Permit Application Status

PRRES20233924


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PRRES20233924
Building Permit - Residential
Certificate of Occupancy
JFE CONSTRUCTION INC
NEW SINGLE FAMILY
NEW HOUSE - FINISHED AND UNFINISHED BASEMENT - COVERED DECK - ENG ROOF SYSTEM ( DEF )
08/10/2023
08/15/2023
02/10/2024
06/07/2024
Locations
Contacts
JFE CONSTRUCTION INC, Address:1314 SW MARKET  
JFE CONSTRUCTION INC, Address:1314 SW MARKET ST  
Angie Mendenhall, Address:1314 SW Market Street  
PERMITTING@JFECONSTRUCTION.COM  
MIKE BRYANT HEATING & COOLING , Address:1711 E 123RD , Phone:(913) 441-7807  
ARROW CIRCLE ELECTRIC, Address:1224 SE CENTURY DR, Phone:(816) 373-4888  
A BRIGHT PLUMBING LLC, Address:18107 E 18TH TER N, Phone:(816) 215-0730  
Reviews

There are no reviews for this permit application.

Fees
Paid Fees Amount Paid Owing Date Paid
8331507-Sanitary Sewer Development Fee $2,159.00 $2,159.00 Paid 08/15/2023
9110073-Right of Way Permit Fee $85.00 $85.00 Paid 08/15/2023
7232302-Residential License Tax Fee $1,022.72 $1,022.72 Paid 08/15/2023
8331401-Water Tap Fee $3,760.00 $3,760.00 Paid 08/15/2023
8350015-Water Meter Fee $680.46 $680.46 Paid 08/15/2023
9110078-Valuation Fee New Single Family $1,650.74 $1,650.74 Paid 08/15/2023
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Footing Inspection - Residential Passed 10/20/2023 10/20/2023
Underslab Plumbing Inspection - Residential Passed 10/20/2023 10/20/2023 10/20/2023
Water Service Inspection - R Partial 10/25/2023 (2:00) 10/25/2023 10/25/2023
Sewer Service Inspection - R Passed 10/25/2023 (2:00) 10/25/2023 10/25/2023
Water Service Inspection - R Passed 10/27/2023 10/27/2023 10/27/2023
Underslab Electrical Inspection - Residential Passed 11/1/2023 11/01/2023
Erosion Control Inspection Residential Failed 11/1/2023 11/1/2023 11/01/2023
DCM1 ESC REQUIRED NO FURTHER INSP
Corrective Action Required
11/01/2023
EROSION CONTROL REQUIRED. NO FURTHER INSPECTIONS WILL BE PERFORMED UNTIL EROSION CONTROL IS INSTALLED AND IN COMPLIANCE.
DCM3 ESC REQUIRED 2 DAY
Corrective Action Required
11/01/2023
EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS.
Electrical Service Inspection Passed 1/11/2024 1/11/2024 01/11/2024
Gas Service Inspection - Residential Passed 1/11/2024 1/11/2024 01/11/2024
All Rough Inspection - Residential Failed 1/11/2024 1/11/2024 01/11/2024
Misc
Corrective Action Required
01/11/2024
-Security blocking basement -Anchor bolts middle third in basement -Tighten anchor bolts at basement under window -Bocca plate at bottom plate basement bathroom
All Rough Inspection - Residential Passed 1/18/2024 1/18/2024 01/18/2024
Misc
Resolved
01/18/2024
-Security blocking basement -Anchor bolts middle third in basement -Tighten anchor bolts at basement under window -Bocca plate at bottom plate basement bathroom
Sidewalk Inspection Partial 2/1/2024 2/1/2024 02/01/2024
Misc
Informational
02/01/2024
2-1-24 Dustin A, Portion of sw is formed and compacted. (west side of dw) Slopes are in compliance. Approved to pour 2-5-24 Dustin A, SW is partially poured.
Driveway Inspection Partial 2/1/2024 2/1/2024 02/01/2024
Misc
Informational
02/01/2024
2-1-24 Dustin A, DW is framed and meets city specs. Approved to pour
Driveway Inspection Passed 2/8/2024 2/8/2024 02/05/2024
Misc
Informational
02/01/2024
2-1-24 Dustin A, DW is framed and meets city specs. Approved to pour 2-5-24 Dustin A, Dw is poured. Slopes are in compliance with city specs. Passed.
Sidewalk Inspection Partial 2/8/2024 2/8/2024 02/05/2024
Misc
Informational
02/01/2024
2-1-24 Dustin A, Portion of sw is formed and compacted. (west side of dw) Slopes are in compliance. Approved to pour 2-5-24 Dustin A, SW is partially poured.
Sidewalk Inspection Partial 2/12/2024 2/12/2024 02/12/2024
Misc
Informational
02/05/2024
2-1-24 Dustin A, Portion of sw is formed and compacted. (west side of dw) Slopes are in compliance. Approved to pour 2-5-24 Dustin A, SW is partially poured. 2-12-24 Dustin A, Conditions have not changed.
Sidewalk Inspection Partial 3/5/2024 3/5/2024 03/04/2024
Misc
Informational
02/12/2024
2-1-24 Dustin A, Portion of sw is formed and compacted. (west side of dw) Slopes are in compliance. Approved to pour 2-5-24 Dustin A, SW is partially poured. 2-12-24 Dustin A, Conditions have not changed. 3-4-24 Dustin A, Conditions have not changed
