Permit Application Status

PRCOM20210427


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PRCOM20210427
Building Permit - Commercial
Certificate of Occupancy
LMCZ ENTERPRISES LLC
NEW COMMERCIAL
NEW BUILDING PET BOARDING AND DAYCARE FACILITY WITH SPACE FOR FUTURE VET CLINIC (PRCOM20211647) this is the SHELL.
01/29/2021
04/12/2021
08/07/2021
07/12/2022
Locations
Contacts
BEAR CONSTRUCTION SERVICES, Address:9218 METCALF #311, Phone:(913) 674-8004  
TOWN & COUNTRY HEATING AND AIR CONDITIONING COMPANY LLC, Address:10674 WIDMER ROAD, Phone:(913) 649-8696  
PRECISE ELECTRIC LLC, Address:3205 STEEL CIR, Phone:(816) 529-1799  
INTEGRITY PLUMBING SERVICES LLC, Address:405 SW Nelson Dr., Phone:(816) 803-9032  
GPD GROUP PROFESSIONAL CORP, Address:520 SOUTH MAIN STREET STE 2531, Phone:(330) 572-2100  
d.mcmillin@bearconstructionservices.com, Address:d.mcmillin@bearconstructionservices.com  
LMCZ ENTERPRISES LLC, Address:2400 SW WINTERFIELD CT  
UES dba GEOTECHNOLOGY LLC, Address:5055 ANTIOCH RD, Phone:(913) 438-1900  
Reviews
Review Type Outcome Est. Completion Date Completed
Alarm Plan Review Released for Construction 03/20/2022
Jim Eden
Alarm testing.
Corrective Action Required
03/20/2022

2018 IFC 904.4.2- Alarm testing. Notification appliances, connections to fire alarm systems, and connections to approved supervising stations shall be tested in accordance with this section and Section 907 to verify proper operation. Coordinate alarm testing with the sprinkler flow testing. Call (816) 969-1300 to schedule a test.
Sprinkler Plan Review Released for Construction 10/20/2021 10/20/2021
Michael Weissenbach
Installation acceptance testing
Corrective Action Required
10/20/2021

2018 IFC 901.5- Installation acceptance testing. Fire detection and alarm systems, fire-extinguishing systems, fire hydrant systems, fire standpipe systems, fire pump systems, private fire service mains and all other fire protection systems and appurtenances thereto shall be subject to acceptance tests as contained in the installation standards and as approved by the fire code official. The fire code official shall be notified before any required acceptance testing. The fire code official shall be notified 48 hours before any required acceptance test. (Informational Purposes) Call (816)969-1300 to schedule a hydrostatic and waterflow test.
Building Plan Review Approved 02/23/2021 04/12/2021
Joe Frogge
Final Development Plan
Resolved
04/12/2021

The building permit for this project cannot be issued until the Development Services Department has received, approved, and processed the Final Development Plan. Action required: Comment is for informational purposes. 2/18/21 - acknowledged in letter
Miscellaneous Correction
Resolved
04/09/2021

A License Tax application completed by the contractor must be submitted to the City of Lee's Summit, Codes Administration Department, and any applicable License Tax paid prior to issuing a building permit. Action required: Comment is for informational purposes. 2/18/21 - acknowledged in letter
IBC 1704.2 Special Inspections
Resolved
02/19/2021

2018 IBC 1704.2 Special inspections. Where application is made for construction as described in this section, the owner or the registered design professional in responsible charge acting as the owner’s agent shall employ one or more approved agencies to perform inspections during construction on the types of work listed under Section 1705. These inspections are in addition to the inspections identified in Lee’s Summit Code of Ordinances Chapter 7. (see code section for exceptions) Action required: Provide statement of special inspections / letter of responsibility from company contracted to perform special inspections. 2/18/21 - acknowledged in letter - should arrive soon
IBC 1803.1 General - geotech
Resolved
02/18/2021

2018 IBC 1803.1 General. Geotechnical investigations shall be conducted in accordance with Section 1803.2 and reported in accordance with Section 1803.6. Where required by the building official or where geotechnical investigations involve in-situ testing, laboratory testing or engineering calculations, such investigations shall be conducted by a registered design professional. Action required: Provide soils report to justify design assumption of soil bearing capacity greater than 2,000psf.
IBC 1209.2 Finish materials
Resolved
02/18/2021

2018 IBC 1209.2 Finish Materials. Walls, Floors and partitions in toilet and bathrooms shall comply with Sections 209.2.1 through 1209.2.4. 2018 1209.2.1 Floors and wall bases. In other than dwelling units, toilet, bathing and shower room floor finish materials shall have a smooth, hard, nonabsorbent surface. The intersections of such floors with walls shall have a smooth, hard, nonabsorbent vertical base that extends upward onto the walls not less than 4 inches. 2018 1209.2.2 Walls and partitions. Walls and partitions within 2 feet of service sinks, urinals and water closets shall have a smooth, hard, nonabsorbent surface, to a height of not less than 4 feet above the floor, and except for structural elements, the materials used in such walls shall be of a type that is not adversely affected by moisture. (See code section for possible exceptions.) 1209.2.3 Showers. (see code for details) 1209.2.4 Waterproof joints. (see code for details) Action required: Specify compliant materials at water closets and janitor's sink. If paint is used it must be epoxy based.
IMC 501.3.1 Location of exhaust outlets
Resolved
02/18/2021

2018 IMC 501.3.1 Location of exhaust outlets. The termination point of exhaust outlets and ducts discharging to the outdoors shall be located with the following minimum distances: (see code for items 1, 2, 4, & 5) 3. For all environmental air exhaust: 3 feet from property lines; 3 feet from operable openings into building for all occupancies other than Group U, and 10 feet from mechanical air intakes. Such exhaust shall not be considered hazardous or noxious. Action required: Modify plans to demonstrate that exhaust outlets are sufficiently distant from intakes.
IPC 702.2 Underground building sanitary drainage and vent
Resolved
02/18/2021

