Permit Application Status

PRCOM20222727


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PRCOM20222727
Building Permit - Commercial
Voided
VAAP CHAPEL RIDGE LLC
NEW COMMERCIAL
GROUND ROOTS COFFEE - NEW BUILDING FOR COFFEE SHOP WITH DRIVE THRU VOIDED THE APPLICATION AS IT HAS BEEN OVER ONE YEAR SINCE THE PERMIT WAS APPROVED AND THE PERMIT HAD NOT BEEN OBTAINED - Mike Weisenborn 03/05/2024 4:27 PM
06/16/2022
02/18/2023
03/05/2024
Locations
Contacts
INNOVATIVE DESIGN & RENOVATION, Address:8011 PASEO #201, Phone:(816) 531-2221  
VAAP CHAPEL RIDGE LLC, Address:5007 W 147TH ST  
STEPHEN MASLAN & COMPANY, Address:8011 PASEO, Phone:(816) 444-6260  
  
  
  
  
  
Reviews
Review Type Outcome Est. Completion Date Completed
Building Plan Review Approved with Conditions 09/08/2022 09/15/2022
Mike Weisenborn
Final Development Plan
Resolved
09/15/2022

The building permit for this project cannot be issued until the Development Services Department has received, approved, and processed the Final Development Plan. Action required: Comment is for informational purposes. 8/22/22 - not addressed 9/1/22 - acknowledged in letter
Health Dept Inspection
Resolved
09/15/2022

For the Health Department inspection contact Deb Sees with the Jackson County Public Works Department, Environmental Health Division at (816) 847-7070. Health Department approval is required prior to receiving any type of Occupancy from the City of Lee's Summit. Action required: Comment is for informational purposes. 8/22/22 - not addressed 9/1/22 - acknowledged in letter
Engineered truss package
Corrective Action Required
08/31/2022

Copies of the engineered truss package were not provided at the time of permit application. Action required: Provide complete truss package or request deferral. (must be approved by architect before submitting to us) 8/22/22 - not addressed 9/1/22 - deferred per request
IBC 1103.1 Where required - accessibility
Resolved
09/01/2022

2018 IBC 1103.1 Where required. Sites, buildings, structures, facilities, elements and spaces, temporary or permanent, shall be accessible to persons with physical disabilities. 2018 IBC 1103.2.2 Employee work areas. Spaces and elements within employee work areas shall only be required to comply with Sections 907.5.2.3.1, 1009 and 1104.3.1 and shall be designed and constructed so that individual with disabilities can approach, enter and exit the work area. Work areas, or portions of work areas, other than raised courtroom stations in accordance with Section 1108.4.1.4, that are less than 300 square feet in area and located 7 inches or more above or below the ground or finished floor where the change in elevation is essential to the function of the space shall be exempt from all requirements. (see code for additional exemptions) Action required: Swinging door into employee work area not compliant in that it does not have the minimum 18" clearance at the latch side per ICC A117.1-2009 Section 404.2.3.2. 8/22/22 - not addressed
Miscellaneous Correction
Resolved
09/01/2022

Inadequate information to complete review: Provide the following: - Provide complete roof access details including ladder, roof hatch, and 30" side rail ladder extension. Reflected ceiling plan and truss plans also affected. 8/22/22 - not addressed - Furnace installation details. (truss mounted? Is this unit rated to be installed for horizontal flow? Looks like an upflow unit.) 8/22/22 - not addressed - Furnace flue complete design. 8/22/22 - not addressed
IPC 802.1 Indirect/special waste
Resolved
09/01/2022

2018 IPC 802.1 Where required. Food-handling equipment, in other than dwelling units, clear-water waste, humidifiers, dish-washing machines and utensils, pots, pans and dishwashing sinks shall discharge though an indirect waste pipe as specified in Sections 802.1.1 through 802.1.8. Fixtures not required to be indirectly connected by this section and the exception to Section 301.6 shall be directly connected to the plumbing system in accordance with Chapter 7. Action required: Provide floor sink at 3 compartment sink to facilitate indirect drain. 8/22/22 - not addressed
IPC 708.1 Cleanouts required
Resolved
09/01/2022

2018 IPC 708.1 Cleanouts Required. Cleanouts shall be provided for drainage piping in accordance with Sections 708.1.1 through 708.1.11. 2018 IPC 708.1.3 Building drain and building sewer junction. The junction of the building drain and the building sewer shall be served by a cleanout that is located at the junction or within 10 feet of the developed length of piping upstream of the junction. For the requirements of this section, the removal of a water closet shall not be required to provide cleanout access. action required: Provide cleanout near where sanitary leaves foundation. 8/22/22 - not addressed
Final Development Plan Review Approved 10/07/2022 09/15/2022
Mike Weisenborn
GROUND ROOTS COFFEE
Licensed Contractors Approved 09/08/2022 09/01/2022
Joe Frogge
LC - MEP Subs
Resolved
09/01/2022

