Summary
PRPWFC20152150
Public Works Infrastructure Permit - Commercial
Final Acceptance
DEVELOPMENT COMPLETE
I-470 Business and Technology Center Lot 12A
09/15/2015
09/15/2015
09/28/2017
Locations
Contacts
Not shown for privacy reasons.
Reviews

There are no reviews for this permit application.

Fees
Paid Fees Amount Paid Owing Date Paid
91100C8-Sanitary Sewer Insp Fees $70.14 $70.14 Paid 09/15/2015
91100C9-Water Insp Fee $102.75 $102.75 Paid 09/15/2015
9110072-Water Test Fee $200.00 $200.00 Paid 09/15/2015
9110068-Storm Fee $1,011.63 $1,011.63 Paid 09/15/2015
9110081-Paved Surface Inspection Fee $7,912.90 $7,912.90 Paid 09/15/2015
9110071-Site Grading Fee $681.14 $681.14 Paid 09/15/2015
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Erosion Control Inspection Failed 12/28/2015
Erosion Control Inspection Failed 6/20/2016 06/20/2016
PW-Erosion and Sediment Control
Corrective Action Required
06/20/2016
Ground at the site is very dry (loose soft dirt abounds). Dust is flying. Dust control needed.
Erosion Control Inspection Partial 08/01/2016
PW-Misc
Informational
08/01/2016
Tom Chandler 08/01/2016 2:05 PM Inspected ESC devices. Will continue to monitor thruoghout construction. No work being done because of rain.
Proof roll parking lot Partial 12/20/2016
PW-Misc
Informational
12/20/2016
Tom Chandler 12/20/2016 1:31 PM Proof rolled loading docks and 2 far north sections of parking lot.
Site Visit Complete 01/09/2017
PW-Misc
Informational
01/09/2017
Tom Chandler 01/09/2017 1:05 PM No work going on today. ESC devices installed and site is in good condition.
Site Visit Partial 1/17/2017 01/18/2017
PW-Misc
Informational
01/18/2017
Tom Chandler 01/18/2017 8:40 AM Monday was a holiday and no work being done today. Site left in good condition and ESC established.
Site Visit Partial 1/31/2017 01/31/2017
PW-Misc
Informational
01/18/2017
Tom Chandler 01/18/2017 8:40 AM Monday was a holiday and no work being done today. Site left in good condition and ESC established. Tom Chandler 01/31/2017 3:37 PM Installing private sidewalk on east and south side of the building.
Site Visit Partial 2/1/2017 02/01/2017
PW-Misc
Informational
01/31/2017
.Tom Chandler 01/18/2017 8:40 AM Monday was a holiday and no work being done today. Site left in good condition and ESC established. Tom Chandler 01/31/2017 3:37 PM Installing private sidewalk on east and south side of the building. Tom Chandler 02/01/2017 3:33 PM Installed the rest of the sidewalk on the south side of the building.
Site Visit Partial 2/6/2017 02/06/2017
PW-Misc
Informational
02/01/2017
.Tom Chandler 01/18/2017 8:40 AM Monday was a holiday and no work being done today. Site left in good condition and ESC established. Tom Chandler 01/31/2017 3:37 PM Installing private sidewalk on east and south side of the building. Tom Chandler 02/01/2017 3:33 PM Installed the rest of the sidewalk on the south side of the building. Tom Chandler 02/06/2017 3:36 PM Begun work on existing CI on Mc Baine. Dug hole to prepare for Fire line tie-in.
Storm Sewer Construction Inspection Partial 2/7/2017 02/07/2017
PW-Misc
Informational
11/30/2016
Tom Chandler 11/30/2016 1:24 PM Storm sewer construction. Tom Chandler 12/20/2016 1:28 PM Storm sewer connection on east side of building installed and stubbed for roof drains. Tom Chandler 02/07/2017 3:59 PM Roof drains line on west side of building installed and connected to existing FI.
Water Line - Construction Inspection Partial 2/7/2017 02/07/2017
PW-Misc
Informational
11/30/2016
Tom Chandler 11/30/2016 1:22 PM Water line has been installed under building footing. Will complete at a later date. Tom Chandler 02/07/2017 4:02 PM Cut-in tee and valve installed for fire line. Connection to building complete. Will do service tap at a later date.
