Summary
PRRES20190046
Building Permit - Residential
Certificate of Occupancy
NEW SINGLE FAMILY
NEW HOUSE - FINISHED BASEMENT - COVERED DECK
01/09/2019
01/17/2019
02/26/2020
Locations
Contacts
JFE CONSTRUCTION INC, Address:1314 SW MARKET ST, Phone:(816) 470-0074  
A & D HEATING AND COOLING INC, Address:2006 W MAIN ST, Phone:(816) 537-7952  
MOOSE ELECTRICAL CONSTRUCTION LLC, Address:105 HARLEQUIN DR, Phone:(816) 682-2693  
MILLER PLUMBING CO, Address:PO BOX 393 , Phone:(913) 851-1333  
CORY@JFECONSTRUCTION.COM  
Reviews
Review Type Outcome Est. Completion Date Completed
Plot Plan Review Approved 01/11/2019 01/15/2019
Steve Conrick
City infrustructure
Corrective Action Required
01/15/2019

Show all manholes, water valve boxes, fire hydrants, and stormwater structures. ***The top elevation of the MH is different that what the adjacent plot plan and as-built show***
Lot elevations
Corrective Action Required
01/15/2019

Existing and finish elevations at all property corners must be provided on the plot plan.
Residential Plan Review Approved 01/11/2019 01/15/2019
Kim Brennan
24 Concrete reinforcement size and spacing.
Corrective Action Required
01/09/2019

Concrete reinforcement size and spacing for the suspended slab
25 Concrete thickness.
Corrective Action Required
01/09/2019

Concrete thickness for the suspended slab
26 Concrete minimum compressive strength.
Corrective Action Required
01/09/2019

