted, Slopes are in compliance at this time. Section left of approach will not be poured due to ADA ramp needing replaced due to it being broke and missing section. I talked with Forrest and explained what needed to be done. Approve to pour the sections we talked about 11-1-24 Dustin A, Sw's are formed and compacted slopes are in compliance. Approved to pour
Sidewalk Inspection Passed 11/12/2024 11/12/2024 11/12/2024
Misc
Corrective Action Required
11/01/2024
10-25-24 Dustin A, Some of the SW is formed and is to city specs and compacted, Slopes are in compliance at this time. Section left of approach will not be poured due to ADA ramp needing replaced due to it being broke and missing section. I talked with Forrest and explained what needed to be done. Approve to pour the sections we talked about 11-1-24 Dustin A, Sw's are formed and compacted slopes are in compliance. Approved to pour 11-12-24 Dustin A, Sw is poured and slopes are in compliance. Pass
Footing Inspection - Residential Passed 12/9/2024 12/09/2024
Misc
Resolved
12/09/2024
Erosion control not in compliance inspection denied
Misc
Informational
12/09/2024
third party inspection performed.
Occupancy Inspection - Codes Residential Not Ready 12/9/2024 12/9/2024 12/09/2024
Misc
Corrective Action Required
12/09/2024
No address posted. Inspection Denied
Occupancy Inspection - Codes Residential Failed 12/11/2024 12/11/2024 12/11/2024
Misc
Corrective Action Required
12/09/2024
-provide address with contrasting color -provide proper illumination for address -final grade and sod -missing gutters -uncover covered water meter -splash blocks and sump pump discharge to extend 36” from foundation -provide attic access cover in garage -missing door to basement
Occupancy Inspection - Codes Residential Failed 12/23/2024 12/23/2024 12/23/2024
Misc
Corrective Action Required
12/11/2024
-ensure address is contrasting in color from backdrop -final grade and sod -water meter needs to be 14”-18” from top of meter to well lid ring(you’re at 28”) -splash blocks and sump pump discharge to extend 36” from foundation
Occupancy Inspection - Codes Residential Ready for Temp CO 12/24/2024 12/24/2024 12/24/2024
Misc
Corrective Action Required
12/23/2024
-ensure address is contrasting in color from backdrop -final grade and sod -water meter needs to be 14”-18” from top of meter to well lid ring(you’re at 28”) (meter risers must be approved by the water department) you also have 3 meter pit risers. Any conservative meter risers must be approved through water department. -splash blocks and sump pump discharge to extend 36” from foundation
Occupancy Inspection - Codes Residential Ready for Temp CO 1/16/2025 01/16/2025
Misc
Corrective Action Required
12/24/2024
TCO EXTENSION LETTER UPLOADED AND APPROVED. FOR ANOTHER 30 DAYS. -ensure address is contrasting in color from backdrop -final grade and sod -water meter needs to be 14”-18” from top of meter to well lid ring(you’re at 28”) (meter risers must be approved by the water department) you also have 3 meter pit risers. Any conservative meter risers must be approved through water department. -splash blocks and sump pump discharge to extend 36” from foundation
Erosion Control Inspection Residential Failed 03/28/2025
DCM1 ESC REQUIRED NO FURTHER INSP
Resolved
03/28/2025
EROSION CONTROL REQUIRED. NO FURTHER INSPECTIONS WILL BE PERFORMED UNTIL EROSION CONTROL IS INSTALLED AND IN COMPLIANCE.
DCM3 ESC REQUIRED 2 DAY
Resolved
03/28/2025
EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS. -maintain straw wattles -clean trash and debris from lot.
Misc
Corrective Action Required
03/28/2025
Erosion control to remain in place until time of sod.
