Review Type |
Outcome |
Est. Completion Date |
Completed |
Alarm Plan Review
|
Released for Construction
|
|
10/24/2019
|
|
Michael Weissenbach
|
|
|
Building Plan Review
|
Approved with Conditions
|
10/07/2019
|
10/03/2019
|
|
Joe Frogge
|
|
License Tax Application
Corrective Action Required
A License Tax application completed by the contractor must be submitted to the City of Lee's Summit, Codes Administration Department, and any applicable License Tax paid prior to issuing a building permit.
Action required: Comment is for informational purposes.
8/29/19 - acknowledged in letter
|
|
Screening - Rooftop equipment
Corrective Action Required
Unified Development Ordinance Article 8, Section 8.180.E
Roof mounted equipment – All roof-mounted equipment shall be screened entirely from view by using parapet walls at the same height as the mechanical units. For additions to existing buildings that do not meet this standard, individual screens will be permitted, with the design subject to approval by the Director.
Action required: Make needed corrections to drawings that provide details as to how mechanical equipment will be screened from all 4 sides per referenced UDO section or provide verification that existing screening is adequate.
8/29/19 - Per architect, the units were installed at white box permit. Field verify
|
|
Bldg - Toilet room wall finish 1210.2.2
Corrective Action Required
1209.2.2 Walls and partitions. Walls and partitions within 2 feet of service sinks, urinals and water closets shall have a smooth, hard, nonabsorbent surface, to a height of not less than 4 feet above the floor, and except for structural elements, the materials used in such walls shall be of a type that is not adversely affected by moisture. (See code section for possible exceptions.)
Action required: Specify compliant wall finish material at mop sink.
8/29/19 - deferred to construction - field verify
|
|
|
Fire Plan Review
|
Approved with Conditions
|
10/07/2019
|
10/01/2019
|
|
Michael Weissenbach
|
|
Construction documents for fire alarm systems
Corrective Action Required
2018 IFC 907.1.1- Construction documents. Construction documents for fire alarm systems shall be submitted for review and approval prior to system installation. Construction documents shall include, but not be limited to, all of the following: 1. .A floor plan which indicates the use of all rooms. 2. Locations of alarm-initiating and notification appliances. 3. Alarm control and trouble signaling equipment. 4. Annunciation. 5. Power connection. 6. Battery calculations. 7. Conductor type and sizes. 8. Voltage drop calculations. 9. Manufacturers, model numbers and listing information for equipment, devices and materials. 10. Details of ceiling height and construction. 11. The interface of fire safety control functions.
(Action Required)
Provide three sets of stamped shop drawings for fire alarm system on any modifications to be done.
|
|
Address numbers required
Corrective Action Required
2018 IFC 505.1- Address numbers. New and existing buildings shall have approved address numbers, building numbers or approved building identification placed in a position that is plainly legible and visible from the street or road fronting the property. These numbers shall contrast with their background. In Multi-tenant commercial building where tenants have multiple entrances located on different sides of the building , each door shall be addressed. Address numbers shall be Arabic numerals or alphabet letters. Numbers shall be a minimum of 4 inches (102 mm) high with a minimum stroke width of 0.5 inch (12.7 mm).
(Verified At Inspection)
|
|
Construction documents - Fire protection systems
Corrective Action Required
2018 IFC 901.2- Construction documents. The fire code official shall have the authority to require construction documents and calculations for all fire protection systems and to require permits be issued for the installation, rehabilitation or modification of any fire protection system. Construction documents for fire protection systems shall be submitted for review and approval prior to system installation.
(Action Required)
Provide three sets of stamped shop drawings for the fire sprinkler system on any modifications to be done.
|
|
Installation acceptance testing
Corrective Action Required
2018 IFC 901.5- Installation acceptance testing. Fire detection and alarm systems, fire-extinguishing systems, fire hydrant systems, fire standpipe systems, fire pump systems, private fire service mains and all other fire protection systems and appurtenances thereto shall be subject to acceptance tests as contained in the installation standards and as approved by the fire code official. The fire code official shall be notified before any required acceptance testing. The fire code official shall be notified 48 hours before any required acceptance test.
