Permit Application Status

PRCOM20215278


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PRCOM20215278
Building Permit - Commercial
Certificate of Occupancy
CHAPEL RIDGE TOWNHOMES LLC
NEW MULTI-FAMILY
NEW 4PLEX
10/08/2021
08/25/2022
06/22/2023
Locations
Contacts
CAPITAL CONSTRUCTION SERVICES LLC, Address:2642 NE HAGAN RD, Phone:(816) 875-0018  
DROTHFUSS@CAPITALCONST.COM  
UNITED HEATING & COOLING, Address:301 DUCK RD, Phone:(816) 761-5262  
INHOME SYSTEMS LLC, Address:510 MISSION RD SW, Phone:(816) 372-0483  
A BRIGHT PLUMBING LLC, Address:201 NE WOODBURY DR, Phone:(816) 867-4540  
DAVIDSON ARCHITECTURE & ENGINEERING, Address:4301 INDIAN CREEK PKWY, Phone:(913) 451-9390  
CHAPEL RIDGE TOWNHOMES LLC, Address:3701 NE AKIN DR  
TEG CHAPEL RIDGE LLC, Address:365 NY 59 STE 110  
Reviews
Review Type Outcome Est. Completion Date Completed
Licensed Contractors Approved 01/07/2022
Joe Frogge
Fees
Paid Fees Amount Paid Owing Date Paid
8331506-EFHB Maybrook, Full $1,874.84 $1,874.84 Paid 08/24/2022
8331507-Sewer Connection Fee $1,320.00 $1,320.00 Paid 08/24/2022
7232302-Residential Excise Tax Fee $2,437.12 $2,437.12 Paid 08/24/2022
9110078-Valuation Fee for New 3 or 4 Family $2,251.12 $2,251.12 Paid 08/24/2022
9110078-Temporary Occupancy Fee $50.00 $50.00 Paid 06/02/2023
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Footing Inspection - Commercial Passed 9/14/2022 (10:00) 9/14/2022 09/14/2022
Underslab Plumbing Inspection - Commercial Passed 9/28/2022 9/28/2022 09/28/2022
Rated Assembly Inspection Partial 12/12/2022 12/12/2022 12/12/2022
Misc
Corrective Action Required
12/12/2022
Attic firewall-1st layer ok
Electrical Service Inspection Passed 2/1/2023 2/1/2023 02/01/2023
Misc
Corrective Action Required
02/01/2023
-Pump pressure up to min ten psi for testing
Gas Service Inspection - Commercial Failed 2/1/2023 2/1/2023 02/01/2023
Misc
Corrective Action Required
02/01/2023
-Provide min ten psi pressure for testing
All Rough Inspection - Commercial Failed 2/1/2023 2/1/2023 02/01/2023
Misc
Corrective Action Required
02/01/2023
-Support AC lines in attic UNIT A: -Complete wiring to kitchen island -Fully nail laundry/bathroom wall stud shoe -Connect ducts to 2nd fl bathroom fans -Protect bathroom wiring at hallway bottom wall plate -Strap top plate and protect AC line at rear closet UNIT B: -Complete wiring to half bathroom fan and kitchen island -Protect 3” waste stack at kitchen/bathroom wall -Fb wall plate opening at bathroom/laundry wall -Protect dryer duct -Protect washer wiring at bottom wall plate -Protect 3” vent stack at master shower/closet wall UNIT C: -Shim gap at porch beam support -Complete wiring to kitchen island -Over notched joist at master bathroom shower trap UNIT D: -Fix half bathroom fan ducting -Complete wiring to kitchen island -Fully nail laundry/bathroom wall stud shoe -Nail corner studs per code -Nail LIB strap at master bedroom wall -Complete installing switch at master bathroom **OK TO INSULATE
All Rough Inspection - Commercial Failed 2/3/2023 2/3/2023 02/03/2023
Misc
Corrective Action Required
02/01/2023
-Support AC lines in attic UNIT A: UNIT B: -Protect clothes washer wiring at bottom wall plate UNIT C: UNIT D: -Fully nail laundry/bathroom wall stud shoe -Complete installing switch at master bathroom
Gas Service Inspection - Commercial Failed 2/3/2023 2/3/2023 02/03/2023
Misc
Corrective Action Required
02/01/2023
-Provide min ten psi pressure for testing Unit D is OK. All other units have either zero or less than 10 psi test pressure
All Rough Inspection - Commercial Passed 2/8/2023 2/8/2023 02/08/2023
Misc
Resolved
02/08/2023
-Support AC lines in attic UNIT A: UNIT B: UNIT C: UNIT D:
Gas Service Inspection - Commercial Failed 2/8/2023 2/8/2023 02/08/2023
Misc
Corrective Action Required
