Permit Application Status

PRCOM20120184


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PRCOM20120184
Building Permit - Commercial
Certificate of Occupancy
SAINT LUKES EAST HOSPITAL
NEW TENANT FINISH
EXPANSION OF EXISTING TENANT SPACE
02/06/2012
04/10/2012
09/23/2012
02/15/2013
Locations
Contacts
ACI BOLAND, Address:11229 NALL, SUITE 140  
MCCOWN GORDON CONSTRUCTION LLC, Address:850 MAIN ST, Phone:(816) 960-1111  
P1 CONSTRUCTION LLC, Address:13605 W 96TH TERR, Phone:(913) 529-5000  
BROADWAY ELECTRICAL CONSTRUCTION CO, Address:510 MIAMI AVENUE, Phone:(913) 621-3553  
P1 CONSTRUCTION LLC, Address:13605 W 96TH TERR, Phone:(913) 529-5000  
SAINT LUKES EAST HOSPITAL, Address:100 NW SAINT LUKES BOULEVARD  
SAINT LUKES EAST HOSPITAL, Address:901 E 104TH ST MAILSTOP 900N  
Reviews
Review Type Outcome Est. Completion Date Completed
Building Plan Review Approved 08/13/2012 08/13/2012
Mike Weisenborn
Fire Plan Review Approved 08/13/2012 08/13/2012
Jim Eden
Misc
Corrective Action Required
08/13/2012

1411.2 Maintenance. Required means of egress shall be maintained during construction and demolition, remodeling or alterations and additions to any building. Exception: Approved temporary means of egress systems and facilities. Egress from the occupied areas of the building shall be maintained throughout construction.
Construction documents - Fire protection systems
Corrective Action Required
08/13/2012

2006 IFC 901.2- Construction documents. The fire code official shall have the authority to require construction documents and calculations for all fire protection systems and to require permits be issued for the installation, rehabilitation or modification of any fire protection system. Construction documents for fire protection systems shall be submitted for review and approval prior to system installation. Provide alarm and sprinkler drawings for review and approval.
Misc
Corrective Action Required
08/13/2012

Fire Department- 2006 IFC 3006.4 Medical gas systems. Medical gas systems including, but not limited to, distribution piping, supply manifolds, connections, pressure regulators and relief devices and valves, shall comply with NFPA 99 and the general provisions of this chapter. Provide documention of line pressure testing on letter. Markings and documentation verified at inspection.
Internal Plan Review (Res) Approved 04/06/2012
Mike Weisenborn
True
Fire Plan Review Approved 04/10/2012 04/06/2012
Mike Weisenborn
Building Plan Review Approved 04/10/2012 04/06/2012
Mike Weisenborn
Misc
Corrective Action Required
04/06/2012

This project requires a third party review of the electrical systems. Action required - Please provide documentation of approval of this review. Mike Weisenborn 03/21/2012 11:07 AM - Provide the revised electrical sheets.
Bldg - Doors - Door swing
Corrective Action Required
04/06/2012

2006 IBC 1008.1.2 - Door swing. Egress doors shall be side-hinged swinging. Exceptions: 1. Private garages, office areas, factory and storage areas with an occupant load of 10 or less. 2. Group I-3 occupancies used as a place of detention. 3. Critical or intensive care patient rooms within suites of health care facilities. 4. Doors within or serving a single dwelling unit in Groups R-2 and R-3. 5. In other than Group H occupancies, revolving doors complying with Section 1008.1.3.1. 6. In other than Group H occupancies, horizontal sliding doors complying with Section 1008.1.3.3 are permitted in a means of egress. 7. Power-operated doors in accordance with Section 1008.1.3.2. 8. Doors serving a bathroom within an individual sleeping unit in Group R-1. Doors shall swing in the direction of egress travel where serving an occupant load of 50 or more persons or a Group H occupancy. The opening force of interior side-swinging doors without closers shall not exceed a 5-pound force. For other side-swinging, sliding and folding doors, the door latch shall release when subjected to a 15-pound force. The door shall be set in motion when subjected to a 30-pound force. The door shall swing to a full-open position when subjected to a 15-pound force. Forces shall be applied to the latch side. Action required - The door at the East end of Public Corridor 101 to the stair enclosure does not meet this requirement. Make needed corrections. Mike Weisenborn 03/21/2012 11:07 AM - Provide the revised electrical sheets.
Internal Plan Review (Res) Rejected 03/23/2012 03/27/2012
Mike Weisenborn
Fire Plan Review Approved 03/23/2012 03/26/2012
Jim Eden
Construction documents - Fire protection systems
Corrective Action Required
03/19/2012

2006 IFC 901.2- Construction documents. The fire code official shall have the authority to require construction documents and calculations for all fire protection systems and to require permits be issued for the installation, rehabilitation or modification of any fire protection system. Construction documents for fire protection systems shall be submitted for review and approval prior to system installation. Provide shop drawings for review and approval.
Construction documents for fire alarm systems
Corrective Action Required
03/19/2012

2006 IFC 907.1.1- Construction documents. Construction documents for fire alarm systems shall be submitted for review and approval prior to system installation. Construction documents shall include, but not be limited to, all of the following: 1. .A floor plan which indicates the use of all rooms. 2. Locations of alarm-initiating and notification appliances. 3. Alarm control and trouble signaling equipment. 4. Annunciation. 5. Power connection. 6. Battery calculations. 7. Conductor type and sizes. 8. Voltage drop calculations. 9. Manufacturers, model numbers and listing information for equipment, devices and materials. 10. Details of ceiling height and construction. 11. The interface of fire safety control functions. Provide shop drawings for review and approval.
Misc
Corrective Action Required
03/19/2012

1411.2 Maintenance. Required means of egress shall be maintained during construction and demolition, remodeling or alterations and additions to any building. Exception: Approved temporary means of egress systems and facilities. Egress from the occupied areas of the building shall be maintained throughout construction. Provide a temporary exiting plan for the different phases of the project.
Misc
Resolved
03/26/2012

Fire Department- 2006 IFC 3006.4 Medical gas systems. Medical gas systems including, but not limited to, distribution piping, supply manifolds, connections, pressure regulators and relief devices and valves, shall comply with NFPA 99 and the general provisions of this chapter. Provide documention of line pressure testing on letter. Markings and documentation verified at inspection.
Misc
Resolved
03/26/2012

For Information Only- The NFPA Life Safety Code is adopted by IFC Chapter 45 as reference only.
Portable fire extinguishers - general
Resolved
03/26/2012

2006 IFC 906.2 - General requirements. Portable fire extinguishers shall be selected, installed and maintained in accordance with this section and NFPA 10. Provide a fire extinguisher in the corridor near the southeast elevators.
Misc
Resolved
03/26/2012

Fire Department- 2 1/2 inch hose valve will be required at Vestibule 135, Exterior door to Corridor 140, and the southeast stair enclosure.
Misc
Resolved
03/26/2012

3006.2 Interior supply location. Medical gases shall be stored in areas dedicated to the storage of such gases without other storage or uses. Where containers of medical gases in quantities greater than the permit amount are located inside buildings, they shall be in a 1-hour exterior room, a 1-hour interior room or a gas cabinet in accordance with Section 3006.2.1, 3006.2.2 or 3006.2.3. 3006.2.1 One-hour exterior rooms. A 1-hour exterior room shall be a room or enclosure separated from the remainder of the building by fire barriers with a fire-resistance rating of not less than 1 hour. Openings between the room or enclosure and interior spaces shall be self-closing smoke- and draft-control assemblies having a fire protection rating of not less than 1 hour. Rooms shall have at least one exterior wall that is provided with at least two vents. Each vent shall not be less than 36 square inches (0.023 m2) in area. One vent shall be within 6 inches (152 mm) of the floor and one shall be within 6 inches (152 mm) of the ceiling. Rooms shall be provided with at least one automatic sprinkler to provide container cooling in case of fire. Action required: Make corrections for the new gas room and modifications to the existing room to meet these requirements. The exterior doors shall be marked with an NFPA 704 placard "Compressed Gas " .
Misc
Resolved
03/26/2012

Indicate the location of the shut-off for medical oxygen coming into the building.
Misc
Resolved
03/26/2012

1021.3 Construction. Exit passageway enclosures shall have walls, floors and ceilings of not less than 1-hour fire-resistance rating, and not less than that required for any connecting exit enclosure. Exit passageways shall be constructed as fire barriers in accordance with Section 706 of the International Building Code. Action required: A rated exit passageway shall be continued from the stairwell enclosure to the exterior of the building. Not required.
Building Plan Review Rejected 03/22/2012 03/21/2012
Mike Weisenborn
License contractors
Resolved
03/21/2012

No person, other than a licensed contractor or employees of a licensed contractor, shall engage in electrical, plumbing or mechanical business, construction, installation or maintenance unless duly licensed in accordance with this section. Expert from Sec. 7-130, Lees Summit Code of Ordinances. Action required - Provide the names of these sub-contractors prior to permit issuance.
Misc
Corrective Action Required
03/19/2012

This project requires a third party review of the electrical systems. Action required - Please provide documentation of approval of this review. Mike Weisenborn 03/21/2012 11:07 AM - Provide the revised electrical sheets.
Plumb - Separate facilities
Resolved
03/21/2012

2006 IPC 403.2 - Separate facilities. Where plumbing fixtures are required, separate facilities shall be provided for each sex. (See code for possible exceptions.) Action required - Please label the restrooms in the waiting area. Mike Weisenborn 03/21/2012 11:06 AM - Corrections have been made.
Bldg - Doors - Door swing
Corrective Action Required
03/19/2012

2006 IBC 1008.1.2 - Door swing. Egress doors shall be side-hinged swinging. Exceptions: 1. Private garages, office areas, factory and storage areas with an occupant load of 10 or less. 2. Group I-3 occupancies used as a place of detention. 3. Critical or intensive care patient rooms within suites of health care facilities. 4. Doors within or serving a single dwelling unit in Groups R-2 and R-3. 5. In other than Group H occupancies, revolving doors complying with Section 1008.1.3.1. 6. In other than Group H occupancies, horizontal sliding doors complying with Section 1008.1.3.3 are permitted in a means of egress. 7. Power-operated doors in accordance with Section 1008.1.3.2. 8. Doors serving a bathroom within an individual sleeping unit in Group R-1. Doors shall swing in the direction of egress travel where serving an occupant load of 50 or more persons or a Group H occupancy. The opening force of interior side-swinging doors without closers shall not exceed a 5-pound force. For other side-swinging, sliding and folding doors, the door latch shall release when subjected to a 15-pound force. The door shall be set in motion when subjected to a 30-pound force. The door shall swing to a full-open position when subjected to a 15-pound force. Forces shall be applied to the latch side. Action required - The door at the East end of Public Corridor 101 to the stair enclosure does not meet this requirement. Make needed corrections. Mike Weisenborn 03/21/2012 11:07 AM - Provide the revised electrical sheets.
Misc
Resolved
03/21/2012

The Life Safety Legend on Sheet A0.2 does not seem to be complete and it is unclear which walls are to be protected on the plans. Action required - Please provide additional information. Mike Weisenborn 03/21/2012 11:08 AM - Corrections have been made.
Bldg - Dressing, fitting and locker rooms
Resolved
03/21/2012

2006 IBC 1109.12.1 - Dressing, fitting and locker rooms. Where dressing rooms, fitting rooms or locker rooms are provided, at least 5 percent, but not less than one, of each type of use in each cluster provided shall be accessible. Action required - Show how these requirements are to be met. Provide information on the lockers and required bench. Mike Weisenborn 03/21/2012 11:08 AM - Corrections have been made.
Accessibility - Shower - Transfer-type dimensions
Resolved
03/21/2012

ICC/ANSI A117.1-2003 608.2.1 - Transfer-type shower compartments. Transfer-type shower compartments shall have a clear inside dimension of 36 inches in width and 36 inches in depth, measured at the center point of opposing sides. An entry 36 inches minimum in width shall be provided. A clearance of 48 inches minimum in length measured perpendicular from the control wall, and 36 inches minimum in depth shall be provided adjacent to the open face of the compartment. Action required - The shower located in the womens locker room does not meet the requirement for clear floor space adjacent to the shower. Make needed corrections. Mike Weisenborn 03/21/2012 11:08 AM - Corrections have been made.
Misc
Resolved
03/21/2012

2006 IBC -1021.3 Construction. Exit passageway enclosures shall have walls, floors and ceilings of not less than 1-hour fire-resistance rating, and not less than that required for any connecting exit enclosure. Exit passageways shall be constructed as fire barriers in accordance with Section 706 of the International Building Code. Action required - As the existing central stairway is constructed as a 2-hour vertical exit enclosure, the corridors from the stairway to the exit discharge point are considered horizontal exit enclosure and they are required to meet all the same requirements for construction as the stairway. Make needed corrections. Mike Weisenborn 03/21/2012 11:11 AM - An exit enclosure is not required as the stairway is not required to be rated. It will never extend above two stories and is located within a B occupancy.
Sprinkler Plan Review Deferred 03/21/2012
Mike Weisenborn
Alarm Plan Review Deferred 03/21/2012
Mike Weisenborn
Internal Plan Review (Res) Rejected 02/21/2012 02/21/2012
Mike Weisenborn
Building Plan Review Rejected 02/21/2012 02/21/2012
Mike Weisenborn
License contractors
Corrective Action Required
02/15/2012