(Informational Purposes)
Call (816)969-1300 to schedule testing. All testing to be complete before an occupancy inspection.
|
|
Portable fire extinguishers - conspicuous locations
Corrective Action Required
2018 IFC 906.5- Conspicuous location. Portable fire extinguishers shall be located in conspicuous locations where they will be readily accessible and immediately available for use. These locations shall be along normal paths of travel, unless the fire code official determines that the hazard posed indicates the need for placement away from normal paths of travel.
(Verified At Inspection)
|
|
Duct smoke detectors
Corrective Action Required
2018 IFC 907.3.1 Duct smoke detectors. Smoke detectors installed in ducts shall be listed for the air velocity, temperature and humidity present in the duct. Duct smoke detectors shall be connected to the building's fire alarm control unit when a fire alarm system is rquired by Section 907.2. Activation of a duct smoke detector shall initiate a visible and audible supervisory signal at a constantly attended location and shall perform the intended fire safety function in accordance with theis code and the International Mechanical Code. Duct smoke detectors shall not be used as a substitute for required open area detection.
(Informational Purposes)
CFM over 2000 will require duct detection.
|
|
|
Licensed Contractors
|
Approved
|
10/07/2019
|
09/30/2019
|
|
Joe Frogge
|
|
|
Licensed Contractors
|
Approved
|
09/06/2019
|
09/09/2019
|
|
Development Center
|
|
LC - General Contractor
Corrective Action Required
Lee's Summit Code of Ordinance, Section7-130.10 - Business License. It shall be unlawful for any person to engage in the construction contracting business without first obtaining a business license as required under the applicable provisions of Chapter 28 of the Lee's Summit Code of Ordinances.
Action required: Either a Class A or Class B license is required. Provide the name of the licensed general contractor.
8/29/19 - acknowledged in letter
|
|
LC - MEP Subs
Corrective Action Required
Lee's Summit Code of Ordinance, Section7-130.4 - Business License. (excerpt)
No person, other than a licensed contractor or employees of a licensed contractor, shall engage in electrical, plumbing or mechanical business, construction, installation or maintenance unless duly licensed in accordance with this section.
Action required: MEP subcontractors are required to be listed on permit. Provide company names of licensed MEP contractors.
8/29/19 - acknowledged in letter
|
|
|
Building Plan Review
|
Approved with Conditions
|
09/06/2019
|
08/29/2019
|
|
Joe Frogge
|
|
License Tax Application
Corrective Action Required
A License Tax application completed by the contractor must be submitted to the City of Lee's Summit, Codes Administration Department, and any applicable License Tax paid prior to issuing a building permit.
Action required: Comment is for informational purposes.
8/29/19 - acknowledged in letter
|
|
Screening - Rooftop equipment
Corrective Action Required
Unified Development Ordinance Article 8, Section 8.180.E
Roof mounted equipment – All roof-mounted equipment shall be screened entirely from view by using parapet walls at the same height as the mechanical units. For additions to existing buildings that do not meet this standard, individual screens will be permitted, with the design subject to approval by the Director.
Action required: Make needed corrections to drawings that provide details as to how mechanical equipment will be screened from all 4 sides per referenced UDO section or provide verification that existing screening is adequate.
8/29/19 - Per architect, the units were installed at white box permit. Field verify
|
|
Miscellaneous Correction
2018 IBC Exit Signs 1013.1 Where Required. Exits and exit access doors shall be marked by an approved exit sign readily visible from any direction of egress travel. The path of egress travel to exits and within exits shall be marked by readily visible exit signs to clearly indicate the direction of egress travel in cases where the exit of the path of egress travel is not immediately visible to the occupants. Intervening means of egress doors within exits shall be marked by exit signs. Exit sign placement shall be such that no point in an exit access corridor or exit passageway is more than 100 feet or the listed viewing distance for the sign, whichever is less, from the nearest visible exit sign. (see code section for exceptions)
Address the following:
- Coordinate architectural and electrical drawings
- provide exit sign at south side of corridor near restrooms
- do not direct exiting through storage room
|
|
Bldg - Egress through intervening spaces 1014.2
2018 IBC 1016.2 Egress through intervening spaces. Egress through intervening spaces shall comply with this section.
Item 5. Egress shall not pass through kitchens, storage rooms, closets or spaces used for similar purposes. (See code section for additional items and exceptions)
Action required: Exiting through storage room not allowed unless you can demonstrate compliance with listed exceptions.
|
|
Bldg - Toilet room wall finish 1210.2.2
Corrective Action Required
1209.2.2 Walls and partitions. Walls and partitions within 2 feet of service sinks, urinals and water closets shall have a smooth, hard, nonabsorbent surface, to a height of not less than 4 feet above the floor, and except for structural elements, the materials used in such walls shall be of a type that is not adversely affected by moisture. (See code section for possible exceptions.)
Action required: Specify compliant wall finish material at mop sink.
8/29/19 - deferred to construction - field verify
|
|
Bldg - Urinal partitions 1210.3.2
2018 IBC 1209.3.2 Urinal partitions. Each urinal utilized by the public or employees shall occupy a separate area with walls or partitions to provide privacy. The walls or partitions shall begin at a height not more than 12 inches from and extend not less than 60 inches above the finished floor surface. The walls or partitions shall extend from the wall surface at each side of the urinal not less than 18 inches or to a point not less than 6 inches beyond the outermost front lip of the urinal measures from the finished back wall surface, whichever is greater.
Exceptions:
1. Urinal partitions shall not be required in a single-occupant or family or assisted-use toilet room with a lockable door.
2. Toilet rooms located in child day care facilities containing two or more urinals shall be permitted to have one urinal without partitions.
Action required: Provide urinal partitions in male restroom or provide lockable door.
|
|
Plan Submittal 2012 Codes
All plans submitted for review on or after April 1, 2019 shall be designed to the requirements of the 2018 International Building Code, 2018 International Mechanical Code, 2018 International Plumbing Code, 2018 International Fuel Gas Code, 2018 International Fire Code, 2017 National Electric Code and the ICC/ANSI A117.1-2017 as amended and adopted by the City of Lee’s Summit.
Action required: Update incorrect code references in General Notes on sheet M0.
|
|
|
Fire Plan Review
|
Approved with Conditions
|
09/06/2019
|
08/29/2019
|
|
Michael Weissenbach
|
|
Construction documents for fire alarm systems
Corrective Action Required
2018 IFC 907.1.1- Construction documents. Construction documents for fire alarm systems shall be submitted for review and approval prior to system installation. Construction documents shall include, but not be limited to, all of the following: 1. .A floor plan which indicates the use of all rooms. 2. Locations of alarm-initiating and notification appliances. 3. Alarm control and trouble signaling equipment. 4. Annunciation. 5. Power connection. 6. Battery calculations. 7. Conductor type and sizes. 8. Voltage drop calculations. 9. Manufacturers, model numbers and listing information for equipment, devices and materials. 10. Details of ceiling height and construction. 11. The interface of fire safety control functions.
(Action Required)
Provide three sets of stamped shop drawings for fire alarm system on any modifications to be done.
|
|
Address numbers required
Corrective Action Required
2018 IFC 505.1- Address numbers. New and existing buildings shall have approved address numbers, building numbers or approved building identification placed in a position that is plainly legible and visible from the street or road fronting the property. These numbers shall contrast with their background. In Multi-tenant commercial building where tenants have multiple entrances located on different sides of the building , each door shall be addressed. Address numbers shall be Arabic numerals or alphabet letters. Numbers shall be a minimum of 4 inches (102 mm) high with a minimum stroke width of 0.5 inch (12.7 mm).
