Permit Application Status

PRRES20220127


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PRRES20220127
Building Permit - Residential
Certificate of Occupancy
JCM DEVELOPMENT LLC
NEW SINGLE FAMILY
NEW HOUSE. UNFINISHED BASEMENT. ROOF TRUSSES. COVERED PATIO.
01/11/2022
01/18/2022
02/09/2023
Locations
Contacts
CLAYTON PROPERTIES GROUP, INC, Address:120 SE 30TH ST, Phone:(816) 246-6700  
JCM DEVELOPMENT LLC, Address:1314 SW MARKET ST  
Summit Homes, Address:120 SE 30th St, Phone:(816) 434-5074 Ext:320  
UNITED HEATING & COOLING, Address:301 DUCK RD, Phone:(816) 761-5262  
ARROW CIRCLE ELECTRIC, Address:1224 SE CENTURY DR, Phone:(816) 373-4888  
RELIABLE MECHANICAL SERVICES INC, Address:1025 W COUCHMAN DR, Phone:(816) 903-7674  
THAD@SUMMITHOMESKC.COM  
Reviews

There are no reviews for this permit application.

Fees
Paid Fees Amount Paid Owing Date Paid
8331507-Sewer Connection Fee $540.00 $540.00 Paid 01/18/2022
8331401-Water Tap Fee $3,655.00 $3,655.00 Paid 01/18/2022
8350015-Water Meter Fee $479.24 $479.24 Paid 01/18/2022
9110073-Right of Way Permit Fee $85.00 $85.00 Paid 01/18/2022
7232302-Residential Excise Tax Fee $1,077.12 $1,077.12 Paid 01/18/2022
9110078-Valuation Fee New Single Family $1,347.16 $1,347.16 Paid 01/18/2022
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Footing Inspection - Residential Passed 2/7/2022 (10:00) 2/7/2022 02/07/2022
Erosion Control Inspection Residential Failed 2/7/2022 2/7/2022 02/07/2022
DCM1 ESC REQUIRED NO FURTHER INSP
Corrective Action Required
02/07/2022
EROSION CONTROL REQUIRED. NO FURTHER INSPECTIONS WILL BE PERFORMED UNTIL EROSION CONTROL IS INSTALLED AND IN COMPLIANCE.
Sewer Service Inspection - R Passed 2/10/2022 02/10/2022
Water Service Inspection - R Passed 2/10/2022 (10:00) 2/10/2022 02/10/2022
Erosion Control Inspection Residential Failed 2/10/2022 2/10/2022 02/10/2022
DCM1 ESC REQUIRED NO FURTHER INSP
Corrective Action Required
02/07/2022
EROSION CONTROL REQUIRED. NO FURTHER INSPECTIONS WILL BE PERFORMED UNTIL EROSION CONTROL IS INSTALLED AND IN COMPLIANCE.
Underslab Plumbing Inspection - Residential Passed 2/16/2022 2/16/2022 02/16/2022
Erosion Control Inspection Residential Failed 2/16/2022 2/16/2022 02/16/2022
DCM1 ESC REQUIRED NO FURTHER INSP
Resolved
02/16/2022
Misc
Corrective Action Required
02/16/2022
CLEAN ALL MUD AND GRAVEL FROM STREET AT FRONT OF LOT
Electrical Service Inspection Passed 9/14/2022 9/14/2022 09/14/2022
Gas Service Inspection - Residential Passed 9/14/2022 9/14/2022 09/14/2022
All Rough Inspection - Residential Failed 9/14/2022 9/14/2022 09/14/2022
Misc
Corrective Action Required
09/14/2022
-PFH portal bracing design per plans/IRC R602.10.6.2 at garage, missing top and bottom plate at header per design -top plate corner lap connection as required by code - see garage wall (different wall heights) -toenail all floor joists per code -address overbored floor joist for bath fan exhaust at great room -support plumbing above 1st floor bath -(2) 2x4 trimmer studs garage entry door per plans -(2) 2x4 trimmer studs kitchen entry per plans -seal all top plate penetrations - see master bed -attic access requires 30” vertical clearance -solid block all sheathing breaks -dbl top plate requires min 24” offset between plate breaks, see 2nd floor bed#2 -provide bocca plate at DWV ceiling line 2nd floor bed#2 -all truss hangers per plans 2nd floor -solid block between joists above steel breams at basement -solid block between joists at cantilevers -pex water line above service panel basement -pan off fireplace cantilever at exterior -provide attic ventilation at covered patio
