Review Type |
Outcome |
Est. Completion Date |
Completed |
Building Plan Review
|
Approved with Conditions
|
08/01/2023
|
07/25/2023
|
|
Joe Frogge
|
|
Misc
Corrective Action Required
This review assumes that their will be no finger/toe nail service.
Action required: Comment is informational. If nail service is provided a dedicate source capture exhaust system will be required.
6/30/2023 - not addressed
**To be field verified
|
|
Miscellaneous Correction
Inadequate information to complete review.
Provide (at a minimum) the following:
-
-
-
- point of service desk details (accessibility?)
6/30/2023 - not addressed
7/19/23 - no desk being used so not applicable
-
- Finish material plan/schedule
6/30/2023 - New walls labelled as "painted." More information required to verify compliance with 2018 IBC 1209.2.2 for walls adjacent to toilet and mop sink.
7/19/23 - Beaded board not allowed by toilet. Wall by mop sink not addressed.
|
|
|
Licensed Contractors
|
Approved
|
07/25/2023
|
07/25/2023
|
|
Joe Frogge
|
|
|
Fire Plan Review
|
Approved with Conditions
|
08/01/2023
|
07/25/2023
|
|
Joe Frogge
|
|
Miscellaneous Correction
Corrective Action Required
All existing conditions are subject to inspection and correction.
|
|
Portable fire extinguishers - general
Corrective Action Required
2018 IFC 906.2- General requirements. Portable fire extinguishers shall be selected, installed and maintained in accordance with this section and NFPA 10.
Provide a minimum of one, 2A:10B:C fire extinguisher.
|
|
|
Fire Plan Review
|
Approved with Conditions
|
07/25/2023
|
07/24/2023
|
|
Jim Eden
|
|
Miscellaneous Correction
Corrective Action Required
All existing conditions are subject to inspection and correction.
|
|
Portable fire extinguishers - general
Corrective Action Required
2018 IFC 906.2- General requirements. Portable fire extinguishers shall be selected, installed and maintained in accordance with this section and NFPA 10.
Provide a minimum of one, 2A:10B:C fire extinguisher.
|
|
|
Building Plan Review
|
Rejected
|
07/25/2023
|
07/19/2023
|
|
Joe Frogge
|
|
Misc
Corrective Action Required
This review assumes that their will be no finger/toe nail service.
Action required: Comment is informational. If nail service is provided a dedicate source capture exhaust system will be required.
6/30/2023 - not addressed
**To be field verified
|
|
Miscellaneous Correction
Corrective Action Required
Inadequate information to complete review.
Provide (at a minimum) the following:
-
-
-
- point of service desk details (accessibility?)
6/30/2023 - not addressed
7/19/23 - no desk being used so not applicable
-
- Finish material plan/schedule
6/30/2023 - New walls labelled as "painted." More information required to verify compliance with 2018 IBC 1209.2.2 for walls adjacent to toilet and mop sink.
7/19/23 - Beaded board not allowed by toilet. Wall by mop sink not addressed.
|
|
IPC 403.1 Minimum number of fixtures
2018 IPC 403.1 Minimum number of fixtures. Plumbing fixtures shall be provided in the minimum number shown in Table 403.1, based on the actual use of the building or space. Uses not shown in Table 403.1 shall be considered individually by the code official. The number of occupants shall be determined by the International Building Code.
Action required: Provide mop sink.
6/30/2023 - Must be service type sink other than break room or restroom type. (purpose is to avoid mops being rinsed in same sink as hand washing and/or food prep sink)
|
|
|
Licensed Contractors
|
Approved
|
07/25/2023
|
07/19/2023
|
|
Joe Frogge
|
|
|
Fire Plan Review
|
Approved with Conditions
|
07/10/2023
|
07/10/2023
|
|
Joe Frogge
|
|
Miscellaneous Correction
Corrective Action Required
All existing conditions are subject to inspection and correction.
|
|
Portable fire extinguishers - general
Corrective Action Required
2018 IFC 906.2- General requirements. Portable fire extinguishers shall be selected, installed and maintained in accordance with this section and NFPA 10.
Provide a minimum of one, 2A:10B:C fire extinguisher.
|
|
|
Licensed Contractors
|
Approved
|
07/10/2023
|
07/10/2023
|
|
Joe Frogge
|
|
LC - MEP Subs
Lee's Summit Code of Ordinance, Section7-130.4 - Business License. (excerpt)
No person, other than a licensed contractor or employees of a licensed contractor, shall engage in electrical, plumbing or mechanical business, construction, installation or maintenance unless duly licensed in accordance with this section.
Action required: MEP subcontractors are required to be listed on permit. Provide company names of licensed MEP contractors.
6/30/2023 - not addressed
|
|
|
Building Plan Review
|
Rejected
|
07/10/2023
|
06/30/2023
|
|
Joe Frogge
|
|
Misc
Corrective Action Required
This review assumes that their will be no finger/toe nail service.
Action required: Comment is informational. If nail service is provided a dedicate source capture exhaust system will be required.