02/03/2023
Unit A only-air leakage from the shutoff valve. I can hear the bubbling sound from it All other units are ok
Rated Assembly Inspection Partial 2/15/2023 2/15/2023 02/15/2023
Misc
Corrective Action Required
12/12/2022
Attic firewall-2nd layer ok Dwelling firewall-1st layer ok
Gas Service Inspection - Commercial Passed 2/17/2023 2/17/2023 02/17/2023
Misc
Resolved
02/17/2023
Unit A only-air leakage from the shutoff valve. I can hear the bubbling sound from it All other units are ok
Rated Assembly Inspection Failed 2/22/2023 2/22/2023 02/22/2023
Misc
Corrective Action Required
02/15/2023
Attic firewall-2nd layer ok Dwelling firewall-2nd layer ok **Fire caulk penetrations of firewall between unit B&C at I beam
Rated Assembly Inspection Passed 2/23/2023 2/23/2023 02/23/2023
Misc
Resolved
02/23/2023
Attic firewall-2nd layer ok Dwelling firewall-2nd layer ok **Fire caulk penetrations of firewall between unit B&C at I beam
Occupancy Inspection - Codes Commercial Failed 5/30/2023 5/30/2023 05/30/2023
Misc
Corrective Action Required
05/30/2023
EXTERIOR: -Final grade, sod, splash blocks -Seal exterior light, wall penetrations, flashing/sealing above service equipment, etc -Install tamper proof caps at AC valves of units A&B UNIT A: -Fix electrical to furnace. Install connector at NM cable entry into furnace enclosure; the cover for the terminal box inside the furnace is missing UNIT B: -Fix electrical to furnace. Secure switch cover plate; NM sheathing must extend min 1/4” into furnace electrical terminal enclosure; install connector at NM cable entry into furnace enclosure; the cover for the terminal box inside the furnace is missing UNIT C: -Install/secure anti-tipping device for range -Fix electrical to furnace. Install connector at NM cable entry into furnace enclosure; the cover for the terminal box inside the furnace is missing UNIT D: -Secure all MC under kitchen sink per code -Fix electrical to furnace. NM cable sheathing must extend min 1/4” into furnace electrical terminal enclosure; install connector at NM cable entry into furnace enclosure; the cover for the terminal box inside the furnace is missing
Occupancy Inspection - Codes Commercial Ready for Temp CO 6/2/2023 6/2/2023 06/02/2023
Misc
Corrective Action Required
05/30/2023
EXTERIOR: -Final grade, sod, splash blocks -Seal exterior light, wall penetrations, flashing/sealing above service equipment, etc UNIT A: UNIT B: UNIT C: -Install/secure anti-tipping device for range UNIT D:
Occupancy Inspection - Codes Commercial Full C of O 6/22/2023 06/22/2023
Misc
Resolved
06/22/2023
EXTERIOR: -Final grade, sod, splash blocks -Seal exterior light, wall penetrations, flashing/sealing above service equipment, etc **TCO APPROVED FOR ALL UNITS
Documents & Images
Date Uploaded File Type Document Name
08/24/2022 Receipt Receipt for transaction:2022-006945
08/25/2022 Letter DS Building Permit
09/14/2022 Letter INSPECTION SUMMARY
09/28/2022 Letter INSPECTION SUMMARY
12/12/2022 Letter INSPECTION SUMMARY
02/01/2023 Letter INSPECTION SUMMARY
02/01/2023 Letter INSPECTION SUMMARY
02/01/2023 Letter INSPECTION SUMMARY
02/03/2023 Letter INSPECTION SUMMARY
02/03/2023 Letter INSPECTION SUMMARY
02/08/2023 Letter INSPECTION SUMMARY
02/08/2023 Letter INSPECTION SUMMARY
02/15/2023 Letter INSPECTION SUMMARY
02/17/2023 Letter INSPECTION SUMMARY
02/22/2023 Letter INSPECTION SUMMARY
02/23/2023 Letter INSPECTION SUMMARY
05/30/2023 Letter INSPECTION SUMMARY
06/02/2023 Certificate/License Codes Temporary Certificate of Occupancy
06/02/2023 Receipt Receipt for transaction:2023-003915
06/22/2023 Letter Codes Final Certificate of Occupancy
06/22/2023 Letter Field Certificate of Occupancy
12/20/2023 Codes Temporary Certificate of Occupancy218
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home