No person, other than a licensed contractor or employees of a licensed contractor, shall engage in electrical, plumbing or mechanical business, construction, installation or maintenance unless duly licensed in accordance with this section. Expert from Sec. 7-130, Lees Summit Code of Ordinances. Action required - Provide the names of these sub-contractors prior to permit issuance.
Misc
Corrective Action Required
02/15/2012

This project requires a third party review of the electrical systems. Action required - Please provide documentation of approval of this review.
Plumb - Separate facilities
Corrective Action Required
02/15/2012

2006 IPC 403.2 - Separate facilities. Where plumbing fixtures are required, separate facilities shall be provided for each sex. (See code for possible exceptions.) Action required - Please label the restrooms in the waiting area.
Bldg - Doors - Door swing
Corrective Action Required
02/21/2012

2006 IBC 1008.1.2 - Door swing. Egress doors shall be side-hinged swinging. Exceptions: 1. Private garages, office areas, factory and storage areas with an occupant load of 10 or less. 2. Group I-3 occupancies used as a place of detention. 3. Critical or intensive care patient rooms within suites of health care facilities. 4. Doors within or serving a single dwelling unit in Groups R-2 and R-3. 5. In other than Group H occupancies, revolving doors complying with Section 1008.1.3.1. 6. In other than Group H occupancies, horizontal sliding doors complying with Section 1008.1.3.3 are permitted in a means of egress. 7. Power-operated doors in accordance with Section 1008.1.3.2. 8. Doors serving a bathroom within an individual sleeping unit in Group R-1. Doors shall swing in the direction of egress travel where serving an occupant load of 50 or more persons or a Group H occupancy. The opening force of interior side-swinging doors without closers shall not exceed a 5-pound force. For other side-swinging, sliding and folding doors, the door latch shall release when subjected to a 15-pound force. The door shall be set in motion when subjected to a 30-pound force. The door shall swing to a full-open position when subjected to a 15-pound force. Forces shall be applied to the latch side. Action required - The door at the East end of Public Corridor 101 to the stair enclosure does not meet this requirement. Make needed corrections.
Misc
Corrective Action Required
02/21/2012

The Life Safety Legend on Sheet A0.2 does not seem to be complete and it is unclear which walls are to be protected on the plans. Action required - Please provide additional information.
Bldg - Dressing, fitting and locker rooms
Corrective Action Required
02/21/2012

2006 IBC 1109.12.1 - Dressing, fitting and locker rooms. Where dressing rooms, fitting rooms or locker rooms are provided, at least 5 percent, but not less than one, of each type of use in each cluster provided shall be accessible. Action required - Show how these requirements are to be met. Provide information on the lockers and required bench.
Accessibility - Shower - Transfer-type dimensions
Corrective Action Required
02/21/2012

ICC/ANSI A117.1-2003 608.2.1 - Transfer-type shower compartments. Transfer-type shower compartments shall have a clear inside dimension of 36 inches in width and 36 inches in depth, measured at the center point of opposing sides. An entry 36 inches minimum in width shall be provided. A clearance of 48 inches minimum in length measured perpendicular from the control wall, and 36 inches minimum in depth shall be provided adjacent to the open face of the compartment. Action required - The shower located in the womens locker room does not meet the requirement for clear floor space adjacent to the shower. Make needed corrections.
Misc
Corrective Action Required
02/21/2012

2006 IBC -1021.3 Construction. Exit passageway enclosures shall have walls, floors and ceilings of not less than 1-hour fire-resistance rating, and not less than that required for any connecting exit enclosure. Exit passageways shall be constructed as fire barriers in accordance with Section 706 of the International Building Code. Action required - As the existing central stairway is constructed as a 2-hour vertical exit enclosure, the corridors from the stairway to the exit discharge point are considered horizontal exit enclosure and they are required to meet all the same requirements for construction as the stairway. Make needed corrections.
Fire Plan Review Rejected 02/16/2012 02/16/2012
Jim Eden
Construction documents - Fire protection systems
Corrective Action Required
02/16/2012

2006 IFC 901.2- Construction documents. The fire code official shall have the authority to require construction documents and calculations for all fire protection systems and to require permits be issued for the installation, rehabilitation or modification of any fire protection system. Construction documents for fire protection systems shall be submitted for review and approval prior to system installation. Provide shop drawings for review and approval.
Construction documents for fire alarm systems
Corrective Action Required
02/16/2012

2006 IFC 907.1.1- Construction documents. Construction documents for fire alarm systems shall be submitted for review and approval prior to system installation. Construction documents shall include, but not be limited to, all of the following: 1. .A floor plan which indicates the use of all rooms. 2. Locations of alarm-initiating and notification appliances. 3. Alarm control and trouble signaling equipment. 4. Annunciation. 5. Power connection. 6. Battery calculations. 7. Conductor type and sizes. 8. Voltage drop calculations. 9. Manufacturers, model numbers and listing information for equipment, devices and materials. 10. Details of ceiling height and construction. 11. The interface of fire safety control functions. Provide shop drawings for review and approval.
Misc
Corrective Action Required
02/16/2012

1411.2 Maintenance. Required means of egress shall be maintained during construction and demolition, remodeling or alterations and additions to any building. Exception: Approved temporary means of egress systems and facilities. Egress from the occupied areas of the building shall be maintained throughout construction. Provide a temporary exiting plan for the different phases of the project.
Misc
Corrective Action Required
02/16/2012

Fire Department- 2006 IFC 3006.4 Medical gas systems. Medical gas systems including, but not limited to, distribution piping, supply manifolds, connections, pressure regulators and relief devices and valves, shall comply with NFPA 99 and the general provisions of this chapter. Provide documention of line pressure testing on letter. Markings and documentation verified at inspection.
Misc
Corrective Action Required
02/16/2012

For Information Only- The NFPA Life Safety Code is adopted by IFC Chapter 45 as reference only.
Portable fire extinguishers - general
Corrective Action Required
02/16/2012

2006 IFC 906.2 - General requirements. Portable fire extinguishers shall be selected, installed and maintained in accordance with this section and NFPA 10. Provide a fire extinguisher in the corridor near the southeast elevators.
Misc
Corrective Action Required
02/16/2012

Fire Department- 2 1/2 inch hose valve will be required at Vestibule 135, Exterior door to Corridor 140, and the southeast stair enclosure.
Misc
Corrective Action Required
02/16/2012

3006.2 Interior supply location. Medical gases shall be stored in areas dedicated to the storage of such gases without other storage or uses. Where containers of medical gases in quantities greater than the permit amount are located inside buildings, they shall be in a 1-hour exterior room, a 1-hour interior room or a gas cabinet in accordance with Section 3006.2.1, 3006.2.2 or 3006.2.3. 3006.2.1 One-hour exterior rooms. A 1-hour exterior room shall be a room or enclosure separated from the remainder of the building by fire barriers with a fire-resistance rating of not less than 1 hour. Openings between the room or enclosure and interior spaces shall be self-closing smoke- and draft-control assemblies having a fire protection rating of not less than 1 hour. Rooms shall have at least one exterior wall that is provided with at least two vents. Each vent shall not be less than 36 square inches (0.023 m2) in area. One vent shall be within 6 inches (152 mm) of the floor and one shall be within 6 inches (152 mm) of the ceiling. Rooms shall be provided with at least one automatic sprinkler to provide container cooling in case of fire. Action required: Make corrections for the new gas room and modifications to the existing room to meet these requirements. The exterior doors shall be marked with an NFPA 704 placard "Compressed Gas " .
Misc
Corrective Action Required
02/16/2012

Indicate the location of the shut-off for medical oxygen coming into the building.
Misc
Corrective Action Required
02/16/2012

