Permit Application Status

PRPWFC20161027


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary


PRPWFC20161027
Public Works Infrastructure Permit - Commercial
Final Acceptance
MARION RIDGE SAFETY STORAGE LLC
DEVELOPMENT COMPLETE
FULL SITE DEVELOPMENT FOR NEW COMMERCIAL BUILDING
05/04/2016
05/24/2016
11/03/2017
Locations
Contacts
WARD DEVELOPMENT & INVESTMENT CO, Address:1120 NW EAGLE RIDGE BLVD, Phone:(816) 229-8115  
MARION RIDGE SAFETY STORAGE LLC, Address:1101 C NW PAMELA BLVD  
Not shown for privacy reasons.
Reviews
Review Type Outcome Est. Completion Date Completed
Licensed Contractors Approved 05/04/2016 05/04/2016
Mike Weisenborn
Fees
Paid Fees Amount Paid Owing Date Paid
91100C8-Sanitary Sewer Insp Fees $87.22 $87.22 Paid 05/04/2016
91100C9-Water Insp Fee $390.15 $390.15 Paid 05/04/2016
9110068-Storm Fee $1,564.44 $1,564.44 Paid 05/04/2016
9110081-Paved Surface Inspection Fee $6,458.91 $6,458.91 Paid 05/04/2016
$6,458.92
9110071-Site Grading Fee $315.94 $315.94 Paid 05/04/2016
9110072-Water Test Fee $200.00 $200.00 Paid 05/04/2016
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Grading/Excavation/Fill Inspection Partial 07/29/2016
PW-Misc
Informational
07/29/2016
Tom Chandler 07/29/2016 10:58 AM Grade work going on today.
Site Visit Complete 1/9/2017 01/09/2017
PW-Misc
Informational
01/09/2017
Tom Chandler 01/09/2017 1:13 PM No work going on today. ESC devices installed and site in good condition.
Storm - Pipe Partial 1/17/2017 01/17/2017
PW-Misc
Informational
01/17/2017
Tom Chandler 01/17/2017 4:02 PM Storm sewer connection made to the existing pipe coming from the existing curb inlet.
Storm - Pipe Partial 1/19/2017 01/19/2017
PW-Misc
Informational
01/17/2017
Tom Chandler 01/17/2017 4:02 PM Storm sewer connection made to the existing pipe coming from the existing curb inlet. Tom Chandler 01/19/2017 12:17 PM 24" HDPE storm pipe installed from existing Structure to FI 1-3 . Backfield and will continue laying 15" HDPE from FI 1-3 to FI 1-2
Storm - Pipe Partial 1/20/2017 01/20/2017
PW-Misc
Informational
01/19/2017
Tom Chandler 01/17/2017 4:02 PM Storm sewer connection made to the existing pipe coming from the existing curb inlet. Tom Chandler 01/19/2017 12:17 PM 24" HDPE storm pipe installed from existing Structure to FI 1-3 . Backfield and will continue laying 15" HDPE from FI 1-3 to FI 1-2. Tom Chandler 01/20/2017 2:40 PM Begun installing 15" HDPE pipe from FI 1-3 to FI 1-2.
Storm - Pipe Partial 1/23/2017 01/23/2017
PW-Misc
Informational
01/20/2017
Tom Chandler 01/17/2017 4:02 PM Storm sewer connection made to the existing pipe coming from the existing curb inlet. Tom Chandler 01/19/2017 12:17 PM 24" HDPE storm pipe installed from existing Structure to FI 1-3 . Backfield and will continue laying 15" HDPE from FI 1-3 to FI 1-2. Tom Chandler 01/20/2017 2:40 PM Begun installing 15" HDPE pipe from FI 1-3 to FI 1-2. Tom Chandler 01/23/2017 3:50 PM Continued installing 15" HDPE towards FI 1-2.
Storm - Pipe Partial 1/24/2017 01/24/2017
PW-Misc
Informational
01/23/2017
Tom Chandler 01/17/2017 4:02 PM Storm sewer connection made to the existing pipe coming from the existing curb inlet. Tom Chandler 01/19/2017 12:17 PM 24" HDPE storm pipe installed from existing Structure to FI 1-3 . Backfield and will continue laying 15" HDPE from FI 1-3 to FI 1-2. Tom Chandler 01/20/2017 2:40 PM Begun installing 15" HDPE pipe from FI 1-3 to FI 1-2. Tom Chandler 01/23/2017 3:50 PM Continued installing 15" HDPE towards FI 1-2. Tom Chandler 01/24/2017 1:41 PM Installed FI 1-2 and continued installing 15" HDPE pipe towards FI 1-1.
