Permit Application Status

PRPWFC20120348


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PRPWFC20120348
Public Works Infrastructure Permit - Commercial
Final Acceptance
HY-VEE INC
DEVELOPMENT COMPLETE
Construction of new gas station
03/01/2012
03/13/2012
02/07/2013
11/27/2012
Locations
Contacts
Not shown for privacy reasons.
HY-VEE INC, Address:5820 WESTOWN PKWY  
Reviews

There are no reviews for this permit application.

Fees
Paid Fees Amount Paid Owing Date Paid
91100C8-Sanitary Sewer Insp Fees $873.30 $873.30 Paid 03/01/2012
91100C9-Water Insp Fee $122.25 $122.25 Paid 03/01/2012
9110072-Water Test Fee $200.00 $200.00 Paid 03/01/2012
9110068-Storm Sewer Inspection Fee $803.10 $803.10 Paid 03/01/2012
9110071-Site Grading Fee $740.18 $740.18 Paid 03/01/2012
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Erosion Control Inspection Passed 4/24/2012 at 12:00 AM 04/25/2012
Grading/Excavation/Fill Inspection Passed/Re-Inspect 4/26/2012 at 12:00 AM 04/26/2012
Grading/Excavation/Fill Inspection Passed/Re-Inspect 4/27/2012 at 12:00 AM 04/27/2012
Grading/Excavation/Fill Inspection Passed/Re-Inspect 5/2/2012 at 12:00 AM 05/03/2012
Grading/Excavation/Fill Inspection Partial 5/5/2012 at 12:00 AM 05/07/2012
Sanitary Sewer - Invert Passed 5/11/2012 at 12:00 AM 05/14/2012
Sanitary Sewer - Air Test Passed 5/16/2012 at 12:00 AM 05/17/2012
Sanitary Sewer - Mandrel Passed 5/16/2012 at 12:00 AM 05/17/2012
Sanitary Sewer - Vacuum Passed 5/16/2012 at 12:00 AM 05/17/2012
Storm Sewer Construction Inspection Passed/Re-Inspect 5/18/2012 at 12:00 AM 05/18/2012
Storm Sewer Construction Inspection Passed 5/19/2012 at 12:00 AM 05/19/2012
Sanitary Sewer Construction Inspection Passed 5/21/2012 at 12:00 AM 05/21/2012
Site Visit Complete 6/18/2012 at 12:00 AM 06/18/2012
Site Visit Complete 6/18/2012 at 12:00 AM 06/18/2012
Site Visit Complete 6/26/2012 at 12:00 AM 06/26/2012
Site Visit Complete 6/28/2012 at 12:00 AM 06/28/2012
Site Visit Complete 7/9/2012 at 12:00 AM 07/09/2012
Erosion Control Inspection Passed 8/24/2012 at 12:00 AM 08/29/2012
Site Visit Complete 5/12/2012 at 12:00 AM 11/09/2012
Verify Substantial Completion Substantial Completion 8/28/2012 at 12:00 AM 11/09/2012
Erosion Control Inspection Passed 5/2/2012 at 12:00 AM 02/04/2013
Documents & Images
Date Uploaded File Type Document Name
03/06/2012 Activity Document 20120306131808386.pdf
03/13/2012 Letter Public Works Permit
05/14/2012 HyVee @ 3rd Street Improvements.jpg
08/29/2012 DOC082912-08292012110434.pdf
08/29/2012 DOC082912-08292012142356.pdf
11/27/2012 DOC112712-11272012142556.pdf
08/29/2013 Letter PW-Punch List
08/29/2013 Letter PW-Permit
08/29/2013 Letter PW-Final Acceptance Commercial
08/29/2013 Letter PW-Punch List
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home