Permit Application Status

PRPWFR20160608


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary


PRPWFR20160608
Public Works Infrastructure Permit - Residential
Final Acceptance
DEVELOPMENT COMPLETE
Mill Creek of Summit Mill, 6th Plat Lots 179-177
03/24/2016
05/16/2016
01/11/2018
Locations
Contacts
MCDC PARTNERS LLC, Address:120 SE 30TH ST  
CHRIS ROSE, Phone:(785) 829-7775  
Redford Const.  
Reviews
Review Type Outcome Est. Completion Date Completed
Licensed Contractors Approved 03/24/2016 01/04/2017
Tom Chandler
Fees
Paid Fees Amount Paid Owing Date Paid
Sanitary Sewer Insp Fees $237.72 $237.72 Paid 08/02/2016
$1,065.62
Sanitary Sewer Insp Fees $827.90 $827.90 Paid 03/24/2016
$827.89
Storm Sewer Inspection Fee $210.64 $210.64 Paid 03/24/2016
Water Insp Fee $604.30 $604.30 Paid 03/24/2016
Paved Surface Inspection Fee $1,129.11 $1,129.11 Paid 03/24/2016
Site Grading Fee $203.63 $203.63 Paid 03/24/2016
Water Test Fee $200.00 $200.00 Paid 03/24/2016
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Erosion Control Inspection Passed 06/15/2016
PW-Misc
Informational
06/15/2016
Tom Chandler 06/15/2016 7:59 AM ESC devices are installed. No other work has been done at this time.
Sanitary Sewer Construction Inspection Passed 08/23/2016
PW-Misc
Informational
08/18/2016
Tom Chandler 08/17/2016 Cored existing MH B-9. Tom Chandler 08/18/2016 3:09 PM Installed 8" DIP to MH 1-1. Wrapped in poly and encased in concrete with #4 rebar according to specs. Installed 8" SDR 26 PVC Sewer main heading towards MH 1-2. Installed approximately 90ft. Tom Chandler 08/22/2016 Finished installation of Sanitary sewer main to include MH A-3 and 5 service laterals. Trench checks and tracer wires installed and backfilled. Sewer marking tape installed as well. Testing can begin on 9/22/2016.
Sanitary Sewer - Invert Passed 08/29/2016
PW-Misc
Informational
08/29/2016
Tom Chandler 08/22/2016 Inverts have been completed.
Sanitary Sewer - Air Test Passed 9/22/2016 10/01/2016
Sanitary Sewer - Mandrel Passed 9/22/2016 10/01/2016
Sanitary Sewer - Vacuum Passed 9/22/2016 10/01/2016
Curb - Proof Roll Passed 10/01/2016
Curb - Compression Strength Passed 10/01/2016
PW-Misc
Informational
10/01/2016
KC Testing was on site and provided testing.
Public Curb Inspection Passed 10/01/2016
Pavement-Proof Roll Passed 9/30/2016 10/01/2016
Miscellaneous PWORKS Inspection Passed 10/15/2016
PW-Misc
Informational
10/15/2016
Tom Chandler 10/15/2016 9:37 AM Sanitary sewer line had TV inspection completed and passed.
Water Line - Hydrostatic Test Passed 11/10/2016 11/10/2016
Water Line - Coliform Test 1 Passed 11/15/2016 11/17/2016
Water Line - Coliform Test 2 Passed 11/16/2016 11/17/2016
Pavement-Surface Passed 12/12/2016
Street - Surface Course Passed 12/12/2016
Install Street and Stop Signs Passed 12/20/2016
Sidewalk Inspection Passed 12/20/2016
Grading/Excavation/Fill Inspection Passed 12/21/2016
Informational
09/12/2016
Record Drawing Review Passed 12/21/2016
Miscellaneous PWORKS Inspection Passed 12/21/2016
Verify Substantial Completion Substantial Completion 01/04/2017
Site Visit Partial 1/18/2017 01/18/2017
PW-Misc
Informational
01/18/2017
Tom Chandler 01/18/2017 9:07 AM Monday was a holiday and no work going on today. Punch list items will be done when weather permits.
Site Visit Partial 3/13/2017 03/13/2017
PW-Misc
Informational
01/18/2017
Tom Chandler 01/18/2017 9:07 AM Monday was a holiday and no work going on today. Punch list items will be done when weather permits.
Record Drawing Review Passed 4/12/2017 04/12/2017
Informational
04/12/2017
Tom Chandler 04/12/2017 8:15 AM As-builts have been resubmitted.
ESC - (Vegetation/Ground Cover) Passed 1/3/2018 at 12:30 PM 01/04/2018
Site Visit Complete 1/3/2018 at 12:15 PM 01/04/2018
PW-Misc
Informational
03/13/2017
Tom Chandler 01/18/2017 9:07 AM Monday was a holiday and no work going on today. Punch list items will be done when weather permits. Tom Chandler 03/13/2017 2:28 PM No work going on today. Talked to Karen Quakenbush about revised water line plans. Should be able to move forward on construction this week on water main.
Documents & Images
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home