Storm - Pipe Partial 1/25/2017 01/25/2017
PW-Misc
Informational
01/24/2017
Tom Chandler 01/17/2017 4:02 PM Storm sewer connection made to the existing pipe coming from the existing curb inlet. Tom Chandler 01/19/2017 12:17 PM 24" HDPE storm pipe installed from existing Structure to FI 1-3 . Backfield and will continue laying 15" HDPE from FI 1-3 to FI 1-2. Tom Chandler 01/20/2017 2:40 PM Begun installing 15" HDPE pipe from FI 1-3 to FI 1-2. Tom Chandler 01/23/2017 3:50 PM Continued installing 15" HDPE towards FI 1-2. Tom Chandler 01/24/2017 1:41 PM Installed FI 1-2 and continued installing 15" HDPE pipe towards FI 1-1. Tom Chandler 01/25/2017 2:53 PM Installed 15"HDPE pipe to FI 1-1 and installed FI 1-1.
Storm - Pipe Partial 1/26/2017 01/26/2017
PW-Misc
Informational
01/25/2017
Tom Chandler 01/17/2017 4:02 PM Storm sewer connection made to the existing pipe coming from the existing curb inlet. Tom Chandler 01/19/2017 12:17 PM 24" HDPE storm pipe installed from existing Structure to FI 1-3 . Backfield and will continue laying 15" HDPE from FI 1-3 to FI 1-2. Tom Chandler 01/20/2017 2:40 PM Begun installing 15" HDPE pipe from FI 1-3 to FI 1-2. Tom Chandler 01/23/2017 3:50 PM Continued installing 15" HDPE towards FI 1-2. Tom Chandler 01/24/2017 1:41 PM Installed FI 1-2 and continued installing 15" HDPE pipe towards FI 1-1. Tom Chandler 01/25/2017 2:53 PM Installed 15"HDPE pipe to FI 1-1 and installed FI 1-1. Tom Chandler 01/26/2017 3:49 PM precesion cutting and coring did curb cut and box cut for removal. Double grate inlet to be installed in the future. commercial entrance to be constructed as well.
Storm - Pipe Partial 1/27/2017 01/27/2017
PW-Misc
Informational
01/26/2017
Tom Chandler 01/17/2017 4:02 PM Storm sewer connection made to the existing pipe coming from the existing curb inlet. Tom Chandler 01/19/2017 12:17 PM 24" HDPE storm pipe installed from existing Structure to FI 1-3 . Backfield and will continue laying 15" HDPE from FI 1-3 to FI 1-2. Tom Chandler 01/20/2017 2:40 PM Begun installing 15" HDPE pipe from FI 1-3 to FI 1-2. Tom Chandler 01/23/2017 3:50 PM Continued installing 15" HDPE towards FI 1-2. Tom Chandler 01/24/2017 1:41 PM Installed FI 1-2 and continued installing 15" HDPE pipe towards FI 1-1. Tom Chandler 01/25/2017 2:53 PM Installed 15"HDPE pipe to FI 1-1 and installed FI 1-1. Tom Chandler 01/26/2017 3:49 PM precesion cutting and coring did curb cut and box cut for removal. Double grate inlet to be installed in the future. commercial entrance to be constructed as well. Tom Chandler 01/27/2017 3:48 PM Insatlled CI 2-2 and 18" HDPE from CI 2-2 to existing CI. poured collars and inverts on FI 1-1, FI 1-2, and FI 1-3.