Site Visit Partial 2/13/2017 02/13/2017
PW-Misc
Informational
02/06/2017
.Tom Chandler 01/18/2017 8:40 AM Monday was a holiday and no work being done today. Site left in good condition and ESC established. Tom Chandler 01/31/2017 3:37 PM Installing private sidewalk on east and south side of the building. Tom Chandler 02/01/2017 3:33 PM Installed the rest of the sidewalk on the south side of the building. Tom Chandler 02/06/2017 3:36 PM Begun work on existing CI on Mc Baine. Dug hole to prepare for Fire line tie-in. Tom Chandler 02/13/2017 3:37 PM Poured curbs in parking lot and 2 sections in the parking lot were paved.
Storm Sewer Construction Inspection Partial 2/13/2017 02/13/2017
PW-Misc
Informational
02/07/2017
Tom Chandler 11/30/2016 1:24 PM Storm sewer construction. Tom Chandler 12/20/2016 1:28 PM Storm sewer connection on east side of building installed and stubbed for roof drains. Tom Chandler 02/07/2017 3:59 PM Roof drains line on west side of building installed and connected to existing FI. Tom Chandler 02/13/2017 3:41 PM poured walls to modify existing FI on SW corner of building.
Site Visit Partial 02/15/2017
PW-Misc
Informational
02/13/2017
.Tom Chandler 01/18/2017 8:40 AM Monday was a holiday and no work being done today. Site left in good condition and ESC established. Tom Chandler 01/31/2017 3:37 PM Installing private sidewalk on east and south side of the building. Tom Chandler 02/01/2017 3:33 PM Installed the rest of the sidewalk on the south side of the building. Tom Chandler 02/06/2017 3:36 PM Begun work on existing CI on Mc Baine. Dug hole to prepare for Fire line tie-in. Tom Chandler 02/13/2017 3:37 PM Poured curbs in parking lot and 2 sections in the parking lot were paved. Tom Chandler 02/15/2017 7:13 AM proof rolled firelanes for parking lot.
Site Visit Partial 2/17/2017 02/17/2017
PW-Misc
Informational
02/15/2017
.Tom Chandler 01/18/2017 8:40 AM Monday was a holiday and no work being done today. Site left in good condition and ESC established. Tom Chandler 01/31/2017 3:37 PM Installing private sidewalk on east and south side of the building. Tom Chandler 02/01/2017 3:33 PM Installed the rest of the sidewalk on the south side of the building. Tom Chandler 02/06/2017 3:36 PM Begun work on existing CI on Mc Baine. Dug hole to prepare for Fire line tie-in. Tom Chandler 02/13/2017 3:37 PM Poured curbs in parking lot and 2 sections in the parking lot were paved. Tom Chandler 02/15/2017 7:13 AM proof rolled firelanes for parking lot. Tom Chandler 02/17/2017 1:12 PM Grading and putting rock down for more sections of parking lot to be paved.
Site Visit Partial 2/21/2017 02/21/2017
PW-Misc
Informational
02/17/2017
.Tom Chandler 01/18/2017 8:40 AM Monday was a holiday and no work being done today. Site left in good condition and ESC established. Tom Chandler 01/31/2017 3:37 PM Installing private sidewalk on east and south side of the building. Tom Chandler 02/01/2017 3:33 PM Installed the rest of the sidewalk on the south side of the building. Tom Chandler 02/06/2017 3:36 PM Begun work on existing CI on Mc Baine. Dug hole to prepare for Fire line tie-in. Tom Chandler 02/13/2017 3:37 PM Poured curbs in parking lot and 2 sections in the parking lot were paved. Tom Chandler 02/15/2017 7:13 AM proof rolled firelanes for parking lot. Tom Chandler 02/17/2017 1:12 PM Grading and putting rock down for more sections of parking lot to be paved. Tom Chandler 02/21/2017 5:11 PM Poured parking lot fire lane just south of th building today.