Lee's Summit Code of Ordinance, Section7-130.4 - Business License. (excerpt) No person, other than a licensed contractor or employees of a licensed contractor, shall engage in electrical, plumbing or mechanical business, construction, installation or maintenance unless duly licensed in accordance with this section. Action required: MEP subcontractors are required to be listed on permit. (Dye Electric not licensed with us) 9/1/22 - Dye Electric still not licensed with us
Fire Plan Review Approved 09/08/2022 09/01/2022
Joe Frogge
Illumination required
Resolved
09/01/2022

[BE] 1008.3.2 Buildings. In the event of power supply failure, in buildings that require two or more means of egress, an emergency electrical system shall automatically illuminate all of the following areas: 1. Interior exit access stairways and ramps 2. Interior and exterior exit stairways and ramps. 3. Exit passageways. 4. Vestibules and areas on the level of discharge used for exit discharge in accordance with Section 1028.1. 5. Exterior landings as required by Section 1010.1.6 for exit doorways that lead directly to the exit discharge. Action required- Provide emergency power for illumination of the exit discharge.
Building Plan Review Rejected 08/26/2022 08/22/2022
Joe Frogge
Final Development Plan
Corrective Action Required
08/04/2022

The building permit for this project cannot be issued until the Development Services Department has received, approved, and processed the Final Development Plan. Action required: Comment is for informational purposes. 8/22/22 - not addressed
Health Dept Review
Resolved
08/19/2022

For the Health Department review contact Deb Sees with the Jackson County Public Works Department, Environmental Services Division, at (816) 847-7070. Health Department approval is required prior to receiving any type of building permit from the City of Lee's Summit. Action required: Comment is for informational purposes.
Health Dept Inspection
Corrective Action Required
08/22/2022

For the Health Department inspection contact Deb Sees with the Jackson County Public Works Department, Environmental Health Division at (816) 847-7070. Health Department approval is required prior to receiving any type of Occupancy from the City of Lee's Summit. Action required: Comment is for informational purposes. 8/22/22 - not addressed
Code analysis required
Resolved
08/22/2022

A code analysis shall be provided which includes but is not limited to occupancy type, occupant load, construction type, actual area, height and floors, allowable area, height and floors, and the codes to which the project is designed. Actions required: - Modify Code Review to show correct occupancy classification which is B. (see 2018 IBC 303.1.1) - Modify Code Review to show correct occupant load calculations. Sales area (1:60) is restricted to area north of counter with product displays. Area with seating to be calculated as Loose Tables & Chairs (1:15)
Engineered truss package
Corrective Action Required
08/04/2022

Copies of the engineered truss package were not provided at the time of permit application. Action required: Provide complete truss package or request deferral. (must be approved by architect before submitting to us) 8/22/22 - not addressed
IBC 1103.1 Where required - accessibility
Corrective Action Required
08/04/2022

2018 IBC 1103.1 Where required. Sites, buildings, structures, facilities, elements and spaces, temporary or permanent, shall be accessible to persons with physical disabilities. 2018 IBC 1103.2.2 Employee work areas. Spaces and elements within employee work areas shall only be required to comply with Sections 907.5.2.3.1, 1009 and 1104.3.1 and shall be designed and constructed so that individual with disabilities can approach, enter and exit the work area. Work areas, or portions of work areas, other than raised courtroom stations in accordance with Section 1108.4.1.4, that are less than 300 square feet in area and located 7 inches or more above or below the ground or finished floor where the change in elevation is essential to the function of the space shall be exempt from all requirements. (see code for additional exemptions) Action required: Swinging door into employee work area not compliant in that it does not have the minimum 18" clearance at the latch side per ICC A117.1-2009 Section 404.2.3.2. 8/22/22 - not addressed
Miscellaneous Correction
Corrective Action Required
08/04/2022

Inadequate information to complete review: Provide the following: - Provide complete roof access details including ladder, roof hatch, and 30" side rail ladder extension. Reflected ceiling plan and truss plans also affected. 8/22/22 - not addressed - Furnace installation details. (truss mounted? Is this unit rated to be installed for horizontal flow? Looks like an upflow unit.) 8/22/22 - not addressed - Furnace flue complete design. 8/22/22 - not addressed
IPC 802.1 Indirect/special waste
Corrective Action Required
08/04/2022