2018 IPC 702.2 Underground building sanitary drainage and vent pipe. Underground building sanitary drainage and vent pipe shall conform to one of the standards listed in Table 702.2. -------------------------------------- 2018 IPC 605.4 Water distribution pipe. Water distribution pipe and tubing shall conform to NSF 61 and shall conform to one of the standards listed in Table 605.4. Hot water distribution pipe and tubing shall have a pressure rating of not less than 100 psi at 180degF. Action required: Provide pipe material schedule. (include NG)
Final Development Plan Review Approved 04/12/2021
Dawn Bell
Special Inspections Review Approved 02/19/2021
Joe Frogge
Licensed Contractors Rejected 02/23/2021 02/18/2021
Joe Frogge
LC - General Contractor
Resolved
04/12/2021

Lee's Summit Code of Ordinance, Section7-130.10 - Business License. It shall be unlawful for any person to engage in the construction contracting business without first obtaining a business license as required under the applicable provisions of Chapter 28 of the Lee's Summit Code of Ordinances. Action required: Either a Class A or Class B license is required. Provide the name of the licensed general contractor and an email address for the on-site contact. 2/18/21 - acknowledged in letter
LC - MEP Subs
Resolved
04/12/2021

Lee's Summit Code of Ordinance, Section7-130.4 - Business License. (excerpt) No person, other than a licensed contractor or employees of a licensed contractor, shall engage in electrical, plumbing or mechanical business, construction, installation or maintenance unless duly licensed in accordance with this section. Action required: MEP subcontractors are required to be listed on permit. Provide company names of licensed MEP contractors. 2/18/21 - acknowledged in letter
Fire Plan Review Approved with Conditions 02/23/2021 02/17/2021
Michael Weissenbach
Construction documents for fire alarm systems
Corrective Action Required
02/16/2021

2018 IFC 907.1.1- Construction documents. Construction documents for fire alarm systems shall be submitted for review and approval prior to system installation. Construction documents shall include, but not be limited to, all of the following: 1. .A floor plan which indicates the use of all rooms. 2. Locations of alarm-initiating and notification appliances. 3. Alarm control and trouble signaling equipment. 4. Annunciation. 5. Power connection. 6. Battery calculations. 7. Conductor type and sizes. 8. Voltage drop calculations. 9. Manufacturers, model numbers and listing information for equipment, devices and materials. 10. Details of ceiling height and construction. 11. The interface of fire safety control functions. (Action Required) Provide PE stamped electronic shop drawings to mike.weissenbach@cityofls.net
Address numbers required
Corrective Action Required
02/16/2021

2018 IFC 505.1- Address numbers. New and existing buildings shall have approved address numbers, building numbers or approved building identification placed in a position that is plainly legible and visible from the street or road fronting the property. These numbers shall contrast with their background. In Multi-tenant commercial building where tenants have multiple entrances located on different sides of the building , each door shall be addressed. Address numbers shall be Arabic numerals or alphabet letters. Numbers shall be a minimum of 4 inches (102 mm) high with a minimum stroke width of 0.5 inch (12.7 mm). (Verified At Inspection)
Knox box required
Corrective Action Required
02/16/2021

2018 IFC 506.1- Where required. Where access to or within a structure or an area is restricted because of secured openings or where immediate access is necessary for life-saving or fire-fighting purposes, the fire code official is authorized to require a key box to be installed in an approved location. The key box shall be of an approved type and shall contain keys to gain necessary access as required by the fire code official. (Action Required) Order a Knoxbox from knoxbox.com. Placement to be made by the FDC. 2/17/2021 (Verified At Inspection)
Construction documents - Fire protection systems
Corrective Action Required
02/16/2021

2018 IFC 901.2- Construction documents. The fire code official shall have the authority to require construction documents and calculations for all fire protection systems and to require permits be issued for the installation, rehabilitation or modification of any fire protection system. Construction documents for fire protection systems shall be submitted for review and approval prior to system installation. (Action Required) Provide PE stamped electronic shop drawings to mike.weissenbach@cityofls.net
Installation acceptance testing
Corrective Action Required
02/16/2021

2018 IFC 901.5- Installation acceptance testing. Fire detection and alarm systems, fire-extinguishing systems, fire hydrant systems, fire standpipe systems, fire pump systems, private fire service mains and all other fire protection systems and appurtenances thereto shall be subject to acceptance tests as contained in the installation standards and as approved by the fire code official. The fire code official shall be notified before any required acceptance testing. The fire code official shall be notified 48 hours before any required acceptance test. (Informational Purposes) Call (816)969-1300 to schedule testing.
Building Plan Review Rejected 02/12/2021 02/08/2021
Joe Frogge
Final Development Plan
Corrective Action Required
02/08/2021

The building permit for this project cannot be issued until the Development Services Department has received, approved, and processed the Final Development Plan. Action required: Comment is for informational purposes.
Miscellaneous Correction
Corrective Action Required
02/08/2021

A License Tax application completed by the contractor must be submitted to the City of Lee's Summit, Codes Administration Department, and any applicable License Tax paid prior to issuing a building permit. Action required: Comment is for informational purposes.
IBC 1704.2 Special Inspections
Corrective Action Required
02/08/2021

2018 IBC 1704.2 Special inspections. Where application is made for construction as described in this section, the owner or the registered design professional in responsible charge acting as the owner’s agent shall employ one or more approved agencies to perform inspections during construction on the types of work listed under Section 1705. These inspections are in addition to the inspections identified in Lee’s Summit Code of Ordinances Chapter 7. (see code section for exceptions) Action required: Provide statement of special inspections / letter of responsibility from company contracted to perform special inspections.
IBC 1803.1 General - geotech
Corrective Action Required
02/08/2021

2018 IBC 1803.1 General. Geotechnical investigations shall be conducted in accordance with Section 1803.2 and reported in accordance with Section 1803.6. Where required by the building official or where geotechnical investigations involve in-situ testing, laboratory testing or engineering calculations, such investigations shall be conducted by a registered design professional. Action required: Provide soils report to justify design assumption of soil bearing capacity greater than 2,000psf.
IBC 1209.2 Finish materials
Corrective Action Required
02/08/2021