(Verified At Inspection)
|
|
Construction documents - Fire protection systems
Corrective Action Required
2018 IFC 901.2- Construction documents. The fire code official shall have the authority to require construction documents and calculations for all fire protection systems and to require permits be issued for the installation, rehabilitation or modification of any fire protection system. Construction documents for fire protection systems shall be submitted for review and approval prior to system installation.
(Action Required)
Provide three sets of stamped shop drawings for the fire sprinkler system on any modifications to be done.
|
|
Installation acceptance testing
Corrective Action Required
2018 IFC 901.5- Installation acceptance testing. Fire detection and alarm systems, fire-extinguishing systems, fire hydrant systems, fire standpipe systems, fire pump systems, private fire service mains and all other fire protection systems and appurtenances thereto shall be subject to acceptance tests as contained in the installation standards and as approved by the fire code official. The fire code official shall be notified before any required acceptance testing. The fire code official shall be notified 48 hours before any required acceptance test.
(Informational Purposes)
Call (816)969-1300 to schedule testing. All testing to be complete before an occupancy inspection.
|
|
Portable fire extinguishers - conspicuous locations
Corrective Action Required
2018 IFC 906.5- Conspicuous location. Portable fire extinguishers shall be located in conspicuous locations where they will be readily accessible and immediately available for use. These locations shall be along normal paths of travel, unless the fire code official determines that the hazard posed indicates the need for placement away from normal paths of travel.
(Verified At Inspection)
|
|
Egress through intervening spaces.
2018 IFC 1016.2 Egress through intervening spaces. Egress through intervening spaces shall comply with this section.
(Action Required)
1. Remove exit sign leading into the warehouse.
2. Provide sheet for exit/emergency lighting.
|
|
Duct smoke detectors
Corrective Action Required
2018 IFC 907.3.1 Duct smoke detectors. Smoke detectors installed in ducts shall be listed for the air velocity, temperature and humidity present in the duct. Duct smoke detectors shall be connected to the building's fire alarm control unit when a fire alarm system is rquired by Section 907.2. Activation of a duct smoke detector shall initiate a visible and audible supervisory signal at a constantly attended location and shall perform the intended fire safety function in accordance with theis code and the International Mechanical Code. Duct smoke detectors shall not be used as a substitute for required open area detection.
(Informational Purposes)
CFM over 2000 will require duct detection.
|
|
|
Fire Plan Review
|
Rejected
|
08/09/2019
|
08/10/2019
|
|
Michael Weissenbach
|
|
Construction documents for fire alarm systems
Corrective Action Required
2018 IFC 907.1.1- Construction documents. Construction documents for fire alarm systems shall be submitted for review and approval prior to system installation. Construction documents shall include, but not be limited to, all of the following: 1. .A floor plan which indicates the use of all rooms. 2. Locations of alarm-initiating and notification appliances. 3. Alarm control and trouble signaling equipment. 4. Annunciation. 5. Power connection. 6. Battery calculations. 7. Conductor type and sizes. 8. Voltage drop calculations. 9. Manufacturers, model numbers and listing information for equipment, devices and materials. 10. Details of ceiling height and construction. 11. The interface of fire safety control functions.
(Action Required)
Provide three sets of stamped shop drawings for fire alarm system on any modifications to be done.
|
|
Address numbers required
Corrective Action Required
2018 IFC 505.1- Address numbers. New and existing buildings shall have approved address numbers, building numbers or approved building identification placed in a position that is plainly legible and visible from the street or road fronting the property. These numbers shall contrast with their background. In Multi-tenant commercial building where tenants have multiple entrances located on different sides of the building , each door shall be addressed. Address numbers shall be Arabic numerals or alphabet letters. Numbers shall be a minimum of 4 inches (102 mm) high with a minimum stroke width of 0.5 inch (12.7 mm).
