Permit Application Status

PRRES20181743


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PRRES20181743
Building Permit - Residential
Certificate of Occupancy
BRIAN CHANEY CONSTRUCTION LLC
NEW SINGLE FAMILY
NEW HOUSE FINISHED AND UNFINISHED BASEMENT COVERED DECK
06/07/2018
06/12/2018
04/30/2020
Locations
Contacts
BRIAN CHANEY CONSTRUCTION LLC, Address:2254 MILAM RD  
BRIAN CHANEY CONSTRUCTION, LLC, Address:PO BOX 646, Phone:(816) 838-0821  
MIDWEST HEATING COOLING & PLUMBING, Address:13228 HOLMES RD, Phone:(816) 943-8513  
O'CONNELL ELECTRIC LLC, Address:11017 S ALLEY JACKSON RD, Phone:(816) 547-4706  
LRW PLUMBING LLC, Address:20631 W 319TH ST, Phone:(913) 568-7737  
Reviews
Review Type Outcome Est. Completion Date Completed
Plot Plan Review Approved 06/11/2018 06/11/2018
Steve Conrick
Spot elevations
Corrective Action Required
06/08/2018

Spot elevations and/or drainage flow arrows shall be provided throughout the lot. ***Please provide contours***
Basement opening elevations
Corrective Action Required
06/08/2018

Minimum Building Opening Elevation (MBOE) and location on structure must be provided on the plot plan. ***The plat lists an MBOE. Please provide it on the plot plan***
Basement egress
Corrective Action Required
06/08/2018