2018 IBC 1209.2 Finish Materials. Walls, Floors and partitions in toilet and bathrooms shall comply with Sections 209.2.1 through 1209.2.4. 2018 1209.2.1 Floors and wall bases. In other than dwelling units, toilet, bathing and shower room floor finish materials shall have a smooth, hard, nonabsorbent surface. The intersections of such floors with walls shall have a smooth, hard, nonabsorbent vertical base that extends upward onto the walls not less than 4 inches. 2018 1209.2.2 Walls and partitions. Walls and partitions within 2 feet of service sinks, urinals and water closets shall have a smooth, hard, nonabsorbent surface, to a height of not less than 4 feet above the floor, and except for structural elements, the materials used in such walls shall be of a type that is not adversely affected by moisture. (See code section for possible exceptions.) 1209.2.3 Showers. (see code for details) 1209.2.4 Waterproof joints. (see code for details) Action required: Specify compliant materials at water closets and janitor's sink. If paint is used it must be epoxy based.
IMC 501.3.1 Location of exhaust outlets
Corrective Action Required
02/08/2021

2018 IMC 501.3.1 Location of exhaust outlets. The termination point of exhaust outlets and ducts discharging to the outdoors shall be located with the following minimum distances: (see code for items 1, 2, 4, & 5) 3. For all environmental air exhaust: 3 feet from property lines; 3 feet from operable openings into building for all occupancies other than Group U, and 10 feet from mechanical air intakes. Such exhaust shall not be considered hazardous or noxious. Action required: Modify plans to demonstrate that exhaust outlets are sufficiently distant from intakes.
IPC 702.2 Underground building sanitary drainage and vent
Corrective Action Required
02/08/2021

2018 IPC 702.2 Underground building sanitary drainage and vent pipe. Underground building sanitary drainage and vent pipe shall conform to one of the standards listed in Table 702.2. -------------------------------------- 2018 IPC 605.4 Water distribution pipe. Water distribution pipe and tubing shall conform to NSF 61 and shall conform to one of the standards listed in Table 605.4. Hot water distribution pipe and tubing shall have a pressure rating of not less than 100 psi at 180degF. Action required: Provide pipe material schedule. (include NG)
Licensed Contractors Rejected 02/12/2021 02/08/2021
Joe Frogge
LC - General Contractor
Corrective Action Required
02/08/2021

Lee's Summit Code of Ordinance, Section7-130.10 - Business License. It shall be unlawful for any person to engage in the construction contracting business without first obtaining a business license as required under the applicable provisions of Chapter 28 of the Lee's Summit Code of Ordinances. Action required: Either a Class A or Class B license is required. Provide the name of the licensed general contractor and an email address for the on-site contact.
LC - MEP Subs
Corrective Action Required
02/08/2021

Lee's Summit Code of Ordinance, Section7-130.4 - Business License. (excerpt) No person, other than a licensed contractor or employees of a licensed contractor, shall engage in electrical, plumbing or mechanical business, construction, installation or maintenance unless duly licensed in accordance with this section. Action required: MEP subcontractors are required to be listed on permit. Provide company names of licensed MEP contractors.
Fire Plan Review Approved with Conditions 02/12/2021 02/03/2021
Michael Weissenbach
Construction documents for fire alarm systems
Corrective Action Required
02/03/2021

2018 IFC 907.1.1- Construction documents. Construction documents for fire alarm systems shall be submitted for review and approval prior to system installation. Construction documents shall include, but not be limited to, all of the following: 1. .A floor plan which indicates the use of all rooms. 2. Locations of alarm-initiating and notification appliances. 3. Alarm control and trouble signaling equipment. 4. Annunciation. 5. Power connection. 6. Battery calculations. 7. Conductor type and sizes. 8. Voltage drop calculations. 9. Manufacturers, model numbers and listing information for equipment, devices and materials. 10. Details of ceiling height and construction. 11. The interface of fire safety control functions. (Action Required) Provide PE stamped electronic shop drawings to mike.weissenbach@cityofls.net
Address numbers required
Corrective Action Required
02/03/2021

2018 IFC 505.1- Address numbers. New and existing buildings shall have approved address numbers, building numbers or approved building identification placed in a position that is plainly legible and visible from the street or road fronting the property. These numbers shall contrast with their background. In Multi-tenant commercial building where tenants have multiple entrances located on different sides of the building , each door shall be addressed. Address numbers shall be Arabic numerals or alphabet letters. Numbers shall be a minimum of 4 inches (102 mm) high with a minimum stroke width of 0.5 inch (12.7 mm). (Verified At Inspection)
Knox box required
Corrective Action Required
02/03/2021

2018 IFC 506.1- Where required. Where access to or within a structure or an area is restricted because of secured openings or where immediate access is necessary for life-saving or fire-fighting purposes, the fire code official is authorized to require a key box to be installed in an approved location. The key box shall be of an approved type and shall contain keys to gain necessary access as required by the fire code official. (Action Required) Order a Knoxbox from knoxbox.com. Placement to be made by the FDC.
Construction documents - Fire protection systems
Corrective Action Required
02/03/2021

2018 IFC 901.2- Construction documents. The fire code official shall have the authority to require construction documents and calculations for all fire protection systems and to require permits be issued for the installation, rehabilitation or modification of any fire protection system. Construction documents for fire protection systems shall be submitted for review and approval prior to system installation. (Action Required) Provide PE stamped electronic shop drawings to mike.weissenbach@cityofls.net
Installation acceptance testing
Corrective Action Required
02/03/2021

