Summary
PRRES20201933
Building Permit - Residential
Final Completion
SPEAKE ROGER L & SHEILA R
ALTERATION SINGLE FAMILY
BASEMENT FINISH HOMEOWNER DOING THE WORK
07/14/2020
07/14/2020
12/30/2020
Locations
Contacts
SPEAKE ROGER L & SHEILA R, Address:1313 NE BRANDYWINE DR  
sheila.speake@usengineering.com  
Reviews
Review Type Outcome Est. Completion Date Completed
Licensed Contractors Approved 07/14/2020 07/14/2020
Kim Brennan
Fees
Paid Fees Amount Paid Owing Date Paid
Valuation Fee for Add/Alter Single Family $116.76 $116.76 Paid 07/14/2020
8331507-Sewer Connection Fee $30.00 $30.00 Paid 07/14/2020
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
All Rough Inspection - Residential Failed 8/27/2020 8/27/2020 08/27/2020
Misc
Corrective Action Required
08/27/2020
Fb wall vertically at max ten ft interval -Complete wiring makeup inside boxes -Install BOCA plate for plumbing protection at bottom and top wall plates in bathroom -Provide a 20-amp circuit for receptacle in bathroom -Staple wiring min 1.25 above bottom of joist; protect wiring where within 1.25” of joist bottom **OK TO INSULATE
Underslab Plumbing Inspection - Residential Passed 8/27/2020 8/27/2020 08/27/2020
All Rough Inspection - Residential Partial 9/1/2020 9/1/2020 at 9:00 AM 09/01/2020
Misc
Corrective Action Required
08/27/2020
-Complete wiring makeup inside boxes **REMOVE ALL FACEPLATES AND DEVICES OUT OF BOXES FOR INSPECTION AT FINAL **OK TO ROCK
Final Inspection - Residential Failed 11/24/2020 (7:00AM to 4:00PM) 11/24/2020 11/24/2020
Miscellaneous Correction
Corrective Action Required
11/24/2020
-Install cover plate on receptacles and switches, install pendant lights -Provide AFCI protection per E3902.16
All Rough Inspection - Residential Passed 12/30/2020
Misc
Resolved
12/30/2020
-Complete wiring makeup inside boxes **REMOVE ALL FACEPLATES AND DEVICES OUT OF BOXES FOR INSPECTION AT FINAL **OK TO ROCK
Final Inspection - Residential Passed 12/30/2020 (7:00AM to 4:00PM) 12/30/2020 12/30/2020
Miscellaneous Correction
Resolved
12/30/2020
-Install cover plate on receptacles and switches, install pendant lights -Provide AFCI protection per E3902.16
Documents & Images
Date Uploaded File Type Document Name
07/14/2020 Scope of Work Scope of Work
07/14/2020 Receipt Receipt for transaction:2020-004424
07/14/2020 Letter DS Building Permit
07/15/2020 Letter DS Building Permit
08/27/2020 Letter INSPECTION SUMMARY
08/27/2020 Letter INSPECTION SUMMARY
09/01/2020 Letter INSPECTION SUMMARY
11/24/2020 Letter INSPECTION SUMMARY
12/30/2020 Letter INSPECTION SUMMARY
12/30/2020 Letter INSPECTION SUMMARY
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home