1021.3 Construction. Exit passageway enclosures shall have walls, floors and ceilings of not less than 1-hour fire-resistance rating, and not less than that required for any connecting exit enclosure. Exit passageways shall be constructed as fire barriers in accordance with Section 706 of the International Building Code. Action required: A rated exit passageway shall be continued from the stairwell enclosure to the exterior of the building.
License Tax Codes Approved 02/16/2012 02/15/2012
Mike Weisenborn
Zoning Review Approved 02/16/2012 02/07/2012
Mike Weisenborn
Fees
Paid Fees Amount Paid Owing Date Paid
9110078-Valuation Fee for New Tenent Finish $20,403.55 $20,403.55 Paid 04/10/2012
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Underslab Plumbing Inspection - Commercial Partial 4/11/2012 4/11/2012 at 12:00 AM 04/11/2012
Misc
Partial Correction
04/11/2012
OK TO COVER WHEN READY PVC DWV UNDER-SLAB PLUMBING PIPING AT AREAS: PHASE 1 PARTIAL EXCLUDING FROM SPACES 157 & 159;
Underslab Plumbing Inspection - Commercial Partial 4/17/2012 at 12:00 AM 04/17/2012
Misc
Partial Correction
04/11/2012
OK TO COVER WHEN READY PVC DWV UNDER-SLAB PLUMBING PIPING AT AREAS: PHASE 1 PARTIAL EXCLUDING FROM SPACES 157 & 159; 1ST FLOOR NORTH SECTION.
Suspended Slab Inspection Partial 4/24/2012 at 12:00 AM 04/24/2012
Misc
Partial Correction
04/24/2012
OK TO POUR WHEN READY UTILITY TUNNEL COVER SLAB EAST 50'
Rough Framing Inspection - Commercial Partial 5/10/2012 (8:00 to 5:00) 5/11/2012 at 12:00 AM 05/11/2012
Misc
Partial Correction
05/11/2012
OK TO TOP-OUT GWB ONE SIDE OF WALL FRAMING DOWN TO ~ 10' A.F.F. AT FOLLOWING WALL PLANES: (CC) FROM (0.3) TO (3.7); (CC.4) FROM (0.3) TO (3.5); (A.5) FROM (6.0) TO (4.9);
Rough Framing Inspection - Commercial Partial 5/16/2012 (8:00 to 5:00) 5/16/2012 at 12:00 AM 05/16/2012
Misc
Partial Correction
05/11/2012
OK TO TOP-OUT GWB ONE SIDE OF WALL FRAMING DOWN TO ~ 10' A.F.F. AT FOLLOWING WALL PLANES: (CC) FROM (0.3) TO (3.7); (CC.4) FROM (0.3) TO (3.5); (A.5) FROM (6.0) TO (4.9);
Rated Assembly Inspection Partial 6/18/2012 at 12:00 AM 05/17/2012
Misc
Partial Correction
05/17/2012
OK TO COVER WHEN READY FOLLOWING COMPONENTS OF RATED ASSEMBLIES: FRAMING AND SHAFT LINER AT INTERIM CLOSURES AT ELEVATOR DOORS @ 1ST FLOOR;
In-wall Inspection Partial 5/17/2012 at 12:00 AM 05/17/2012
Misc
Partial Correction
05/17/2012
OK TO TOP-OUT GWB WALL DOWN TO ~ 10' A.F.F. AT FOLLOWING WALL PLANES: (CC) FROM (0.3) TO (3.7); (A.5) FROM (6.0) TO (4.9); (CC.4) FROM (0.5) TO (3.4); 149 OR-4 N WALL; 141 OR-5 N WALL;
Misc
Partial Correction
05/17/2012
OK TO COVER WHEN READY GWB WALLS FULL HEIGHT @ FOLLOWING LOCATIONS: AHU RM 147 NE CORNER FOR MOUNTING OF DP-E1-28-HA; 126 & 127 FOR EQUIPMENT INSTALL; TEMPORARY EGRESS CORRIDOR @ 117; INFILL BELOW WINDOWS ALONG (DD) FROM (3.8) TO (5.1);
In-wall Inspection Partial 5/17/2012 at 12:00 AM 05/17/2012
Misc
Partial Correction
05/17/2012
OK TO TOP-OUT GWB WALL DOWN TO ~ 10' A.F.F. AT FOLLOWING WALL PLANES: (CC) FROM (0.3) TO (3.7); (A.5) FROM (6.0) TO (4.9); (CC.4) FROM (0.5) TO (3.4); 149 OR-4 N WALL; 141 OR-5 N WALL; 118;
Misc
Partial Correction
05/17/2012
OK TO COVER WHEN READY GWB WALLS FULL HEIGHT @ FOLLOWING LOCATIONS: AHU RM 147 NE CORNER FOR MOUNTING OF DP-E1-28-HA; 126 & 127 FOR EQUIPMENT INSTALL; TEMPORARY EGRESS CORRIDOR @ 117; INFILL BELOW WINDOWS ALONG (DD) FROM (3.8) TO (5.1);
Rated Assembly Inspection Partial 5/17/2012 at 12:00 AM 05/17/2012
Misc
Partial Correction
05/17/2012
OK TO COVER WHEN READY FOLLOWING COMPONENTS OF RATED ASSEMBLIES: FRAMING AND SHAFT LINER AT INTERIM CLOSURES AT ELEVATOR DOORS @ 1ST & 2ND FLOORS;
In-wall Inspection Partial 5/22/2012 at 12:00 AM 05/22/2012
Misc
Partial Correction
05/17/2012
OK TO TOP-OUT GWB WALL DOWN TO ~ 10' A.F.F. AT FOLLOWING WALL PLANES: (CC) FROM (0.3) TO (3.7); (A.5) FROM (6.0) TO (4.9); (CC.4) FROM (0.5) TO (3.4); 149 OR-4 N WALL; 141 OR-5 N WALL; 118; ..A-CC 2-2.7 144,145 SOUTH SIDE;DD-CC 1.5-2 N7s 138; a-a.5 5.7 at door 117-2; b-cc 2.7 n side corr 143.
Misc
Partial Correction
05/17/2012
OK TO COVER WHEN READY GWB WALLS FULL HEIGHT @ FOLLOWING LOCATIONS: AHU RM 147 NE CORNER FOR MOUNTING OF DP-E1-28-HA; 126 & 127 FOR EQUIPMENT INSTALL; TEMPORARY EGRESS CORRIDOR @ 117; INFILL BELOW WINDOWS ALONG (DD) FROM (3.8) TO (5.1);
Rough Framing Inspection - Commercial Passed 5/31/2012 (8:00 to 5:00) 5/31/2012 at 12:00 AM 05/31/2012
Misc
Resolved
05/31/2012
OK TO TOP-OUT WALL GWB DOWN TO ~ 10' A.F.F. AT FOLLOWING WALL PLANES: (CC) FROM (0.3) TO (3.7); (CC.4) FROM (0.3) TO (3.5); (A.5) FROM (6.0) TO (4.9);
In-wall Inspection Partial 05/31/2012
Misc
Partial Correction
05/22/2012
OK TO TOP-OUT GWB WALL DOWN TO ~ 10' A.F.F. AT FOLLOWING WALL PLANES: (CC) FROM (0.3) TO (3.7); (A.5) FROM (6.0) TO (4.9); (CC.4) FROM (0.5) TO (3.4); 149 OR-4 N WALL; 141 OR-5 N WALL; 118; ..A-CC 2-2.7 144,145 SOUTH SIDE;DD-CC 1.5-2 N7s 138; a-a.5 5.7 at door 117-2; b-cc 2.7 n side corr 143. OK TO TOP-OUT WALL GWB DOWN TO ~ 10' A.F.F. AT FOLLOWING WALL PLANES: (CC) FROM (0.3) TO (3.7); (CC.4) FROM (0.3) TO (3.5); (A.5) FROM (6.0) TO (4.9);
Misc
Partial Correction
05/22/2012
OK TO COVER WHEN READY GWB WALLS FULL HEIGHT @ FOLLOWING LOCATIONS: AHU RM 147 NE CORNER FOR MOUNTING OF DP-E1-28-HA; 126 & 127 FOR EQUIPMENT INSTALL; TEMPORARY EGRESS CORRIDOR @ 117; INFILL BELOW WINDOWS ALONG (DD) FROM (3.8) TO (5.1);
Misc
Partial Correction
05/31/2012
OK TO TOP-OUT GWB WALL DOWN TO ~ 10' A.F.F. AT FOLLOWING SPACES OR WALL PLANES: 136; 137; 138; 140; 118; 119 ALCOVE AT WEST; 119E; 119F; WALL ON (6.) FROM (BB.2) TO (CC.6);
Misc
Corrective Action Required
05/31/2012
TOP-OUT NOT APPROVED AT FOLLOWING LOCATIONS DUE TO NEED FOR PROTECTION OF COPPER PIPING IN OR NEAR CONTACT WITH STEEL FRAMING FROM GALVANIC ACTION AND PHYSICAL DAMAGE: 139 WEST WALL; OR-4 SOUTH WALL; OR-5 EAST WALL; BULKHEAD ABOVE DOOR OPENING (143)
In-wall Inspection Partial 6/1/2012 at 12:00 AM 06/01/2012
Misc
Partial Correction
05/31/2012
OK TO TOP-OUT GWB WALL DOWN TO ~ 10' A.F.F. AT FOLLOWING WALL PLANES: (CC) FROM (0.3) TO (3.7); (A.5) FROM (6.0) TO (4.9); (CC.4) FROM (0.5) TO (3.4); 149 OR-4 N WALL; 141 OR-5 N WALL; 118; ..A-CC 2-2.7 144,145 SOUTH SIDE;DD-CC 1.5-2 N7s 138; a-a.5 5.7 at door 117-2; b-cc 2.7 n side corr 143. OK TO TOP-OUT WALL GWB DOWN TO ~ 10' A.F.F. AT FOLLOWING WALL PLANES: (CC) FROM (0.3) TO (3.7); (CC.4) FROM (0.3) TO (3.5); (A.5) FROM (6.0) TO (4.9);
Misc
Partial Correction
05/31/2012
OK TO COVER WHEN READY GWB WALLS FULL HEIGHT @ FOLLOWING LOCATIONS: AHU RM 147 NE CORNER FOR MOUNTING OF DP-E1-28-HA; 126 & 127 FOR EQUIPMENT INSTALL; TEMPORARY EGRESS CORRIDOR @ 117; INFILL BELOW WINDOWS ALONG (DD) FROM (3.8) TO (5.1); BEHIND HVAC WALL CHASE @ 136 & 138;
Misc
Partial Correction
05/31/2012
OK TO TOP-OUT GWB WALL DOWN TO ~ 10' A.F.F. AT FOLLOWING SPACES OR WALL PLANES: 136; 137; 138; 140; 118; 119 ALCOVE AT WEST; 119E; 119F; WALL ON (6.) FROM (BB.2) TO (CC.6); OR-4; OR-5; 124; 125; 126; 127; 128; 129; 130; 131; 133; 139; BULKHEAD ABOVE DOOR OPENING (143); EAST EXTERIOR WALL ABOVE WINDOWS ALONG (DD) FROM (3.7) TO (5.9);
Misc
Resolved
06/01/2012
TOP-OUT NOT APPROVED AT FOLLOWING LOCATIONS DUE TO NEED FOR PROTECTION OF COPPER PIPING IN OR NEAR CONTACT WITH STEEL FRAMING FROM GALVANIC ACTION AND PHYSICAL DAMAGE: 139 WEST WALL; OR-4 SOUTH WALL; OR-5 EAST WALL; BULKHEAD ABOVE DOOR OPENING (143)
Rated Assembly Inspection Partial 6/7/2012 at 12:00 AM 06/07/2012
Misc
Partial Correction
05/17/2012
OK TO COVER WHEN READY FOLLOWING COMPONENTS OF RATED ASSEMBLIES AT INTERIM CLOSURES AT ELEVATOR DOORS @ 1ST & 2ND FLOORS: FRAMING AND SHAFT LINER; 1ST LAYER 5/8" TYPE X GWB;
In-wall Inspection Partial 6/7/2012 6/7/2012 at 12:00 AM 06/07/2012
Misc
Resolved
06/07/2012
OK TO TOP-OUT GWB WALL DOWN TO ~ 10' A.F.F. AT FOLLOWING WALL PLANES: (CC) FROM (0.3) TO (3.7); (A.5) FROM (6.0) TO (4.9); (CC.4) FROM (0.5) TO (3.4); 149 OR-4 N WALL; 141 OR-5 N WALL; 118; ..A-CC 2-2.7 144,145 SOUTH SIDE;DD-CC 1.5-2 N7s 138; a-a.5 5.7 at door 117-2; b-cc 2.7 n side corr 143. OK TO TOP-OUT WALL GWB DOWN TO ~ 10' A.F.F. AT FOLLOWING WALL PLANES: (CC) FROM (0.3) TO (3.7); (CC.4) FROM (0.3) TO (3.5); (A.5) FROM (6.0) TO (4.9);
Misc
Partial Correction
06/01/2012
OK TO COVER WHEN READY GWB WALLS FULL HEIGHT @ FOLLOWING LOCATIONS: AHU RM 147 NE CORNER FOR MOUNTING OF DP-E1-28-HA; 126 & 127 FOR EQUIPMENT INSTALL; TEMPORARY EGRESS CORRIDOR @ 117; INFILL BELOW WINDOWS ALONG (DD) FROM (3.8) TO (5.1); BEHIND HVAC WALL CHASE @ 136 & 138; 119B; 119C; 120; 121; 123; 123A; 123B; 123C; 123D; 123E; 124; 125; 129; 130; 131; 132; 134; 135; BULKHEAD ABOVE DOOR 140; FOR CABLE TRAY @ PART OF CORR 143; WALL PLANE ON (7) FROM (BB.9) TO (DD);
