PRRES20216029
Building Permit - Residential
Certificate of Occupancy
CMH PARKS INC
NEW SINGLE FAMILY
NEW HOUSE - FINISHED BASEMENT - COVERED PATIO
11/18/2021
11/22/2021
01/30/2023
Locations
Contacts
CLAYTON PROPERTIES GROUP, INC, Address:120 SE 30TH ST, Phone:(816) 246-6700  
CMH PARKS INC, Address:5000 CLAYTON RD  
Summit Homes, Address:120 SE 30th St, Phone:(816) 434-5074 Ext:320  
UNITED HEATING & COOLING, Address:301 DUCK RD, Phone:(816) 761-5262  
ARROW CIRCLE ELECTRIC, Address:1224 SE CENTURY DR, Phone:(816) 373-4888  
RELIABLE MECHANICAL SERVICES INC, Address:1025 W COUCHMAN DR, Phone:(816) 903-7674  
LOREN@SUMMITHOMESKC.COM  
Reviews

There are no reviews for this permit application.

Fees
Paid Fees Amount Paid Owing Date Paid
Valuation Fee New Single Family $0.00 $0.00 $0.00 N/A
Right of Way Permit Fee $85.00 $85.00 Paid 11/22/2021
Residential Excise Tax Fee $1,077.12 $1,077.12 Paid 11/22/2021
8331507-Sewer Connection Fee $600.00 $600.00 Paid 11/22/2021
Water Tap Fee $3,655.00 $3,655.00 Paid 11/22/2021
Water Meter Fee $479.24 $479.24 Paid 11/22/2021
Not Ready Inspection Fee $50.00 $50.00 Paid 01/17/2023
Not Ready Inspection Fee $75.00 $75.00 Paid 01/17/2023
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Underslab Plumbing Inspection - Residential Passed 1/14/2022 1/14/2022 01/14/2022
01/14/2022
Sewer Service Inspection - R Passed 1/14/2022 (10:15) 1/14/2022 01/14/2022
Footing Inspection - Residential Passed 1/14/2022 01/14/2022
Misc
Informational
01/14/2022
third party inspection performed
Water Service Inspection - R Passed 1/19/2022 (11:00) 1/19/2022 01/19/2022
All Rough Inspection - Residential Not Ready 6/29/2022 6/29/2022 06/29/2022
Misc
Corrective Action Required
06/29/2022
inspection denied provide gravel filter
Gas Service Inspection - Residential Failed 6/29/2022 6/29/2022 06/29/2022
Misc
Corrective Action Required
06/29/2022
inspection denied no gravel filter
Electrical Service Inspection Failed 6/29/2022 6/29/2022 06/29/2022
Misc
Corrective Action Required
06/29/2022
inspection denied no gravel filter
Erosion Control Inspection Residential Failed 6/29/2022 06/29/2022
DCM3 ESC REQUIRED 2 DAY
Corrective Action Required
06/29/2022
EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS. provide gravel filter
Electrical Service Inspection Failed 7/1/2022 7/1/2022 07/01/2022
Misc
Resolved
07/01/2022
inspection denied no gravel filter
Misc
Corrective Action Required
07/01/2022
connect ufer ground to middle grounded bus bar
Gas Service Inspection - Residential Not Ready 7/1/2022 7/1/2022 07/01/2022
Misc
Resolved
07/01/2022
inspection denied no gravel filter
Misc
Corrective Action Required
07/01/2022
complete gas line install for inspection (see fireplace)
All Rough Inspection - Residential Failed 7/1/2022 7/1/2022 07/01/2022
Misc
Resolved
07/01/2022
inspection denied provide gravel filter
Misc
Corrective Action Required
07/01/2022
-install all windows and doors -Seal penetrations from hvac chase into joists space -missing lib bed 1 bath -GT Bearing stud -secure and protect gas line at fire place -complete gas line install at fireplace -cspf nailing at great room windows and slider -missing lib bed 4 -provide attic accesses throughout home as required by code -hgus26-2 hanger missing nails and installed to high. -missing tjc37 in garage -address columns in basement not correct size -fire block furr out wall into furr down in basement see strairs -address over drilled floor joist in unfinished area W wall -provide access to W side of furnace unfinished area -connect ufer ground to middle grounded bus bar
Electrical Service Inspection Passed 7/26/2022 7/26/2022 07/26/2022
Misc
Resolved
07/26/2022
connect ufer ground to middle grounded bus bar
Gas Service Inspection - Residential Passed 7/26/2022 7/26/2022 07/26/2022
Misc
Resolved
07/26/2022
complete gas line install for inspection (see fireplace)
All Rough Inspection - Residential Passed 7/26/2022 7/26/2022 07/26/2022
Misc
Resolved
07/26/2022
-install all windows and doors -Seal penetrations from hvac chase into joists space -missing lib bed 1 bath -GT Bearing stud -secure and protect gas line at fire place -complete gas line install at fireplace -cspf nailing at great room windows and slider -missing lib bed 4 -provide attic accesses throughout home as required by code -hgus26-2 hanger missing nails and installed to high. -missing tjc37 in garage -address columns in basement not correct size -fire block furr out wall into furr down in basement see strairs -address over drilled floor joist in unfinished area W wall -provide access to W side of furnace unfinished area -connect ufer ground to middle grounded bus bar
Driveway Inspection Partial 8/25/2022 8/25/2022 08/25/2022
Misc
Informational
08/25/2022
8-25-22 RH. Drive way was formed up and aggregate was placed and compacted.
