Permit Application Status

PRRES20212005


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PRRES20212005
Building Permit - Residential
Certificate of Occupancy
NEW SINGLE FAMILY
NEW HOUSE - FININISHED AND UNFINISHED BASEMENT - COVERED PATIO
04/26/2021
06/29/2021
10/27/2021
12/29/2023
Locations
Contacts
SPELLERBERG ENTERPRISES LLC, Address:613 NE VIEWPARK DR, Phone:(816) 550-5535  
SPELLERBERGENTERPRISES@GMAIL.COM  
AFC HEATING AND COOLING, Address:824 NW MAIN ST , Phone:(816) 347-8388  
NEW HEIGHTS ELECTRIC LLC, Address:P O BOX 163, Phone:(816) 625-9504  
TRI-COUNTY PLUMBING LLC, Address:PO BOX 234, Phone:(816) 720-3222  
Reviews
Review Type Outcome Est. Completion Date Completed
Residential Plan Review Approved 05/04/2021 05/06/2021
Brandon Kalwei
14 Identify roof covering material (IRC Section R905)
Corrective Action Required
04/30/2021

Identify roof covering material (IRC Section R905)
Misc
Corrective Action Required
04/30/2021

plans show SE Carter St. needs to be SE Carter Rd.
Plot Plan Review Approved 05/04/2021 04/30/2021
Brandon Kalwei
Rear yard dimension
Corrective Action Required
04/30/2021

The rear yard demision(s) must be provided on the plot plan. need to show covered patio that is on house plans with rear yard dimensions to it
Deck location
Corrective Action Required
04/30/2021

Deck location, with dimensions to property lines must be provided on the plot plan. need to show covered patio that is on house plans.
Basement opening elevations
Corrective Action Required
04/30/2021

Minimum Building Opening Elevation (MBOE) and location on structure must be provided on the plot plan.
As-graded plot plan
Corrective Action Required
04/30/2021

A as-graded plot plan per Section 7-160, Code of Ordinances, is required prior to occupancy.
Plot Plan Review Rejected 04/28/2021 04/26/2021
Brandon Kalwei
Rear yard dimension
Corrective Action Required
04/26/2021

The rear yard demision(s) must be provided on the plot plan. need to show covered patio that is on house plans with rear yard dimensions to it
Deck location
Corrective Action Required
04/26/2021

Deck location, with dimensions to property lines must be provided on the plot plan. need to show covered patio that is on house plans.
Basement opening elevations
Corrective Action Required
04/26/2021

Minimum Building Opening Elevation (MBOE) and location on structure must be provided on the plot plan.
As-graded plot plan
Corrective Action Required
04/26/2021

A as-graded plot plan per Section 7-160, Code of Ordinances, is required prior to occupancy.
Residential Plan Review Rejected 04/28/2021 04/26/2021
Brandon Kalwei
14 Identify roof covering material (IRC Section R905)
Corrective Action Required
04/26/2021

Identify roof covering material (IRC Section R905)
Misc
Corrective Action Required
04/26/2021

