Inspection |
Outcome |
Requested |
Scheduled |
Date Inspected |
Site Visit
|
Partial
|
|
|
08/10/2022
|
|
Misc
|
Site Visit
|
Partial
|
|
|
08/26/2022
|
|
Misc
|
Footing Inspection - Commercial
|
Passed
|
8/30/2022 (8:00)
|
8/30/2022
|
08/30/2022
|
Site Visit
|
Partial
|
|
|
08/31/2022
|
|
Misc
|
Site Visit
|
Partial
|
|
|
09/07/2022
|
|
Misc
|
Erosion Control Inspection Residential
|
Partial
|
|
|
09/07/2022
|
|
Misc
|
Site Visit
|
Partial
|
|
|
09/12/2022
|
|
Misc
|
Erosion Control Inspection Residential
|
Partial
|
|
|
09/12/2022
|
|
Misc
|
Pavement-Aggregate Base
|
Passed
|
|
|
09/21/2022
|
|
Misc
|
Pavement-Surface
|
Passed
|
|
|
09/21/2022
|
|
Misc
|
In-wall Inspection
|
Failed
|
9/27/2022
|
9/27/2022
|
09/27/2022
|
|
Miscellaneous Correction
Corrective Action Required
|
Pavement-Curb Construction
|
Passed
|
|
|
09/29/2022
|
|
Misc
|
In-wall Inspection
|
Passed
|
|
10/5/2022
|
10/05/2022
|
|
Miscellaneous Correction
|
Erosion Control Inspection Residential
|
Passed
|
|
|
11/16/2022
|
|
Misc
|
Occupancy Inspection - Engineering
|
Passed
|
|
11/16/2022
|
11/16/2022
|
|
Misc
|
Occupancy Inspection - Planning
|
Failed
|
|
11/16/2022
|
11/16/2022
|
|
Corrective Action Required
|
Above Ceiling Inspection
|
Passed
|
|
11/16/2022
|
11/16/2022
|
Occupancy Inspection - Codes Commercial
|
Failed
|
11/16/2022
|
11/16/2022
|
11/16/2022
|
|
Miscellaneous Correction
Corrective Action Required
|
Occupancy Inspection - Fire
|
Passed
|
11/16/2022
|
11/16/2022
|
11/17/2022
|
Occupancy Inspection - Codes Commercial
|
Ready for Temp CO
|
|
|
11/17/2022
|
|
Miscellaneous Correction
Corrective Action Required
|
|
Miscellaneous Correction
Corrective Action Required
|
Occupancy Inspection - Planning
|
Passed
|
|
|
04/03/2023
|
Occupancy Inspection - Codes Commercial
|
Full C of O
|
|
|
04/03/2023
|
|
Miscellaneous Correction
|
|
Miscellaneous Correction
|