Summary
PRRES20231576
Building Permit - Residential
Certificate of Occupancy
NLV PERGOLA PARK LLC
NEW SINGLE FAMILY
NEW HOUSE - UNFINISHED BASEMENT -
04/11/2023
04/18/2023
10/09/2023
11/28/2023
Locations
Contacts
LANDROCK SIGNATURE HOMES LLC, Address:4335 MCGEE ST, Phone:(816) 863-5588  
NLV PERGOLA PARK LLC, Address:3152 SW GRANDSTAND CIR  
JP Roberts, Address:4335 McGee St  
JPROBERTS23@HOTMAIL.COM  
MIDWEST HEATING COOLING & PLUMBING, Address:13228 HOLMES RD, Phone:(816) 943-8513  
PREMIER ELECTRIC & LIGHTING DESIGN, Address:PO BOX 1311, Phone:(816) 564-7660  
CENTURY PLUMBING, Address:14001 CENTURY LN, Phone:(816) 765-6066  
Reviews

There are no reviews for this permit application.

Fees
Paid Fees Amount Paid Owing Date Paid
Sanitary Sewer Development Fee $1,384.00 $1,384.00 Paid 04/18/2023
Right of Way Permit Fee $85.00 $85.00 Paid 04/18/2023
Residential Excise Tax Fee $1,022.72 $1,022.72 Paid 04/18/2023
Water Tap Fee $3,730.00 $3,730.00 Paid 04/18/2023
Water Meter Fee $550.50 $550.50 Paid 04/18/2023
Valuation Fee New Single Family $1,370.93 $1,370.93 Paid 04/18/2023
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Footing Inspection - Residential Passed 4/24/2023 04/24/2023
Misc
Informational
04/24/2023
- UFER in center of garage wall.
Erosion Control Inspection Residential Partial 4/24/2023 04/24/2023
Misc
Corrective Action Required
04/24/2023
Up to code at time of inspection
Erosion Control Inspection Residential Failed 4/26/2023 04/26/2023
DCM2 ESC DEFICIENT INSTALLATION
Corrective Action Required
04/24/2023
DEFICIENT EROSION CONTROL INSTALLATION. NO FURTHER INSPECTIONS UNTIL ADEQUATE EROSION CONTROL PROVIDED.
Underslab Plumbing Inspection - Residential Passed 5/3/2023 5/3/2023 05/03/2023
Sewer Service Inspection - R Passed 5/16/2023 (2:00) 5/16/2023 05/16/2023
Erosion Control Inspection Residential Failed 5/17/2023 05/17/2023
DCM2 ESC DEFICIENT INSTALLATION
Corrective Action Required
04/26/2023
DEFICIENT EROSION CONTROL INSTALLATION. NO FURTHER INSPECTIONS UNTIL ADEQUATE EROSION CONTROL PROVIDED. -PROVIDE SILT FENCE AT FRONT OF LOT. - REMOVE CONSTRUCTION TRASH
Water Service Inspection - R Partial 5/17/2023 05/17/2023
Misc
Corrective Action Required
05/17/2023
PARTIAL: POLY THROUGH FOUNDATION OUT TO COPPER. WAITING ON TAP.
Water Service Inspection - R Passed 5/18/2023 (9:15) 5/18/2023 05/18/2023
Misc
Resolved
05/18/2023
PARTIAL: POLY THROUGH FOUNDATION OUT TO COPPER. WAITING ON TAP.
All Rough Inspection - Residential Failed 6/7/2023 6/7/2023 06/07/2023
Misc
Corrective Action Required
06/07/2023
Portal frame and front porch cover only - portal frame ok to cover, missing anchor bolts, washers, nuts - front porch- full joist above door has insufficient bearing, provide hangers.