Misc
Resolved
06/07/2012
OK TO TOP-OUT GWB WALL DOWN TO ~ 10' A.F.F. AT FOLLOWING SPACES OR WALL PLANES: 136; 137; 138; 140; 118; 119 ALCOVE AT WEST; 119E; 119F; WALL ON (6.) FROM (BB.2) TO (CC.6); OR-4; OR-5; 124; 125; 126; 127; 128; 129; 130; 131; 133; 139; BULKHEAD ABOVE DOOR OPENING (143); EAST EXTERIOR WALL ABOVE WINDOWS ALONG (DD) FROM (3.7) TO (5.9);
In-wall Inspection Partial 6/8/2012 at 12:00 AM 06/08/2012
Misc
Partial Correction
06/07/2012
OK TO COVER WHEN READY GWB WALLS FULL HEIGHT @ FOLLOWING LOCATIONS: AHU RM 147 NE CORNER FOR MOUNTING OF DP-E1-28-HA; 126 & 127 FOR EQUIPMENT INSTALL; TEMPORARY EGRESS CORRIDOR @ 117; INFILL BELOW WINDOWS ALONG (DD) FROM (3.8) TO (5.1); BEHIND HVAC WALL CHASE @ 136 & 138; 119B; 119C; 120; 121; 123; 123A; 123B; 123C; 123D; 123E; 124; 125; 129; 130; 131; 132; 134; 135; BULKHEAD ABOVE DOOR 140; FOR CABLE TRAY @ PART OF CORR 143; WALL PLANE ON (7) FROM (BB.9) TO (DD);
Misc
Partial Correction
06/08/2012
OK TO TOP-OUT GWB WALL DOWN TO ~ 10' A.F.F. AT FOLLOWING WALL PLANES: (CC) FROM (0.3) TO (3.7); (A.5) FROM (6.0) TO (4.9); (CC.4) FROM (0.5) TO (3.4); 149 OR-4 N WALL; 141 OR-5 N WALL; 118; ..A-CC 2-2.7 144,145 SOUTH SIDE;DD-CC 1.5-2 N7s 138; a-a.5 5.7 at door 117-2; b-cc 2.7 n side corr 143. OK TO TOP-OUT WALL GWB DOWN TO ~ 10' A.F.F. AT FOLLOWING WALL PLANES: (CC) FROM (0.3) TO (3.7); (CC.4) FROM (0.3) TO (3.5); (A.5) FROM (6.0) TO (4.9); ON (1) FROM (B) TO (CC);
In-wall Inspection Partial 6/12/2012 (8:00 to 5:00) 6/12/2012 at 12:00 AM 06/12/2012
Misc
Partial Correction
06/08/2012
OK TO COVER WHEN READY GWB WALLS FULL HEIGHT @ FOLLOWING LOCATIONS: AHU RM 147 NE CORNER FOR MOUNTING OF DP-E1-28-HA; 126 & 127 FOR EQUIPMENT INSTALL; TEMPORARY EGRESS CORRIDOR @ 117; INFILL BELOW WINDOWS ALONG (DD) FROM (3.8) TO (5.1); BEHIND HVAC WALL CHASE @ 136 & 138; 119B; 119C; 120; 121; 123; 123A; 123B; 123C; 123D; 123E; 124; 125; 129; 130; 131; 132; 134; 135; BULKHEAD ABOVE DOOR 140; FOR CABLE TRAY @ PART OF CORR 143; WALL PLANE ON (7) FROM (BB.9) TO (DD); 101 FROM (A) TO (CC.3); 118; 119D; 119E; 119F;
Misc
Partial Correction
06/08/2012
OK TO TOP-OUT GWB WALL DOWN TO ~ 10' A.F.F. AT FOLLOWING WALL PLANES: (CC) FROM (0.3) TO (3.7); (A.5) FROM (6.0) TO (4.9); (CC.4) FROM (0.5) TO (3.4); 149 OR-4 N WALL; 141 OR-5 N WALL; 118; ..A-CC 2-2.7 144,145 SOUTH SIDE;DD-CC 1.5-2 N7s 138; a-a.5 5.7 at door 117-2; b-cc 2.7 n side corr 143. OK TO TOP-OUT WALL GWB DOWN TO ~ 10' A.F.F. AT FOLLOWING WALL PLANES: (CC) FROM (0.3) TO (3.7); (CC.4) FROM (0.3) TO (3.5); (A.5) FROM (6.0) TO (4.9); ON (1) FROM (B) TO (CC);
Rated Assembly Inspection Partial 6/12/2012 at 12:00 AM 06/12/2012
Misc
Partial Correction
06/07/2012
OK TO COVER WHEN READY FOLLOWING COMPONENTS OF RATED ASSEMBLIES AT INTERIM CLOSURES AT ELEVATOR DOORS @ 1ST & 2ND FLOORS: FRAMING AND SHAFT LINER; 1ST + 2ND LAYERS 5/8" TYPE X GWB OK TO TAPE, MUD & FIRE-SEAL
In-wall Inspection Partial 6/12/2012 at 12:00 AM 06/12/2012
Misc
Partial Correction
06/12/2012
OK TO COVER WHEN READY GWB WALLS FULL HEIGHT @ FOLLOWING LOCATIONS: AHU RM 147 NE CORNER FOR MOUNTING OF DP-E1-28-HA; 126 & 127 FOR EQUIPMENT INSTALL; TEMPORARY EGRESS CORRIDOR @ 117; INFILL BELOW WINDOWS ALONG (DD) FROM (3.8) TO (5.1); BEHIND HVAC WALL CHASE @ 136 & 138; 119B; 119C; 120; 121; 123; 123A; 123B; 123C; 123D; 123E; 124; 125; 129; 130; 131; 132; 134; 135; BULKHEAD ABOVE DOOR 140; FOR CABLE TRAY @ PART OF CORR 143; WALL PLANE ON (7) FROM (BB.9) TO (DD); 101 FROM (A) TO (CC.3); 118; 119; 119D; 119E; 119F;
Misc
Partial Correction
06/12/2012
OK TO TOP-OUT GWB WALL DOWN TO ~ 10' A.F.F. AT FOLLOWING WALL PLANES: (CC) FROM (0.3) TO (3.7); (A.5) FROM (6.0) TO (4.9); (CC.4) FROM (0.5) TO (3.4); 149 OR-4 N WALL; 141 OR-5 N WALL; 118; ..A-CC 2-2.7 144,145 SOUTH SIDE;DD-CC 1.5-2 N7s 138; a-a.5 5.7 at door 117-2; b-cc 2.7 n side corr 143. OK TO TOP-OUT WALL GWB DOWN TO ~ 10' A.F.F. AT FOLLOWING WALL PLANES: (CC) FROM (0.3) TO (3.7); (CC.4) FROM (0.3) TO (3.5); (A.5) FROM (6.0) TO (4.9); ON (1) FROM (B) TO (CC);
Above Ceiling Inspection Partial 6/18/2012 6/18/2012 at 12:00 AM 06/18/2012
Misc
Partial Correction
06/18/2012
OK TO COVER WHEN READY GWB CEILING FRAMING + ABOVE-CEILING SYSTEMS @ FOLLOWING SPACES: SOFFIT @ NURSE STATION 120;
Rated Assembly Inspection Partial 6/18/2012 at 12:00 AM 06/18/2012
Misc
Partial Correction
06/12/2012
OK TO COVER WHEN READY FOLLOWING COMPONENTS OF RATED ASSEMBLIES AT INTERIM CLOSURES AT ELEVATOR DOORS @ 1ST & 2ND FLOORS: FRAMING AND SHAFT LINER; 1ST + 2ND LAYERS 5/8" TYPE X GWB OK TO TAPE, MUD & FIRE-SEAL 1ST FLOOR OK TO BUILD FALSE WALL IN FRONT OF DOOR OPENINGS AFTER MUD/TAPE IS COMPLETED
In-wall Inspection Partial 6/18/2012 6/18/2012 at 12:00 AM 06/18/2012
Misc
Partial Correction
06/12/2012
OK TO COVER WHEN READY GWB WALLS FULL HEIGHT @ FOLLOWING LOCATIONS: AHU RM 147 NE CORNER FOR MOUNTING OF DP-E1-28-HA; 126 & 127 FOR EQUIPMENT INSTALL; TEMPORARY EGRESS CORRIDOR @ 117; INFILL BELOW WINDOWS ALONG (DD) FROM (3.8) TO (5.1); BEHIND HVAC WALL CHASE @ 136 & 138; 119B; 119C; 120; 121; 123; 123A; 123B; 123C; 123D; 123E; 124; 125; 129; 130; 131; 132; 134; 135; BULKHEAD ABOVE DOOR 140; FOR CABLE TRAY @ PART OF CORR 143; WALL PLANE ON (7) FROM (BB.9) TO (DD); 101 FROM (A) TO (CC.3); 118; 119; 119D; 119E; 119F; ON (DD) FROM (3.7) TO (7); 142 W WALL; ON (3) FROM (A) TO (B) {CORR 143 S WALL};
Misc
Partial Correction
06/12/2012
OK TO TOP-OUT GWB WALL DOWN TO ~ 10' A.F.F. AT FOLLOWING WALL PLANES: (CC) FROM (0.3) TO (3.7); (A.5) FROM (6.0) TO (4.9); (CC.4) FROM (0.5) TO (3.4); 149 OR-4 N WALL; 141 OR-5 N WALL; 118; ..A-CC 2-2.7 144,145 SOUTH SIDE;DD-CC 1.5-2 N7s 138; a-a.5 5.7 at door 117-2; b-cc 2.7 n side corr 143. OK TO TOP-OUT WALL GWB DOWN TO ~ 10' A.F.F. AT FOLLOWING WALL PLANES: (CC) FROM (0.3) TO (3.7); (CC.4) FROM (0.3) TO (3.5); (A.5) FROM (6.0) TO (4.9); ON (1) FROM (B) TO (CC); 142;
In-wall Inspection Not Ready 6/20/2012 06/20/2012
Misc
Partial Correction
06/18/2012
OK TO COVER WHEN READY GWB WALLS FULL HEIGHT @ FOLLOWING LOCATIONS: AHU RM 147 NE CORNER FOR MOUNTING OF DP-E1-28-HA; 126 & 127 FOR EQUIPMENT INSTALL; TEMPORARY EGRESS CORRIDOR @ 117; INFILL BELOW WINDOWS ALONG (DD) FROM (3.8) TO (5.1); BEHIND HVAC WALL CHASE @ 136 & 138; 119B; 119C; 120; 121; 123; 123A; 123B; 123C; 123D; 123E; 124; 125; 129; 130; 131; 132; 134; 135; BULKHEAD ABOVE DOOR 140; FOR CABLE TRAY @ PART OF CORR 143; WALL PLANE ON (7) FROM (BB.9) TO (DD); 101 FROM (A) TO (CC.3); 118; 119; 119D; 119E; 119F; ON (DD) FROM (3.7) TO (7); 142 W WALL; ON (3) FROM (A) TO (B) {CORR 143 S WALL};
Misc
Partial Correction
06/18/2012
OK TO TOP-OUT GWB WALL DOWN TO ~ 10' A.F.F. AT FOLLOWING WALL PLANES: (CC) FROM (0.3) TO (3.7); (A.5) FROM (6.0) TO (4.9); (CC.4) FROM (0.5) TO (3.4); 149 OR-4 N WALL; 141 OR-5 N WALL; 118; ..A-CC 2-2.7 144,145 SOUTH SIDE;DD-CC 1.5-2 N7s 138; a-a.5 5.7 at door 117-2; b-cc 2.7 n side corr 143. OK TO TOP-OUT WALL GWB DOWN TO ~ 10' A.F.F. AT FOLLOWING WALL PLANES: (CC) FROM (0.3) TO (3.7); (CC.4) FROM (0.3) TO (3.5); (A.5) FROM (6.0) TO (4.9); ON (1) FROM (B) TO (CC); 142;
In-wall Inspection Partial 6/21/2012 6/21/2012 at 12:00 AM 06/21/2012
Misc
Partial Correction
06/20/2012
OK TO COVER WHEN READY GWB WALLS FULL HEIGHT @ FOLLOWING LOCATIONS: AHU RM 147 NE CORNER FOR MOUNTING OF DP-E1-28-HA; 126 & 127 FOR EQUIPMENT INSTALL; TEMPORARY EGRESS CORRIDOR @ 117; INFILL BELOW WINDOWS ALONG (DD) FROM (3.8) TO (5.1); BEHIND HVAC WALL CHASE @ 136 & 138; 119B; 119C; 120; 121; 123; 123A; 123B; 123C; 123D; 123E; 124; 125; 129; 130; 131; 132; 134; 135; BULKHEAD ABOVE DOOR 140; FOR CABLE TRAY @ PART OF CORR 143; WALL PLANE ON (7) FROM (BB.9) TO (DD); 101 FROM (A) TO (CC.3); 118; 119; 119D; 119E; 119F; ON (DD) FROM (3.7) TO (7); 142 W WALL; ON (3) FROM (A) TO (B) {CORR 143 S WALL}; 136; 137; 138; 139; 140; 141; 143; 144; 145; 146; 147; 149 S,E,W WALLS;
Misc
Partial Correction
06/20/2012
OK TO TOP-OUT GWB WALL DOWN TO ~ 10' A.F.F. AT FOLLOWING WALL PLANES: (CC) FROM (0.3) TO (3.7); (A.5) FROM (6.0) TO (4.9); (CC.4) FROM (0.5) TO (3.4); 149 OR-4 N WALL; 141 OR-5 N WALL; 118; ..A-CC 2-2.7 144,145 SOUTH SIDE;DD-CC 1.5-2 N7s 138; a-a.5 5.7 at door 117-2; b-cc 2.7 n side corr 143. OK TO TOP-OUT WALL GWB DOWN TO ~ 10' A.F.F. AT FOLLOWING WALL PLANES: (CC) FROM (0.3) TO (3.7); (CC.4) FROM (0.3) TO (3.5); (A.5) FROM (6.0) TO (4.9); ON (1) FROM (B) TO (CC); 142;
Rated Assembly Inspection Partial 6/26/2012 6/26/2012 at 12:00 AM 06/26/2012
Misc
Resolved
06/26/2012
