CMH PARKS INC
NEW SINGLE FAMILY
NEW HOUSE - ROOF TRUSSES - UNFINISHED BASEMENT - COVERED DECK STOP WORK ORDER generated on 01/04/2022 12:00 AM by username 'Patrick Schonfeldt'. STOP WORK ORDER removed on 01/05/2022 12:00 AM by username 'Patrick Schonfeldt'.
11/01/2021
11/03/2021
05/05/2023
Locations
Contacts
CLAYTON PROPERTIES GROUP, INC, Address:120 SE 30TH ST, Phone:(816) 246-6700  
CMH PARKS INC, Address:5000 CLAYTON RD  
Summit Homes, Address:120 SE 30th St, Phone:(816) 434-5074 Ext:320  
PERMITTING@SUMMITHOMESKC.COM  
UNITED HEATING & COOLING, Address:301 DUCK RD, Phone:(816) 761-5262  
ARROW CIRCLE ELECTRIC, Address:1224 SE CENTURY DR, Phone:(816) 373-4888  
RELIABLE MECHANICAL SERVICES INC, Address:1025 W COUCHMAN DR, Phone:(816) 903-7674  
Reviews

There are no reviews for this permit application.

Fees
Paid Fees Amount Paid Owing Date Paid
8331504-EFHB Middle Big Creek, Full $602.64 $602.64 Paid 11/03/2021
8331507-Sewer Connection Fee $540.00 $540.00 Paid 11/03/2021
9110073-Right of Way Permit Fee $85.00 $85.00 Paid 11/03/2021
7232302-Residential License Tax Fee $1,077.12 $1,077.12 Paid 11/03/2021
9110078-Valuation Fee New Single Family $1,323.19 $1,323.19 Paid 11/03/2021
8331401-Water Tap Fee $3,655.00 $3,655.00 Paid 11/03/2021
8350015-Water Meter Fee $479.24 $479.24 Paid 11/03/2021
9110080-Not Ready Inspection Fee $50.00 $50.00 Paid 03/21/2023
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Underslab Plumbing Inspection - Residential Not Ready 1/4/2022 1/4/2022 01/04/2022
Misc
Corrective Action Required
01/04/2022
INSPECTION DENIED FOOTING POURED WITHOUT INSPECTION
Footing Inspection - Residential Failed - Stop Work 1/4/2022 1/4/2022 01/04/2022
Misc
Corrective Action Required
01/04/2022
FOOTING POURED WITHOUT INSPECTION, ENGINEER REPORT REQUIRED TO BE UPLOADED TO PERMIT WITHIN 48 HOURS OF INSPECTION
Footing Inspection - Residential Passed 1/5/2022 1/5/2022 01/05/2022
Misc
Informational
01/05/2022
APPROVED PER BRADLEY HUXOL 12/3/21 STOP WORK REMOVED
Underslab Plumbing Inspection - Residential Passed 1/6/2022 1/6/2022 01/06/2022
Misc
Resolved
01/06/2022
INSPECTION DENIED FOOTING POURED WITHOUT INSPECTION
Sewer Service Inspection - R Passed 1/14/2022 (11:30) 1/14/2022 01/14/2022
Water Service Inspection - R Passed 1/19/2022 (1:00) 1/19/2022 01/19/2022
Gas Service Inspection - Residential Passed 7/13/2022 7/13/2022 07/13/2022
Electrical Service Inspection Failed 7/13/2022 7/13/2022 07/13/2022
Misc
Corrective Action Required
07/13/2022
connect ufer ground to middle grounded bus bar.
All Rough Inspection - Residential Failed 7/13/2022 7/13/2022 07/13/2022
Misc
Corrective Action Required
07/13/2022
-pfh at single car garage per plans -add cut joist above garage for dwv and pex, pex lines also drilled to close to each other in this area -complete/address panning in furr down/furr out in garage -fire block E garage wall into furr down -fire block furr out into furr down -block hvac chase into furr down -fix RA panning above fridge -address joist above kitchen drilled for pex holes closer than 2” -solid block under cantilever -address joist hanger install incorrectly kitchen/great room garage wall -hanger for beam above front stoop -install blocking to plans at stairwell front wall , uncover to inspect nailing -gt bearing and hold downs bed 4 closet -protect NM Within 6’ of attic access -fire block basement stairwell wall vertically,horizontally every 10’ -address over drilled joist near egress window in basement -address holes in floor joist drilled to close together near egress window -uncover ufer and connect to middle grounded bus bar -solid blocking under kitchen island to plans
All Rough Inspection - Residential Failed 7/19/2022 7/19/2022 07/19/2022
Misc
Corrective Action Required
07/13/2022
-pfh at single car garage per plans -address return air pan at garage wall to furred down -fire block furr out into furr down, (seal annular spaces around electrical) -block hvac chase into furr down -fix return air pan above fridge -address joist above kitchen drilled for pex holes closer than 2” -address joist hanger install incorrectly kitchen/great room garage wall -hanger for beam above front stoop -gt bearing and hold downs bed 4 closet -stud shoe at master bath exterior stud -address over drilled joist near egress window in basement (PROVIDE ENGINEER LETTER FOR FIELD FIX WITH STRAP) -address holes in floor joist drilled to close together near egress window (BORES LESS THAN 2” APART) -uncover ufer and connect to middle grounded bus bar
Electrical Service Inspection Passed 8/30/2022 8/30/2022 08/30/2022
Misc
Resolved
08/30/2022
All Rough Inspection - Residential Failed 8/30/2022 8/30/2022 08/30/2022
Misc
Corrective Action Required
07/19/2022
-fire block hvac chase into furr down (not complete) -hanger for beam above front stoop (cannot inspect with cover, remove fascia to see beam bearing end) -gt bearing and hold downs bed 4 closet (not complete) -address joist above kitchen drilled for pex holes closer than 2” -address over drilled joist near egress window in basement (PROVIDE ENGINEER LETTER FOR FIELD FIX WITH STRAP) -address holes in floor joist drilled to close together near egress window (BORES LESS THAN 2” APART)
All Rough Inspection - Residential Failed 9/16/2022 9/16/2022 09/16/2022
Misc
Corrective Action Required
08/30/2022
-hanger for beam above front stoop (cannot inspect with cover, remove fascia to see beam bearing end) **OK TO INSULATE**
All Rough Inspection - Residential Passed 9/20/2022 9/20/2022 09/20/2022
Misc
Resolved
09/20/2022
Driveway Inspection Partial 11/9/2022 11/9/2022 11/02/2022
Misc
Informational
11/02/2022
11-2-22 RH. Driveway is formed up and aggregate is placed and compacted. Approved to pour.
