Permit Application Status

PRRES20232451


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PRRES20232451
Building Permit - Residential
Certificate of Occupancy
NEW SINGLE FAMILY
NEW HOUSE. UNFINISHED BASEMENT. COVERED PATIO.
05/30/2023
06/14/2023
11/29/2023
08/16/2024
Locations
Contacts
WALKER CUSTOM HOMES, LLC, Address:PO BOX 3194, Phone:(913) 208-2026  
Jason walker, Address:PO Box 247, Phone:(913) 208-2026  
5 STAR HEATING & COOLING, Address:211 NW 12TH, Phone:(816) 517-3341  
ARROW CIRCLE ELECTRIC, Address:1224 SE CENTURY DR, Phone:(816) 373-4888  
TRI-COUNTY PLUMBING LLC, Address:PO BOX 234, Phone:(816) 720-3222  
WALKERCUSTOMHOMESKC@GMAIL.COM  
Reviews

There are no reviews for this permit application.

Fees
Paid Fees Amount Paid Owing Date Paid
9110073-Right of Way Permit Fee $85.00 $85.00 Paid 06/14/2023
7232302-Residential License Tax Fee $1,022.72 $1,022.72 Paid 06/14/2023
8331401-Water Tap Fee $3,730.00 $3,730.00 Paid 06/14/2023
8350015-Water Meter Fee $550.50 $550.50 Paid 06/14/2023
8331507-Sanitary Sewer Development Fee $1,384.00 $1,384.00 Paid 06/14/2023
9110078-Valuation Fee New Single Family $1,835.31 $1,835.31 Paid 06/14/2023
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Footing Inspection - Residential Passed 6/21/2023 6/21/2023 06/21/2023
Underslab Plumbing Inspection - Residential Passed 6/29/2023 06/29/2023
Sewer Service Inspection - R Passed 6/30/2023 (8:00) 6/30/2023 06/30/2023
Water Service Inspection - R Partial 6/30/2023 (8:00) 6/30/2023 06/30/2023
Misc
Corrective Action Required
06/30/2023
Pex ran from foundation roughly 15’
Water Service Inspection - R Passed 6/30/2023 (1:00) 6/30/2023 06/30/2023
Misc
Resolved
06/30/2023
Pex ran from foundation roughly 15’
All Rough Inspection - Residential Partial 8/30/2023 8/30/2023 08/30/2023
Misc
Informational
08/30/2023
Garage portal frame exterior inspected and okay to cover
Electrical Service Inspection Passed 9/15/2023 9/15/2023 09/15/2023
Gas Service Inspection - Residential Failed 9/15/2023 9/15/2023 09/15/2023
Misc
Corrective Action Required
09/15/2023
Complete gas line installs for inspection or provide shutoffs at csst gas line ends
All Rough Inspection - Residential Failed 9/15/2023 9/15/2023 09/15/2023
Misc
Resolved
09/15/2023
Garage portal frame exterior inspected and okay to cover
Misc
Corrective Action Required
09/15/2023
-anchor bolts in garage to be in the middle 1/3 of sill plate. -remove/move trash and building materials to inspect all of garage -address rafter landing on multiple blocks throughout -address plumbing and electrical drilled closer than 2” above garage entry bathroom -fire block garage wall to kitchen furr down -complete plumbing for master bath shower -address holes drilled closer than 2” to one another above master bed entry -plans call for 3 king studs each side of front entry -solid block sheathing seams bed 4 bath -weld beam web stiffeners to plans and provide weld certificate on file
All Rough Inspection - Residential Failed 10/24/2023 10/24/2023 10/24/2023
Misc
Corrective Action Required
09/15/2023
-anchor bolts in garage to be in the middle 1/3 of sill plate. -address rafter landing on multiple blocks throughout -address plumbing and electrical drilled closer than 2” above garage entry bathroom (fix not to engineer specifications) -address holes drilled closer than 2” to one another above master bed entry(fix not to engineer specifications)
All Rough Inspection - Residential Failed 10/24/2023 10/24/2023 10/24/2023
Misc
Corrective Action Required
10/24/2023
-anchor bolts in garage to be in the middle 1/3 of sill plate. -address plumbing and electrical drilled closer than 2” above garage entry bathroom (fix not to engineer specifications) -address holes drilled closer than 2” to one another above master bed entry(fix not to engineer specifications)
Gas Service Inspection - Residential Passed 10/24/2023 10/24/2023 10/24/2023
Misc
Resolved
10/24/2023
Complete gas line installs for inspection or provide shutoffs at csst gas line ends
All Rough Inspection - Residential Passed 10/25/2023 10/25/2023 10/25/2023
Misc