All Rough Inspection - Residential Passed 10/13/2022 10/13/2022 10/13/2022
Misc
Resolved
10/13/2022
Driveway Inspection Passed 10/31/2022 10/31/2022 10/31/2022
Misc
Informational
10/31/2022
On Monday, 10-31-2022 I performed and passed a driveway inspection for concrete placement .
Erosion Control Inspection Residential Failed 11/14/2022 11/14/2022 11/14/2022
Misc
Resolved
11/14/2022
CLEAN ALL MUD AND GRAVEL FROM STREET AT FRONT OF LOT
DCM3 ESC REQUIRED 2 DAY
Corrective Action Required
11/14/2022
EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS. CLEAN MUD FROM STREET
Piers/Caissons Inspection - Residential Passed 01/12/2023
Misc
Informational
01/12/2023
pads poured at time of footing
Erosion Control Inspection Residential Passed 01/12/2023
DCM3 ESC REQUIRED 2 DAY
Resolved
01/12/2023
EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS. CLEAN MUD FROM STREET
Occupancy Inspection - Codes Residential Failed 1/12/2023 1/12/2023 01/12/2023
Misc
Corrective Action Required
01/12/2023
- address shall be contrasting in color - Final grading and sod - Splash blocks - Seal top of light fixtures exterior - Seal top of meter can and A/C disconnect - Guard required East end of front porch over 30” to grade - Uncover smoke alarm - Missing outlet cover in kitchen counter - Outlet in laundry dead
Occupancy Inspection - Codes Residential Full C of O 2/9/2023 2/9/2023 02/09/2023
Misc
Resolved
02/09/2023
- address shall be contrasting in color - Final grading and sod - Splash blocks - Seal top of light fixtures exterior - Seal top of meter can and A/C disconnect
Documents & Images
Date Uploaded File Type Document Name
01/11/2022 CB #15 - PERMIT APPLICATION
01/13/2022 Approved Plans APPROVED DRAWINGS
01/13/2022 Approved Plans APPROVED TRUSS LAYOUT
01/13/2022 Approved Plans APPROVED TRUSS PACKAGE
01/18/2022 Permit Codes Residential Plan Review
01/18/2022 Plot Plan APPROVED PLOT PLAN
01/18/2022 Permit DS Building Permit
01/18/2022 Receipt Receipt for transaction:2022-000297
02/07/2022 Letter INSPECTION SUMMARY
02/07/2022 Letter INSPECTION SUMMARY
02/10/2022 Letter INSPECTION SUMMARY
02/10/2022 Letter INSPECTION SUMMARY
02/10/2022 Letter INSPECTION SUMMARY
02/16/2022 Letter INSPECTION SUMMARY
02/16/2022 Letter INSPECTION SUMMARY
08/29/2022 Strong-Drive® SDWC TRUSS PT3
09/14/2022 Letter INSPECTION SUMMARY
09/14/2022 Letter INSPECTION SUMMARY
09/14/2022 Letter INSPECTION SUMMARY
09/24/2022 CB 15 - Overbored Floor Joist - Engineering Letter
10/13/2022 Letter INSPECTION SUMMARY
10/31/2022 Letter INSPECTION SUMMARY
11/14/2022 Letter INSPECTION SUMMARY
01/12/2023 Letter INSPECTION SUMMARY
01/12/2023 Letter INSPECTION SUMMARY
01/12/2023 Letter INSPECTION SUMMARY
01/12/2023 Letter INSPECTION SUMMARY
02/09/2023 Letter Field Certificate of Occupancy
02/09/2023 Letter Codes Final Certificate of Occupancy
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home