Sidewalk Inspection Partial 3/11/2024 3/11/2024 03/11/2024
Misc
Informational
03/04/2024
2-1-24 Dustin A, Portion of sw is formed and compacted. (west side of dw) Slopes are in compliance. Approved to pour 2-5-24 Dustin A, SW is partially poured. 2-12-24 Dustin A, Conditions have not changed. 3-4-24 Dustin A, Conditions have not changed 3-11-24 Dustin A, Conditions have not changed
Sidewalk Inspection Partial 3/19/2024 3/19/2024 03/19/2024
Misc
Informational
03/11/2024
2-1-24 Dustin A, Portion of sw is formed and compacted. (west side of dw) Slopes are in compliance. Approved to pour 2-5-24 Dustin A, SW is partially poured. 2-12-24 Dustin A, Conditions have not changed. 3-4-24 Dustin A, Conditions have not changed 3-11-24 Dustin A, Conditions have not changed 3-19-24 Dustin A, Conditions have not changed
Sidewalk Inspection Partial 4/29/2024 4/29/2024 04/29/2024
Misc
Informational
03/19/2024
2-1-24 Dustin A, Portion of sw is formed and compacted. (west side of dw) Slopes are in compliance. Approved to pour 2-5-24 Dustin A, SW is partially poured. 2-12-24 Dustin A, Conditions have not changed. 3-4-24 Dustin A, Conditions have not changed 3-11-24 Dustin A, Conditions have not changed 3-19-24 Dustin A, Conditions have not changed 4-28-24 DP. The SW left of the DW is formed, aggregate compacted, approved to pour. The two sidewalk panels at 2110 are out of compliance and already have occupancy. 2106 Will get 2 transition panels and pour the rest of their sw in compliance.
Sidewalk Inspection Passed 5/2/2024 5/2/2024 05/02/2024
Misc
Resolved
05/02/2024
2-1-24 Dustin A, Portion of sw is formed and compacted. (west side of dw) Slopes are in compliance. Approved to pour 2-5-24 Dustin A, SW is partially poured. 2-12-24 Dustin A, Conditions have not changed. 3-4-24 Dustin A, Conditions have not changed 3-11-24 Dustin A, Conditions have not changed 3-19-24 Dustin A, Conditions have not changed 4-28-24 DP. The SW left of the DW is formed, aggregate compacted, approved to pour. The two sidewalk panels at 2110 are out of compliance and already have occupancy. 2106 Will get 2 transition panels and pour the rest of their sw in compliance.
Occupancy Inspection - Codes Residential Failed 5/29/2024 5/29/2024 05/29/2024
Misc
Corrective Action Required
05/29/2024
-Identify sewer tracer wire -address deck not built to plans and post to beam connections -obtain issued lawn irrigation permit
Plot Plan Inspection Passed 05/29/2024
Occupancy Inspection - Codes Residential Full C of O 6/7/2024 6/7/2024 06/07/2024
Misc
Resolved
06/07/2024
-Identify sewer tracer wire -address deck not built to plans and post to beam connections -obtain issued lawn irrigation permit
Documents & Images
Date Uploaded File Type Document Name
08/10/2023 2106 SW RED BARN LN_PERMIT_8-8-23
08/10/2023 RHF-62
08/10/2023 HF62 - Tax App
08/14/2023 Plot Plan approved plot plan
08/14/2023 Permit Codes Residential Plan Review
08/14/2023 HF62 - Permit App
08/14/2023 Approved Plans approved plans
08/14/2023 Permit Codes Residential Plan Review
08/15/2023 Permit DS Building Permit
08/15/2023 Receipt Receipt for transaction:2023-006311
10/12/2023 Wilmoth 2106 SW Red Barn Ln LSMO Footing Inspection Report 10-11-23
10/20/2023 Letter INSPECTION SUMMARY
10/20/2023 Letter INSPECTION SUMMARY
10/27/2023 Letter INSPECTION SUMMARY
10/27/2023 Letter INSPECTION SUMMARY
10/27/2023 Letter INSPECTION SUMMARY
11/01/2023 Letter INSPECTION SUMMARY
11/01/2023 Letter INSPECTION SUMMARY
11/07/2023 2106 sw red barn ln_all slab deck pier insp_2023-11-03
01/11/2024 Letter INSPECTION SUMMARY
01/11/2024 Letter INSPECTION SUMMARY
01/11/2024 Letter INSPECTION SUMMARY
01/18/2024 Letter INSPECTION SUMMARY
02/01/2024 Letter INSPECTION SUMMARY
02/01/2024 Letter INSPECTION SUMMARY
02/01/2024 Letter INSPECTION SUMMARY
02/05/2024 Letter INSPECTION SUMMARY
02/05/2024 Letter INSPECTION SUMMARY
02/12/2024 Letter INSPECTION SUMMARY
03/04/2024 Letter INSPECTION SUMMARY
03/11/2024 Letter INSPECTION SUMMARY
03/19/2024 Letter INSPECTION SUMMARY
04/29/2024 Letter INSPECTION SUMMARY
05/02/2024 Letter INSPECTION SUMMARY
05/29/2024 Letter INSPECTION SUMMARY
05/29/2024 Letter INSPECTION SUMMARY
06/05/2024 3RD Party Insp Report DECK ENGINEER REPORT
06/07/2024 Letter Field Certificate of Occupancy
06/07/2024 Letter Codes Final Certificate of Occupancy
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home