Summary
PRRES20224900
Building Permit - Residential
Certificate of Occupancy
NEW SINGLE FAMILY
NEW HOUSE - PARTIAL FINISHED BASEMENT - COVERED DECK
10/03/2022
10/31/2022
04/02/2023
08/31/2023
Locations
Contacts
WALKER CUSTOM HOMES, LLC, Address:PO BOX 3194, Phone:(913) 208-2026  
Jason walker, Address:PO Box 247, Phone:(913) 208-2026  
5 STAR HEATING & COOLING, Address:211 NW 12TH, Phone:(816) 517-3341  
ARROW CIRCLE ELECTRIC, Address:1224 SE CENTURY DR, Phone:(816) 373-4888  
TRI-COUNTY PLUMBING LLC, Address:PO BOX 234, Phone:(816) 720-3222  
WALKERCUSTOMHOMESKC@GMAIL.COM  
Reviews

There are no reviews for this permit application.

Fees
Paid Fees Amount Paid Owing Date Paid
9110078-Valuation Fee New Single Family $1,400.23 $1,400.23 Paid 10/31/2022
9110073-Right of Way Permit Fee $85.00 $85.00 Paid 10/31/2022
7232302-Residential License Tax Fee $1,022.72 $1,022.72 Paid 10/31/2022
8331401-Water Tap Fee $3,730.00 $3,730.00 Paid 10/31/2022
8350015-Water Meter Fee $550.50 $550.50 Paid 10/31/2022
8331507-Sanitary Sewer Development Fee $1,384.00 $1,384.00 Paid 10/31/2022
9110080-Not Ready Inspection Fee $75.00 $75.00 Paid 01/09/2023
9110080-Not Ready Inspection Fee $75.00 $75.00 Paid 01/09/2023
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Driveway Inspection Not Ready 11/1/2022 11/1/2022 11/01/2022
Misc
Informational
11/01/2022
11-1-22 RH. No driveway to inspect.
Sidewalk Inspection Not Ready 11/1/2022 11/01/2022
Misc
Informational
11/01/2022
11-1-22 RH. No sidewalk to inspect.
Footing Inspection - Residential Passed 12/1/2022 12/01/2022
Underslab Plumbing Inspection - Residential Passed 12/1/2022 12/1/2022 12/01/2022
Sewer Service Inspection - R Passed 12/2/2022 (9:30) 12/2/2022 12/02/2022
Water Service Inspection - R Partial 12/2/2022 12/02/2022
Misc
Corrective Action Required
12/02/2022
partial water pex ran from foundation roughly 15' out
Water Service Inspection - R Passed 12/5/2022 (9:15) 12/5/2022 12/05/2022
Misc
Corrective Action Required
12/02/2022
partial water pex ran from foundation roughly 15' out
Gas Service Inspection - Residential Passed 3/14/2023 3/14/2023 03/14/2023
Electrical Service Inspection Passed 3/14/2023 3/14/2023 03/14/2023
Piers/Caissons Inspection - Residential Passed 3/14/2023 03/14/2023
All Rough Inspection - Residential Failed 3/14/2023 3/14/2023 03/14/2023
Misc
Corrective Action Required
03/14/2023
-provide city stamped plans on site -missing joist hanger at attic access above garage -anchor bolts to be in the middle 1/3 of sill plate through out -fill top plate penetrations at laundry -missing lvl above garage entry see plans -missing nail in hanger at kitchen/great room -frame great room W wall to plans -missing stud in stud pack at master entry -secure gas line within 12” of disconnect -address bath vent in master bath address vent line and provide manufacturer documentation for installation in wall -midway strap dwv in stud bay 2” of less in diameter -seal above bed 4 joist space used for R/a -fire block furr down ends in basement -connect sw bed 3 exterior wall corners together to code and NW corner game area -nail exterior wall corners together to code -address exterior deck post to beam connection -
All Rough Inspection - Residential Passed 4/7/2023 4/7/2023 04/07/2023
Misc
Corrective Action Required
03/14/2023
Okay to insulate will check deck at final -address exterior deck post to beam connection (does not meet code)
Driveway Inspection Partial 5/2/2023 5/2/2023 05/02/2023
Misc
Informational
11/01/2022
11-1-22 RH. No driveway to inspect. 5-2-23 RH. Driveway is formed up and aggregate is placed and compacted. Approved to pour.