OK TO COVER WHEN READY FOLLOWING COMPONENTS OF RATED ASSEMBLIES AT INTERIM CLOSURES AT ELEVATOR DOORS @ 1ST & 2ND FLOORS: FRAMING AND SHAFT LINER; 1ST + 2ND LAYERS 5/8" TYPE X GWB OK TO TAPE, MUD & FIRE-SEAL 1ST FLOOR OK TO BUILD FALSE WALL IN FRONT OF DOOR OPENINGS AFTER MUD/TAPE IS COMPLETED
Misc
Partial Correction
06/26/2012
ALL DESIGNATED SMOKE WALLS FOUND TO BE SCREWED AT 8"/12" PATTERN SIMILAR TO THAT AT DESIGNATED FIRE WALLS.
Misc
Partial Correction
06/26/2012
OK TO TAPE, MUD & FIRE SEAL FIRE-RATED WALLS AT FOLLOWING LOCATIONS: CORRIDOR 140 EAST WALL NORTH OF CC.4/1.5; 138 N WALL;
Rated Assembly Inspection Partial 6/27/2012 6/27/2012 at 12:00 AM 06/27/2012
Misc
Partial Correction
06/26/2012
ALL DESIGNATED SMOKE WALLS FOUND TO BE SCREWED AT 8"/12" PATTERN SIMILAR TO THAT AT DESIGNATED FIRE WALLS.
Misc
Partial Correction
06/26/2012
OK TO TAPE, MUD & FIRE SEAL FIRE-RATED WALLS AT FOLLOWING LOCATIONS: CORRIDOR 140 EAST WALL NORTH OF CC.4/1.5; 138 N WALL; 139 S&W WALLS;
In-wall Inspection Partial 6/28/2012 6/28/2012 at 12:00 AM 06/28/2012
Misc
Partial Correction
06/21/2012
OK TO COVER WHEN READY GWB WALLS FULL HEIGHT @ FOLLOWING LOCATIONS: AHU RM 147 NE CORNER FOR MOUNTING OF DP-E1-28-HA; 126 & 127 FOR EQUIPMENT INSTALL; TEMPORARY EGRESS CORRIDOR @ 117; INFILL BELOW WINDOWS ALONG (DD) FROM (3.8) TO (5.1); BEHIND HVAC WALL CHASE @ 136 & 138; 119B; 119C; 120; 121; 123; 123A; 123B; 123C; 123D; 123E; 124; 125; 129; 130; 131; 132; 134; 135; BULKHEAD ABOVE DOOR 140; FOR CABLE TRAY @ PART OF CORR 143; WALL PLANE ON (7) FROM (BB.9) TO (DD); 101 FROM (A) TO (CC.3); 118; 119; 119D; 119E; 119F; ON (DD) FROM (3.7) TO (7); 142 W WALL; ON (3) FROM (A) TO (B) {CORR 143 S WALL}; 136; 137; 138; 139; 140; 141; 143; 144; 145; 146; 147; 149 S,E,W WALLS; 142 ALL WALLS; MODIFICATIONS @ 136 N & 138 S;
Misc
Partial Correction
06/21/2012
OK TO TOP-OUT GWB WALL DOWN TO ~ 10' A.F.F. AT FOLLOWING WALL PLANES: (CC) FROM (0.3) TO (3.7); (A.5) FROM (6.0) TO (4.9); (CC.4) FROM (0.5) TO (3.4); 149 OR-4 N WALL; 141 OR-5 N WALL; 118; ..A-CC 2-2.7 144,145 SOUTH SIDE;DD-CC 1.5-2 N7s 138; a-a.5 5.7 at door 117-2; b-cc 2.7 n side corr 143. OK TO TOP-OUT WALL GWB DOWN TO ~ 10' A.F.F. AT FOLLOWING WALL PLANES: (CC) FROM (0.3) TO (3.7); (CC.4) FROM (0.3) TO (3.5); (A.5) FROM (6.0) TO (4.9); ON (1) FROM (B) TO (CC); 142;
In-wall Inspection Partial 7/3/2012 7/3/2012 at 12:00 AM 07/03/2012
Misc
Partial Correction
06/28/2012
OK TO COVER WHEN READY GWB WALLS FULL HEIGHT @ FOLLOWING LOCATIONS: AHU RM 147 NE CORNER FOR MOUNTING OF DP-E1-28-HA; 126 & 127 FOR EQUIPMENT INSTALL; TEMPORARY EGRESS CORRIDOR @ 117; INFILL BELOW WINDOWS ALONG (DD) FROM (3.8) TO (5.1); BEHIND HVAC WALL CHASE @ 136 & 138; 119B; 119C; 120; 121; 123; 123A; 123B; 123C; 123D; 123E; 124; 125; 129; 130; 131; 132; 134; 135; BULKHEAD ABOVE DOOR 140; FOR CABLE TRAY @ PART OF CORR 143; WALL PLANE ON (7) FROM (BB.9) TO (DD); 101 FROM (A) TO (CC.3); 118; 119; 119D; 119E; 119F; ON (DD) FROM (3.7) TO (7); 142 W WALL; ON (3) FROM (A) TO (B) {CORR 143 S WALL}; 136; 137; 138; 139; 140; 141; 143; 144; 145; 146; 147; 149 S,E,W WALLS; 142 ALL WALLS; MODIFICATIONS @ 136 N & 138 S; 101 SOUTH WALL;
Misc
Partial Correction
06/28/2012
OK TO TOP-OUT GWB WALL DOWN TO ~ 10' A.F.F. AT FOLLOWING WALL PLANES: (CC) FROM (0.3) TO (3.7); (A.5) FROM (6.0) TO (4.9); (CC.4) FROM (0.5) TO (3.4); 149 OR-4 N WALL; 141 OR-5 N WALL; 118; ..A-CC 2-2.7 144,145 SOUTH SIDE;DD-CC 1.5-2 N7s 138; a-a.5 5.7 at door 117-2; b-cc 2.7 n side corr 143. OK TO TOP-OUT WALL GWB DOWN TO ~ 10' A.F.F. AT FOLLOWING WALL PLANES: (CC) FROM (0.3) TO (3.7); (CC.4) FROM (0.3) TO (3.5); (A.5) FROM (6.0) TO (4.9); ON (1) FROM (B) TO (CC); 142;
In-wall Inspection Partial 7/5/2012 7/5/2012 at 12:00 AM 07/05/2012
Misc
Partial Correction
07/03/2012
OK TO COVER WHEN READY GWB WALLS FULL HEIGHT @ FOLLOWING LOCATIONS: AHU RM 147 NE CORNER FOR MOUNTING OF DP-E1-28-HA; 126 & 127 FOR EQUIPMENT INSTALL; TEMPORARY EGRESS CORRIDOR @ 117; INFILL BELOW WINDOWS ALONG (DD) FROM (3.8) TO (5.1); BEHIND HVAC WALL CHASE @ 136 & 138; 119B; 119C; 120; 121; 123; 123A; 123B; 123C; 123D; 123E; 124; 125; 129; 130; 131; 132; 134; 135; BULKHEAD ABOVE DOOR 140; FOR CABLE TRAY @ PART OF CORR 143; WALL PLANE ON (7) FROM (BB.9) TO (DD); 101 FROM (A) TO (CC.3); 118; 119; 119D; 119E; 119F; ON (DD) FROM (3.7) TO (7); 142 W WALL; ON (3) FROM (A) TO (B) {CORR 143 S WALL}; 136; 137; 138; 139; 140; 141; 143; 144; 145; 146; 147; 149 S,E,W WALLS; 142 ALL WALLS; MODIFICATIONS @ 136 N & 138 S; 101 SOUTH WALL; 134 PLAN EAST WALL
Misc
Partial Correction
07/03/2012
OK TO TOP-OUT GWB WALL DOWN TO ~ 10' A.F.F. AT FOLLOWING WALL PLANES: (CC) FROM (0.3) TO (3.7); (A.5) FROM (6.0) TO (4.9); (CC.4) FROM (0.5) TO (3.4); 149 OR-4 N WALL; 141 OR-5 N WALL; 118; ..A-CC 2-2.7 144,145 SOUTH SIDE;DD-CC 1.5-2 N7s 138; a-a.5 5.7 at door 117-2; b-cc 2.7 n side corr 143. OK TO TOP-OUT WALL GWB DOWN TO ~ 10' A.F.F. AT FOLLOWING WALL PLANES: (CC) FROM (0.3) TO (3.7); (CC.4) FROM (0.3) TO (3.5); (A.5) FROM (6.0) TO (4.9); ON (1) FROM (B) TO (CC); 142;
In-wall Inspection Partial 7/5/2012 at 12:00 AM 07/05/2012
Misc
Partial Correction
07/05/2012
OK TO COVER WHEN READY GWB WALLS FULL HEIGHT @ FOLLOWING LOCATIONS: AHU RM 147 NE CORNER FOR MOUNTING OF DP-E1-28-HA; 126 & 127 FOR EQUIPMENT INSTALL; TEMPORARY EGRESS CORRIDOR @ 117; INFILL BELOW WINDOWS ALONG (DD) FROM (3.8) TO (5.1); BEHIND HVAC WALL CHASE @ 136 & 138; 119B; 119C; 120; 121; 123; 123A; 123B; 123C; 123D; 123E; 124; 125; 129; 130; 131; 132; 134; 135; BULKHEAD ABOVE DOOR 140; FOR CABLE TRAY @ PART OF CORR 143; WALL PLANE ON (7) FROM (BB.9) TO (DD); 101 FROM (A) TO (CC.3); 118; 119; 119D; 119E; 119F; ON (DD) FROM (3.7) TO (7); 142 W WALL; ON (3) FROM (A) TO (B) {CORR 143 S WALL}; 136; 137; 138; 139; 140; 141; 143; 144; 145; 146; 147; 149 S,E,W WALLS; 142 ALL WALLS; MODIFICATIONS @ 136 N & 138 S; 101 SOUTH WALL; 153 PLAN EAST WALL
Misc
Partial Correction
07/05/2012
OK TO TOP-OUT GWB WALL DOWN TO ~ 10' A.F.F. AT FOLLOWING WALL PLANES: (CC) FROM (0.3) TO (3.7); (A.5) FROM (6.0) TO (4.9); (CC.4) FROM (0.5) TO (3.4); 149 OR-4 N WALL; 141 OR-5 N WALL; 118; ..A-CC 2-2.7 144,145 SOUTH SIDE;DD-CC 1.5-2 N7s 138; a-a.5 5.7 at door 117-2; b-cc 2.7 n side corr 143. OK TO TOP-OUT WALL GWB DOWN TO ~ 10' A.F.F. AT FOLLOWING WALL PLANES: (CC) FROM (0.3) TO (3.7); (CC.4) FROM (0.3) TO (3.5); (A.5) FROM (6.0) TO (4.9); ON (1) FROM (B) TO (CC); 142;
Above Ceiling Inspection Passed 7/9/2012 7/9/2012 at 12:00 AM 07/09/2012
Misc
Partial Correction
06/18/2012
OK TO COVER WHEN READY GWB CEILING FRAMING + ABOVE-CEILING SYSTEMS @ FOLLOWING SPACES: SOFFIT @ NURSE STATION 120; 141; 142; 146;
Rated Assembly Inspection Partial 7/9/2012 7/9/2012 at 12:00 AM 07/09/2012
Misc
Partial Correction
06/27/2012
ALL DESIGNATED SMOKE WALLS FOUND TO BE SCREWED AT 8"/12" PATTERN SIMILAR TO THAT AT DESIGNATED FIRE WALLS.
Misc
Partial Correction
06/27/2012
OK TO TAPE, MUD & FIRE SEAL FIRE-RATED WALLS AT FOLLOWING LOCATIONS: CORRIDOR 140 EAST WALL NORTH OF CC.4/1.5; 138 N WALL; 139 S&W WALLS;
Misc
Partial Correction
07/09/2012
OK TO COVER WHEN READY COMPONENTS OF TYPE "F" 2HR RATED WALL ASSEMBLY: 2ND FLR AHU EAST & SOUTH WALLS FRAMING + SHAFT LINER;
In-wall Inspection Partial 7/12/2012 at 12:00 AM 07/12/2012
Misc
Partial Correction
07/05/2012
OK TO COVER WHEN READY GWB WALLS FULL HEIGHT @ FOLLOWING LOCATIONS: AHU RM 147 NE CORNER FOR MOUNTING OF DP-E1-28-HA; 126 & 127 FOR EQUIPMENT INSTALL; TEMPORARY EGRESS CORRIDOR @ 117; INFILL BELOW WINDOWS ALONG (DD) FROM (3.8) TO (5.1); BEHIND HVAC WALL CHASE @ 136 & 138; 119B; 119C; 120; 121; 123; 123A; 123B; 123C; 123D; 123E; 124; 125; 129; 130; 131; 132; 134; 135; BULKHEAD ABOVE DOOR 140; FOR CABLE TRAY @ PART OF CORR 143; WALL PLANE ON (7) FROM (BB.9) TO (DD); 101 FROM (A) TO (CC.3); 118; 119; 119D; 119E; 119F; ON (DD) FROM (3.7) TO (7); 142 W WALL; ON (3) FROM (A) TO (B) {CORR 143 S WALL}; 136; 137; 138; 139; 140; 141; 143; 144; 145; 146; 147; 149 S,E,W WALLS; 142 ALL WALLS; MODIFICATIONS @ 136 N & 138 S; 101 SOUTH WALL; 153 PLAN EAST WALL; UTILITY CHASES AT 100 SW & 102 NE;
Misc
Resolved
07/12/2012
OK TO TOP-OUT GWB WALL DOWN TO ~ 10' A.F.F. AT FOLLOWING WALL PLANES: (CC) FROM (0.3) TO (3.7); (A.5) FROM (6.0) TO (4.9); (CC.4) FROM (0.5) TO (3.4); 149 OR-4 N WALL; 141 OR-5 N WALL; 118; ..A-CC 2-2.7 144,145 SOUTH SIDE;DD-CC 1.5-2 N7s 138; a-a.5 5.7 at door 117-2; b-cc 2.7 n side corr 143. OK TO TOP-OUT WALL GWB DOWN TO ~ 10' A.F.F. AT FOLLOWING WALL PLANES: (CC) FROM (0.3) TO (3.7); (CC.4) FROM (0.3) TO (3.5); (A.5) FROM (6.0) TO (4.9); ON (1) FROM (B) TO (CC); 142;
Rated Assembly Inspection Partial 7/12/2012 7/12/2012 at 12:00 AM 07/12/2012
Misc
Partial Correction
07/09/2012