6/30/2023 - not addressed
**To be field verified
|
|
Miscellaneous Correction
Corrective Action Required
Inadequate information to complete review.
Provide (at a minimum) the following:
-
-
-
- point of service desk details (accessibility?)
6/30/2023 - not addressed
-
- Finish material plan/schedule
6/30/2023 - New walls labelled as "painted." More information required to verify compliance with 2018 IBC 1209.2.2 for walls adjacent to toilet and mop sink.
|
|
Gen - Plan submittal documents
Lee's Summit Code Of Ordinances 7-137. - Submittal Documents. Construction documents, special inspection and structural observation programs, and other data shall be submitted in two (2) or more sets with each application for a permit. A registered design professional licensed by the State of Missouri shall prepare the construction documents. Where special conditions exist, the Building Official is authorized to require additional construction documents to be prepared by a registered design professional licensed by the State of Missouri.
Action required: Plans must be professionally designed/sealed. To appeal for a waiver contact Tracy Deister at 816.969.1200 or Tracy.Deister@CityofLS.net
7/10/23 - Per builder, preparer of plans has engineer's seal. Per Tracy Deister we won't require the seal
|
|
Code analysis required
A code analysis shall be provided which includes but is not limited to occupancy type, occupant load, construction type, actual area, height and floors, allowable area, height and floors, and the codes to which the project is designed.
Action required: Provide code analysis
7/10/23 - Per Tracy Deister we won't require the seal
|
|
IPC 403.1 Minimum number of fixtures
Corrective Action Required
2018 IPC 403.1 Minimum number of fixtures. Plumbing fixtures shall be provided in the minimum number shown in Table 403.1, based on the actual use of the building or space. Uses not shown in Table 403.1 shall be considered individually by the code official. The number of occupants shall be determined by the International Building Code.
Action required: Provide mop sink.
6/30/2023 - Must be service type sink other than break room or restroom type. (purpose is to avoid mops being rinsed in same sink as hand washing and/or food prep sink)
|
|
|
Building Plan Review
|
Rejected
|
06/16/2023
|
06/16/2023
|
|
Joe Frogge
|
|
Misc
Corrective Action Required
This review assumes that their will be no finger/toe nail service.
Action required: Comment is informational. If nail service is provided a dedicate source capture exhaust system will be required.
|
|
Miscellaneous Correction
Corrective Action Required
Inadequate information to complete review.
Provide (at a minimum) the following:
- Plan that shows new work vs. existing
- MEP designs or detailed scopes of work.
- label use of all equipment, devices, furniture, etc. (what are the desk looking things with a circle?)
- point of service desk details (accessibility?)
- Wall construction details
- Finish material plan/schedule
|
|
Gen - Plan submittal documents
Corrective Action Required
Lee's Summit Code Of Ordinances 7-137. - Submittal Documents. Construction documents, special inspection and structural observation programs, and other data shall be submitted in two (2) or more sets with each application for a permit. A registered design professional licensed by the State of Missouri shall prepare the construction documents. Where special conditions exist, the Building Official is authorized to require additional construction documents to be prepared by a registered design professional licensed by the State of Missouri.
Action required: Plans must be professionally designed/sealed. To appeal for a waiver contact Tracy Deister at 816.969.1200 or Tracy.Deister@CityofLS.net
|
|
Code analysis required
Corrective Action Required
A code analysis shall be provided which includes but is not limited to occupancy type, occupant load, construction type, actual area, height and floors, allowable area, height and floors, and the codes to which the project is designed.
Action required: Provide code analysis
|
|
IPC 403.1 Minimum number of fixtures
Corrective Action Required
2018 IPC 403.1 Minimum number of fixtures. Plumbing fixtures shall be provided in the minimum number shown in Table 403.1, based on the actual use of the building or space. Uses not shown in Table 403.1 shall be considered individually by the code official. The number of occupants shall be determined by the International Building Code.
Action required: Provide mop sink.
|
|
|
Licensed Contractors
|
Rejected
|
06/16/2023
|
06/16/2023
|
|
Joe Frogge
|
|
LC - MEP Subs
Corrective Action Required
Lee's Summit Code of Ordinance, Section7-130.4 - Business License. (excerpt)
No person, other than a licensed contractor or employees of a licensed contractor, shall engage in electrical, plumbing or mechanical business, construction, installation or maintenance unless duly licensed in accordance with this section.
Action required: MEP subcontractors are required to be listed on permit. Provide company names of licensed MEP contractors.
|
|
|
Fire Plan Review
|
Approved with Conditions
|
06/16/2023
|
06/15/2023
|
|
Jim Eden
|
|
Miscellaneous Correction
Corrective Action Required
All existing conditions are subject to inspection and correction.
|
|
Portable fire extinguishers - general
Corrective Action Required
2018 IFC 906.2- General requirements. Portable fire extinguishers shall be selected, installed and maintained in accordance with this section and NFPA 10.
Provide a minimum of one, 2A:10B:C fire extinguisher.
|
|
|