2018 IFC 901.5- Installation acceptance testing. Fire detection and alarm systems, fire-extinguishing systems, fire hydrant systems, fire standpipe systems, fire pump systems, private fire service mains and all other fire protection systems and appurtenances thereto shall be subject to acceptance tests as contained in the installation standards and as approved by the fire code official. The fire code official shall be notified before any required acceptance testing. The fire code official shall be notified 48 hours before any required acceptance test. (Informational Purposes) Call (816)969-1300 to schedule testing.
Fees
Paid Fees Amount Paid Owing Date Paid
Valuation Fee for New Commercial $7,720.00 $7,720.00 Paid 04/05/2021
Commercial Excise Tax Fee $63,225.00 $63,225.00 Paid 04/20/2022
8331507-Sewer Connection Fee $930.00 $930.00 Paid 04/05/2021
Sanitary Sewer Insp Fees $107.10 $107.10 Paid 03/31/2021
Water Insp Fee $205.98 $205.98 Paid 03/31/2021
Storm Sewer Inspection Fee $1,354.38 $1,354.38 Paid 03/31/2021
Paved Surface Inspection Fee $5,304.60 $5,304.60 Paid 03/31/2021
Site Grading Fee $500.25 $500.25 Paid 03/31/2021
Water Test Fee $200.00 $200.00 Paid 03/31/2021
Water Tap Fee $23,873.00 $23,873.00 Paid 03/31/2021
Water Meter Fee $2,401.70 $2,401.70 Paid 03/31/2021
Right of Way Permit Fee $80.00 $80.00 Paid 03/31/2021
After Hours Inspections (Public Works)(Per Hour) $100.00 $100.00 Paid 04/20/2022
After Hours Inspections (Public Works)(Per Hour) $100.00 $100.00 Paid 04/20/2022
Not Ready Inspection Fee $50.00 $50.00 Paid 04/20/2022
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Storm Sewer Construction Inspection Partial 6/22/2021 06/22/2021
Misc
Informational
06/22/2021
6/22/21 Tuesday Contractor (Bair Const.) has installed line 100. Approximately 90’ of 18” HP Storm pipe, 101 (OS) outlet structure, & 100 MH construction manhole see C-300 & C-602. Contractor schedule to pour collars and inverts on Line 100. Contractor expect to begin installation of storm Line 300 starting from the Basin see C-300. 6/23/21 Wednesday Contractor (Bair Const.) continued to install Line 300 18” HP Storm pipe. Contractor should reach just pass 301 (GSI) Nyoplast curb inlet approximately 200 plus feet of Line 300 will be installed from 6/22 to 6/23. 7/6/21 Tuesday Contractor (Bair Const.) continued to installed Line 300 Approximately 165’ of 15”HP storm from Sta 301 to 302 on 7/2/21 Friday. Contractor began the installation of storm Line 200 for roof drains.
Fire Line Construction Inspection Partial 7/13/2021 07/13/2021
Misc
Informational
07/13/2021
7/12/21 Monday Contractor continued fire line construction as-per project plans. Installation of fire hydrant was on 7/9/21 Friday. 7/13/21 Tuesday Contractor searching and found 8” water main @ 250 NW Mc Nary CT. Contractor working on contacting the City to get Meter Pit assembly to hook up domestic water line. 7/19/21 Monday Contractor poured backing block behind fire hydrant. Back flow preventer still need to be installed. Meter was installed and hooked up to the main. 8/2/21 Monday Inspected the flange of the fire line that 90 bends from the base of building into building. Inspect passed. 8/11/21 Wednesday Contractor framed floor for Backflow Preventer vault. 10/29/21 Friday Flush fire line @ 11:40PM.
Footing Inspection - Commercial Partial 7/19/2021 (2:00) 7/19/2021 07/19/2021
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
07/19/2021
- C LINE, 1 LINE, 7 LINE COMPLETE, A LINE 1-4 5-7, (7) COLUMN PADS B LINE, UFER LOCATED SW CORNER -
Underslab Plumbing Inspection - Commercial Partial 7/21/2021 07/21/2021
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
07/21/2021
- MAIN TRUNK N TO S CENTER OF BLDG EXIT WEST SIDE -
Sanitary Sewer Construction Inspection Passed 8/3/2021 08/03/2021
Misc
Informational
07/08/2021
Thursday 7/8/21 Began to locate Sanitary line for tie-in. General construction onsite dropping off equipment and materials. Shoring boxes were dropped off to safely install sanitary main. 7/12/21 Monday Contractor performed a tie-in to existing 10” Clay sanitary main starting @ 10:30PM. The flow was lowest starting at this time. Wye and the HardBack Fernco were used for tie-in. The contractor was not able to perform because they did not have the 10” HardBack Fernco they mistakenly thought it was 8” Clay sanitary main. Tie-in will be done tomorrow. 7/13/21 Tuesday Contractor is performing tie-in. Contractor installed wye & hardback Fernco & will finish running sanitary line to future building possibly tomorrow. 7/14/21 Wednesday Contractor Installed a stick pipe and a bend for sanitary out of the wye. 7/19/21 Monday Contractor completed sanitary line to where it will exit the future building. 8/3/21 Tuesday (Bair Const.) Contractor installed clean out just outside bldg per plans hard back join the the domestic schedule 40, sewer line with the 6” outside sanitary SDR-26 with a Hard Back Fernco. Wye for the clean then 22 degree bend to line up with second clean-out as-per plan. Sanitary line is complete.