Occupancy Inspection - Codes Residential Ready for Temp CO 4/12/2025 04/15/2025
Misc
Corrective Action Required
01/16/2025
TCO EXTENSION LETTER UPLOADED AND APPROVED. FOR ANOTHER 30 DAYS. -ensure address is contrasting in color from back drop or illuminated
Occupancy Inspection - Codes Residential Failed 4/16/2025 4/16/2025 04/16/2025
Misc
Corrective Action Required
04/15/2025
TCO EXTENSION LETTER UPLOADED AND APPROVED. FOR ANOTHER 30 DAYS. -ensure address is contrasting in color from back drop or illuminated
Occupancy Inspection - Codes Residential Full C of O 5/8/2025 5/8/2025 05/08/2025
Misc
Resolved
05/08/2025
Documents & Images
Date Uploaded File Type Document Name
06/24/2024 H3 #78 - Permit App
06/27/2024 Approved Plans APPROVED PLANS
06/27/2024 Approved Plans APPROVED TRUSS LAYOUT
06/27/2024 Approved Plans APPROVED TRUSS PACKAGE
06/27/2024 Approved Plans APPROVED PLOT PLAN
06/27/2024 Permit Codes Residential Plan Review
06/27/2024 Permit DS Building Permit
06/27/2024 Receipt Receipt for transaction:2024-005299
07/18/2024 3RD Party Insp Report THIRD PARTY FOOTING INSPECTION
07/22/2024 Letter INSPECTION SUMMARY
07/22/2024 Letter INSPECTION SUMMARY
07/29/2024 Letter INSPECTION SUMMARY
07/31/2024 Letter INSPECTION SUMMARY
08/06/2024 Letter INSPECTION SUMMARY
10/07/2024 Letter INSPECTION SUMMARY
10/07/2024 Letter INSPECTION SUMMARY
10/07/2024 Letter INSPECTION SUMMARY
10/08/2024 Letter INSPECTION SUMMARY
10/08/2024 Letter INSPECTION SUMMARY
10/11/2024 Letter INSPECTION SUMMARY
10/16/2024 Letter INSPECTION SUMMARY
10/17/2024 Letter INSPECTION SUMMARY
10/18/2024 Letter INSPECTION SUMMARY
10/25/2024 Letter INSPECTION SUMMARY
10/25/2024 Letter INSPECTION SUMMARY
10/25/2024 Letter INSPECTION SUMMARY
10/25/2024 Letter INSPECTION SUMMARY
11/01/2024 Letter INSPECTION SUMMARY
11/01/2024 Letter INSPECTION SUMMARY
11/12/2024 Letter INSPECTION SUMMARY
12/04/2024 Receipt Receipt for transaction:2024-009327
12/09/2024 Letter INSPECTION SUMMARY
12/09/2024 Letter INSPECTION SUMMARY
12/11/2024 Letter INSPECTION SUMMARY
12/23/2024 Letter INSPECTION SUMMARY
12/24/2024 Letter INSPECTION SUMMARY
12/26/2024 Certificate/License Codes Temporary Certificate of Occupancy
12/26/2024 Receipt Receipt for transaction:2024-009659
01/15/2025 HT #78 - TCO Extension app 1_15_25
02/19/2025 Certificate/License Codes Temporary Certificate of Occupancy
02/19/2025 Receipt Receipt for transaction:2025-000998
03/13/2025 Certificate/License Codes Temporary Certificate of Occupancy
03/13/2025 Receipt Receipt for transaction:2025-001547
03/28/2025 Letter INSPECTION SUMMARY
03/28/2025 Letter INSPECTION SUMMARY
04/02/2025 HT #78 - TCO Extension app 4_2_25
04/15/2025 Certificate/License Codes Temporary Certificate of Occupancy
04/15/2025 Receipt Receipt for transaction:2025-002341
04/16/2025 Letter INSPECTION SUMMARY
04/16/2025 Letter INSPECTION SUMMARY
05/08/2025 Letter Codes Final Certificate of Occupancy
05/08/2025 Letter Field Certificate of Occupancy
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home