ALL DESIGNATED SMOKE WALLS FOUND TO BE SCREWED AT 8"/12" PATTERN SIMILAR TO THAT AT DESIGNATED FIRE WALLS.
Misc
Partial Correction
07/09/2012
OK TO TAPE, MUD & FIRE SEAL FIRE-RATED WALLS AT FOLLOWING LOCATIONS: CORRIDOR 140 EAST WALL NORTH OF CC.4/1.5; 138 N WALL; 139 S&W WALLS;
Misc
Partial Correction
07/09/2012
OK TO COVER WHEN READY COMPONENTS OF TYPE "F" 2HR RATED WALL ASSEMBLY: 2ND FLR AHU EAST & SOUTH WALLS FRAMING, SHAFT LINER + ONE LAYER 5/8" TYPE X GWB;
In-wall Inspection Partial 7/13/2012 7/13/2012 at 12:00 AM 07/13/2012
Misc
Partial Correction
07/12/2012
OK TO COVER WHEN READY GWB WALLS FULL HEIGHT @ FOLLOWING LOCATIONS: AHU RM 147 NE CORNER FOR MOUNTING OF DP-E1-28-HA; 126 & 127 FOR EQUIPMENT INSTALL; TEMPORARY EGRESS CORRIDOR @ 117; INFILL BELOW WINDOWS ALONG (DD) FROM (3.8) TO (5.1); BEHIND HVAC WALL CHASE @ 136 & 138; 119B; 119C; 120; 121; 123; 123A; 123B; 123C; 123D; 123E; 124; 125; 129; 130; 131; 132; 134; 135; BULKHEAD ABOVE DOOR 140; FOR CABLE TRAY @ PART OF CORR 143; WALL PLANE ON (7) FROM (BB.9) TO (DD); 101 FROM (A) TO (CC.3); 118; 119; 119D; 119E; 119F; ON (DD) FROM (3.7) TO (7); 142 W WALL; ON (3) FROM (A) TO (B) {CORR 143 S WALL}; 136; 137; 138; 139; 140; 141; 143; 144; 145; 146; 147; 149 S,E,W WALLS; 142 ALL WALLS; MODIFICATIONS @ 136 N & 138 S; 101 SOUTH WALL; 153 PLAN EAST WALL; UTILITY CHASES AT 100 SW & 102 NE; 119A S WALL; 122; 147 W WALL;
Above Ceiling Inspection Partial 7/13/2012 7/13/2012 at 12:00 AM 07/13/2012
Misc
Partial Correction
07/13/2012
OK TO COVER WHEN READY GWB CEILING FRAMING + ABOVE-CEILING SYSTEMS @ FOLLOWING SPACES: SOFFIT @ NURSE STATION 120; 141; 142; 146; 149(OR#4);
In-wall Inspection Partial 7/16/2012 at 12:00 AM 07/16/2012
Misc
Partial Correction
07/13/2012
OK TO COVER WHEN READY GWB WALLS FULL HEIGHT @ FOLLOWING LOCATIONS: AHU RM 147 NE CORNER FOR MOUNTING OF DP-E1-28-HA; 126 & 127 FOR EQUIPMENT INSTALL; TEMPORARY EGRESS CORRIDOR @ 117; INFILL BELOW WINDOWS ALONG (DD) FROM (3.8) TO (5.1); BEHIND HVAC WALL CHASE @ 136 & 138; 119B; 119C; 120; 121; 123; 123A; 123B; 123C; 123D; 123E; 124; 125; 129; 130; 131; 132; 134; 135; BULKHEAD ABOVE DOOR 140; FOR CABLE TRAY @ PART OF CORR 143; WALL PLANE ON (7) FROM (BB.9) TO (DD); 101 FROM (A) TO (CC.3); 118; 119; 119D; 119E; 119F; ON (DD) FROM (3.7) TO (7); 142 W WALL; ON (3) FROM (A) TO (B) {CORR 143 S WALL}; 136; 137; 138; 139; 140; 141; 143; 144; 145; 146; 147; 149 S,E,W WALLS; 142 ALL WALLS; MODIFICATIONS @ 136 N & 138 S; 101 SOUTH WALL; 153 PLAN EAST WALL; UTILITY CHASES AT 100 SW & 102 NE; 119A S WALL; 122; 147 W WALL; CHASE @ (B)/(1)
Rated Assembly Inspection Partial 7/16/2012 at 12:00 AM 07/16/2012
Misc
Partial Correction
07/12/2012
ALL DESIGNATED SMOKE WALLS FOUND TO BE SCREWED AT 8"/12" PATTERN SIMILAR TO THAT AT DESIGNATED FIRE WALLS.
Misc
Partial Correction
07/12/2012
OK TO TAPE, MUD & FIRE SEAL FIRE-RATED WALLS AT FOLLOWING LOCATIONS: CORRIDOR 140 EAST WALL NORTH OF CC.4/1.5; 138 N WALL; 139 S&W WALLS; 122 BOTH FACES; ON (6.0) FROM (CC.3) TO (DD) SOUTH FACE
Misc
Partial Correction
07/12/2012
OK TO COVER WHEN READY COMPONENTS OF TYPE "F" 2HR RATED WALL ASSEMBLY: 2ND FLR AHU EAST & SOUTH WALLS FRAMING, SHAFT LINER + ONE LAYER 5/8" TYPE X GWB;
In-wall Inspection Partial 7/18/2012 (8:00 to 5:00) 7/18/2012 at 12:00 AM 07/18/2012
Misc
Partial Correction
07/16/2012
OK TO COVER WHEN READY GWB WALLS FULL HEIGHT @ FOLLOWING LOCATIONS: AHU RM 147 NE CORNER FOR MOUNTING OF DP-E1-28-HA; 126 & 127 FOR EQUIPMENT INSTALL; TEMPORARY EGRESS CORRIDOR @ 117; INFILL BELOW WINDOWS ALONG (DD) FROM (3.8) TO (5.1); BEHIND HVAC WALL CHASE @ 136 & 138; 119B; 119C; 120; 121; 123; 123A; 123B; 123C; 123D; 123E; 124; 125; 129; 130; 131; 132; 134; 135; BULKHEAD ABOVE DOOR 140; FOR CABLE TRAY @ PART OF CORR 143; WALL PLANE ON (7) FROM (BB.9) TO (DD); 101 FROM (A) TO (CC.3); 118; 119; 119D; 119E; 119F; ON (DD) FROM (3.7) TO (7); 142 W WALL; ON (3) FROM (A) TO (B) {CORR 143 S WALL}; 136; 137; 138; 139; 140; 141; 143; 144; 145; 146; 147; 149 S,E,W WALLS; 142 ALL WALLS; MODIFICATIONS @ 136 N & 138 S; 101 SOUTH WALL; 153 PLAN EAST WALL; UTILITY CHASES AT 100 SW & 102 NE; 119A S WALL; 122; 147 W WALL; CHASE @ (B)/(1); 119A S WALL AFTER RE-WORK;
In-wall Inspection Partial 7/18/2012 at 12:00 AM 07/18/2012
Misc
Partial Correction
07/18/2012
OK TO COVER WHEN READY GWB WALLS FULL HEIGHT @ FOLLOWING LOCATIONS: AHU RM 147 NE CORNER FOR MOUNTING OF DP-E1-28-HA; 126 & 127 FOR EQUIPMENT INSTALL; TEMPORARY EGRESS CORRIDOR @ 117; INFILL BELOW WINDOWS ALONG (DD) FROM (3.8) TO (5.1); BEHIND HVAC WALL CHASE @ 136 & 138; 119B; 119C; 120; 121; 123; 123A; 123B; 123C; 123D; 123E; 124; 125; 129; 130; 131; 132; 134; 135; BULKHEAD ABOVE DOOR 140; FOR CABLE TRAY @ PART OF CORR 143; WALL PLANE ON (7) FROM (BB.9) TO (DD); 101 FROM (A) TO (CC.3); 118; 119; 119D; 119E; 119F; ON (DD) FROM (3.7) TO (7); 142 W WALL; ON (3) FROM (A) TO (B) {CORR 143 S WALL}; 136; 137; 138; 139; 140; 141; 143; 144; 145; 146; 147; 149 S,E,W WALLS; 142 ALL WALLS; MODIFICATIONS @ 136 N & 138 S; 101 SOUTH WALL; 153 PLAN EAST WALL; UTILITY CHASES AT 100 SW & 102 NE; 119A S WALL; 122; 147 W WALL; CHASE @ (B)/(1); 119A S WALL AFTER RE-WORK; 122 ONE CHASE + ONE COLUMN WRAP;
Rated Assembly Inspection Partial 7/19/2012 at 12:00 AM 07/19/2012
Misc
Partial Correction
07/16/2012
ALL DESIGNATED SMOKE WALLS FOUND TO BE SCREWED AT 8"/12" PATTERN SIMILAR TO THAT AT DESIGNATED FIRE WALLS.
Misc
Partial Correction
07/16/2012
OK TO TAPE, MUD & FIRE SEAL FIRE-RATED WALLS AT FOLLOWING LOCATIONS: CORRIDOR 140 EAST WALL NORTH OF CC.4/1.5; 138 N WALL; 139 S&W WALLS; 122 BOTH FACES; ON (6.0) FROM (CC.3) TO (DD) SOUTH FACE; 119A S WALL;
Misc
Partial Correction
07/16/2012
OK TO COVER WHEN READY COMPONENTS OF TYPE "F" 2HR RATED WALL ASSEMBLY: 2ND FLR AHU EAST & SOUTH WALLS FRAMING, SHAFT LINER + ONE LAYER 5/8" TYPE X GWB;
Above Ceiling Inspection Not Ready 8/8/2012 8/8/2012 at 12:00 AM 08/08/2012
Misc
Partial Correction
07/13/2012
OK TO COVER WHEN READY GWB CEILING FRAMING + ABOVE-CEILING SYSTEMS @ FOLLOWING SPACES: SOFFIT @ NURSE STATION 120; 141; 142; 146; 149(OR#4);
Misc
Corrective Action Required
08/08/2012
ABOVE-CEILING INSPECTION @ ACT TILE SPACES: AGREED TO RESUME INSPECTION AFTER 1) ALL CEILING SUPPORT WIRES ARE HUNG STRAIGHT FROM GRID TO ATTACHMENT TO DECK ABOVE 2) ALL MC CABLES ARE SECURED WITHIN 12" OF ENTRY TO BOX (EXCEPT FIXTURE WHIPS NOT > 6' LONG)
In-wall Inspection Partial 8/9/2012 at 12:00 AM 08/09/2012
Misc
Partial Correction
07/18/2012
OK TO COVER WHEN READY GWB WALLS FULL HEIGHT @ FOLLOWING LOCATIONS: AHU RM 147 NE CORNER FOR MOUNTING OF DP-E1-28-HA; 126 & 127 FOR EQUIPMENT INSTALL; TEMPORARY EGRESS CORRIDOR @ 117; INFILL BELOW WINDOWS ALONG (DD) FROM (3.8) TO (5.1); BEHIND HVAC WALL CHASE @ 136 & 138; 119B; 119C; 120; 121; 123; 123A; 123B; 123C; 123D; 123E; 124; 125; 129; 130; 131; 132; 134; 135; BULKHEAD ABOVE DOOR 140; FOR CABLE TRAY @ PART OF CORR 143; WALL PLANE ON (7) FROM (BB.9) TO (DD); 101 FROM (A) TO (CC.3); 118; 119; 119D; 119E; 119F; ON (DD) FROM (3.7) TO (7); 142 W WALL; ON (3) FROM (A) TO (B) {CORR 143 S WALL}; 136; 137; 138; 139; 140; 141; 143; 144; 145; 146; 147; 149 S,E,W WALLS; 142 ALL WALLS; MODIFICATIONS @ 136 N & 138 S; 101 SOUTH WALL; 153 PLAN EAST WALL; UTILITY CHASES AT 100 SW & 102 NE; 119A S WALL; 122; 147 W WALL; CHASE @ (B)/(1); 119A S WALL AFTER RE-WORK; 122 ONE CHASE + ONE COLUMN WRAP; ELEVATOR EQUIPMENT CLOSET + CHASE; GAS 156
Above Ceiling Inspection Partial 8/9/2012 8/9/2012 at 12:00 AM 08/09/2012
Misc
Partial Correction
08/08/2012
OK TO COVER WHEN READY GWB CEILING FRAMING + ABOVE-CEILING SYSTEMS @ FOLLOWING SPACES: SOFFIT @ NURSE STATION 120; 141; 142; 146; 149(OR#4);
Misc
Partial Correction
08/09/2012
PHASE 1 ABOVE-CEILING INSPECTION @ ACT TILE SPACES: ALL OK TO COVER EXCEPT 101; 143; FULL TILE + BORDER TILE AT LOCATIONS WHERE DOOR OPERATORS HAVE YET TO BE INSTALLED
Rated Assembly Inspection Partial 8/14/2012 8/14/2012 at 12:00 AM 08/14/2012
Misc
Partial Correction
07/19/2012
ALL DESIGNATED SMOKE WALLS FOUND TO BE SCREWED AT 8"/12" PATTERN SIMILAR TO THAT AT DESIGNATED FIRE WALLS.
Misc
Partial Correction
07/19/2012
OK TO TAPE, MUD & FIRE SEAL FIRE-RATED WALLS AT FOLLOWING LOCATIONS: CORRIDOR 140 EAST WALL NORTH OF CC.4/1.5; 138 N WALL; 139 S&W WALLS; 122 BOTH FACES; ON (6.0) FROM (CC.3) TO (DD) SOUTH FACE; 119A S WALL; ELEVATOR CLOSET SIDE & FRONT WALLS ONE LAYER BOTH FACES 5/8" TYPE X GWB; GAS ROOM EAST WALL ONE LAYER BOTH FACES 5/8" TYPE X GWB
Misc
Partial Correction
07/19/2012