Site Visit Partial 2/28/2017 02/28/2017
PW-Misc
Informational
02/21/2017
.Tom Chandler 01/18/2017 8:40 AM Monday was a holiday and no work being done today. Site left in good condition and ESC established. Tom Chandler 01/31/2017 3:37 PM Installing private sidewalk on east and south side of the building. Tom Chandler 02/01/2017 3:33 PM Installed the rest of the sidewalk on the south side of the building. Tom Chandler 02/06/2017 3:36 PM Begun work on existing CI on Mc Baine. Dug hole to prepare for Fire line tie-in. Tom Chandler 02/13/2017 3:37 PM Poured curbs in parking lot and 2 sections in the parking lot were paved. Tom Chandler 02/15/2017 7:13 AM proof rolled firelanes for parking lot. Tom Chandler 02/17/2017 1:12 PM Grading and putting rock down for more sections of parking lot to be paved. Tom Chandler 02/21/2017 5:11 PM Poured parking lot fire lane just south of th building today.
PW-Misc
Informational
02/28/2017
Tom Chandler 02/28/2017 10:22 AM Finishing parking lot on south end of building today. Will do curbs and commercial entrance to tie into McBaine drive at end of week.
Site Visit Partial 3/6/2017 03/06/2017
PW-Misc
Informational
02/28/2017
.Tom Chandler 01/18/2017 8:40 AM Monday was a holiday and no work being done today. Site left in good condition and ESC established. Tom Chandler 01/31/2017 3:37 PM Installing private sidewalk on east and south side of the building. Tom Chandler 02/01/2017 3:33 PM Installed the rest of the sidewalk on the south side of the building. Tom Chandler 02/06/2017 3:36 PM Begun work on existing CI on Mc Baine. Dug hole to prepare for Fire line tie-in. Tom Chandler 02/13/2017 3:37 PM Poured curbs in parking lot and 2 sections in the parking lot were paved. Tom Chandler 02/15/2017 7:13 AM proof rolled firelanes for parking lot. Tom Chandler 02/17/2017 1:12 PM Grading and putting rock down for more sections of parking lot to be paved. Tom Chandler 02/21/2017 5:11 PM Poured parking lot fire lane just south of th building today.
PW-Misc
Informational
02/28/2017
Tom Chandler 02/28/2017 10:22 AM Finishing parking lot on south end of building today. Will do curbs and commercial entrance to tie into McBaine drive at end of week.
PW-Misc
Informational
03/06/2017
Tom Chandler 03/06/2017 3:24 PM Talked to Kent Ward today about existing Sanitary sewer manholes along Independence drive. Need adjust ring and barrel section on 2 of the existing structures.
Curb - Proof Roll Passed 03/09/2017
Water Line - Construction Inspection Partial 2/8/2017 03/13/2017
PW-Misc
Informational
02/07/2017
Tom Chandler 11/30/2016 1:22 PM Water line has been installed under building footing. Will complete at a later date. Tom Chandler 02/07/2017 4:02 PM Cut-in tee and valve installed for fire line. Connection to building complete. Will do service tap at a later date.
Site Visit Partial 3/9/2017 03/13/2017
PW-Misc
Informational
03/06/2017
.Tom Chandler 01/18/2017 8:40 AM Monday was a holiday and no work being done today. Site left in good condition and ESC established. Tom Chandler 01/31/2017 3:37 PM Installing private sidewalk on east and south side of the building. Tom Chandler 02/01/2017 3:33 PM Installed the rest of the sidewalk on the south side of the building. Tom Chandler 02/06/2017 3:36 PM Begun work on existing CI on Mc Baine. Dug hole to prepare for Fire line tie-in. Tom Chandler 02/13/2017 3:37 PM Poured curbs in parking lot and 2 sections in the parking lot were paved. Tom Chandler 02/15/2017 7:13 AM proof rolled firelanes for parking lot. Tom Chandler 02/17/2017 1:12 PM Grading and putting rock down for more sections of parking lot to be paved. Tom Chandler 02/21/2017 5:11 PM Poured parking lot fire lane just south of th building today.
PW-Misc
Informational
03/06/2017
Tom Chandler 02/28/2017 10:22 AM Finishing parking lot on south end of building today. Will do curbs and commercial entrance to tie into McBaine drive at end of week.