Concrete minimum compressive strength. (IRC Section 402.2) for the suspended slab
Fees
Paid Fees Amount Paid Owing Date Paid
9110078-Valuation Fee New Single Family $1,195.77 $1,195.77 Paid 01/17/2019
9110073-Right of Way Permit Fee $80.00 $80.00 Paid 01/17/2019
8331507-Sewer Connection Fee $540.00 $540.00 Paid 01/17/2019
8331401-Water Tap Fee $3,409.00 $3,409.00 Paid 01/17/2019
8350015-Water Meter Fee $408.37 $408.37 Paid 01/17/2019
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Footing Inspection - Residential Passed 2/13/2019 (11:30) 2/13/2019 at 11:30 AM 02/13/2019
Underslab Plumbing Inspection - Residential Passed 3/5/2019 3/5/2019 at 8:55 AM 03/05/2019
Sewer Service Inspection - R Passed 3/11/2019 3/11/2019 at 8:25 AM 03/11/2019
Water Service Inspection - R Partial 3/11/2019 03/11/2019
Piers/Caissons Inspection - Residential Failed 4/2/2019 (8:00) 4/2/2019 04/02/2019
Misc
Corrective Action Required
04/02/2019
Piers need to be 36” deep, no stamped plan on site
Piers/Caissons Inspection - Residential Passed 4/3/2019 4/3/2019 04/03/2019
Misc
Corrective Action Required
04/02/2019
Piers need to be 36” deep, no stamped plan on site
Rough Framing Inspection - Residential Passed 4/9/2019 4/9/2019 at 8:30 AM 04/09/2019
Informational
04/09/2019
GARAGE PORTAL FRAMING OK
Water Service Inspection - R Passed 4/17/2019 (8:15) 4/17/2019 04/17/2019
Gas Service Inspection - Residential Passed 5/30/2019 05/30/2019
Electrical Service Inspection Failed 5/30/2019 05/30/2019
Misc
Corrective Action Required
05/30/2019
-Install grounding clamp listed for aluminum conductor
All Rough Inspection - Residential Failed 5/30/2019 05/30/2019
Misc
Corrective Action Required
05/30/2019
FRAMING: -Install trim and flashing above window -Complete Install windows above slide door -Fb the b-vent chase from roof; Fb fireplace space; Fb shower wall from roof; Fb wall from joist space at basement shared bathroom ; Fb at top of vertical Fireblock; Fb basement wall from soffit -Nail great room ceiling beam hanger near I beam -Support over notched bottom of valley rafter in garage -Solidblock under garage I beam point load -Support lvl beam at stair wall (shim gap) MECHANICAL: -Seal return air space below fireplace **OK TO INSULATE
Electrical Service Inspection Passed 6/5/2019 6/5/2019 06/05/2019
Misc
Resolved
06/05/2019
-Install grounding clamp listed for aluminum conductor
All Rough Inspection - Residential Failed 6/5/2019 6/5/2019 at 1:10 PM 06/05/2019
Misc
Corrective Action Required
05/30/2019
-Fb the b-vent chase from roof **need min 1" clearance from b-vent to OSB Fb basement wall from soffit **get some insulation and pack in the opening at wall-to-furdown intersection at rear basement bedroom and at rear wall of basement recreation rm -Support lvl beam at stair wall (shim gap) **protect the electrical wire below **OK TO INSULATE
All Rough Inspection - Residential Passed 6/10/2019 6/10/2019 at 8:55 AM 06/10/2019
Misc
Resolved
06/10/2019
-Fb the b-vent chase from roof **need min 1" clearance from b-vent to OSB Fb basement wall from soffit **get some insulation and pack in the opening at wall-to-furdown intersection at rear basement bedroom and at rear wall of basement recreation rm -Support lvl beam at stair wall (shim gap) **protect the electrical wire below **OK TO INSULATE
Driveway Inspection Partial 7/3/2019 (P.M.) 7/3/2019 07/03/2019
Informational
07/03/2019
Driveway forms and materials passed pre-inspection .
Sidewalk Inspection Partial 7/3/2019 7/3/2019 07/03/2019
Informational
07/03/2019
Sidewalk forms and materials passed pre-inspection .
Occupancy Inspection - Codes Residential Failed 9/10/2019 9/10/2019 at 7:30 AM 09/10/2019
Misc
Corrective Action Required
09/10/2019
-Driveway and sidewalk not approved on record -Obtain lawn irrigation permit and submit to the city the valve test report -Sewer manhole at front corner of lot is buried -Final grade, sod, splashblocks -Clean out travel&mud from storm inlet -Seal exterior lights -Front entry light fixtures do not meet security code -Pendant light not allowed within master bathroom tub zone -Provide access to basement storage -Remove foundation wall ties in mechanical space
Erosion Control Inspection Residential Passed 9/10/2019 09/10/2019
Informational
09/10/2019
EROSION CONTROL IS IN COMPLIANCE. MAINTAIN UNTIL SODDING
Driveway Inspection Passed 9/12/2019 09/12/2019
Misc
Informational
09/12/2019
Driveway has passed inspection.
Sidewalk Inspection Passed 9/12/2019 09/12/2019
Misc
Informational
09/12/2019
Sidewalk has passed inspeciton.
Occupancy Inspection - Codes Residential Full C of O 2/26/2020 2/26/2020 at 8:35 AM 02/26/2020
Misc
Resolved
02/26/2020
-Sewer manhole at front corner of lot is buried -Final grade, sod, splashblocks -Clean out travel&mud from storm inlet -Seal exterior lights -Front entry light fixtures do not meet security code -Pendant light not allowed within master bathroom tub zone -Provide access to basement storage -Remove foundation wall ties in mechanical space
Documents & Images
Date Uploaded File Type Document Name
01/09/2019 Letter Codes Residential Plan Review
01/17/2019 Receipt Receipt for transaction: 2019-000187
01/17/2019 Letter Codes Building Permit
01/22/2019 Drawing DOC011819-01182019094745
01/22/2019 Plot Plan DOC011819-01182019094759
02/13/2019 Letter INSPECTION SUMMARY
03/05/2019 Letter INSPECTION SUMMARY
03/11/2019 Letter INSPECTION SUMMARY
03/11/2019 Letter INSPECTION SUMMARY
04/02/2019 Letter INSPECTION SUMMARY
04/02/2019 Letter INSPECTION SUMMARY
04/03/2019 Letter INSPECTION SUMMARY
04/09/2019 Letter INSPECTION SUMMARY
04/17/2019 Letter INSPECTION SUMMARY
05/30/2019 Letter INSPECTION SUMMARY
05/30/2019 Letter INSPECTION SUMMARY
05/30/2019 Letter INSPECTION SUMMARY
06/05/2019 Letter INSPECTION SUMMARY
06/05/2019 Letter INSPECTION SUMMARY
06/10/2019 Letter INSPECTION SUMMARY
07/03/2019 Letter DE-Daily Inspection Summary
09/10/2019 Letter INSPECTION SUMMARY
09/10/2019 Letter INSPECTION SUMMARY
09/12/2019 Letter DE-Daily Inspection Summary
09/12/2019 Letter DE-Daily Inspection Summary
02/26/2020 Letter Codes Final Certificate of Occupancy
02/26/2020 Letter Field Certificate of Occupancy
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide: