Inspection |
Outcome |
Requested |
Scheduled |
Date Inspected |
All Rough Inspection - Commercial
|
Failed
|
4/19/2019
|
4/19/2019
|
04/19/2019
|
|
LOWER LEVEL
Corrective Action Required
|
|
FIRST FLOOR
Corrective Action Required
|
|
SECOND FLOOR
Corrective Action Required
|
Sprinkler - Hydrostatic Test
|
Passed
|
|
4/24/2019
|
04/24/2019
|
All Rough Inspection - Commercial
|
Failed
|
4/29/2019
|
4/29/2019
|
04/29/2019
|
|
LOWER LEVEL
Corrective Action Required
|
|
FIRST FLOOR
Corrective Action Required
|
|
SECOND FLOOR
Corrective Action Required
|
All Rough Inspection - Commercial
|
Passed
|
5/1/2019
|
5/1/2019
|
05/01/2019
|
|
LOWER LEVEL
|
|
FIRST FLOOR
|
|
SECOND FLOOR
|
Rated Assembly Inspection
|
Partial
|
5/3/2019
|
5/3/2019
|
05/07/2019
|
|
SECOND FLOOR
Corrective Action Required
|
|
FIRST FLOOR
Corrective Action Required
|
|
LOWER LEVEL
Corrective Action Required
|
|
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
|
Rated Assembly Inspection
|
Partial
|
|
5/7/2019
|
05/07/2019
|
|
SECOND FLOOR
Corrective Action Required
|
|
FIRST FLOOR
Corrective Action Required
|
|
LOWER LEVEL
Corrective Action Required
|
|
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
|
Rated Assembly Inspection
|
Partial
|
5/9/2019
|
5/9/2019
|
05/09/2019
|
|
SECOND FLOOR
Corrective Action Required
|
|
FIRST FLOOR
Corrective Action Required
|
|
LOWER LEVEL
Corrective Action Required
|
|
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
|
Rated Assembly Inspection
|
Partial
|
5/13/2019
|
5/13/2019
|
05/13/2019
|
|
SECOND FLOOR
Corrective Action Required
|
|
FIRST FLOOR
Corrective Action Required
|
|
LOWER LEVEL
Corrective Action Required
|
|
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
|
Rated Assembly Inspection
|
Partial
|
5/14/2019
|
5/14/2019
|
05/14/2019
|
|
SECOND FLOOR
Corrective Action Required
|
|
FIRST FLOOR
Corrective Action Required
|
|
LOWER LEVEL
Corrective Action Required
|
|
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
|
Rated Assembly Inspection
|
Partial
|
5/17/2019
|
5/17/2019 at 11:05 AM
|
05/17/2019
|
|
SECOND FLOOR
Corrective Action Required
|
|
FIRST FLOOR
Corrective Action Required
|
|
LOWER LEVEL
Corrective Action Required
|
|
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
|
Rated Assembly Inspection
|
Partial
|
5/24/2019
|
5/24/2019
|
05/24/2019
|
|
SECOND FLOOR
Corrective Action Required
|
|
FIRST FLOOR
Corrective Action Required
|
|
LOWER LEVEL
Corrective Action Required
|
|
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
|
Rated Assembly Inspection
|
Partial
|
5/28/2019
|
5/28/2019
|
05/28/2019
|
|
SECOND FLOOR
Corrective Action Required
|
|
FIRST FLOOR
Corrective Action Required
|
|
LOWER LEVEL
Corrective Action Required
|
|
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
|
Rated Assembly Inspection
|
Partial
|
5/30/2019
|
5/30/2019
|
05/30/2019
|
|
SECOND FLOOR
Corrective Action Required
|
|
FIRST FLOOR
Corrective Action Required
|
|
LOWER LEVEL
Corrective Action Required
|
|
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
|
Rated Assembly Inspection
|
Partial
|
6/12/2019
|
6/12/2019
|
06/12/2019
|
|
SECOND FLOOR
Corrective Action Required
|
|
FIRST FLOOR
Corrective Action Required
|
|
LOWER LEVEL
Corrective Action Required
|
|
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
|
|
Misc
Corrective Action Required
|
Rated Assembly Inspection
|
Partial
|
6/14/2019
|
6/14/2019 at 10:10 AM
|
06/14/2019
|
|
SECOND FLOOR
Corrective Action Required
|
|
FIRST FLOOR
Corrective Action Required
|
|
LOWER LEVEL
Corrective Action Required
|
|
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
|
|
Misc
Corrective Action Required
|
Rated Assembly Inspection
|
Partial
|
7/1/2019
|
7/1/2019
|
07/01/2019
|
|
SECOND FLOOR
Corrective Action Required
|
|
FIRST FLOOR
Corrective Action Required
|
|
LOWER LEVEL
Corrective Action Required
|
|
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
|
|
Misc
Corrective Action Required
|
Electrical Service Inspection
|
Passed
|
7/2/2019
|
7/2/2019
|
07/02/2019
|
Rated Assembly Inspection
|
Partial
|
7/3/2019
|
7/3/2019
|
07/03/2019
|
|
SECOND FLOOR
Corrective Action Required
|
|
FIRST FLOOR
Corrective Action Required
|
|
LOWER LEVEL
Corrective Action Required
|
|
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
|
|
Misc
|
Rated Assembly Inspection
|
Failed
|
7/16/2019
|
7/16/2019
|
07/16/2019
|
|
SECOND FLOOR
Corrective Action Required
|
|
FIRST FLOOR
Corrective Action Required
|
|
LOWER LEVEL
Corrective Action Required
|
|
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
|
|
Misc
Corrective Action Required
|
Above Ceiling Inspection
|
Failed
|
7/18/2019
|
7/18/2019
|
07/18/2019
|
|
Misc
Corrective Action Required
|
Sprinkler - Flow Test
|
Passed
|
|
9/19/2019
|
09/19/2019
|
Alarm Test
|
Passed
|
|
9/19/2019
|
09/19/2019
|
Occupancy Inspection - Codes Commercial
|
Failed
|
10/11/2019
|
10/11/2019
|
10/11/2019
|
|
Misc
Corrective Action Required
|
Occupancy Inspection - Planning
|
Temporary C of O
|
|
|
10/11/2019
|
|
Corrective Action Required
|
|
Corrective Action Required
|
Occupancy Inspection - Fire
|
Failed
|
|
10/11/2019
|
10/11/2019
|
Occupancy Inspection - Fire
|
Passed
|
|
10/15/2019
|
10/15/2019
|
Occupancy Inspection - Codes Commercial
|
Failed
|
10/15/2019
|
10/15/2019
|
10/15/2019
|
|
Misc
Corrective Action Required
|
Occupancy Inspection - Engineering
|
Temporary C of O
|
|
10/30/2019
|
11/05/2019
|
Occupancy Inspection - Codes Commercial
|
Full C of O
|
|
11/6/2019
|
11/06/2019
|
|
Misc
|