Storm - Pipe Partial 1/31/2017 01/31/2017
PW-Misc
Informational
01/27/2017
Tom Chandler 01/17/2017 4:02 PM Storm sewer connection made to the existing pipe coming from the existing curb inlet. Tom Chandler 01/19/2017 12:17 PM 24" HDPE storm pipe installed from existing Structure to FI 1-3 . Backfield and will continue laying 15" HDPE from FI 1-3 to FI 1-2. Tom Chandler 01/20/2017 2:40 PM Begun installing 15" HDPE pipe from FI 1-3 to FI 1-2. Tom Chandler 01/23/2017 3:50 PM Continued installing 15" HDPE towards FI 1-2. Tom Chandler 01/24/2017 1:41 PM Installed FI 1-2 and continued installing 15" HDPE pipe towards FI 1-1. Tom Chandler 01/25/2017 2:53 PM Installed 15"HDPE pipe to FI 1-1 and installed FI 1-1. Tom Chandler 01/26/2017 3:49 PM precesion cutting and coring did curb cut and box cut for removal. Double grate inlet to be installed in the future. commercial entrance to be constructed as well. Tom Chandler 01/27/2017 3:48 PM Insatlled CI 2-2 and 18" HDPE from CI 2-2 to existing CI. poured collars and inverts on FI 1-1, FI 1-2, and FI 1-3. Tom Chandler 01/31/2017 3:40 PM Installed approximately 40ft. of 18" HDPE pipe from CI 2-2 heading towards CI 2-1.
Storm - Pipe Partial 2/1/2017 02/01/2017
PW-Misc
Informational
01/31/2017
Tom Chandler 01/17/2017 4:02 PM Storm sewer connection made to the existing pipe coming from the existing curb inlet. Tom Chandler 01/19/2017 12:17 PM 24" HDPE storm pipe installed from existing Structure to FI 1-3 . Backfield and will continue laying 15" HDPE from FI 1-3 to FI 1-2. Tom Chandler 01/20/2017 2:40 PM Begun installing 15" HDPE pipe from FI 1-3 to FI 1-2. Tom Chandler 01/23/2017 3:50 PM Continued installing 15" HDPE towards FI 1-2. Tom Chandler 01/24/2017 1:41 PM Installed FI 1-2 and continued installing 15" HDPE pipe towards FI 1-1. Tom Chandler 01/25/2017 2:53 PM Installed 15"HDPE pipe to FI 1-1 and installed FI 1-1. Tom Chandler 01/26/2017 3:49 PM precesion cutting and coring did curb cut and box cut for removal. Double grate inlet to be installed in the future. commercial entrance to be constructed as well. Tom Chandler 01/27/2017 3:48 PM Insatlled CI 2-2 and 18" HDPE from CI 2-2 to existing CI. poured collars and inverts on FI 1-1, FI 1-2, and FI 1-3. Tom Chandler 01/31/2017 3:40 PM Installed approximately 40ft. of 18" HDPE pipe from CI 2-2 heading towards CI 2-1. Tom Chandler 02/01/2017 3:27 PM Installed 18" HDPE pipe all the way to CI 2-1. Installed CI 2-1 and poured collars and inverts for CI 2-1,CI 2-2 and existing CI.
Storm - Pipe Passed 2/2/2017 02/02/2017
PW-Misc
Informational
02/01/2017
Tom Chandler 01/17/2017 4:02 PM Storm sewer connection made to the existing pipe coming from the existing curb inlet. Tom Chandler 01/19/2017 12:17 PM 24" HDPE storm pipe installed from existing Structure to FI 1-3 . Backfield and will continue laying 15" HDPE from FI 1-3 to FI 1-2. Tom Chandler 01/20/2017 2:40 PM Begun installing 15" HDPE pipe from FI 1-3 to FI 1-2. Tom Chandler 01/23/2017 3:50 PM Continued installing 15" HDPE towards FI 1-2. Tom Chandler 01/24/2017 1:41 PM Installed FI 1-2 and continued installing 15" HDPE pipe towards FI 1-1. Tom Chandler 01/25/2017 2:53 PM Installed 15"HDPE pipe to FI 1-1 and installed FI 1-1. Tom Chandler 01/26/2017 3:49 PM precesion cutting and coring did curb cut and box cut for removal. Double grate inlet to be installed in the future. commercial entrance to be constructed as well. Tom Chandler 01/27/2017 3:48 PM Insatlled CI 2-2 and 18" HDPE from CI 2-2 to existing CI. poured collars and inverts on FI 1-1, FI 1-2, and FI 1-3. Tom Chandler 01/31/2017 3:40 PM Installed approximately 40ft. of 18" HDPE pipe from CI 2-2 heading towards CI 2-1. Tom Chandler 02/01/2017 3:27 PM Installed 18" HDPE pipe all the way to CI 2-1. Installed CI 2-1 and poured collars and inverts for CI 2-1,CI 2-2 and existing CI. Tom Chandler 02/02/2017 3:54 PM Backfilled and set remaining lids on storm boxes. Storm sewer is complete. Will still have to clean boxes at end of project.