plans show SE Carter St. needs to be SE Carter Rd.
Fees
Paid Fees Amount Paid Owing Date Paid
9110078-Valuation Fee New Single Family $1,348.30 $1,348.30 Paid 06/29/2021
8331507-Sewer Connection Fee $540.00 $540.00 Paid 06/29/2021
9110073-Right of Way Permit Fee $80.00 $80.00 Paid 06/29/2021
7232302-Residential Excise Tax Fee $1,077.12 $1,077.12 Paid 06/29/2021
8331401-Water Tap Fee $3,581.00 $3,581.00 Paid 06/29/2021
8350015-Water Meter Fee $455.54 $455.54 Paid 06/29/2021
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Footing Inspection - Residential Passed 8/6/2021 (11:00) 8/6/2021 08/06/2021
Sewer Service Inspection - R Passed 9/21/2021 (1:00) 9/21/2021 09/21/2021
Water Service Inspection - R Passed 9/22/2021 (1:00) 9/22/2021 09/22/2021
Underslab Plumbing Inspection - Residential Passed 10/6/2021 10/6/2021 10/06/2021
Piers/Caissons Inspection - Residential Passed 1/14/2022 (8:00) 1/14/2022 01/14/2022
Electrical Service Inspection Passed 5/13/2022 5/13/2022 05/13/2022
Gas Service Inspection - Residential Failed 5/13/2022 5/13/2022 05/13/2022
Misc
Corrective Action Required
05/13/2022
GAS PRESSURE 0 PSI, MUST MAINTAIN 10 PSI FOR TEST
All Rough Inspection - Residential Failed 5/13/2022 5/13/2022 05/13/2022
Misc
Corrective Action Required
05/13/2022
-provide anchor bolts within 12” of plate breaks - see garage -support hips -fur out garage wall HVAC to allow for insulation -min 24” lap between top plate breaks- see garage wall -Fireblock deadspace next to pantry door -12” oc nailing all abutting and intersecting corners -seal all top plate penetrations- see pantry, great room, 2nd floor bathroom -fireblock fireplace lid -address header at great room overbored for DWV and bores less than 2” apart -address hips landing on blocks, amount of taper cut for hips from 2x10 hip -address hip and dbl joist notched master bath -protect NM within 6’ of attic entry -min (2) nails each top and bottom plate LIB straps -provide joist hanger ceiling to header 2nd floor bedroom closet -provide structural straps at top plate bored 50% or more load bearing wall -(2) 2x12 header master bedroom windows per plans -nail joist hanger basement header above furnace -nail 3” oc grid pattern dining room exterior sheathing CS-PF per plans/IRC R602.10.6.4 -Gas pressure 0 psi
Erosion Control Inspection Residential Partial 5/13/2022 05/13/2022
Gas Service Inspection - Residential Passed 5/23/2022 5/23/2022 05/23/2022
Misc
Resolved
05/23/2022
GAS PRESSURE 0 PSI, MUST MAINTAIN 10 PSI FOR TEST
All Rough Inspection - Residential Failed 5/23/2022 5/23/2022 05/23/2022
Misc
Corrective Action Required
05/13/2022
-address hips landing on blocks, amount of taper cut for hips from 2x10 hip,address hip and dbl joist notched master bath Have engineer address field fix for hips **OK TO INSULATE**
Erosion Control Inspection Residential Partial 05/23/2022
All Rough Inspection - Residential Passed 5/31/2022 5/31/2022 05/31/2022
Misc
Resolved
05/31/2022
-address hips landing on blocks, amount of taper cut for hips from 2x10 hip,address hip and dbl joist notched master bath Have engineer address field fix for hips **OK TO INSULATE**
Driveway Inspection Passed 8/25/2022 8/25/2022 08/24/2022
Misc
Informational
08/24/2022
On Wednesday 8-24-2022. I performed and passed a driveway for concrete placement at this address.
Sidewalk Inspection Partial 9/9/2022 9/9/2022 09/09/2022
Misc
Informational
09/09/2022
9-9-22 RH. Sidewalk is formed up and aggregate placed and compacted.
Plot Plan Inspection Failed 10/4/2022 10/04/2022
Misc
Corrective Action Required
10/04/2022
- Lower water meter pit and maintain meter height 14"-18" below lid.
Erosion Control Inspection Residential Failed 11/14/2022 11/14/2022 11/14/2022
DCM1 ESC REQUIRED NO FURTHER INSP
Corrective Action Required
11/14/2022
EROSION CONTROL REQUIRED. NO FURTHER INSPECTIONS WILL BE PERFORMED UNTIL EROSION CONTROL IS INSTALLED AND IN COMPLIANCE.
Erosion Control Inspection Residential Failed 3/9/2023 3/9/2023 03/09/2023
DCM1 ESC REQUIRED NO FURTHER INSP
Corrective Action Required
11/14/2022
EROSION CONTROL REQUIRED. NO FURTHER INSPECTIONS WILL BE PERFORMED UNTIL EROSION CONTROL IS INSTALLED AND IN COMPLIANCE. EROSION CONTROL REQUIRED TO BE WITHIN COMPLAINCE UNTIL SOD IS PLACED
Occupancy Inspection - Codes Residential Failed 5/1/2023 5/1/2023 05/01/2023
Misc
Informational
05/01/2023
Canceled do to wood floor being sanded for finish
Occupancy Inspection - Codes Residential Failed 5/2/2023 5/2/2023 05/02/2023
Misc
Corrective Action Required
05/02/2023