Basement egress location(s) and elevation of the lowest adjacent grade must be provided on the plot plan. ***Give walk out elevation***
Residential Plan Review Approved 06/11/2018 06/07/2018
Brandon Kalwei
Fees
Paid Fees Amount Paid Owing Date Paid
Valuation Fee New Single Family $869.31 $869.31 Paid 06/12/2018
Right of Way Permit Fee $75.00 $75.00 Paid 06/12/2018
8331507-Sewer Connection Fee $390.00 $390.00 Paid 06/12/2018
Water Tap Fee $3,343.00 $3,343.00 Paid 06/12/2018
Water Meter Fee $431.83 $431.83 Paid 06/12/2018
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Footing Inspection - Residential Passed 6/15/2018 (11:00) 6/15/2018 at 10:50 AM 06/15/2018
Underslab Plumbing Inspection - Residential Passed 7/11/2018 7/11/2018 at 9:30 AM 07/11/2018
Erosion Control Inspection Residential Failed 7/26/2018 07/26/2018
DCM2 ESC DEFICIENT INSTALLATION
Corrective Action Required
07/26/2018
DEFICIENT EROSION CONTROL INSTALLATION. NO FURTHER INSPECTIONS UNTIL ADEQUATE EROSION CONTROL PROVIDED.
Piers/Caissons Inspection - Residential Passed 7/26/2018 7/26/2018 at 9:25 AM 07/26/2018
Water Service Inspection - R Partial 9/19/2018 (1:00) 9/18/2018 at 1:20 PM 09/18/2018
Water Service Inspection - R Passed 9/19/2018 9/19/2018 at 9:20 AM 09/19/2018
Erosion Control Inspection Residential Failed 9/19/2018 09/19/2018
DCM2 ESC DEFICIENT INSTALLATION
Corrective Action Required
07/26/2018
DEFICIENT EROSION CONTROL INSTALLATION. NO FURTHER INSPECTIONS UNTIL ADEQUATE EROSION CONTROL PROVIDED.
Sewer Service Inspection - R Passed 9/19/2018 at 1:40 PM 09/19/2018
All Rough Inspection - Residential Failed 9/25/2018 9/25/2018 at 10:00 AM 09/25/2018
Misc
Corrective Action Required
09/25/2018
FRAMING: -Brace 16” lvl bearing end from rotation -Install support device at triple lvl connection per plan -Install support for bottom of hip rafter at front bedroom; move valley support strut to bearing wall -Fb plumbing space at front bathroom -Install security blocking for basement exterior door -Provide a middle pier support for deck beam -Install missing stud outside basement bedrooms -Fb basement wall space from ceiling space -Install interior wall bracing per plan -Strap CSPF wall at rear dining and entry per plan; nail sheathing per plan PLUMBING: -Protect plumbing throughout per code; install stud shoe at studs bored more than 60% width for non-bearing and 40% for bearing -Slope attic vent toward drain -Install tubs and complete all plumbing -Vent 2” shower trap within 8 ft of trap weir -Support DVW no farther than 4 ft ELECTRICAL: -Protect wiring running across bottom of joists near panel -Secure SE cable within 12” of panel -Bond gas piping -Reinstall electrical wiring outside basement bedrooms **OK TO INSULATE
Electrical Service Inspection Passed 9/25/2018 9/25/2018 09/25/2018
Gas Service Inspection - Residential Passed 9/25/2018 9/25/2018 09/25/2018
All Rough Inspection - Residential Failed 10/1/2018 10/1/2018 at 8:55 AM 10/01/2018
Misc
Corrective Action Required
09/25/2018
FRAMING: -Install support device at triple lvl connection per plan **You must support the triple 18" lvl beam to the double 16" lvl -Install support for bottom of hip rafter at front bedroom; move valley support strut to bearing wall **see roof support page of the plan -Provide a middle pier support for deck beam **check later. -Install interior wall bracing per plan -Strap CSPF wall at rear dining and entry per plan; nail sheathing per plan **OK TO INSULATE
All Rough Inspection - Residential Failed 10/3/2018 10/3/2018 at 9:05 AM 10/03/2018
Misc
Corrective Action Required
10/01/2018
-Strap CSPF wall at rear dining and entry per plan; nail sheathing per plan **PLEASE LOOK AT PAGE D4 OF THE PLAN. THE PICTURE DETAIL SHOWS EXACTLY HOW THE CS-PF IS FRAMED. SEE HOW THE STRAPS EXTEND ALL THE WAY TO THE TOP PLATES? ALSO NOTICE THE LOCATION OF THE STRAPS? IT'S ON THE INNDER SIDE NEXT TO THE WINDOW. SEE THE NAILING PATTERN?
All Rough Inspection - Residential Passed 10/4/2018 10/4/2018 at 10:00 AM 10/04/2018
Misc
Resolved
10/04/2018
-Strap CSPF wall at rear dining and entry per plan; nail sheathing per plan
Driveway Inspection Partial 10/23/2018 10/23/2018 at 3:15 PM 10/24/2018
Misc
Corrective Action Required
10/24/2018
Forms and aggregate were in place and meets spec
Driveway Inspection Passed 11/7/2018 11/08/2018
Misc
Corrective Action Required
10/24/2018
Forms and aggregate were in place and meets spec
Informational
11/08/2018
Contractor installed driveway in accordance spec.
Erosion Control Inspection Residential Passed 04/24/2020
DCM2 ESC DEFICIENT INSTALLATION
Resolved
04/24/2020
DEFICIENT EROSION CONTROL INSTALLATION. NO FURTHER INSPECTIONS UNTIL ADEQUATE EROSION CONTROL PROVIDED.
Occupancy Inspection - Codes Residential Failed 4/24/2020 4/24/2020 at 8:30 AM 04/24/2020
Misc
Corrective Action Required
04/24/2020
-Install tamper-proof caps at AC valves -Graspable handrail required for garage stair -Garage door not self closing -Install box extensions for switch & receptacle boxes recessed more than 1/4” behind kitchen and wet bar countertop backsplash -Hammer arrestor for dish washer -Securely fasten water heater LFNC per code -Receptacle located within six ft of the wet bar sink must be gfci-protected -Remove paper facing from insulation or cover -Install anti-back flow device for basement hose bib -Locate and make accessible the grounding connection to ufer
Occupancy Inspection - Codes Residential Full C of O 4/30/2020 4/30/2020 at 9:35 AM 04/30/2020
Misc
Resolved
04/30/2020
-Install tamper-proof caps at AC valves -Graspable handrail required for garage stair -Garage door not self closing -Install box extensions for switch & receptacle boxes recessed more than 1/4” behind kitchen and wet bar countertop backsplash -Hammer arrestor for dish washer -Securely fasten water heater LFNC per code -Receptacle located within six ft of the wet bar sink must be gfci-protected -Remove paper facing from insulation or cover -Install anti-back flow device for basement hose bib -Locate and make accessible the grounding connection to ufer
Documents & Images
Date Uploaded File Type Document Name
06/08/2018 Letter Codes Residential Plan Review
06/12/2018 Receipt Receipt for transaction: 2018-003772
06/12/2018 Letter Codes Building Permit
06/13/2018 Plans DOC061318-008
06/15/2018 Letter Inspection Summary
07/11/2018 Letter Inspection Summary
07/26/2018 Letter Inspection Summary
09/18/2018 Letter Inspection Summary
09/19/2018 Letter Inspection Summary
09/19/2018 Letter Inspection Summary
09/25/2018 Letter Inspection Summary
10/01/2018 Letter Inspection Summary
10/03/2018 Letter Inspection Summary
10/04/2018 Letter Inspection Summary
10/24/2018 Letter Inspection Summary
11/08/2018 Letter DE-Daily Inspection Summary
04/24/2020 Letter INSPECTION SUMMARY
04/28/2020 Letter Inspection Summary
04/30/2020 Letter Codes Final Certificate of Occupancy
04/30/2020 Letter Field Certificate of Occupancy
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home