Roof Drain Partial 2/2/2017 02/02/2017
PW-Misc
Informational
02/02/2017
Tom Chandler 02/02/2017 3:59 PM Begun installation of 8" HDPE roof drain line starting at CI 2-2.
Roof Drain Partial 2/3/2017 02/03/2017
PW-Misc
Informational
02/02/2017
Tom Chandler 02/02/2017 3:59 PM Begun installation of 8" HDPE roof drain line starting at CI 2-2. Tom Chandler 02/03/2017 3:14 PM Installed 8" HDPE roof drain line south of the 45. Approximately 60ft. of pipe installed.
Roof Drain Partial 2/6/2017 02/06/2017
PW-Misc
Informational
02/03/2017
Tom Chandler 02/02/2017 3:59 PM Begun installation of 8" HDPE roof drain line starting at CI 2-2. Tom Chandler 02/03/2017 3:14 PM Installed 8" HDPE roof drain line south of the 45. Approximately 60ft. of pipe installed. Tom Chandler 02/06/2017 3:40 PM Construction of 8" HDPE roof drain line is complete and stubbed at building. Will tie in roof drains at later date.
Water Line - Construction Taps Removed Partial 02/17/2017
PW-Misc
Informational
02/17/2017
Tom Chandler 02/17/2017 1:17 PM Installing water line going into building and water line going to private hydrant.
Water Line - Construction Taps Removed Partial 2/28/2017 02/28/2017
PW-Misc
Informational
02/17/2017
Tom Chandler 02/17/2017 1:17 PM Installing water line going into building and water line going to private hydrant. Tom Chandler 02/28/2017 4:15 PM Water department performed test shutdown and located valves. Will need to do shutdown to cut in a tee for a fire line and backflow valve and vault.
Water Line - Construction Taps Removed Partial 3/14/2017 03/14/2017
PW-Misc
Informational
02/28/2017
Tom Chandler 02/17/2017 1:17 PM Installing water line going into building and water line going to private hydrant. Tom Chandler 02/28/2017 4:15 PM Water department performed test shutdown and located valves. Will need to do shutdown to cut in a tee for a fire line and backflow valve and vault. Tom Chandler 03/14/2017 3:13 PM Water department will be out in the morning to help locate water line. Will do shut down in the afternoon to allow for cut-in tee to be installed.
Water Line - Construction Taps Removed Partial 3/15/2017 03/15/2017
PW-Misc
Informational
03/14/2017
Tom Chandler 02/17/2017 1:17 PM Installing water line going into building and water line going to private hydrant. Tom Chandler 02/28/2017 4:15 PM Water department performed test shutdown and located valves. Will need to do shutdown to cut in a tee for a fire line and backflow valve and vault. Tom Chandler 03/14/2017 3:13 PM Water department will be out in the morning to help locate water line. Will do shut down in the afternoon to allow for cut-in tee to be installed. Tom Chandler 03/15/2017 4:22 PM Water has been shut down after water department located the water main. Will do the cut-in tee in the morning. Will pour thrust tomorrow as well.
Water Line - Construction Taps Removed Passed 3/20/2017 03/20/2017
PW-Misc
Informational
03/15/2017
Tom Chandler 02/17/2017 1:17 PM Installing water line going into building and water line going to private hydrant. Tom Chandler 02/28/2017 4:15 PM Water department performed test shutdown and located valves. Will need to do shutdown to cut in a tee for a fire line and backflow valve and vault. Tom Chandler 03/14/2017 3:13 PM Water department will be out in the morning to help locate water line. Will do shut down in the afternoon to allow for cut-in tee to be installed. Tom Chandler 03/15/2017 4:22 PM Water has been shut down after water department located the water main. Will do the cut-in tee in the morning. Will pour thrust blocks tomorrow as well. Tom Chandler 03/20/2017 3:46 PM Water department completed water tap this morning. Will set meter and pit tomorrow. Vault and backflow preventer were installed 03/17/17. Bob Burns covered for me on that day.