-Front porch electrical outlet is not GFCI protected -oven vent hood is not installed -wood above garage doors need to be sealed -electrical outlet for water sprinkler needs to state it is non GFCI protected -basement stair landing to first carpeted step riser is 6 5/8 the next step riser is 7 1/4 which does not meet code (IBC 1011.5.4) -sump pump electrical outlet needs to state it is non GFCI protected -irrigation permit needs to be obtained -splash pads are not installed -sump pump discharge needs to extend out at least 36 inches from the foundation -sidewalk inspection pending at the time of this inspection (9:35am)
Erosion Control Inspection Residential Passed 5/2/2023 05/02/2023
DCM1 ESC REQUIRED NO FURTHER INSP
Resolved
05/02/2023
EROSION CONTROL REQUIRED. NO FURTHER INSPECTIONS WILL BE PERFORMED UNTIL EROSION CONTROL IS INSTALLED AND IN COMPLIANCE. EROSION CONTROL REQUIRED TO BE WITHIN COMPLAINCE UNTIL SOD IS PLACED
Plot Plan Inspection Passed 5/2/2023 05/02/2023
Misc
Resolved
05/02/2023
- Lower water meter pit and maintain meter height 14"-18" below lid.
Occupancy Inspection - Codes Residential Failed 5/5/2023 5/5/2023 05/05/2023
Misc
Corrective Action Required
05/02/2023
-Front porch electrical outlet is not GFCI protected -wood penetrations above interior garage doors need to be sealed -not all splash pads are not installed -sidewalk inspection pending at the time of this inspection (9:35am) 05/02/2023 -sidewalk inspection is still pending (05/05/2023)
Sidewalk Inspection Failed 5/5/2023 5/5/2023 05/05/2023
Misc
Informational
09/09/2022
9-9-22 RH. Sidewalk is formed up and aggregate placed and compacted. 5-5-23 PS Final sidewalk inspection is failed, there is a cracked sidewalk panel at last panel on east side of lot that will need to be replaced. Apply white cure evenly across entire sidewalk surface as required by LS specifications
Occupancy Inspection - Codes Residential Temporary C of O 5/8/2023 5/8/2023 05/08/2023
Misc
Partial Correction
05/08/2023
-sidewalk inspection pending at the time of this inspection (9:35am) 05/02/2023 -sidewalk inspection is still pending (05/05/2023)
Sidewalk Inspection Partial 7/17/2023 7/17/2023 07/17/2023
Misc
Informational
05/05/2023
9-9-22 RH. Sidewalk is formed up and aggregate placed and compacted. 5-5-23 PS Final sidewalk inspection is failed, there is a cracked sidewalk panel at last panel on east side of lot that will need to be replaced. Apply white cure evenly across entire sidewalk surface as required by LS specifications 7-17-23 PS Performed pore pour inspection for replacement panel that was cracked on east end of lot. OK to pour replacement panel.
Sidewalk Inspection Passed 8/11/2023 8/11/2023 08/11/2023
Misc
Informational
07/17/2023
9-9-22 RH. Sidewalk is formed up and aggregate placed and compacted. 5-5-23 PS Final sidewalk inspection is failed, there is a cracked sidewalk panel at last panel on east side of lot that will need to be replaced. Apply white cure evenly across entire sidewalk surface as required by LS specifications 7-17-23 PS Performed pore pour inspection for replacement panel that was cracked on east end of lot. OK to pour replacement panel. 8-11-23 PS Cracked panel has been replaced. Sidewalk meets ADA and LS specs
Occupancy Inspection - Codes Residential Full C of O 12/29/2023 12/29/2023
Misc
Resolved
12/29/2023
-sidewalk inspection pending at the time of this inspection (9:35am) 05/02/2023 -sidewalk inspection is still pending (05/05/2023)
Documents & Images
Date Uploaded File Type Document Name
04/26/2021 Application Form APPLICATION
04/26/2021 24 Cobey Creek Staked
04/26/2021 Letter Codes Residential Plan Review
04/30/2021 24 Cobey Creek Revised MBOE
04/30/2021 Plot Plan APPROVED PLOT PLAN
06/29/2021 Permit DS Building Permit
06/29/2021 Receipt Receipt for transaction:2021-005123
08/06/2021 Letter INSPECTION SUMMARY
09/21/2021 Letter INSPECTION SUMMARY
09/22/2021 Letter INSPECTION SUMMARY
10/06/2021 Letter INSPECTION SUMMARY
10/14/2021 Approved Plans approved plans
01/14/2022 Letter INSPECTION SUMMARY
05/13/2022 Letter INSPECTION SUMMARY
05/13/2022 Letter INSPECTION SUMMARY
05/13/2022 Letter INSPECTION SUMMARY
05/13/2022 Letter INSPECTION SUMMARY
05/23/2022 Letter INSPECTION SUMMARY
05/23/2022 Letter INSPECTION SUMMARY
05/23/2022 Letter INSPECTION SUMMARY
05/26/2022 Spellerberg 516 Carter R-I
05/31/2022 Letter INSPECTION SUMMARY
09/09/2022 Letter INSPECTION SUMMARY
10/03/2022 Plot Plan APPROVED AS GRADED PLOT PLAN
10/04/2022 Letter INSPECTION SUMMARY
11/14/2022 Letter INSPECTION SUMMARY
03/09/2023 Letter INSPECTION SUMMARY
03/09/2023 Letter INSPECTION SUMMARY
05/01/2023 Letter INSPECTION SUMMARY
05/02/2023 Letter INSPECTION SUMMARY
05/02/2023 Letter INSPECTION SUMMARY
05/02/2023 Letter INSPECTION SUMMARY
05/05/2023 Letter INSPECTION SUMMARY
05/05/2023 Letter INSPECTION SUMMARY
05/08/2023 Certificate/License Codes Temporary Certificate of Occupancy
07/17/2023 Letter INSPECTION SUMMARY
08/11/2023 Letter INSPECTION SUMMARY
12/29/2023 Letter Codes Final Certificate of Occupancy
12/29/2023 Letter Field Certificate of Occupancy
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home