OK TO COVER WHEN READY COMPONENTS OF TYPE "F" 2HR RATED WALL ASSEMBLY: 2ND FLR AHU EAST & SOUTH WALLS FRAMING, SHAFT LINER + TWO LAYERS 5/8" TYPE X GWB; ELEVATOR CLOSET WALL AT UTILITY CHASE SHAFT LINER + ONE LAYER 5/8" TYPE X GWB; GAS ROOM SOUTH WALL SHAFT LINER + ONE LAYER 5/8" TYPE X GWB
Above Ceiling Inspection Partial 8/16/2012 8/16/2012 at 12:00 AM 08/16/2012
Misc
Partial Correction
08/09/2012
OK TO COVER WHEN READY PHASE 1 GWB CEILING FRAMING + ABOVE-CEILING SYSTEMS @ ALL SPACES EXCEPT WHERE LIGHT FIXTURES RECENTLY INSTALLED
Misc
Partial Correction
08/09/2012
ABOVE-CEILING INSPECTION @ PHASE 1 ACT TILE SPACES: ALL OK TO COVER EXCEPT 100 E 4'; 101 WEST 6'; FULL TILE + BORDER TILE AT LOCATIONS WHERE INSTALLATION & WIRING OF DOOR OPERATORS IS IN PROGRESS
Underslab Plumbing Inspection - Commercial Passed 8/16/2012 at 12:00 AM 08/16/2012
Misc
Resolved
08/16/2012
OK TO COVER WHEN READY PVC DWV UNDER-SLAB PLUMBING PIPING AT AREAS: PHASE 1 PARTIAL EXCLUDING FROM SPACES 157 & 159; 1ST FLOOR NORTH SECTION.
Corrective Action Required
01/02/2013
Suspended Slab Inspection Passed 8/16/2012 at 12:00 AM 08/16/2012
Misc
Resolved
08/16/2012
OK TO POUR WHEN READY UTILITY TUNNEL COVER SLAB EAST 50'
Above Ceiling Inspection Not Ready 8/17/2012 8/17/2012 at 12:00 AM 08/17/2012
Misc
Partial Correction
08/16/2012
OK TO COVER WHEN READY GWB CEILING FRAMING + ABOVE-CEILING SYSTEMS @ ALL SPACES EXCEPT WHERE LIGHT FIXTURES RECENTLY INSTALLED
Misc
Partial Correction
08/16/2012
ABOVE-CEILING INSPECTION @ ACT TILE SPACES: ALL OK TO COVER EXCEPT 100 E 4'; 101 WEST 6'; FULL TILE + BORDER TILE AT LOCATIONS WHERE INSTALLATION & WIRING OF DOOR OPERATORS IS IN PROGRESS
Above Ceiling Inspection Partial 8/21/2012 8/21/2012 at 12:00 AM 08/21/2012
Misc
Resolved
08/21/2012
OK TO COVER WHEN READY GWB CEILING FRAMING + ABOVE-CEILING SYSTEMS @ ALL SPACES EXCEPT WHERE LIGHT FIXTURES RECENTLY INSTALLED
Misc
Resolved
08/21/2012
ABOVE-CEILING INSPECTION @ ACT TILE SPACES: ALL OK TO COVER EXCEPT 100 E 4'; 101 WEST 6'; FULL TILE + BORDER TILE AT LOCATIONS WHERE INSTALLATION & WIRING OF DOOR OPERATORS IS IN PROGRESS
Misc
Partial Correction
08/21/2012
OK TO COVER WHEN READY ALL ACT AND GWB CEILING FRAMING AND ABOVE-CEILING SYSTEMS AT FOLLOWING: PHASE 1 AREA;
In-wall Inspection Partial 8/16/2012 at 12:00 AM 08/21/2012
Misc
Resolved
08/16/2012
OK TO COVER WHEN READY GWB WALLS FULL HEIGHT @ FOLLOWING LOCATIONS: AHU RM 147 NE CORNER FOR MOUNTING OF DP-E1-28-HA; 126 & 127 FOR EQUIPMENT INSTALL; TEMPORARY EGRESS CORRIDOR @ 117; INFILL BELOW WINDOWS ALONG (DD) FROM (3.8) TO (5.1); BEHIND HVAC WALL CHASE @ 136 & 138; 119B; 119C; 120; 121; 123; 123A; 123B; 123C; 123D; 123E; 124; 125; 129; 130; 131; 132; 134; 135; BULKHEAD ABOVE DOOR 140; FOR CABLE TRAY @ PART OF CORR 143; WALL PLANE ON (7) FROM (BB.9) TO (DD); 101 FROM (A) TO (CC.3); 118; 119; 119D; 119E; 119F; ON (DD) FROM (3.7) TO (7); 142 W WALL; ON (3) FROM (A) TO (B) {CORR 143 S WALL}; 136; 137; 138; 139; 140; 141; 143; 144; 145; 146; 147; 149 S,E,W WALLS; 142 ALL WALLS; MODIFICATIONS @ 136 N & 138 S; 101 SOUTH WALL; 153 PLAN EAST WALL; UTILITY CHASES AT 100 SW & 102 NE; 119A S WALL; 122; 147 W WALL; CHASE @ (B)/(1); 119A S WALL AFTER RE-WORK; 122 ONE CHASE + ONE COLUMN WRAP; ELEVATOR EQUIPMENT CLOSET + CHASE; GAS 156
In-wall Inspection Partial 8/21/2012 at 12:00 AM 08/21/2012
Misc
Partial Correction
08/21/2012
OK TO COVER WHEN READY WALL FRAMING AND IN-WALL SYSTEMS AT FOLLOWING LOCATIONS: PHASE 1 WALLS;
Rated Assembly Inspection Partial 8/16/2012 at 12:00 AM 08/21/2012
Misc
Resolved
08/16/2012
ALL DESIGNATED SMOKE WALLS FOUND TO BE SCREWED AT 8"/12" PATTERN SIMILAR TO THAT AT DESIGNATED FIRE WALLS.
Misc
Resolved
08/16/2012
OK TO TAPE, MUD & FIRE SEAL FIRE-RATED WALLS AT FOLLOWING LOCATIONS: CORRIDOR 140 EAST WALL NORTH OF CC.4/1.5; 138 N WALL; 139 S&W WALLS; 122 BOTH FACES; ON (6.0) FROM (CC.3) TO (DD) SOUTH FACE; 119A S WALL; ELEVATOR CLOSET SIDE & FRONT WALLS ONE LAYER BOTH FACES 5/8" TYPE X GWB; GAS ROOM EAST WALL ONE LAYER BOTH FACES 5/8" TYPE X GWB
Misc
Resolved
08/16/2012
OK TO COVER WHEN READY COMPONENTS OF TYPE "F" 2HR RATED WALL ASSEMBLY: 2ND FLR AHU EAST & SOUTH WALLS FRAMING, SHAFT LINER + TWO LAYERS 5/8" TYPE X GWB; ELEVATOR CLOSET WALL AT UTILITY CHASE SHAFT LINER + ONE LAYER 5/8" TYPE X GWB; GAS ROOM SOUTH WALL SHAFT LINER + ONE LAYER 5/8" TYPE X GWB
Rated Assembly Inspection Partial 8/21/2012 at 12:00 AM 08/21/2012
Misc
Partial Correction
08/21/2012
COMPONENTS OF RATED ASSEMBLIES OK TO COVER AT FOLLOWING LOCATIONS: PHASE 1 COMPLETE;
Alarm Test Partial 8/16/2012 at 12:00 AM 08/22/2012
Sprinkler - Hydrostatic Test Passed 8/17/2012 at 12:00 AM 08/22/2012
Alarm Test Partial 8/16/2012 at 12:00 AM 08/22/2012
Occupancy Inspection - Fire Temporary C of O 8/23/2012 at 12:00 AM 08/23/2012
Misc
Corrective Action Required
08/23/2012
-uncover all sprinkler heads throughout phased areas - label sprinkler system valves in stairway, 1st and 2nd floors -permanent room labeling - med-gas line certification test -label all med-gas valving as to area served - test all exit lights room/corridor lighting, outlets with generator power - test the 1st floor stairway flow alarm
Occupancy Inspection - Codes Commercial Partial 8/23/2012 8/23/2012 at 12:00 AM 08/23/2012
Misc
Corrective Action Required
08/23/2012
RESOLVE ANY ISSUES WITH OTHER DEPARTMENTS: - FIRE - PUBLIC WORKS - WATER - PLANNING AND DEVELOPMENT OK TO SET UP FOR BUSINESS OPERATION; NO PUBLIC NOR PATIENTS PRIOR TO APPROVAL
Misc
Corrective Action Required
08/23/2012
OBTAIN FINAL CERTIFICATION OF LIGHTNING PROTECTION SYSTEM
Misc
Corrective Action Required
08/23/2012
PROVIDE WITNESS CERTIFICATION OF GENERATOR TEST OF EMERGENCY ELECTRICAL SYSTEM
Misc
Corrective Action Required
08/23/2012
SPACES NOT READY FOR FINAL INSPECTION: - AHU - OR#4 - 145 (PLUMBING WORK IN PROGRESS)
Misc
Corrective Action Required
08/23/2012
INSTALL WIRE GUARDS OVER UNPROTECTED LUMINAIRES AT SERVER ROOM, STERIS EQUIPMENT ACCESS SPACE
Occupancy Inspection - Codes Commercial Partial 8/24/2012 at 12:00 AM 08/24/2012
Misc
Corrective Action Required
08/23/2012
RESOLVE ANY ISSUES WITH FIRE DEPARTMENT OK TO SET UP FOR BUSINESS OPERATION; NO PUBLIC NOR PATIENTS PRIOR TO APPROVAL
Misc
Resolved
08/24/2012
OBTAIN FINAL CERTIFICATION OF LIGHTNING PROTECTION SYSTEM
Misc
Corrective Action Required
08/23/2012
PROVIDE WITNESSED CERTIFICATION OF GENERATOR TEST OF EMERGENCY ELECTRICAL SYSTEM
Misc
Corrective Action Required
08/23/2012
SPACES NOT READY FOR FINAL INSPECTION: - AHU - OR#4 - 145 (PLUMBING WORK IN PROGRESS)
Misc
Corrective Action Required
08/23/2012
INSTALL WIRE GUARDS OVER UNPROTECTED LUMINAIRES AT SERVER ROOM, STERIS EQUIPMENT ACCESS SPACE
Occupancy Inspection - Codes Commercial Partial 8/27/2012 at 12:00 AM 08/27/2012
Misc
Corrective Action Required
08/24/2012
RESOLVE ANY ISSUES WITH FIRE DEPARTMENT OK TO SET UP FOR BUSINESS OPERATION; NO PUBLIC NOR PATIENTS PRIOR TO APPROVAL
Misc
Corrective Action Required
08/24/2012
PROVIDE WITNESSED CERTIFICATION OF GENERATOR TEST OF EMERGENCY ELECTRICAL SYSTEM
Misc
Corrective Action Required
08/24/2012
SPACES NOT READY FOR FINAL INSPECTION: - AHU - OR#4 - 145 (PLUMBING WORK IN PROGRESS)
Misc
Corrective Action Required
08/24/2012
INSTALL WIRE GUARDS OVER UNPROTECTED LUMINAIRES AT SERVER ROOM, STERIS EQUIPMENT ACCESS SPACE
Misc
Corrective Action Required
08/27/2012
ROOFTOPS: - COMPLETE RTU ENCLOSURES - ELECT RECEPTS MUST HAVE IN-USE COVERS - VERIFY ELECT RECEPTS WITHIN 10m OF RTU'S - CHECK RE OPEN JOINT UNDER STONE COPING - FINAL CLEANUP - LOW ROOF NOT READY FOR INSP PER JASON
Occupancy Inspection - Codes Commercial Temporary C of O 8/29/2012 at 12:00 AM 08/29/2012
Misc
Corrective Action Required
08/27/2012
RESOLVE ANY ISSUES WITH FIRE DEPARTMENT
Misc
Corrective Action Required
08/29/2012
PROVIDE CERTIFICATION OF LIGHTNING PROTECTION SYSTEM
Misc
Corrective Action Required
08/27/2012
SPACES NOT READY FOR FINAL INSPECTION: - AHU - OR#4 - ROOFTOPS
Misc
Resolved
08/29/2012
INSTALL WIRE GUARDS OVER UNPROTECTED LUMINAIRES AT SERVER ROOM, STERIS EQUIPMENT ACCESS SPACE
Misc
Corrective Action Required
08/27/2012
ROOFTOPS: - COMPLETE RTU ENCLOSURES - ELECT RECEPTS MUST HAVE IN-USE COVERS - VERIFY ELECT RECEPTS WITHIN 10m OF RTU'S - CHECK RE OPEN JOINT UNDER STONE COPING - FINAL CLEANUP - LOW ROOF NOT READY FOR INSP PER JASON
Occupancy Inspection - Fire Temporary C of O 8/29/2012 at 12:00 AM 08/29/2012
Misc
Corrective Action Required
08/23/2012
-uncover all sprinkler heads throughout phased areas - label sprinkler system valves in stairway, 1st and 2nd floors -permanent room labeling - med-gas line certification test -label all med-gas valving as to area served - test all exit lights room/corridor lighting, outlets with generator power - test the 1st floor stairway flow alarm
