Summary
PRCOM20215273
Building Permit - Commercial
Certificate of Occupancy
CHAPEL RIDGE TOWNHOMES LLC
NEW MULTI-FAMILY
NEW 4PLEX
10/08/2021
01/21/2022
06/19/2023
Locations
Contacts
CAPITAL CONSTRUCTION SERVICES LLC, Address:2642 NE HAGAN RD, Phone:(816) 875-0018  
DROTHFUSS@CAPITALCONST.COM  
UNITED HEATING & COOLING, Address:301 DUCK RD, Phone:(816) 761-5262  
INHOME SYSTEMS LLC, Address:510 MISSION RD SW, Phone:(816) 372-0483  
A BRIGHT PLUMBING LLC, Address:201 NE WOODBURY DR, Phone:(816) 867-4540  
DAVIDSON ARCHITECTURE & ENGINEERING, Address:4301 INDIAN CREEK PKWY, Phone:(913) 451-9390  
CHAPEL RIDGE TOWNHOMES LLC, Address:3701 NE AKIN DR  
TEG CHAPEL RIDGE LLC, Address:365 NY 59 STE 110  
Reviews
Review Type Outcome Est. Completion Date Completed
Licensed Contractors Approved 01/07/2022
Joe Frogge
Fees
Paid Fees Amount Paid Owing Date Paid
8331506-EFHB Maybrook, Full $1,874.84 $1,874.84 Paid 01/20/2022
8331507-Sewer Connection Fee $1,320.00 $1,320.00 Paid 01/20/2022
7232302-Residential Excise Tax Fee $2,437.12 $2,437.12 Paid 01/20/2022
9110078-Valuation Fee for New 3 or 4 Family $2,349.12 $2,349.12 Paid 01/20/2022
9110078-Temporary Occupancy Fee $50.00 $50.00 Paid 06/02/2023
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Footing Inspection - Commercial Passed 3/28/2022 (2:00) 3/28/2022 03/28/2022
Underslab Plumbing Inspection - Commercial Passed 4/8/2022 4/8/2022 04/08/2022
Rated Assembly Inspection Partial 6/21/2022 6/21/2022 06/21/2022
Misc
Corrective Action Required
06/21/2022
Attic separation wall-1st layer OK
Electrical Service Inspection Passed 7/27/2022 7/27/2022 07/27/2022
Gas Service Inspection - Commercial Failed 7/27/2022 07/27/2022
Misc
Corrective Action Required
07/27/2022
-Unit B pressure gauge is defective. Needle not moving when pressure is released **Other units gas test OK
All Rough Inspection - Commercial Failed 7/27/2022 7/27/2022 07/27/2022
Misc
Corrective Action Required
07/27/2022
COMMON: -Missing support clips at roof deck edge -Install insulation shield for b-vent in attic UNIT A: -Nail garage PFH wall sheathing to header beam per code -Fb wire penetrations of plate above 3-gang kitchen light switch -Support plumbing above kitchen area per code -Fb bottom wall plate penetrations at rear bedroom; AC line penetration at closet -Nail brace strap behind bathroom tub -Nail all holes of corner truss hangers above rear bedroom and master bathroom -Bathroom tub plumbing outside wall space -Complete electrical to light box above laundry -Protect wiring at bottom wall plate near light switch -Tie down girder truss UNIT B: -Nail garage PFH wall sheathing to header beam per code -Remove bonding screw from neutral bus bar -Vent connections cannot be below the trap weirs -Support plumbing above kitchen area and dining per code -Insulate the AC line -Protect plumbing at rear bathroom -Plumbing vent cannot be located within 4 ft of firewall -Replace gas test pressure gauge. Needle not moving when pressure is released -Support vent in attic. FYI: wall needs to be rocked -Fb all wall plate penetrations UNIT C: -Nail garage PFH wall sheathing to header beam per code -Full support for I beam at half bathroom -Close hole at master shower bottom wall plate -Vent connections cannot be below the trap weirs -Support vent in attic -Fb all wall plate penetrations UNIT D: -Complete dryer ducting -Protect wiring at bottom wall plate below upper landing stair light switch -Nail all holes of corner truss hangers above rear bedroom and master bathroom **HAVE A LADDER ON SITE. I WANT TO VERIFY THE ATTIC DUCT INSULATION **OK TO INSULATE
All Rough Inspection - Commercial Failed 8/4/2022 8/4/2022 08/04/2022
Misc
Corrective Action Required
07/27/2022
Support all gas piping Csst per code. UNIT A: -Nail all holes of corner truss hangers above rear bedroom and master bathroom UNIT B: -Remove bonding screw from neutral bus bar -Protect plumbing at rear bathroom -Plumbing vent cannot be located within 4 ft of firewall - repair plywood.. -Replace gas test pressure gauge. Needle not moving when pressure is released -Support vent in attic. FYI: wall needs to be rocked UNIT C: UNIT D: -Nail all holes of corner truss hangers above rear bedroom and master bathroom
All Rough Inspection - Commercial Failed 8/11/2022 8/11/2022 08/11/2022