Roof Drain Passed 2/8/2017 03/20/2017
PW-Misc
Informational
02/06/2017
Tom Chandler 02/02/2017 3:59 PM Begun installation of 8" HDPE roof drain line starting at CI 2-2. Tom Chandler 02/03/2017 3:14 PM Installed 8" HDPE roof drain line south of the 45. Approximately 60ft. of pipe installed. Tom Chandler 02/06/2017 3:40 PM Construction of 8" HDPE roof drain line is complete and stubbed at building. Will tie in roof drains at later date.
Water Line - Valve Passed 03/20/2017
PW-Misc
Informational
03/20/2017
Tom Chandler 03/20/2017 3:51 PM 8" gate inline valve installed on existing water main. 8"x6" cut-in tee installed for new fire line. 6" gate valve installed on new fire line as well.
Water Line - Thrust Restraint Passed 03/20/2017
PW-Misc
Informational
03/20/2017
Tom Chandler 03/20/2017 3:56 PM Thrust blocks, straddle blocks, and collars have been completed.
Water Line - Tapping Sleeve Passed 3/21/2017 03/21/2017
Water Line - Hydrostatic Test Passed 3/22/2017 03/22/2017
Sanitary Sewer Construction Inspection Passed 04/11/2017
Informational
04/11/2017
Sanitary sewer stub was located at approximately 120ft. from existing manhole. Contractor tied into stub and ran lateral service line to the building. (2) clean outs were installed according to plans.
Erosion Control Inspection Passed 04/27/2017
Site Visit Partial 4/27/2017 04/27/2017
Informational
04/27/2017
Tom Chandler 04/27/2017 3:18 PM No work goning on today. Mud tracked out on McBaine drive. Called contractor to have it cleaned up at approximately 9:15AM.
Curb - Proof Roll Passed 05/12/2017
Proof roll parking lot Partial 5/12/2017 05/12/2017
Informational
05/12/2017
Tom Chandler 05/12/2017 3:35 PM completed proof roll on north side parking lot. Will pour on 05/15/17.
Proof roll parking lot Passed 5/15/2017 05/15/2017
Informational
05/15/2017
Tom Chandler 05/15/2017 4:11 PM Proof rolled west side parking lot. Will pour on 05/16/2017. All proof rolls on parking lot are complete and passed final inspections.
Driveway Inspection Partial 5/17/2017 05/17/2017
Informational
05/17/2017
Tom Chandler 05/17/2017 5:11 PM Inspected forms and compacted aggregate. Poured this afternoon.
Driveway Inspection Passed 5/22/2017 05/19/2017
Informational
05/19/2017
Tom Chandler 05/19/2017 8:08 AM Driveway has been completed and passed final inspection.
Verify Substantial Completion Substantial Completion 7/28/2017 07/31/2017
Erosion Control Inspection Failed 8/15/2017 at 1:15 PM 08/15/2017
PW-Devices for Erosion and Sediment Control
Corrective Action Required
08/15/2017
There are problems with the erosion control devices on your site.Tom Chandler 08/15/2017 1:35 PM Silt has left the property and is in the roadway. Will need to clean silt and repair silt fence that has failed.
Erosion Control Inspection Failed 8/16/2017 at 10:30 AM 08/16/2017
PW-Devices for Erosion and Sediment Control
Corrective Action Required
08/15/2017
There are problems with the erosion control devices on your site.Tom Chandler 08/15/2017 1:35 PM Silt has left the property and is in the roadway. Will need to clean silt and repair silt fence that has failed. Tom Chandler 08/16/2017 10:39 AM The silt fence still needs repaired and area to be vegetated. Rain has been falling off and on most of the morning. Someone has started to remove from roadway. Began raining heavy again and was not able to finish removing silt from roadway.