Erosion Control Inspection Residential Failed 6/7/2023 06/07/2023
DCM2 ESC DEFICIENT INSTALLATION
Corrective Action Required
05/17/2023
-PROVIDE SILT FENCE OF SWADDLES AT FRONT OF LOT. - REMOVE CONSTRUCTION TRASH - PROVIDE EROSION CONTROL AROUND SPOILAGE PILE
Electrical Service Inspection Passed 7/19/2023 7/19/2023 07/19/2023
Gas Service Inspection - Residential Passed 7/19/2023 7/19/2023 07/19/2023
Erosion Control Inspection Residential Partial 7/19/2023 07/19/2023
DCM2 ESC DEFICIENT INSTALLATION
Resolved
07/19/2023
-PROVIDE SILT FENCE OF SWADDLES AT FRONT OF LOT. - REMOVE CONSTRUCTION TRASH - PROVIDE EROSION CONTROL AROUND SPOILAGE PILE
Misc
Corrective Action Required
07/19/2023
Satisfactory at this time
All Rough Inspection - Residential Failed 7/19/2023 7/19/2023 07/19/2023
Misc
Resolved
07/19/2023
Portal frame and front porch cover only - portal frame ok to cover, missing anchor bolts, washers, nuts - front porch- full joist above door has insufficient bearing, provide hangers.
Misc
Corrective Action Required
07/19/2023
Over notched stud at garage at sill plate - Complete vent in powder room - Block return air in to soffit in pantry - Fire block kitchen wall and the other end around pantry soffit - Address over bored joist above kitchen island - Solid block cantilever at front porch - Fire block ceiling to wall in master bedroom - Missing studs master bedroom - Bathroom vents missing upstairs - Address cut joint by furnace
All Rough Inspection - Residential Failed 7/24/2023 7/24/2023 07/24/2023
Misc
Corrective Action Required
07/19/2023
- Block return air in to soffit in pantry (now blocking return air from stud to joist space) - Address over bored joist above kitchen island
All Rough Inspection - Residential Passed 8/11/2023 8/11/2023 08/11/2023
Misc
Resolved
08/11/2023
- Block return air in to soffit in pantry (now blocking return air from stud to joist space) - Address over bored joist above kitchen island
Sidewalk Inspection Partial 9/18/2023 9/18/2023 09/18/2023
Misc
Informational
09/18/2023
9-18-23 A.A SW is formed , aggregate is compacted and slopes are in compliance. Conditions can change, approved to pour.
Sidewalk Inspection Partial 9/25/2023 9/25/2023 09/25/2023
Misc
Informational
09/18/2023
9-18-23 A.A SW is formed , aggregate is compacted and slopes are in compliance. Conditions can change, approved to pour. 9-25-23 A.A, SW is poured. Slopes are in compliance . Cannot pass until forms are pulled
Sidewalk Inspection Partial 9/29/2023 9/29/2023 09/29/2023
Misc
Informational
09/25/2023
9-18-23 A.A SW is formed , aggregate is compacted and slopes are in compliance. Conditions can change, approved to pour. 9-25-23 A.A, SW is poured. Slopes are in compliance . Cannot pass until forms are pulled 9-29-23 D.A Conditions have not changed
Sidewalk Inspection Partial 10/6/2023 10/6/2023 10/06/2023
Misc
Informational
09/29/2023
9-18-23 A.A SW is formed , aggregate is compacted and slopes are in compliance. Conditions can change, approved to pour. 9-25-23 A.A, SW is poured. Slopes are in compliance . Cannot pass until forms are pulled 9-29-23 D.A Conditions have not changed 10-6-23 Dustin A, Conditions have not changed
Sidewalk Inspection Partial 10/13/2023 10/13/2023 10/13/2023
Misc
Informational
10/06/2023
9-18-23 A.A SW is formed , aggregate is compacted and slopes are in compliance. Conditions can change, approved to pour. 9-25-23 A.A, SW is poured. Slopes are in compliance . Cannot pass until forms are pulled 9-29-23 D.A Conditions have not changed 10-6-23 Dustin A, Conditions have not changed 10-13-23 Dustin A, Conditions have not changed
Sidewalk Inspection Partial 10/19/2023 10/19/2023 10/18/2023
Misc
Informational
10/13/2023
9-18-23 A.A SW is formed , aggregate is compacted and slopes are in compliance. Conditions can change, approved to pour. 9-25-23 A.A, SW is poured. Slopes are in compliance . Cannot pass until forms are pulled 9-29-23 D.A Conditions have not changed 10-6-23 Dustin A, Conditions have not changed 10-13-23 Dustin A, Conditions have not changed 10-18-23 Dustin A, Conditions have not changed
Erosion Control Inspection Residential Failed 11/3/2023 10/27/2023
DCM3 ESC REQUIRED 2 DAY
Corrective Action Required
07/19/2023
EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS. - Remove porta toilet from street. - Remove mud and debris from street - repair erosion control at front of lot.