PW-Misc
Informational
03/06/2017
Tom Chandler 03/06/2017 3:24 PM Talked to Kent Ward today about existing Sanitary sewer manholes along Independence drive. Need adjust ring and barrel section on 2 of the existing structures.
Site Visit Partial 3/13/2017 03/13/2017
PW-Misc
Informational
03/13/2017
Tom Chandler 03/06/2017 3:24 PM Talked to Kent Ward today about existing Sanitary sewer manholes along Independence drive. Need adjust ring and barrel section on 2 of the existing structures.
PW-Misc
Informational
03/13/2017
Tom Chandler 02/28/2017 10:22 AM Finishing parking lot on south end of building today. Will do curbs and commercial entrance to tie into McBaine drive at end of week.
PW-Misc
Informational
03/13/2017
.Tom Chandler 01/18/2017 8:40 AM Monday was a holiday and no work being done today. Site left in good condition and ESC established. Tom Chandler 01/31/2017 3:37 PM Installing private sidewalk on east and south side of the building. Tom Chandler 02/01/2017 3:33 PM Installed the rest of the sidewalk on the south side of the building. Tom Chandler 02/06/2017 3:36 PM Begun work on existing CI on Mc Baine. Dug hole to prepare for Fire line tie-in. Tom Chandler 02/13/2017 3:37 PM Poured curbs in parking lot and 2 sections in the parking lot were paved. Tom Chandler 02/15/2017 7:13 AM proof rolled firelanes for parking lot. Tom Chandler 02/17/2017 1:12 PM Grading and putting rock down for more sections of parking lot to be paved. Tom Chandler 02/21/2017 5:11 PM Poured parking lot fire lane just south of th building today. Tom Chandler 03/13/2017 2:24 PM poured fire lane section of parking lot on east side of building.
Site Visit Partial 3/20/2017 03/20/2017
PW-Misc
Informational
03/13/2017
Tom Chandler 03/06/2017 3:24 PM Talked to Kent Ward today about existing Sanitary sewer manholes along Independence drive. Need adjust ring and barrel section on 2 of the existing structures. Tom Chandler 03/20/2017 3:42 PM Removed curb from McBaine so new curb could be formed for commercial entrance to added later in the week.
PW-Misc
Informational
03/13/2017
Tom Chandler 02/28/2017 10:22 AM Finishing parking lot on south end of building today. Will do curbs and commercial entrance to tie into McBaine drive at end of week.
PW-Misc
Informational
03/13/2017
.Tom Chandler 01/18/2017 8:40 AM Monday was a holiday and no work being done today. Site left in good condition and ESC established. Tom Chandler 01/31/2017 3:37 PM Installing private sidewalk on east and south side of the building. Tom Chandler 02/01/2017 3:33 PM Installed the rest of the sidewalk on the south side of the building. Tom Chandler 02/06/2017 3:36 PM Begun work on existing CI on Mc Baine. Dug hole to prepare for Fire line tie-in. Tom Chandler 02/13/2017 3:37 PM Poured curbs in parking lot and 2 sections in the parking lot were paved. Tom Chandler 02/15/2017 7:13 AM proof rolled firelanes for parking lot. Tom Chandler 02/17/2017 1:12 PM Grading and putting rock down for more sections of parking lot to be paved. Tom Chandler 02/21/2017 5:11 PM Poured parking lot fire lane just south of th building today. Tom Chandler 03/13/2017 2:24 PM poured fire lane section of parking lot on east side of building.
Driveway Inspection Partial 3/23/2017 03/24/2017
PW-Misc
Informational
03/24/2017
Tom Chandler 03/24/2017 7:45 AM Completed driveway on south end of McBaine. Will do driveway on east side later.
Driveway Inspection Partial 4/13/2017 04/13/2017
PW-Misc
Informational
03/24/2017
Tom Chandler 03/24/2017 7:45 AM Completed driveway on south end of McBaine. Will do driveway on east side later. Tom Chandler 04/13/2017 12:20 PM Poured curbs on North drive entrance on McBaine. Will pour drive at a later time.