(Verified At Inspection)
|
|
Construction documents - Fire protection systems
Corrective Action Required
2018 IFC 901.2- Construction documents. The fire code official shall have the authority to require construction documents and calculations for all fire protection systems and to require permits be issued for the installation, rehabilitation or modification of any fire protection system. Construction documents for fire protection systems shall be submitted for review and approval prior to system installation.
(Action Required)
Provide three sets of stamped shop drawings for the fire sprinkler system on any modifications to be done.
|
|
Installation acceptance testing
Corrective Action Required
2018 IFC 901.5- Installation acceptance testing. Fire detection and alarm systems, fire-extinguishing systems, fire hydrant systems, fire standpipe systems, fire pump systems, private fire service mains and all other fire protection systems and appurtenances thereto shall be subject to acceptance tests as contained in the installation standards and as approved by the fire code official. The fire code official shall be notified before any required acceptance testing. The fire code official shall be notified 48 hours before any required acceptance test.
(Informational Purposes)
Call (816)969-1300 to schedule testing. All testing to be complete before an occupancy inspection.
|
|
Portable fire extinguishers - conspicuous locations
Corrective Action Required
2018 IFC 906.5- Conspicuous location. Portable fire extinguishers shall be located in conspicuous locations where they will be readily accessible and immediately available for use. These locations shall be along normal paths of travel, unless the fire code official determines that the hazard posed indicates the need for placement away from normal paths of travel.
(Verified At Inspection)
|
|
Egress through intervening spaces.
Corrective Action Required
2018 IFC 1016.2 Egress through intervening spaces. Egress through intervening spaces shall comply with this section.
(Action Required)
1. Remove exit sign leading into the warehouse.
2. Provide sheet for exit/emergency lighting.
|
|
Duct smoke detectors
Corrective Action Required
2018 IFC 907.3.1 Duct smoke detectors. Smoke detectors installed in ducts shall be listed for the air velocity, temperature and humidity present in the duct. Duct smoke detectors shall be connected to the building's fire alarm control unit when a fire alarm system is rquired by Section 907.2. Activation of a duct smoke detector shall initiate a visible and audible supervisory signal at a constantly attended location and shall perform the intended fire safety function in accordance with theis code and the International Mechanical Code. Duct smoke detectors shall not be used as a substitute for required open area detection.
(Informational Purposes)
|
|
|
Building Plan Review
|
Rejected
|
08/09/2019
|
08/09/2019
|
|
Joe Frogge
|
|
License Tax Application
Corrective Action Required
A License Tax application completed by the contractor must be submitted to the City of Lee's Summit, Codes Administration Department, and any applicable License Tax paid prior to issuing a building permit.
Action required: Comment is for informational purposes.
|
|
Misc
2018 IBC 1606.2 Design dead load. For purposes of design, the actual weights of materials of construction and fixed service equipment shall be used. In the absence of definite information, values used shall be subject to the approval of the building official.
Action required: Provide engineered design for new roof penetrations and loads or provide engineer’s report to verify that existing roof structure will support additional load.
8/19/19 - verified that structural mods were designed under shell permit PRCOM20191560
|
|
Screening - Rooftop equipment
Corrective Action Required
Unified Development Ordinance Article 8, Section 8.180.E
Roof mounted equipment – All roof-mounted equipment shall be screened entirely from view by using parapet walls at the same height as the mechanical units. For additions to existing buildings that do not meet this standard, individual screens will be permitted, with the design subject to approval by the Director.