Resolved
10/25/2023
-anchor bolts in garage to be in the middle 1/3 of sill plate. -address plumbing and electrical drilled closer than 2” above garage entry bathroom (fix not to engineer specifications) -address holes drilled closer than 2” to one another above master bed entry(fix not to engineer specifications)
Driveway Inspection Partial 11/15/2023 11/15/2023
Misc
Informational
11/15/2023
11-15-23 Dustin A, DW is formed and aggregate is compacted. Depths is in compliance. Will need to maintain ada specs through approach
Driveway Inspection Partial 11/28/2023 11/28/2023 11/21/2023
Misc
Informational
11/15/2023
11-15-23 Dustin A, DW is formed and aggregate is compacted. Depths is in compliance. Will need to maintain ada specs through approach
Erosion Control Inspection Residential Failed 12/18/2023 12/18/2023
Misc
Corrective Action Required
12/18/2023
clean all construction trash from lot.
DCM3 ESC REQUIRED 2 DAY
Corrective Action Required
12/18/2023
EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS.
Sidewalk Inspection Partial 3/4/2024 03/04/2024
Misc
Informational
03/04/2024
3-4-24 Dustin A, SW is formed to city specs. Approved to pour
Sidewalk Inspection Passed 3/11/2024 3/11/2024 03/11/2024
Misc
Informational
03/04/2024
3-4-24 Dustin A, SW is formed to city specs. Approved to pour 3-11-24 Dustin A, SW is poured to city specs. Passed
Occupancy Inspection - Codes Residential Failed 7/30/2024 7/30/2024 07/30/2024
Misc
Corrective Action Required
07/30/2024
-Identify sewer tracer wire -address pending driveway inspection -provide as graded plot plan
Driveway Inspection Passed 8/1/2024 08/01/2024
Misc
Informational
11/21/2023
11-15-23 Dustin A, DW is formed and aggregate is compacted. Depths is in compliance. Will need to maintain ada specs through approach 8-1-24 Dustin A, Dw is poured to city specs. Slopes are in compliance. Passed
Plot Plan Inspection Passed 8/16/2024 08/16/2024
Erosion Control Inspection Residential Passed 8/16/2024 08/16/2024
Misc
Resolved
08/16/2024
clean all construction trash from lot.
DCM3 ESC REQUIRED 2 DAY
Resolved
08/16/2024
EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS.
Occupancy Inspection - Codes Residential Full C of O 8/16/2024 8/16/2024 08/16/2024
Misc
Resolved
08/16/2024
-Identify sewer tracer wire -address pending driveway inspection -provide as graded plot plan
Documents & Images
Date Uploaded File Type Document Name
05/30/2023 2611 Barley Field Dr City Signed Application
06/02/2023 Approved Plans APPROVED PLANS
06/02/2023 Permit Codes Residential Plan Review
06/09/2023 Photograph APPROVED PLOT PLAN
06/09/2023 Permit Codes Residential Plan Review
06/14/2023 Permit DS Building Permit
06/14/2023 Receipt Receipt for transaction:2023-004361
06/21/2023 Wilmoth 2611 SW Barley Field Dr LSMO Hook Farms Lot 175 3rd Party Subgrade and Footing Inspection Report 6-19-23
06/21/2023 Letter INSPECTION SUMMARY
06/30/2023 Letter INSPECTION SUMMARY
06/30/2023 Letter INSPECTION SUMMARY
06/30/2023 Letter INSPECTION SUMMARY
06/30/2023 Letter INSPECTION SUMMARY
07/13/2023 Final_2023_07_10_DPier_LSMO_Pat Cochran
08/30/2023 Letter INSPECTION SUMMARY
09/15/2023 Letter INSPECTION SUMMARY
09/15/2023 Letter INSPECTION SUMMARY
09/15/2023 Letter INSPECTION SUMMARY
09/27/2023 Walker 2611 Barleyfield Drive 9-22
10/23/2023 HKF175 (Walker Custom Homes) - Inspection Letter (October 10, 2023) 2611
10/24/2023 Letter INSPECTION SUMMARY
10/24/2023 Letter INSPECTION SUMMARY
10/24/2023 Letter INSPECTION SUMMARY
11/15/2023 Letter INSPECTION SUMMARY
11/21/2023 Letter INSPECTION SUMMARY
12/18/2023 Letter INSPECTION SUMMARY
03/04/2024 Letter INSPECTION SUMMARY
03/11/2024 Letter INSPECTION SUMMARY
07/29/2024 Letter INSPECTION SUMMARY
07/29/2024 Letter Codes 140 Day Letter
07/30/2024 Letter INSPECTION SUMMARY
08/01/2024 Letter INSPECTION SUMMARY
08/15/2024 Plot Plan APPROVED PLOT PLAN
08/16/2024 Letter INSPECTION SUMMARY
08/16/2024 Letter INSPECTION SUMMARY
08/16/2024 Letter Field Certificate of Occupancy
08/16/2024 Letter Codes Final Certificate of Occupancy
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home