Sidewalk Inspection Partial 4/19/2017 04/19/2017
Informational
04/19/2017
Tom Chandler 04/19/2017 2:47 PM Inspected forms only. ADA ramp dowels installed and aggregate installed and compacted. Pouring today and will install truncated dome panels.
Storm Sewer Construction Inspection Passed 04/26/2017
PW-Misc
Informational
02/13/2017
Tom Chandler 11/30/2016 1:24 PM Storm sewer construction. Tom Chandler 12/20/2016 1:28 PM Storm sewer connection on east side of building installed and stubbed for roof drains. Tom Chandler 02/07/2017 3:59 PM Roof drains line on west side of building installed and connected to existing FI. Tom Chandler 02/13/2017 3:41 PM poured walls to modify existing FI on SW corner of building. Tom Chandler 04/26/2017 3:07 PM CI converted with new lid and grate has been installed and grouted. Storm sewer construction is complete.
Driveway Inspection Passed 4/25/2017 04/26/2017
PW-Misc
Informational
04/13/2017
Tom Chandler 03/24/2017 7:45 AM Completed driveway on south end of McBaine. Will do driveway on east side later. Tom Chandler 04/13/2017 12:20 PM Poured curbs on North drive entrance on McBaine. Will pour drive at a later time. Tom Chandler 04/26/2017 3:11 PM North drive entrance on McBaine has been completed.
Sidewalk Inspection Partial 4/25/2017 04/26/2017
Informational
04/26/2017
Tom Chandler 04/26/2017 3:14 PM Poured sidewalk between the (2) driveways on McBaine.
Sanitary Sewer - Manhole Adjustment Passed 5/4/2017 05/04/2017
Informational
05/04/2017
Tom Chandler 05/04/2017 3:12 PM Added a 36" barrel section to existing Manhole 14-025. Wrapped and Backfilled. There is a fiber optic line running right along the southwest of the manhole base. Evidence of bore hitting cone section of the manhole as well.
Water Line - Construction Inspection Passed 5/16/2017 05/16/2017
PW-Misc
Informational
03/13/2017
Tom Chandler 11/30/2016 1:22 PM Water line has been installed under building footing. Will complete at a later date. Tom Chandler 02/07/2017 4:02 PM Cut-in tee and valve installed for fire line. Connection to building complete. Will do service tap at a later date. Tom Chandler 05/16/2017 3:18 PM Water tap installed by water department for domestic service line and (2) irragation lines.
Sanitary Sewer - Abandonment Passed 5/24/2017 05/25/2017
Corrective Action Required
05/25/2017
Tom Chandler 05/25/2017 1:45 PM Abandoned Ductile iron stub at the main according to plans. Capped and plug, then backfilled.
Proof roll parking lot Passed 06/07/2017
Grading/Excavation/Fill Inspection Passed 08/03/2017
Site Visit Complete 08/03/2017
PW-Misc
Informational
03/20/2017
Tom Chandler 03/06/2017 3:24 PM Talked to Kent Ward today about existing Sanitary sewer manholes along Independence drive. Need adjust ring and barrel section on 2 of the existing structures. Tom Chandler 03/20/2017 3:42 PM Removed curb from McBaine so new curb could be formed for commercial entrance to added later in the week.
PW-Misc
Informational
03/20/2017
Tom Chandler 02/28/2017 10:22 AM Finishing parking lot on south end of building today. Will do curbs and commercial entrance to tie into McBaine drive at end of week.
PW-Misc
Informational
03/20/2017
.Tom Chandler 01/18/2017 8:40 AM Monday was a holiday and no work being done today. Site left in good condition and ESC established. Tom Chandler 01/31/2017 3:37 PM Installing private sidewalk on east and south side of the building. Tom Chandler 02/01/2017 3:33 PM Installed the rest of the sidewalk on the south side of the building. Tom Chandler 02/06/2017 3:36 PM Begun work on existing CI on Mc Baine. Dug hole to prepare for Fire line tie-in. Tom Chandler 02/13/2017 3:37 PM Poured curbs in parking lot and 2 sections in the parking lot were paved. Tom Chandler 02/15/2017 7:13 AM proof rolled firelanes for parking lot. Tom Chandler 02/17/2017 1:12 PM Grading and putting rock down for more sections of parking lot to be paved. Tom Chandler 02/21/2017 5:11 PM Poured parking lot fire lane just south of th building today. Tom Chandler 03/13/2017 2:24 PM poured fire lane section of parking lot on east side of building.