Driveway Inspection Passed 11/9/2022 11/09/2022
Misc
Informational
11/02/2022
11-2-22 RH. Driveway is formed up and aggregate is placed and compacted. Approved to pour. 11-9-22 RH. Driveway meets LS specification.
Occupancy Inspection - Codes Residential Failed 3/22/2023 3/22/2023 03/22/2023
Misc
Corrective Action Required
03/22/2023
-no sidewalk inspection contact field -Stair rise from 1st to second floor is over 3/8 difference 7 3/4 steps top step 7 inches -master closet can lights too close to shelves, min 12 inch to edge of fixture -garage stairs over 3/8 difference between top and bottom -seal angled box out in garage -stair rise inconsistent basement stairs -Missing anti-siphon device at basement hose bib -provide inch and a half bearing at landing and deck
Sidewalk Inspection Passed 3/23/2023 03/23/2023
Misc
Informational
03/23/2023
3-23-23 RH. Sidewalk meets LS and ADA specification.
Occupancy Inspection - Codes Residential Failed 4/21/2023 4/21/2023 04/21/2023
Misc
Corrective Action Required
03/22/2023
-Stair rise from 1st to second (wood) floor is over 3/8 difference 7 3/4 steps top step 7 inches -garage stairs over 3/8 difference between top and bottom -basement stair to carpet platform stair riser is over 7 3/4 -seal 2x6 at ceiling in garage -exterior patio door needs 2 three inch screws in each hinge
Erosion Control Inspection Residential Passed 4/21/2023 04/21/2023
Occupancy Inspection - Codes Residential Failed 4/28/2023 4/28/2023 04/28/2023
Misc
Corrective Action Required
04/21/2023
-Stair rise from 1st to second (wood) floor is over 3/8 difference 7 3/4 steps top step 7 inches -basement stair to carpet platform stair riser is over 7 3/4. 04/28/2023 -New carpet that is tacked in place on the second floor at the staircase will not meet code - basement stair to carpet platform will not allow enough room for proper foot tread
Plot Plan Inspection Passed 5/5/2023 05/05/2023
Occupancy Inspection - Codes Residential Full C of O 5/5/2023 5/5/2023 05/05/2023
Misc
Resolved
05/05/2023
-Stair rise from 1st to second (wood) floor is over 3/8 difference 7 3/4 steps top step 7 inches -basement stair to carpet platform stair riser is over 7 3/4. 04/28/2023 -New carpet that is tacked in place on the second floor at the staircase will not meet code - basement stair to carpet platform will not allow enough room for proper foot tread
Documents & Images
Date Uploaded File Type Document Name
11/01/2021 MN #110 - PERMIT APP
11/01/2021 Approved Plans approved plans
11/01/2021 Approved Plans APPROVED TRUSS LAYOUT
11/01/2021 Approved Plans APPROVED TRUSS PACKAGE
11/01/2021 Plot Plan APPROVED PLOT PLAN
11/03/2021 Permit Codes Residential Plan Review
11/03/2021 Permit DS Building Permit
11/03/2021 Receipt Receipt for transaction:2021-008487
01/04/2022 Letter INSPECTION SUMMARY
01/04/2022 Letter Stop Work Order
01/04/2022 110 Manor at Stoney Creek-FTNG
01/05/2022 Letter INSPECTION SUMMARY
01/06/2022 Letter INSPECTION SUMMARY
01/14/2022 Letter INSPECTION SUMMARY
01/19/2022 Letter INSPECTION SUMMARY
07/13/2022 Letter INSPECTION SUMMARY
07/13/2022 Letter INSPECTION SUMMARY
07/13/2022 Letter INSPECTION SUMMARY
07/19/2022 Letter INSPECTION SUMMARY
08/30/2022 Letter INSPECTION SUMMARY
08/30/2022 Letter INSPECTION SUMMARY
09/13/2022 110 Manor at Stoney Creek letter
09/16/2022 Letter INSPECTION SUMMARY
09/20/2022 Letter INSPECTION SUMMARY
11/02/2022 Letter INSPECTION SUMMARY
11/09/2022 Letter INSPECTION SUMMARY
03/21/2023 Receipt Receipt for transaction:2023-001585
03/22/2023 Letter INSPECTION SUMMARY
03/23/2023 Letter INSPECTION SUMMARY
04/21/2023 Letter INSPECTION SUMMARY
04/21/2023 Letter INSPECTION SUMMARY
04/28/2023 Letter INSPECTION SUMMARY
05/05/2023 Letter INSPECTION SUMMARY
05/05/2023 Letter Codes Final Certificate of Occupancy
05/05/2023 Letter Field Certificate of Occupancy
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home