2018 IPC 802.1 Where required. Food-handling equipment, in other than dwelling units, clear-water waste, humidifiers, dish-washing machines and utensils, pots, pans and dishwashing sinks shall discharge though an indirect waste pipe as specified in Sections 802.1.1 through 802.1.8. Fixtures not required to be indirectly connected by this section and the exception to Section 301.6 shall be directly connected to the plumbing system in accordance with Chapter 7. Action required: Provide floor sink at 3 compartment sink to facilitate indirect drain. 8/22/22 - not addressed
IPC 708.1 Cleanouts required
Corrective Action Required
08/04/2022

2018 IPC 708.1 Cleanouts Required. Cleanouts shall be provided for drainage piping in accordance with Sections 708.1.1 through 708.1.11. 2018 IPC 708.1.3 Building drain and building sewer junction. The junction of the building drain and the building sewer shall be served by a cleanout that is located at the junction or within 10 feet of the developed length of piping upstream of the junction. For the requirements of this section, the removal of a water closet shall not be required to provide cleanout access. action required: Provide cleanout near where sanitary leaves foundation. 8/22/22 - not addressed
Fire Plan Review Rejected 08/26/2022 08/22/2022
Joe Frogge
Illumination required
Corrective Action Required
08/04/2022

[BE] 1008.3.2 Buildings. In the event of power supply failure, in buildings that require two or more means of egress, an emergency electrical system shall automatically illuminate all of the following areas: 1. Interior exit access stairways and ramps 2. Interior and exterior exit stairways and ramps. 3. Exit passageways. 4. Vestibules and areas on the level of discharge used for exit discharge in accordance with Section 1028.1. 5. Exterior landings as required by Section 1010.1.6 for exit doorways that lead directly to the exit discharge. Action required- Provide emergency power for illumination of the exit discharge.
Licensed Contractors Rejected 08/26/2022 08/22/2022
Joe Frogge
LC - MEP Subs
Corrective Action Required
08/04/2022

Lee's Summit Code of Ordinance, Section7-130.4 - Business License. (excerpt) No person, other than a licensed contractor or employees of a licensed contractor, shall engage in electrical, plumbing or mechanical business, construction, installation or maintenance unless duly licensed in accordance with this section. Action required: MEP subcontractors are required to be listed on permit. (Dye Electric not licensed with us)
Health Department Review Approved 08/19/2022
Joe Frogge
Fire Plan Review Approved with Conditions 06/30/2022 06/27/2022
Jim Eden
Illumination required
Corrective Action Required
06/27/2022

[BE] 1008.3.2 Buildings. In the event of power supply failure, in buildings that require two or more means of egress, an emergency electrical system shall automatically illuminate all of the following areas: 1. Interior exit access stairways and ramps 2. Interior and exterior exit stairways and ramps. 3. Exit passageways. 4. Vestibules and areas on the level of discharge used for exit discharge in accordance with Section 1028.1. 5. Exterior landings as required by Section 1010.1.6 for exit doorways that lead directly to the exit discharge. Action required- Provide emergency power for illumination of the exit discharge.
Building Plan Review Rejected 06/30/2022 06/27/2022
Joe Frogge
Final Development Plan
Corrective Action Required
06/27/2022

The building permit for this project cannot be issued until the Development Services Department has received, approved, and processed the Final Development Plan. Action required: Comment is for informational purposes.
Health Dept Review
Corrective Action Required
06/27/2022

For the Health Department review contact Deb Sees with the Jackson County Public Works Department, Environmental Services Division, at (816) 847-7070. Health Department approval is required prior to receiving any type of building permit from the City of Lee's Summit. Action required: Comment is for informational purposes.
Health Dept Inspection
Corrective Action Required
06/27/2022

For the Health Department inspection contact Deb Sees with the Jackson County Public Works Department, Environmental Health Division at (816) 847-7070. Health Department approval is required prior to receiving any type of Occupancy from the City of Lee's Summit. Action required: Comment is for informational purposes.
Code analysis required
Corrective Action Required
06/27/2022

A code analysis shall be provided which includes but is not limited to occupancy type, occupant load, construction type, actual area, height and floors, allowable area, height and floors, and the codes to which the project is designed. Actions required: - Modify Code Review to show correct occupancy classification which is B. (see 2018 IBC 303.1.1) - Modify Code Review to show correct occupant load calculations. Sales area (1:60) is restricted to area north of counter with product displays. Area with seating to be calculated as Loose Tables & Chairs (1:15)
Engineered truss package
Corrective Action Required
06/27/2022

