Summary
PRCOM20254604
Building Permit - Commercial
Certificate of Occupancy
PINE TREE PLAZA LLC
CHANGE OF TENANT
CHANGE OF TENANT TO NEW DMV OFFICE
10/23/2025
11/05/2025
05/03/2026
11/13/2025
Locations
Contacts
PINE TREE PLAZA LLC, Address:601 E SOUTH ST  
DROTTZ CONSTRUCTION GROUP LLC, Address:116 N MISSOURI , Phone:(816) 289-5146  
Vern Drottz - Drottz Construction Group, Phone:(816) 289-5746  
HASENOHR ELECTRICAL SERVICES INC, Address:5542 N FLORA AVE, Phone:(816) 365-5366  
Reviews
Review Type Outcome Est. Completion Date Completed
Building Plan Review Approved 11/13/2025 11/05/2025
Joe Frogge
Miscellaneous Correction
Resolved
11/05/2025

Inadequate information to complete review. Actions required: - Label use of room with drinking fountain. (Not allowed to be storage) - Provide electrical scope of work. (how will new counters receive power?)
IBC 1004.1 Design occupant load
Resolved
11/05/2025

2018 IBC 1004.1 Design occupant load. In determining means of egress requirements, the number of occupants for whom means of egress facilities shall be provided shall be determined in accordance with this section. Action required: Calculate occupant loads in the 2 waiting areas as 1:15 loose tables and chairs. (my rough calc shows > 65 which will be fine for egress)
ICC A117.1 404.2.3.2 Swinging Doors Maneuvering Clearance
Resolved
11/05/2025

ICC A117.1 Section 404.2.3.2 Swinging Doors and gates. Swinging doors and gates shall have maneuvering clearances complying with Table 404.2.3.2. Action required: Provide minimum 18" of clearance at latch side of door on the east side of Office 104. 11/5/2025 - legal non-compliant per architect
Fire Plan Review Approved 11/13/2025 11/05/2025
Joe Frogge
Licensed Contractors Approved 11/05/2025 11/05/2025
Joe Frogge
Fire Plan Review Approved 11/04/2025 11/04/2025
Craig Hill
Building Plan Review Rejected 11/04/2025 10/31/2025
Joe Frogge
Miscellaneous Correction
Corrective Action Required
10/31/2025

Inadequate information to complete review. Actions required: - Label use of room with drinking fountain. (Not allowed to be storage) - Provide electrical scope of work. (how will new counters receive power?)
IBC 1004.1 Design occupant load
Corrective Action Required
10/31/2025

2018 IBC 1004.1 Design occupant load. In determining means of egress requirements, the number of occupants for whom means of egress facilities shall be provided shall be determined in accordance with this section. Action required: Calculate occupant loads in the 2 waiting areas as 1:15 loose tables and chairs. (my rough calc shows > 65 which will be fine for egress)
ICC A117.1 404.2.3.2 Swinging Doors Maneuvering Clearance
Corrective Action Required
10/31/2025

ICC A117.1 Section 404.2.3.2 Swinging Doors and gates. Swinging doors and gates shall have maneuvering clearances complying with Table 404.2.3.2. Action required: Provide minimum 18" of clearance at latch side of door on the east side of Office 104.
Licensed Contractors Approved 11/04/2025 10/31/2025
Joe Frogge
Fees
Paid Fees Amount Paid Owing Date Paid
Valuation Fee for Change of Tenant $50.00 $50.00 Paid 11/05/2025
$15,460.50
Commercial Excise Tax Fee $7,730.25 $7,730.25 Paid 10/28/2025
$7,730.25
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
All Rough Inspection - Commercial Passed 11/10/2025 11/10/2025 11/10/2025
In-wall Inspection Passed 11/10/2025 11/10/2025
Occupancy Inspection - Fire Passed 11/13/2025 11/13/2025 11/13/2025
Occupancy Inspection - Codes Commercial Full C of O 11/13/2025 11/13/2025 11/13/2025
Documents & Images
Date Uploaded File Type Document Name
10/23/2025 Application Form APPLICATION
10/28/2025 Plans 1of1
10/28/2025 Letter License Tax Bill
11/04/2025 Letter DS P/R Corrections Document
11/05/2025 Plans A1 sealed
11/05/2025 Letter Submittal Letter
11/05/2025 Approved Plans Approved construction plan
11/05/2025 Receipt Receipt for transaction:2025-008221
11/05/2025 Letter DS Building Permit
11/10/2025 Letter INSPECTION SUMMARY
11/10/2025 Letter INSPECTION SUMMARY
11/13/2025 Letter Codes Final Certificate of Occupancy
11/13/2025 Letter Field Certificate of Occupancy
11/13/2025 Letter INSPECTION SUMMARY
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home