Sidewalk Inspection Partial 5/3/2023 05/03/2023
Misc
Informational
05/03/2023
5-3-23 RH. Sidewalk is formed up and aggregate is placed and compacted on the left side of the driveway. Approved to pour.
Sidewalk Inspection Passed 5/9/2023 5/9/2023 05/10/2023
Misc
Informational
11/01/2022
11-1-22 RH. No sidewalk to inspect. 5-10-23 RH. Sidewalk meets LS and ADA Inspection.
Driveway Inspection Passed 5/9/2023 5/9/2023 05/10/2023
Misc
Informational
05/02/2023
11-1-22 RH. No driveway to inspect. 5-2-23 RH. Driveway is formed up and aggregate is placed and compacted. Approved to pour. 5-10-23 RH. Driveway meets LS and ADA specification.
Erosion Control Inspection Residential Passed 08/23/2023
Plot Plan Inspection Passed 08/23/2023
Occupancy Inspection - Codes Residential Failed 8/23/2023 8/23/2023 08/23/2023
Misc
Corrective Action Required
08/23/2023
Front steps not to be greater a than 3/8” difference in risers.
Occupancy Inspection - Codes Residential Full C of O 8/31/2023 8/31/2023 08/31/2023
Misc
Resolved
08/31/2023
Front steps not to be greater a than 3/8” difference in risers.
Documents & Images
Date Uploaded File Type Document Name
10/03/2022 2506 SW Tracker Ln City Application
10/04/2022 Permit Codes Residential Plan Review
10/24/2022 Approved Plans Approved Drawings
10/24/2022 Plot Plan Approved Plot Plan
10/24/2022 Permit Codes Residential Plan Review
10/31/2022 Permit DS Building Permit
10/31/2022 Receipt Receipt for transaction:2022-008605
11/01/2022 Letter INSPECTION SUMMARY
11/01/2022 Letter INSPECTION SUMMARY
11/01/2022 Letter INSPECTION SUMMARY
11/22/2022 Wilmoth 2506 SW Tracker LN LSMO Hook Farms Lot 127 3rd Party Subgrade and Footing Inspection Report 11-21-22
12/01/2022 Letter INSPECTION SUMMARY
12/01/2022 Letter INSPECTION SUMMARY
12/02/2022 Letter INSPECTION SUMMARY
12/02/2022 Letter INSPECTION SUMMARY
12/05/2022 Letter INSPECTION SUMMARY
12/16/2022 Final_2022_12_14_DPier_LSMO_Pat Cohran Concrete
01/09/2023 Receipt Receipt for transaction:2023-000127
03/14/2023 Letter INSPECTION SUMMARY
03/14/2023 Letter INSPECTION SUMMARY
03/14/2023 Letter INSPECTION SUMMARY
03/14/2023 Letter INSPECTION SUMMARY
03/16/2023 Specification-Sheet-688-EN-FR (2)
04/03/2023 2506 SW Tracker Lane - Structural Letter (April 3, 2023)
04/07/2023 Letter INSPECTION SUMMARY
05/02/2023 Letter INSPECTION SUMMARY
05/03/2023 Letter INSPECTION SUMMARY
05/10/2023 Letter INSPECTION SUMMARY
05/10/2023 Letter INSPECTION SUMMARY
08/23/2023 Letter INSPECTION SUMMARY
08/23/2023 Letter INSPECTION SUMMARY
08/23/2023 Letter INSPECTION SUMMARY
08/31/2023 Letter Field Certificate of Occupancy
08/31/2023 Letter Codes Final Certificate of Occupancy
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home