Fire Line - Flush Passed 08/03/2017
Fire Line - Hydrostatic Test Passed 08/03/2017
Storm - Pipe Passed 08/03/2017
ESC - (Vegetation/Ground Cover) Partial 8/15/2017 at 1:00 PM 08/15/2017
Informational
08/15/2017
Tom Chandler 08/15/2017 1:31 PM All sodded areas are complete. There is a small area off-site with stockpile that needs vegetation.
Site Visit Complete 8/17/2017 at 10:15 AM 08/17/2017
Informational
08/17/2017
Tom Chandler 08/17/2017 10:28 AM Check site for any problems with erosion control. No visible signs of runoff contamination. Sod has been installed. A small offsite area still needs seeding, but has vegetated buffer and no visible runoff.
Site Visit Complete 8/22/2017 at 9:35 AM 08/22/2017
Informational
08/22/2017
Tom Chandler 08/22/2017 10:09 AM ESC devices are installed and in good shape.
Verify Substantial Completion Substantial Completion 8/23/2017 08/23/2017
Site Visit Partial 8/28/2017 at 11:00 AM 08/28/2017
Site Visit Complete 9/1/2017 08/29/2017
Informational
08/29/2017
Tom Chandler 08/29/2017 8:08 AM Was on-site on 08/28/2017 with Bart to go over punch list items.
Sidewalk Inspection Partial 9/5/2017 at 9:15 AM 09/05/2017
Sidewalk Inspection Passed 9/6/2017 09/11/2017
Verify Substantial Completion Substantial Completion 9/11/2017 at 7:05 AM 09/11/2017
Storm - Inlets Clean Passed 09/15/2017
Informational
08/29/2017
Tom Chandler 08/29/2017 8:06 AM Was on-site with Bart Reese to go over punch list items.
Verify Final Inspection Status (PW) Complete 9/15/2017 at 8:01 AM 09/15/2017
ESC - (Vegetation/Ground Cover) Passed 09/28/2017
Documents & Images
Date Uploaded File Type Document Name
09/15/2015 Receipt Receipt for transaction: 2015-005392
12/28/2015 Letter PW-Permit
06/20/2016 Letter PW-Daily Inspection Summary
08/01/2016 Letter PW-Daily Inspection Summary
01/18/2017 Letter PW-Site Visit
01/31/2017 Letter PW-Daily Inspection Summary
02/01/2017 Letter PW-Daily Inspection Summary
02/06/2017 Letter PW-Daily Inspection Summary
02/07/2017 Letter PW-Daily Inspection Summary
02/07/2017 Letter PW-Daily Inspection Summary
02/13/2017 Letter PW-Daily Inspection Summary
02/13/2017 Letter PW-Daily Inspection Summary
02/15/2017 Letter PW-Daily Inspection Summary
02/17/2017 Letter PW-Daily Inspection Summary
02/21/2017 Letter PW-Daily Inspection Summary
03/06/2017 Letter PW-Daily Inspection Summary
03/13/2017 Letter PW-Daily Inspection Summary
03/13/2017 Letter PW-Daily Inspection Summary
03/20/2017 Letter PW-Daily Inspection Summary
03/24/2017 Letter PW-Daily Inspection Summary
04/13/2017 Letter PW-Daily Inspection Summary
04/19/2017 Letter PW-Daily Inspection Summary
04/26/2017 Letter PW-Daily Inspection Summary
04/26/2017 Letter PW-Daily Inspection Summary
04/26/2017 Letter PW-Daily Inspection Summary
05/04/2017 Letter PW-Daily Inspection Summary
05/16/2017 Letter PW-Daily Inspection Summary
05/25/2017 Letter PW-Daily Inspection Summary
08/22/2017 Letter PW-Daily Inspection Summary
09/01/2017 Letter DE-Punch List
09/01/2017 Letter DE-Certificate of Substantial Completion Multiple Lot
09/28/2017 Letter DE-Certificate of Final Acceptance (Commercial)
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.