Sidewalk Inspection Partial 10/31/2023 10/31/2023 10/30/2023
Misc
Informational
10/18/2023
9-18-23 A.A SW is formed , aggregate is compacted and slopes are in compliance. Conditions can change, approved to pour. 9-25-23 A.A, SW is poured. Slopes are in compliance . Cannot pass until forms are pulled 9-29-23 D.A Conditions have not changed 10-6-23 Dustin A, Conditions have not changed 10-13-23 Dustin A, Conditions have not changed 10-18-23 Dustin A, Conditions have not changed 10-30-23 Dustin A, Conditions have not changed forms still need pulled.
Erosion Control Inspection Residential Passed 11/16/2023 11/16/2023
DCM3 ESC REQUIRED 2 DAY
Resolved
11/16/2023
EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS. - Remove porta toilet from street. - Remove mud and debris from street - repair erosion control at front of lot.
Plot Plan Inspection Passed 11/16/2023 11/16/2023
Occupancy Inspection - Codes Residential Full C of O 11/28/2023 11/28/2023 11/28/2023
Documents & Images
Date Uploaded File Type Document Name
04/11/2023 1029 SW Armie St_ Excise Tax Application
04/11/2023 1029 SW Armie St_ Permit Application
04/11/2023 COMPLETE SET 1029 SW Armie St_- MO
04/11/2023 LOT 87 CON 3-21-2023
04/12/2023 Approved Plans APPROVED PLANS
04/12/2023 Permit Codes Residential Plan Review
04/17/2023 LOT 87 CITY 4-17-23
04/18/2023 Plot Plan approved plot plan
04/18/2023 Permit Codes Residential Plan Review
04/18/2023 Permit DS Building Permit
04/18/2023 Receipt Receipt for transaction:2023-002149
04/24/2023 Letter INSPECTION SUMMARY
04/24/2023 Letter INSPECTION SUMMARY
04/26/2023 Letter INSPECTION SUMMARY
05/03/2023 Letter INSPECTION SUMMARY
05/16/2023 Letter INSPECTION SUMMARY
05/17/2023 Letter INSPECTION SUMMARY
05/17/2023 Letter INSPECTION SUMMARY
05/18/2023 Letter INSPECTION SUMMARY
06/07/2023 Letter INSPECTION SUMMARY
06/07/2023 Letter INSPECTION SUMMARY
07/19/2023 Letter INSPECTION SUMMARY
07/19/2023 Letter INSPECTION SUMMARY
07/19/2023 Letter INSPECTION SUMMARY
07/19/2023 Letter INSPECTION SUMMARY
07/24/2023 Letter INSPECTION SUMMARY
09/18/2023 Letter INSPECTION SUMMARY
09/25/2023 Letter INSPECTION SUMMARY
09/29/2023 Letter INSPECTION SUMMARY
09/29/2023 Letter INSPECTION SUMMARY
10/06/2023 Letter INSPECTION SUMMARY
10/13/2023 Letter INSPECTION SUMMARY
10/18/2023 Letter INSPECTION SUMMARY
10/27/2023 Letter INSPECTION SUMMARY
10/30/2023 Letter INSPECTION SUMMARY
10/30/2023 Letter INSPECTION SUMMARY
11/28/2023 Letter Field Certificate of Occupancy
11/28/2023 Letter Codes Final Certificate of Occupancy
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home