Action required: Make needed corrections to drawings that provide details as to how mechanical equipment will be screened from all 4 sides per referenced UDO section or provide verification that existing screening is adequate.
|
|
Miscellaneous Correction
Corrective Action Required
2018 IBC Exit Signs 1013.1 Where Required. Exits and exit access doors shall be marked by an approved exit sign readily visible from any direction of egress travel. The path of egress travel to exits and within exits shall be marked by readily visible exit signs to clearly indicate the direction of egress travel in cases where the exit of the path of egress travel is not immediately visible to the occupants. Intervening means of egress doors within exits shall be marked by exit signs. Exit sign placement shall be such that no point in an exit access corridor or exit passageway is more than 100 feet or the listed viewing distance for the sign, whichever is less, from the nearest visible exit sign. (see code section for exceptions)
Address the following:
- Coordinate architectural and electrical drawings
- provide exit sign at south side of corridor near restrooms
- do not direct exiting through storage room
|
|
Bldg - Egress through intervening spaces 1014.2
Corrective Action Required
2018 IBC 1016.2 Egress through intervening spaces. Egress through intervening spaces shall comply with this section.
Item 5. Egress shall not pass through kitchens, storage rooms, closets or spaces used for similar purposes. (See code section for additional items and exceptions)
Action required: Exiting through storage room not allowed unless you can demonstrate compliance with listed exceptions.
|
|
Bldg - Toilet room wall finish 1210.2.2
Corrective Action Required
1209.2.2 Walls and partitions. Walls and partitions within 2 feet of service sinks, urinals and water closets shall have a smooth, hard, nonabsorbent surface, to a height of not less than 4 feet above the floor, and except for structural elements, the materials used in such walls shall be of a type that is not adversely affected by moisture. (See code section for possible exceptions.)
Action required: Specify compliant wall finish material at mop sink.
|
|
Bldg - Urinal partitions 1210.3.2
Corrective Action Required
2018 IBC 1209.3.2 Urinal partitions. Each urinal utilized by the public or employees shall occupy a separate area with walls or partitions to provide privacy. The walls or partitions shall begin at a height not more than 12 inches from and extend not less than 60 inches above the finished floor surface. The walls or partitions shall extend from the wall surface at each side of the urinal not less than 18 inches or to a point not less than 6 inches beyond the outermost front lip of the urinal measures from the finished back wall surface, whichever is greater.
Exceptions:
1. Urinal partitions shall not be required in a single-occupant or family or assisted-use toilet room with a lockable door.
2. Toilet rooms located in child day care facilities containing two or more urinals shall be permitted to have one urinal without partitions.
Action required: Provide urinal partitions in male restroom or provide lockable door.
|
|
Plan Submittal 2012 Codes
Corrective Action Required
All plans submitted for review on or after April 1, 2019 shall be designed to the requirements of the 2018 International Building Code, 2018 International Mechanical Code, 2018 International Plumbing Code, 2018 International Fuel Gas Code, 2018 International Fire Code, 2017 National Electric Code and the ICC/ANSI A117.1-2017 as amended and adopted by the City of Lee’s Summit.
Action required: Update incorrect code references in General Notes on sheet M0.
|
|
|
Licensed Contractors
|
Rejected
|
08/09/2019
|
08/09/2019
|
|
Joe Frogge
|
|
LC - General Contractor
Corrective Action Required
Lee's Summit Code of Ordinance, Section7-130.10 - Business License. It shall be unlawful for any person to engage in the construction contracting business without first obtaining a business license as required under the applicable provisions of Chapter 28 of the Lee's Summit Code of Ordinances.
Action required: Either a Class A or Class B license is required. Provide the name of the licensed general contractor.
|
|
LC - MEP Subs
Corrective Action Required
Lee's Summit Code of Ordinance, Section7-130.4 - Business License. (excerpt)
No person, other than a licensed contractor or employees of a licensed contractor, shall engage in electrical, plumbing or mechanical business, construction, installation or maintenance unless duly licensed in accordance with this section.
Action required: MEP subcontractors are required to be listed on permit. Provide company names of licensed MEP contractors.
|
|
|