Sidewalk Inspection Partial 8/25/2022 08/25/2022
Misc
Informational
08/25/2022
8-25-22 RH. Sidewalk is formed up and aggregate is placed and compacted.
Sidewalk Inspection Partial 8/26/2022 8/26/2022 08/26/2022
Misc
Informational
08/25/2022
8-25-22 RH. Sidewalk is formed up and aggregate is placed and compacted.
Driveway Inspection Passed 9/1/2022 9/1/2022 08/30/2022
Misc
Informational
08/25/2022
8-25-22 RH. Drive way was formed up and aggregate was placed and compacted.
Misc
Informational
08/30/2022
On Tuesday, 8-30-2022 I performed a visual driveway inspection ad found it to meet city standards.
Plot Plan Inspection Passed 11/4/2022 11/04/2022
Piers/Caissons Inspection - Residential Passed 1/17/2023 01/17/2023
Occupancy Inspection - Codes Residential Failed 1/17/2023 1/17/2023 01/17/2023
Misc
Corrective Action Required
01/17/2023
-pay all fees -address pending sidewalk inspection -splash blocks and sump pump discharge to extend 36” from foundation -outlet in entry bath not working -outlets in garage to be GFCI protected If not GFCI protected to be single receptacle and labeled -office and master afci protection at breaker panel -lockouts for all hardwired appliances at panel -spark ring at kitchen and wet bar outlets where as required by code -stairs at rear patio greater than 3/8” difference -spark ring above fireplace -smoke detectors dead battery
Sidewalk Inspection Passed 1/20/2023 1/20/2023 01/20/2023
Misc
Informational
08/26/2022
8-25-22 RH. Sidewalk is formed up and aggregate is placed and compacted. 1-20-23 PS Sidewalk meets ADA and LS Specifications
Erosion Control Inspection Residential Passed 01/30/2023
DCM3 ESC REQUIRED 2 DAY
Resolved
01/30/2023
EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS. provide gravel filter
Occupancy Inspection - Codes Residential Full C of O 1/30/2023 1/30/2023 01/30/2023
Misc
Resolved
01/30/2023
-pay all fees -address pending sidewalk inspection -splash blocks and sump pump discharge to extend 36” from foundation -lockouts for -spark ring at kitchen and wet bar outlets where as required by code -stairs at rear patio greater than 3/8” difference -spark ring above fireplace -smoke detectors dead battery
Documents & Images
Date Uploaded File Type Document Name
11/18/2021 HT #122 - PERMIT APPLICATION
11/19/2021 Permit Codes Residential Plan Review
11/22/2021 Plot Plan Approved Plot Plan
11/22/2021 Approved Plans Approved Drawings
11/22/2021 Approved Plans Approved Truss Layout
11/22/2021 Approved Plans Approved Truss Pacakge
11/22/2021 Permit Codes Residential Plan Review
11/22/2021 Permit DS Building Permit
11/22/2021 Receipt Receipt for transaction:2021-008883
01/10/2022 122 Hawthorne Ridge-FTNG
01/14/2022 Letter INSPECTION SUMMARY
01/14/2022 Letter INSPECTION SUMMARY
01/14/2022 Letter INSPECTION SUMMARY
01/19/2022 Letter INSPECTION SUMMARY
06/08/2022 Letter Codes 140 Day Letter
06/29/2022 Letter INSPECTION SUMMARY
06/29/2022 Letter INSPECTION SUMMARY
06/29/2022 Letter INSPECTION SUMMARY
06/29/2022 Letter INSPECTION SUMMARY
07/01/2022 Letter INSPECTION SUMMARY
07/01/2022 Letter INSPECTION SUMMARY
07/01/2022 Letter INSPECTION SUMMARY
07/26/2022 Letter INSPECTION SUMMARY
07/26/2022 Letter INSPECTION SUMMARY
07/26/2022 Letter INSPECTION SUMMARY
07/26/2022 122 Hawthorne Ridge Letter (002)
08/25/2022 Letter INSPECTION SUMMARY
08/25/2022 Letter INSPECTION SUMMARY
08/26/2022 Letter INSPECTION SUMMARY
08/30/2022 Letter INSPECTION SUMMARY
11/02/2022 Plot Plan Approved As-Graded Plot Plan
01/17/2023 Letter INSPECTION SUMMARY
01/17/2023 Letter INSPECTION SUMMARY
01/17/2023 Letter INSPECTION SUMMARY
01/17/2023 Receipt Receipt for transaction:2023-000279
01/20/2023 Letter INSPECTION SUMMARY
01/30/2023 Letter INSPECTION SUMMARY
01/30/2023 Letter Field Certificate of Occupancy
01/30/2023 Letter Codes Final Certificate of Occupancy
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home