Underslab Plumbing Inspection - Commercial Passed 8/4/2021 08/04/2021
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
07/21/2021
- MAIN TRUNK N TO S CENTER OF BLDG EXIT WEST SIDE -
Underslab Electrical Inspection - Commercial Partial 8/5/2021 8/5/2021 08/05/2021
Misc
Informational
08/05/2021
- UNDERSLAB CONDUIT SOUTH END OF BLDG -
Underground Electrical Inspection - Commercial Passed 8/17/2021 08/17/2021
Misc
Informational
08/17/2021
UNDER GROUND CONDUIT WEST SIDE OF BLDG TRANSFORMER TO BUILDING, METER CAN TO ELECTRICAL ROOM
Underslab Electrical Inspection - Commercial Passed 9/10/2021 9/10/2021 09/10/2021
Misc
Informational
08/05/2021
- UNDERSLAB CONDUIT SOUTH END OF BLDG - - UNDERSLAB CONDUIT COMPLETE -
Site Visit Partial 10/21/2021 10/21/2021
Misc
Informational
10/21/2021
10/21/21 Thursday (Bair Const.) Site Visit - preparation for 6’X6’X6’ Tee Fire Lane tie-in. The crew was not on site to expose water main and make necessary preparation. 12/13/21 Monday (Bair Const.) Met with contractor about the moving sidewalk over to stop from removing tree. I explain that all changes need to be reflected in the as-built. 12//16/21 Thursday (Bair Const.) Seed was done yesterday @ of site, contractor text message me some specifications of their seeding. 12/20/21 Monday (Bair Const.) The contractor is looking to install drive approach before Christmas. Continued grading and general site work on project. 02/24/22 Thursday No work onsite. 03/31/22 Thursday No work onsite. 04/20/22 Wednesday Reviewing site for TCO Monday 04/25/22. Surface asphalt and re-stripping is schedule for 04/21/22 . Hydro seeding was done for 99% of project. 04/27/22 (Bair Construction) Talked with Rob of BairConst & later the Engineer Designer about the as-built for the basin at job site for TCO.
Water Line - Construction Inspection Partial 10/21/2021 10/21/2021
Misc
Informational
10/21/2021
10/21/21 Thursday (Bair Const.) Tie-in on the 6” water main to the Backflow Preventer for PetSuites. Contractor began to prep for water shut around 4:50PM. Contractor is installing a 6” gate valve to the Backflow Preventer, 6” sleeves & 6”X6”X6” Tee on existing 6” main. 34” from tee to 6” valve and approximately 2’ to bothe sleeves from Tee. Turn water back on @ 10:30PM. Flushing line as water main was being connected.
Miscellaneous Inspection Partial 10/21/2021 10/21/2021
Miscellaneous Correction
Informational
10/21/2021
10/21/21 Thursday (Bair Const.) Contractor installed foundation pad for dumpster encloser
Fire Line - Hydrostatic Test Passed 10/29/2021 10/29/2021
Misc
Informational
10/29/2021
10/29/21 Friday (Bair Const Don’s crew) 2 hour fire line hydrostatic test with Backflow preventer to the inside of building. Test passed inspection, bleed line of air pressure from hydrant to check line pressure actually existence.
Rough Framing Inspection - Commercial Passed 11/8/2021 11/08/2021
Misc
Informational
11/08/2021
EXTERIOR METAL STUD FACADES ALL 4 SIDES OK TO COVER
Piers/Caissons Inspection - Commercial Failed 11/9/2021 (8:00) 11/9/2021 11/09/2021
Miscellaneous Correction
Corrective Action Required
11/09/2021
(3) LIGHT POLE BASES PROVIDE (8) # 5 VERT BARS W/ # 4 WRAP PER PLAN
Piers/Caissons Inspection - Commercial Partial 11/9/2021 11/09/2021
Misc
Informational
11/09/2021
(3) LIGHT POLE BASES 2 EAST 1 SOUTH (8) # 5 VERT BARS W/ # 4 WRAP PER PLAN, DRIVEN GROIND ROUND AT EACH PIER
Underground Electrical Inspection - Commercial Partial 11/16/2021 11/16/2021 11/16/2021
Misc
Informational
11/16/2021
UNDERGROUND CONDUIT FOR 3 LIGHT POLE BASES (2) EAST (1) SOUTH DRIVEN GROUND RODS IN PLACE
Pavement-Stabilized Subgrade Partial 11/17/2021 11/17/2021
Misc
Informational
11/17/2021
11/17/21 Wednesday (Bair Excavation) Proof partially pass area near the dumpster need to be addressed. Contractor will skim off between 6” to a 1’ and add shot rock to stabilize subgrade. Contractor will document that the work is done and send pictures to my email as verification.
In-wall Inspection Failed 12/6/2021 12/6/2021 12/06/2021
Miscellaneous Correction
Corrective Action Required
12/06/2021
: IN WALL NORTH END ( SHELL PERMIT ) PROVIDE MIDPOINT SUPPORT VERTICAL 2" & SMALLER DWV ROOM 112 NAIL BOTTOM PLATE BEHIND DOOR
Pavement-Curb Construction Partial 12/6/2021 12/06/2021
Misc
Informational
12/06/2021
12/06/21 Monday Contractor poured curbs in the parking lot. Blankets are supposed to cover the curbs as per project manager.
In-wall Inspection Passed 12/7/2021 12/7/2021 12/07/2021
Miscellaneous Correction
Resolved
12/07/2021
: IN WALL NORTH END ( SHELL PERMIT )
Pavement-Aggregate Base Partial 12/9/2021 12/09/2021
Misc
Informational
12/09/2021
12/09/21 Thursday Bairs Construction Contractor paved the parking with type 2 asphalt base sent the specifications through email of mix of the asphalt. Base pavement appears to be acceptable.
Grading/Excavation/Fill Inspection Partial 12/14/2021 12/14/2021
Misc
Informational
12/14/2021
12/14/21 Tuesday Contractor grading landscaping around storm and detention. Rip-rap was installed as-per plans.