Erosion Control Inspection Partial 8/17/2017 at 10:40 AM 08/17/2017
PW-Devices for Erosion and Sediment Control
Corrective Action Required
08/16/2017
There are problems with the erosion control devices on your site.Tom Chandler 08/15/2017 1:35 PM Silt has left the property and is in the roadway. Will need to clean silt and repair silt fence that has failed. Tom Chandler 08/16/2017 10:39 AM The silt fence still needs repaired and area to be vegetated. Rain has been falling off and on most of the morning. Someone has started to remove from roadway. Began raining heavy again and was not able to finish removing silt from roadway. Tom Chandler 08/17/2017 11:19 AM Contractor still needs to correct silt fence and clean roadway. Someone had begun working on cleaning roadway while I was there. Will go back to inspect progress in the afternoon.
Erosion Control Inspection Passed 8/17/2017 at 3:30 PM 08/18/2017
PW-Devices for Erosion and Sediment Control
Corrective Action Required
08/17/2017
There are problems with the erosion control devices on your site.Tom Chandler 08/15/2017 1:35 PM Silt has left the property and is in the roadway. Will need to clean silt and repair silt fence that has failed. Tom Chandler 08/16/2017 10:39 AM The silt fence still needs repaired and area to be vegetated. Rain has been falling off and on most of the morning. Someone has started to remove from roadway. Began raining heavy again and was not able to finish removing silt from roadway. Tom Chandler 08/17/2017 11:19 AM Contractor still needs to correct silt fence and clean roadway. Someone had begun working on cleaning roadway while I was there. Will go back to inspect progress in the afternoon. Tom Chandler 08/18/2017 7:59 AM Silt has been cleaned from roadway and ESC devices have been repaired.
Erosion Control Inspection Failed 8/22/2017 at 9:30 AM 08/22/2017
Corrective Action Required
08/22/2017
Tom Chandler 08/22/2017 10:04 AM Need to repair ESC devices and clean silt off roadway.
Site Visit Partial 8/28/2017 at 11:30 AM 08/28/2017
Storm - Inlets Clean Passed 11/03/2017
ESC - (Vegetation/Ground Cover) Passed 11/03/2017
Erosion Control Inspection Passed 11/03/2017
Documents & Images
Date Uploaded File Type Document Name
05/04/2016 Receipt Receipt for transaction: 2016-001639
05/24/2016 Letter PW-Permit
01/17/2017 Letter PW-Daily Inspection Summary
01/19/2017 IMG_0041
01/19/2017 IMG_0039
01/19/2017 IMG_0596
01/19/2017 IMG_0600
01/19/2017 Letter PW-Daily Inspection Summary
01/20/2017 Letter PW-Daily Inspection Summary
01/23/2017 Letter PW-Daily Inspection Summary
01/24/2017 Letter PW-Daily Inspection Summary
01/25/2017 Letter PW-Daily Inspection Summary
01/26/2017 Letter PW-Daily Inspection Summary
01/27/2017 Letter PW-Daily Inspection Summary
01/31/2017 Letter PW-Daily Inspection Summary
02/01/2017 Letter PW-Daily Inspection Summary
02/02/2017 Letter PW-Daily Inspection Summary
02/02/2017 Letter PW-Daily Inspection Summary
02/03/2017 Letter PW-Daily Inspection Summary
02/06/2017 Letter PW-Daily Inspection Summary
02/17/2017 Letter PW-Daily Inspection Summary
02/28/2017 Letter PW-Daily Inspection Summary
03/14/2017 Letter PW-Daily Inspection Summary
03/20/2017 Letter PW-Daily Inspection Summary
03/20/2017 Letter PW-Daily Inspection Summary
03/20/2017 Letter PW-Daily Inspection Summary
03/21/2017 Letter PW-Daily Inspection Summary
03/22/2017 Letter PW-Daily Inspection Summary
04/11/2017 Letter PW-Daily Inspection Summary
05/15/2017 Letter PW-Daily Inspection Summary
05/19/2017 Letter PW-Daily Inspection Summary
07/27/2017 Letter PW-Punch List
07/31/2017 Letter PW-Certificate of Substantial Completion Multiple Lot
08/02/2017 DOC080217-08022017110624
08/15/2017 Letter PW-Daily Inspection Summary
08/17/2017 Letter PW-Daily Inspection Summary
08/18/2017 Letter PW-Daily Inspection Summary
08/22/2017 Letter PW-Daily Inspection Summary
11/03/2017 Letter DE-Certificate of Final Acceptance (Commercial)
11/03/2017 Twin Lakes Insurance Signed Certificate of Final Acceptance
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home