Copies of the engineered truss package were not provided at the time of permit application. Action required: Provide complete truss package or request deferral. (must be approved by architect before submitting to us)
IBC 1103.1 Where required - accessibility
Corrective Action Required
06/27/2022

2018 IBC 1103.1 Where required. Sites, buildings, structures, facilities, elements and spaces, temporary or permanent, shall be accessible to persons with physical disabilities. 2018 IBC 1103.2.2 Employee work areas. Spaces and elements within employee work areas shall only be required to comply with Sections 907.5.2.3.1, 1009 and 1104.3.1 and shall be designed and constructed so that individual with disabilities can approach, enter and exit the work area. Work areas, or portions of work areas, other than raised courtroom stations in accordance with Section 1108.4.1.4, that are less than 300 square feet in area and located 7 inches or more above or below the ground or finished floor where the change in elevation is essential to the function of the space shall be exempt from all requirements. (see code for additional exemptions) Action required: Swinging door into employee work area not compliant in that it does not have the minimum 18" clearance at the latch side per ICC A117.1-2009 Section 404.2.3.2.
Miscellaneous Correction
Corrective Action Required
06/27/2022

Inadequate information to complete review: Provide the following: - Provide complete roof access details including ladder, roof hatch, and 30" side rail ladder extension. Reflected ceiling plan and truss plans also affected. - Furnace installation details. (truss mounted? Is this unit rated to be installed for horizontal flow? Looks like an upflow unit.) - Furnace flue complete design.
IPC 802.1 Indirect/special waste
Corrective Action Required
06/27/2022

2018 IPC 802.1 Where required. Food-handling equipment, in other than dwelling units, clear-water waste, humidifiers, dish-washing machines and utensils, pots, pans and dishwashing sinks shall discharge though an indirect waste pipe as specified in Sections 802.1.1 through 802.1.8. Fixtures not required to be indirectly connected by this section and the exception to Section 301.6 shall be directly connected to the plumbing system in accordance with Chapter 7. Action required: Provide floor sink at 3 compartment sink to facilitate indirect drain.
IPC 708.1 Cleanouts required
Corrective Action Required
06/27/2022

2018 IPC 708.1 Cleanouts Required. Cleanouts shall be provided for drainage piping in accordance with Sections 708.1.1 through 708.1.11. 2018 IPC 708.1.3 Building drain and building sewer junction. The junction of the building drain and the building sewer shall be served by a cleanout that is located at the junction or within 10 feet of the developed length of piping upstream of the junction. For the requirements of this section, the removal of a water closet shall not be required to provide cleanout access. action required: Provide cleanout near where sanitary leaves foundation.
Licensed Contractors Rejected 06/30/2022 06/27/2022
Joe Frogge
LC - General Contractor
Resolved
06/28/2022

Lee's Summit Code of Ordinance, Section7-130.10 - Business License. It shall be unlawful for any person to engage in the construction contracting business without first obtaining a business license as required under the applicable provisions of Chapter 28 of the Lee's Summit Code of Ordinances. Action required: Either a Class A or Class B license is required. Provide the company name of the licensed general contractor and an email address & phone number for the on-site contact which is where inspection reports will be sent.
LC - MEP Subs
Corrective Action Required
06/27/2022

Lee's Summit Code of Ordinance, Section7-130.4 - Business License. (excerpt) No person, other than a licensed contractor or employees of a licensed contractor, shall engage in electrical, plumbing or mechanical business, construction, installation or maintenance unless duly licensed in accordance with this section. Action required: MEP subcontractors are required to be listed on permit. Provide company names of licensed MEP contractors.
Inspections

There are no inspections for this permit application.

Documents & Images
Date Uploaded File Type Document Name
06/16/2022 Application Form Commercial Permit Application (GROUND ROOTS COFFEE1)
06/16/2022 Engineer Report/Study Ground Roots Structural Calcs
06/16/2022 Plans Ground Roots coffee Sealed 5-20-22-1
06/16/2022 Letter License Tax Bill
06/28/2022 Letter DS P/R Corrections Document
08/03/2022 Letter code response for ground roots coffee
08/19/2022 Plans Ground Roots coffee Sealed 8-19-22
08/19/2022 Email health department
08/22/2022 Letter DS P/R Corrections Document
08/31/2022 Letter DS P_R Corrections Document-2ground roots coffee8-25-22
08/31/2022 Plans Ground Roots coffee Sealed 8-30-22
09/15/2022 Approved Plans Approved Ground Roots Coffee FDP
01/10/2023 Plans Ground Roots coffee Sealed 1-10-23
01/12/2023 Approved Plans approved - Ground Roots coffee Sealed 1-10-23
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home