Driveway Inspection Partial 12/29/2021 12/29/2021
Misc
Informational
12/29/2021
12/29/21 Wednesday (Steller Concrete) Commercial driveway is to be poured. Contractor are preparing grounds to pour drive approach.
Sidewalk Inspection Partial 12/29/2021 12/29/2021
Misc
Informational
12/29/2021
12/29/21 Wednesday Sidewalk pre-inspection passed. Sidewalk will be poured today.
Misc
Informational
12/30/2021
12/30/21 Thursday Sidewalk was poured today contractor will cover with blankets due to weather.
Gas Piping Inspection - Commercial Passed 1/31/2022 01/31/2022
Gas Service Inspection - Commercial Passed 1/31/2022 1/31/2022 01/31/2022
Electrical Service Inspection Passed 2/2/2022 2/2/2022 02/02/2022
Above Ceiling Inspection Partial 3/2/2022 03/02/2022
Miscellaneous Correction
Corrective Action Required
03/02/2022
- ROOMS 102,113,115,116,117, VENT BATH EXHAUST TO ROOF. OK TO DROP TILE IN OTHER ROOMS -
Footing Inspection - Commercial Passed 3/2/2022 03/02/2022
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
07/19/2021
- C LINE, 1 LINE, 7 LINE COMPLETE, A LINE 1-4 5-7, (7) COLUMN PADS B LINE, UFER LOCATED SW CORNER -
Above Ceiling Inspection Partial 3/4/2022 3/4/2022 03/04/2022
Miscellaneous Correction
Corrective Action Required
03/02/2022
- ROOMS 117, VENT BATH EXHAUST TO ROOF. OK TO DROP TILE IN OTHER ROOMS -
Above Ceiling Inspection Passed 3/14/2022 3/14/2022 03/14/2022
Miscellaneous Correction
Resolved
03/14/2022
- ROOMS 117 - OK TO DROP TILE IN OTHER ROOMS -
Sprinkler - Hydrostatic Test Passed 3/18/2022 03/18/2022
Alarm Test Not Ready 4/12/2022 04/12/2022
Sprinkler - Flow Test Failed 4/12/2022 04/12/2022
Alarm Test Failed 4/15/2022 04/15/2022
Sprinkler - Flow Test Passed 4/15/2022 04/15/2022
Alarm Test Passed 4/18/2022 04/18/2022
Corrective Action Required
04/18/2022
Alarm strobes need to terminate on silence.
Pavement-Surface Partial 4/19/2022 04/22/2022
Misc
Informational
04/22/2022
04/22/22 Friday (Wil-Pav) Contractor laid surface asphalt. Milling (contractor had to build up some areas to aid with building access) of base was done where needed and tacking of parking lot was done. Last ticket for asphalt will be sent to my phone for verification if I am not on site when they finish. Rob from Bair construction gave me three asphalt tickets the 1st, 2nd, & the 5th. Asphalt APWA Type 3 R.
Miscellaneous Inspection Passed 4/25/2022 04/25/2022
Miscellaneous Correction
Informational
10/21/2021
10/21/21 Thursday (Bair Const.) Contractor installed foundation pad for dumpster encloser
Piers/Caissons Inspection - Commercial Passed 4/25/2022 04/25/2022
Misc
Informational
11/09/2021
(3) LIGHT POLE BASES 2 EAST 1 SOUTH (8) # 5 VERT BARS W/ # 4 WRAP PER PLAN, DRIVEN GROUND ROUND AT EACH PIER
Underground Electrical Inspection - Commercial Passed 4/25/2022 04/25/2022
Misc
Informational
11/16/2021
UNDERGROUND CONDUIT FOR 3 LIGHT POLE BASES (2) EAST (1) SOUTH DRIVEN GROUND RODS IN PLACE
Occupancy Inspection - Fire Temporary C of O 4/19/2022 4/25/2022 04/25/2022
Corrective Action Required
04/25/2022
Mount Exit signs on exterior gates. Exterior gate locks need to have panic hardware or shall be readily openable from the egress side without the use of a key or special knowledge or effort. Until this can be done the gates need to remain unlocked.
Occupancy Inspection - Codes Commercial Failed 4/25/2022 4/25/2022 04/25/2022
Miscellaneous Correction
Corrective Action Required
04/25/2022
:CODES: RESTROOM MIRRORS SHALL BE 40" TO REFLECTIVE SURFACE COMPLETE AWNING ABOVE TRIPLE WINDOW FRONT OF BLDG UPLOAD SPECIAL INSPECTION FINAL REPORT TO PERMIT FIRE TCO OK WATER TCO OK PLANNING FIELD ENGINEERING
Occupancy Inspection - Engineering Failed 4/25/2022 04/25/2022
Misc
Corrective Action Required
04/25/2022
Needed for Temporary Occupancy 1. Accepted As-builts Needed for For Final Occupancy 1. 70% vegetation needs to be established. 2. Trash and debris need to be cleaned up. 3. Remove silt fence in back of building when vegetation has been established. 4. Make sure curb inlet in front of building is cleaned out. 5. Dumpster needs to be removed.
Occupancy Inspection - Planning Temporary C of O 4/25/2022 04/29/2022
Occupancy Inspection - Codes Commercial Failed 5/4/2022 5/4/2022 05/04/2022
Miscellaneous Correction
Corrective Action Required
04/25/2022
:CODES: COMPLETE AWNING ABOVE TRIPLE WINDOW FRONT OF BLDG UPLOAD SPECIAL INSPECTION FINAL REPORT TO PERMIT FIRE WATER PLANNING FIELD ENGINEERING
Occupancy Inspection - Fire Failed 5/4/2022 05/04/2022
Corrective Action Required
05/04/2022
Exit sign needs to be added to the north vinyl gate. Move double exit sign to the North one exit. Exterior gate locks need to have panic hardware or shall be readily openable from the egress side without the use of a key or special knowledge or effort. Until this can be done the gates need to remain unlocked.
Pavement-Stabilized Subgrade Passed 05/04/2022
Storm Sewer Construction Inspection Passed 5/4/2022 05/04/2022
Misc
Informational
06/22/2021