Misc
Corrective Action Required
08/04/2022
UNIT A: -Nail all holes of corner truss hangers above master bathroom **no access UNIT B: -Plumbing vent cannot be located within 4 ft of firewall **repair plywood.. -Replace gas test pressure gauge. Needle not moving when pressure is released **no access UNIT C: UNIT D:
Rated Assembly Inspection Partial 8/12/2022 8/12/2022 08/12/2022
Misc
Corrective Action Required
06/21/2022
Attic separation wall-2nd layer OK Dwelling separation-1st layer OK
Rated Assembly Inspection Partial 8/22/2022 8/22/2022 08/22/2022
Misc
Corrective Action Required
08/12/2022
Attic separation wall-2nd layer OK Dwelling separation-2nd layer OK -Fire caulk penetrations at I beam. Fully caulking around penetrations -Close excessive gap between FlameBlock sheathings located within 4 ft of firewall
Rated Assembly Inspection Passed 8/26/2022 8/26/2022 08/26/2022
Misc
Resolved
08/26/2022
Attic separation wall-2nd layer OK Dwelling separation-2nd layer OK -Fire caulk penetrations at I beam. Fully caulking around penetrations -Close excessive gap between FlameBlock sheathings located within 4 ft of firewall
Occupancy Inspection - Codes Commercial Failed 12/20/2022 12/20/2022 12/20/2022
Misc
Corrective Action Required
12/20/2022
EXTERIOR: -Final grade, sod, splash blocks -Flashing above protrusion behind electrical service -Seal exterior wall penetrations; seal lights -AC coolant line caps missing UNIT A: -Adjust garage door to fully self-close -2nd fl bathroom receptacle is loose -Anti-hammer arrestor for washer water supply outlet -Move water heater P/T discharge pipe into pan UNIT B: -Gas service failed. **replace gas test pressure gauge. Needle not moving when pressure is released -First floor smoke alarm not interconnected -Washer receptacle not tripping -Anti-hammer arrestor for washer water supply outlet UNIT C: -Anti-hammer arrestor for washer water supply outlet -Master bathroom fan not working UNIT D: -Provide min 6” clearance from single-wall connector to combustible. Too close -Anti-hammer arrestor for washer water supply outlet
Gas Service Inspection - Commercial Passed 12/28/2022 12/28/2022 12/28/2022
Misc
Resolved
12/28/2022
-Unit B pressure gauge is defective. Needle not moving when pressure is released **Other units gas test OK
All Rough Inspection - Commercial Passed 12/28/2022
Misc
Resolved
12/28/2022
UNIT A: -Nail all holes of corner truss hangers above master bathroom **no access UNIT B: -Plumbing vent cannot be located within 4 ft of firewall **repair plywood.. -Replace gas test pressure gauge. Needle not moving when pressure is released **no access UNIT C: UNIT D:
Occupancy Inspection - Codes Commercial Ready for Temp CO 12/29/2022 12/29/2022 12/29/2022
Misc
Corrective Action Required
12/20/2022
EXTERIOR: -Final grade, sod, splash blocks -Flashing above protrusion behind electrical service -Seal exterior wall penetrations; seal lights. **TCO APPROVED FOR ALL UNITS
Occupancy Inspection - Codes Commercial Full C of O 6/19/2023 06/19/2023
Misc
Resolved
06/19/2023
EXTERIOR: -Final grade, sod, splash blocks -Flashing above protrusion behind electrical service -Seal exterior wall penetrations; seal lights. **TCO APPROVED FOR ALL UNITS
Documents & Images
Date Uploaded File Type Document Name
01/20/2022 Receipt Receipt for transaction:2022-000334
02/23/2022 Letter DS Building Permit
03/28/2022 Letter INSPECTION SUMMARY
04/08/2022 Letter INSPECTION SUMMARY
06/21/2022 Letter INSPECTION SUMMARY
07/27/2022 Letter INSPECTION SUMMARY
07/27/2022 Letter INSPECTION SUMMARY
07/27/2022 Letter INSPECTION SUMMARY
08/04/2022 Letter INSPECTION SUMMARY
08/11/2022 Letter INSPECTION SUMMARY
08/12/2022 Letter INSPECTION SUMMARY
08/22/2022 Letter INSPECTION SUMMARY
08/26/2022 Letter INSPECTION SUMMARY
12/20/2022 Letter INSPECTION SUMMARY
12/28/2022 Letter INSPECTION SUMMARY
12/28/2022 Letter INSPECTION SUMMARY
06/02/2023 Certificate/License Codes Temporary Certificate of Occupancy
06/02/2023 Receipt Receipt for transaction:2023-003915
06/19/2023 Letter Codes Final Certificate of Occupancy
06/19/2023 Letter Field Certificate of Occupancy
06/23/2023 Letter DS Building Permit
12/20/2023 Codes Temporary Certificate of Occupancy214
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home