6/22/21 Tuesday Contractor (Bair Const.) has installed line 100. Approximately 90’ of 18” HP Storm pipe, 101 (OS) outlet structure, & 100 MH construction manhole see C-300 & C-602. Contractor schedule to pour collars and inverts on Line 100. Contractor expect to begin installation of storm line 300 starting from the Basin see C-300.
Sanitary - Material Verification Passed 5/4/2022 05/04/2022
Water Service Inspection Passed 5/4/2022 05/04/2022
Misc
Informational
07/14/2021
Contractor installed meter and meter pit.
Pavement-Proof Roll Passed 5/4/2022 05/04/2022
Sanitary Sewer Construction Inspection Passed 05/04/2022
Misc
Informational
07/08/2021
Thursday 7/8/21 Began to locate Sanitary line for tie-in. General construction onsite dropping off equipment and materials. Shoring boxes were dropped off to safely install sanitary main.
Fire Line Construction Inspection Passed 05/04/2022
Misc
Informational
07/13/2021
7/12/21 Monday Contractor continued fire line construction as-per project plans. Installation of fire hydrant was on 7/9/21 Friday.
Pavement-Curb Construction Passed 05/04/2022
Misc
Informational
12/06/2021
12/06/21 Monday Contractor poured curbs in the parking lot. Blankets are supposed to cover the curbs as per project manager.
Pavement-Aggregate Base Passed 05/04/2022
Misc
Informational
12/09/2021
12/09/21 Thursday Bairs Construction Contractor paved the parking with type 2 asphalt base sent the specifications through email of mix of the asphalt. Base pavement appears to be acceptable.
Grading/Excavation/Fill Inspection Passed 05/04/2022
Misc
Informational
12/14/2021
12/14/21 Tuesday Contractor grading landscaping around storm and detention. Rip-rap was installed as-per plans.
Driveway Inspection Passed 05/04/2022
Misc
Informational
12/29/2021
12/29/21 Wednesday (Steller Concrete) Commercial driveway is to be poured. Contractor are preparing grounds to pour drive approach.
Sidewalk Inspection Passed 05/04/2022
Misc
Informational
12/29/2021
12/29/21 Wednesday Sidewalk pre-inspection passed. Sidewalk will be poured today.
Pavement-Surface Passed 05/04/2022
Misc
Informational
04/22/2022
04/22/22 Friday (Wil-Pav) Contractor laid surface asphalt.
Occupancy Inspection - Engineering Failed 5/4/2022 05/04/2022
Misc
Corrective Action Required
05/04/2022
Needed for Temporary Occupancy 1. Accepted As-builts Needed for For Final Occupancy 1. 70% vegetation needs to be established. 2. Trash and debris need to be cleaned up. 3. Remove silt fence in back of building when vegetation has been established. 4. Make sure curb inlet in front of building is cleaned out. 5. Dumpster needs to be removed.
Occupancy Inspection - Water Utilities Passed 5/10/2022 05/10/2022
Occupancy Inspection - Fire Passed 5/25/2022 05/25/2022
Corrective Action Required
05/25/2022
All life safety was appropriate. Okay to occupy with approval form codes.
Site Visit Complete 05/26/2022
Misc
Informational
10/21/2021
10/21/21 Thursday (Bair Const.) Site Visit - preparation for 6’X6’X6’ Tee Fire Lane tie-in. The crew was not on site to expose water main and make necessary preparation. 05/26/22 Thursday (Bair Const.) As-built were received earlier in the week for detention area. Onsite inspection observation appears that detention area is work as planned ( this has been a rainy week) with over 2” of rain during this rain event detention drains as-per plan.
Occupancy Inspection - Planning Temporary C of O 6/7/2022 06/07/2022
Occupancy Inspection - Planning Temporary C of O 6/7/2022 06/07/2022
Occupancy Inspection - Planning Temporary C of O 6/7/2022 06/07/2022
Occupancy Inspection - Planning Passed 6/7/2022 06/07/2022
Occupancy Inspection - Planning Passed 6/7/2022 06/07/2022
Occupancy Inspection - Codes Commercial Temporary C of O 6/7/2022 06/07/2022
Miscellaneous Correction
Corrective Action Required
05/04/2022
:CODES: FIELD ENGINEERING
Occupancy Inspection - Engineering Passed 6/7/2022 06/23/2022
Misc
Corrective Action Required
05/04/2022
Needed for Temporary Occupancy 1. Accepted As-builts Needed for For Final Occupancy 1. 70% vegetation needs to be established. 2. Trash and debris need to be cleaned up. 3. Remove silt fence in back of building when vegetation has been established. 4. Make sure curb inlet in front of building is cleaned out. 5. Dumpster needs to be removed.
Misc
Resolved
06/23/2022
06/23/22 Thursday Contractor has appeared to resolved all issues. Occupancy passed approximately two weeks ago.
Record Drawing Review Passed 5/27/2022 06/23/2022
Misc
Resolved
06/23/2022
06/23/22 Thursday Record drawing have been received and appear to be completed.
Occupancy Inspection - Codes Commercial Full C of O 07/12/2022
Miscellaneous Correction
Resolved
07/12/2022
:CODES: FIELD ENGINEERING
Documents & Images
Date Uploaded File Type Document Name
01/29/2021 Application Form PetSuites -Lee's Summit Permit Application-CERT
02/02/2021 Plans 2020_02_01 PetSuites Permit Set
02/03/2021 Letter Fire Building Plan Review
02/08/2021 Letter DS P/R Corrections Document
02/16/2021 Letter 2021_02_12 PetSuites Lee's Summit, MO List of Changes (Addendum 1)
02/16/2021 Letter Lee's Summit, MO Plan Review Response Letter
02/16/2021 Engineer Report/Study Geotech Report Proposed PetSuites
02/16/2021 Plans 2021_02_12 PetSuites Lee's Summit, MO Addendum 1
02/17/2021 Letter Fire Building Plan Review
02/19/2021 Engineer Report/Study J036943_03 - PetSuites Initial SI Letter 2021-2-18
03/31/2021 Receipt Receipt for transaction:2021-001648
04/05/2021 Receipt Receipt for transaction:2021-001726
04/06/2021 MEP Contractors
04/09/2021 Approved FDP Petsuites 4.9.21
04/09/2021 Application Form PetSuites Tax Application
04/12/2021 approved - 2021_02_12 PetSuites Lee's Summit, MO Addendum 1
04/12/2021 Letter License Tax Bill
04/12/2021 Letter DS Building Permit
06/22/2021 Letter INSPECTION SUMMARY
06/22/2021 Letter INSPECTION SUMMARY
06/23/2021 image.jpg
07/08/2021 Letter INSPECTION SUMMARY
07/13/2021 Letter INSPECTION SUMMARY
07/13/2021 Letter INSPECTION SUMMARY
07/13/2021 image.jpg0
07/13/2021 image.jpg1
07/13/2021 Letter INSPECTION SUMMARY
07/13/2021 image.jpg2
07/13/2021 64792958104__17EC227E-F792-420F-AFBF-C00C8995C29C.MOV
07/13/2021 image.jpg3
07/13/2021 image.jpg4
07/14/2021 image.jpg5
07/14/2021 image.jpg6
07/14/2021 image.jpg7
07/14/2021 image.jpg8
07/19/2021 Letter INSPECTION SUMMARY
07/21/2021 Letter INSPECTION SUMMARY
08/02/2021 image.jpg9
08/02/2021 image.jpg10
08/02/2021 image.jpg11
08/02/2021 image.jpg12
08/03/2021 image.jpg13
08/03/2021 Letter INSPECTION SUMMARY
08/04/2021 Letter INSPECTION SUMMARY
08/05/2021 Letter INSPECTION SUMMARY
08/11/2021 image.jpg14
08/17/2021 Letter INSPECTION SUMMARY
09/10/2021 Letter INSPECTION SUMMARY
10/20/2021 Letter Fire (Sprinkler) Plan Review
10/21/2021 Letter INSPECTION SUMMARY
10/21/2021 Letter INSPECTION SUMMARY
10/21/2021 Letter INSPECTION SUMMARY
10/21/2021 Letter INSPECTION SUMMARY
10/21/2021 image.jpg15
10/29/2021 Letter INSPECTION SUMMARY
11/08/2021 Letter INSPECTION SUMMARY
11/09/2021 Letter INSPECTION SUMMARY
11/09/2021 Letter INSPECTION SUMMARY
11/16/2021 Letter INSPECTION SUMMARY
11/17/2021 Letter INSPECTION SUMMARY
12/06/2021 Letter INSPECTION SUMMARY
12/06/2021 Letter INSPECTION SUMMARY
12/07/2021 Letter INSPECTION SUMMARY
12/09/2021 image.jpg16
12/09/2021 Letter INSPECTION SUMMARY
12/09/2021 Letter INSPECTION SUMMARY
12/13/2021 Letter INSPECTION SUMMARY
12/14/2021 Letter INSPECTION SUMMARY
12/29/2021 image.jpg17
12/29/2021 Letter INSPECTION SUMMARY
12/29/2021 Letter INSPECTION SUMMARY
12/30/2021 image.jpg18
12/30/2021 image.jpg19
12/30/2021 image.jpg20
12/30/2021 Letter INSPECTION SUMMARY
01/31/2022 Letter INSPECTION SUMMARY
01/31/2022 Letter INSPECTION SUMMARY
02/02/2022 Letter INSPECTION SUMMARY
03/02/2022 Letter INSPECTION SUMMARY
03/02/2022 Letter INSPECTION SUMMARY
03/04/2022 Letter INSPECTION SUMMARY
03/07/2022 PetSuites Submittal Packet
03/07/2022 FA-01 REV #3 PetSuites Lee's Summit, MO
03/07/2022 FA-02 REV #3 PetSuites Lee's Summit, MO
03/07/2022 PetSuites Lee's Summit City Plan Review Response Letter
03/14/2022 Letter INSPECTION SUMMARY
03/18/2022 stamped
03/20/2022 Letter Fire (Alarm) Plan Review Notice
04/15/2022 Letter Fire Loss Reduction Form
04/15/2022 Letter Fire Loss Reduction Form
04/18/2022 Letter Fire Loss Reduction Form
04/20/2022 Receipt Receipt for transaction:2022-002232
04/22/2022 image
04/22/2022 image0
04/22/2022 Letter INSPECTION SUMMARY
04/22/2022 Letter INSPECTION SUMMARY
04/22/2022 image1
04/25/2022 Letter INSPECTION SUMMARY
04/25/2022 Letter INSPECTION SUMMARY
04/25/2022 Letter INSPECTION SUMMARY
04/25/2022 Letter Fire Loss Reduction Form
04/25/2022 Letter INSPECTION SUMMARY
04/25/2022 Letter INSPECTION SUMMARY
04/27/2022 Letter INSPECTION SUMMARY
04/27/2022 Letter INSPECTION SUMMARY
04/27/2022 Letter INSPECTION SUMMARY
05/02/2022 J036943.03 Final Special Inspection Report
05/03/2022 Letter INSPECTION SUMMARY
05/04/2022 Letter INSPECTION SUMMARY
05/04/2022 Letter Inspection Summary
05/04/2022 Letter Fire Loss Reduction Form
05/10/2022 Letter INSPECTION SUMMARY
05/10/2022 Letter INSPECTION SUMMARY
05/10/2022 Letter INSPECTION SUMMARY
05/10/2022 Letter INSPECTION SUMMARY
05/10/2022 Letter INSPECTION SUMMARY
05/10/2022 Letter INSPECTION SUMMARY
05/10/2022 Letter INSPECTION SUMMARY
05/10/2022 Letter INSPECTION SUMMARY
05/10/2022 Letter INSPECTION SUMMARY
05/10/2022 Letter INSPECTION SUMMARY
05/10/2022 Letter INSPECTION SUMMARY
05/10/2022 Letter INSPECTION SUMMARY
05/10/2022 Letter INSPECTION SUMMARY
05/10/2022 Letter INSPECTION SUMMARY
05/11/2022 2008920 PETSUITES LEE'S SUMMIT
05/20/2022 2022-05-20 BASIN AS-BUILTS
05/26/2022 image2
05/25/2022 Letter Fire Loss Reduction Form
06/01/2022 Letter INSPECTION SUMMARY
06/07/2022 Letter Codes Temporary Certificate of Occupancy
06/23/2022 Letter INSPECTION SUMMARY
06/23/2022 Letter INSPECTION SUMMARY
06/23/2022 Letter INSPECTION SUMMARY
07/12/2022 Letter Codes Final Certificate of Occupancy
07/21/2022 Letter INSPECTION SUMMARY
07/21/2022 Letter Field Certificate of Occupancy
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home