Miscellaneous Inspection Passed 8/29/2012 at 7:30 AM 08/29/2012
Underslab Plumbing Inspection - Commercial Partial 9/19/2012 at 12:00 AM 09/19/2012
Misc
Partial Correction
09/19/2012
OK TO COVER WHEN READY PHASE 2 UNDER-SLAB DWV PIPING AT FOLLOWING LOCATIONS: 107; 184; 185; 188; 189; 191; 191A; 192; 192A; 193; 194E&F;
In-wall Inspection Partial 9/25/2012 9/25/2012 at 12:00 AM 09/25/2012
Misc
Partial Correction
08/21/2012
OK TO COVER WHEN READY WALL FRAMING AND IN-WALL SYSTEMS AT FOLLOWING LOCATIONS: PHASE 2 WALLS: 157; 157A; 159; 162;
Underslab Plumbing Inspection - Commercial Partial 9/25/2012 9/25/2012 at 12:00 AM 09/25/2012
Misc
Partial Correction
09/19/2012
OK TO COVER WHEN READY PHASE 2 UNDER-SLAB DWV PIPING AT FOLLOWING LOCATIONS: 107; 184; 185; 188; 189; 191; 191A; 192; 192A; 193; 194E&F; 153; 159;
In-wall Inspection Partial 9/25/2012 at 12:00 AM 09/25/2012
Misc
Partial Correction
09/25/2012
OK TO COVER WHEN READY WALL FRAMING AND IN-WALL SYSTEMS AT PHASE 2 WALLS @ FOLLOWING LOCATIONS: 157; 157A; 159; 162;
Rated Assembly Inspection Partial 9/28/2012 9/28/2012 at 12:00 AM 09/28/2012
Misc
Partial Correction
08/21/2012
COMPONENTS OF RATED ASSEMBLIES OK TO COVER AT FOLLOWING LOCATIONS: PHASE 1 COMPLETE. PHASE 2 SPACES 157; 157A; 159 OK TO TAPE, MUD & FIRE-SEAL 5/8" TYPE X GWB;
In-wall Inspection Partial 9/28/2012 at 12:00 AM 09/28/2012
Misc
Partial Correction
09/25/2012
OK TO COVER WHEN READY WALL FRAMING AND IN-WALL SYSTEMS AT PHASE 2 WALLS @ FOLLOWING LOCATIONS: 157; 157A; 159; 162; 207; 210
In-wall Inspection Partial 9/28/2012 at 12:00 AM 09/28/2012
Misc
Partial Correction
09/28/2012
OK TO COVER WHEN READY WALL FRAMING AND IN-WALL SYSTEMS AT PHASE 2 WALLS @ FOLLOWING LOCATIONS: 157; 157A; 159; 162;
Above Ceiling Inspection Partial 10/3/2012 10/3/2012 at 12:00 AM 10/03/2012
Misc
Partial Correction
08/21/2012
OK TO COVER WHEN READY ALL ACT AND GWB CEILING FRAMING AND ABOVE-CEILING SYSTEMS AT FOLLOWING: PHASE 1 AREA; STERILE STORAGE ROOM 153
In-wall Inspection Partial 10/12/2012 (8:00 to 5:00) 10/12/2012 at 12:00 AM 10/12/2012
Misc
Partial Correction
09/28/2012
OK TO COVER WHEN READY WALL FRAMING AND IN-WALL SYSTEMS AT PHASE 2 WALLS @ FOLLOWING LOCATIONS: 157; 157A; 159; 162;
Misc
Partial Correction
10/12/2012
OK TO COVER WHEN READY WALL FRAMING AND IN-WALL SYSTEMS @ PHASE 2A WITH EXCEPTION OF AREAS MARKED ON 8-1/2 x 11 PRINT SEGMENT DATED 10/11.
Above Ceiling Inspection Partial 10/12/2012 at 12:00 AM 10/12/2012
Misc
Partial Correction
10/03/2012
OK TO COVER WHEN READY ALL ACT AND GWB CEILING FRAMING AND ABOVE-CEILING SYSTEMS AT FOLLOWING: PHASE 1 AREA; STERILE STORAGE ROOM 153
Misc
Partial Correction
10/12/2012
OK TO COVER WHEN READY UPPER CEILING FRAMING AT PHASE 2A CORRIDOR.
In-wall Inspection Partial 10/15/2012 (8:00 to 5:00) 10/15/2012 at 12:00 AM 10/15/2012
Misc
Partial Correction
10/12/2012
OK TO COVER WHEN READY WALL FRAMING AND IN-WALL SYSTEMS AT PHASE 2 WALLS @ FOLLOWING LOCATIONS: 157; 157A; 159; 162;
Misc
Partial Correction
10/12/2012
OK TO COVER WHEN READY WALL FRAMING AND IN-WALL SYSTEMS @ PHASE 2A
Above Ceiling Inspection Partial 10/17/2012 10/17/2012 at 12:00 AM 10/17/2012
Misc
Partial Correction
10/12/2012
OK TO COVER WHEN READY ALL ACT AND GWB CEILING FRAMING AND ABOVE-CEILING SYSTEMS AT PHASE 1 AREA
Misc
Partial Correction
10/12/2012
OK TO COVER WHEN READY CEILING FRAMING AND ABOVE-CEILING SYSTEMS AT FOLLOWING: UPPER CEILING FRAMING AT PHASE 2A CORRIDOR; STERILE STORAGE ROOM 153; 157; 157A; 159; SERPENTINE SOFFIT @ 101; 193;
Rated Assembly Inspection Partial 10/17/2012 10/17/2012 at 12:00 AM 10/17/2012
Misc
Partial Correction
09/28/2012
COMPONENTS OF RATED ASSEMBLIES OK TO COVER AT FOLLOWING LOCATIONS: PHASE 1 COMPLETE. PHASE 2 SPACES 157; 157A; 159 OK TO TAPE, MUD & FIRE-SEAL 5/8" TYPE X GWB; 185 INSIDE FACE FULL HEIGHT, OUTSIDE FACES TO 10' AFF @ N & E; 194 FROM B/5.3 TO A/3.0 TO A/4.0;
Above Ceiling Inspection Partial 10/17/2012 at 12:00 AM 10/17/2012
Misc
Partial Correction
10/17/2012
OK TO COVER WHEN READY ALL ACT AND GWB CEILING FRAMING AND ABOVE-CEILING SYSTEMS AT PHASE 1 AREA
Misc
Partial Correction
10/17/2012
OK TO COVER WHEN READY CEILING FRAMING AND ABOVE-CEILING SYSTEMS AT FOLLOWING: UPPER CEILING FRAMING AT PHASE 2A CORRIDOR; STERILE STORAGE ROOM 153; 157; 157A; 159; SERPENTINE SOFFIT @ 101; SOFFIT @ 193;
Occupancy Inspection - Codes Commercial Temporary C of O 10/17/2012 at 12:00 AM 10/17/2012
Misc
Corrective Action Required
08/29/2012
RESOLVE ANY ISSUES WITH FIRE DEPARTMENT
Misc
Corrective Action Required
08/29/2012
PROVIDE CERTIFICATION OF LIGHTNING PROTECTION SYSTEM
Misc
Corrective Action Required
08/29/2012
SPACES NOT READY FOR FINAL INSPECTION: - AHU - OR#4 - ROOFTOPS
Misc
Corrective Action Required
08/29/2012
ROOFTOPS: - COMPLETE RTU ENCLOSURES - ELECT RECEPTS MUST HAVE IN-USE COVERS - VERIFY ELECT RECEPTS WITHIN 10m OF RTU'S - CHECK RE OPEN JOINT UNDER STONE COPING - FINAL CLEANUP - LOW ROOF NOT READY FOR INSP PER JASON
Above Ceiling Inspection Partial 10/19/2012 at 12:00 AM 10/19/2012
Misc
Partial Correction
10/17/2012
OK TO COVER WHEN READY ALL ACT AND GWB CEILING FRAMING AND ABOVE-CEILING SYSTEMS AT PHASE 1 AREA
Misc
Partial Correction
10/17/2012
OK TO COVER WHEN READY CEILING FRAMING AND ABOVE-CEILING SYSTEMS AT FOLLOWING: UPPER CEILING FRAMING AT PHASE 2A CORRIDOR; STERILE STORAGE ROOM 153; 157; 157A; 159; SERPENTINE SOFFIT @ 101; SOFFIT @ 193; SOFFIT @ 194 EAST WALL;
Rated Assembly Inspection Partial 10/19/2012 at 12:00 AM 10/19/2012
Misc
Partial Correction
10/17/2012
COMPONENTS OF RATED ASSEMBLIES OK TO COVER AT FOLLOWING LOCATIONS: PHASE 1 COMPLETE. PHASE 2 SPACES 157; 157A; 159 OK TO TAPE, MUD & FIRE-SEAL 5/8" TYPE X GWB; 185 INSIDE FACE FULL HEIGHT, OUTSIDE FACES TO 10' AFF @ N & E; 194 FROM 3/C.3 TO A/3.0 TO A/4.0;
Occupancy Inspection - Codes Commercial Temporary C of O 10/19/2012 10/19/2012 at 12:00 AM 10/19/2012
Misc
Corrective Action Required
10/17/2012
FOLLOWING PHASES/SPACES OK FOR TEMPORARY OCCUPANCY & USE: PHASE 1; PHASE 2F; RESOLVE ANY ISSUES WITH FIRE DEPARTMENT
Misc
Corrective Action Required
10/17/2012
PROVIDE CERTIFICATION OF LIGHTNING PROTECTION SYSTEM
Misc
Corrective Action Required
10/17/2012
SPACES NOT READY FOR FINAL INSPECTION: - OR#4 - ROOFTOPS (SOME WORK NOT COMPLETED)
Misc
Corrective Action Required
10/17/2012
ROOFTOPS: - IFGC 404.8: EXPOSED METALLIC PIPING MUST BE PERMANENTLY PROTECTED WITH PAINT OR BY OTHER APPROVED MEANS. - FINAL CLEANUP: REMOVE ALL DEBRIS AND UNUSED MATERIAL
Misc
Corrective Action Required
10/19/2012
ROOFTOP SCREENING OF MECHANICAL EQUIPMENT SUBJECT TO APPROVAL BY PLANNING & DEVELOPMENT DEPARTMENT
Rated Assembly Inspection Partial 10/23/2012 10/23/2012 at 12:00 AM 10/23/2012
Misc
Partial Correction
10/19/2012
COMPONENTS OF RATED ASSEMBLIES OK TO COVER AT FOLLOWING LOCATIONS: PHASE 1 COMPLETE; PHASE 2 SPACES 157; 157A; 159 OK TO TAPE, MUD & FIRE-SEAL 5/8" TYPE X GWB; 185 INSIDE & OUTSIDE FACES FULL HEIGHT; 194 FROM 3/C.3 TO A/3.0 TO A/4.0
In-wall Inspection Partial 11/6/2012 11/6/2012 at 12:00 AM 11/06/2012
Misc
Partial Correction
10/15/2012
OK TO COVER WHEN READY WALL FRAMING AND IN-WALL SYSTEMS AT PHASE 2 WALLS @ FOLLOWING LOCATIONS: 157; 157A; 159; 162; 149 (OR-4) W WALL AFTER TWO E-BOX STAND-OFFS ARE EXTENDED; 150 (OR-3) AFTER DOORS JAMB STUDS ARE SCREWED TO BASE TRACK AND APPARENTLY-ABANDONED ELECTRICAL WIRING IS REMOVED OR SECURED;
Misc
Partial Correction
10/15/2012
OK TO COVER WHEN READY WALL FRAMING AND IN-WALL SYSTEMS @ PHASE 2A
Underslab Plumbing Inspection - Commercial Partial 11/12/2012 11/12/2012 at 12:00 AM 11/12/2012
Misc
Partial Correction
09/25/2012
OK TO COVER WHEN READY PHASE 2 UNDER-SLAB DWV PIPING AT FOLLOWING LOCATIONS: 107; 184; 185; 188; 189; 191; 191A; 192; 192A; 193; 194E&F; 153; 159; 167;
Above Ceiling Inspection Partial 11/14/2012 11/14/2012 at 12:00 AM 11/14/2012
Misc
Partial Correction
10/19/2012
OK TO COVER WHEN READY ALL ACT AND GWB CEILING FRAMING AND ABOVE-CEILING SYSTEMS AT PHASE 1 AREA
Misc
Partial Correction
10/19/2012
OK TO COVER WHEN READY GWB CEILING FRAMING AND ABOVE-CEILING SYSTEMS AT: UPPER CEILING FRAMING AT PHASE 2A CORRIDOR; STERILE STORAGE ROOM 153; 157; 157A; 159; SERPENTINE SOFFIT @ 101; SOFFIT @ 193; SOFFIT @ 194 EAST WALL;
Misc
Partial Correction
11/14/2012
OK TO COVER WHEN READY ACT CEILING FRAMING + ABOVE-CEILING SYSTEMS @ FOLLOWING PHASE 2A SPACES:
Above Ceiling Inspection Partial 11/15/2012 at 12:00 AM 11/15/2012
Misc
Partial Correction
11/14/2012
OK TO COVER WHEN READY ALL ACT AND GWB CEILING FRAMING AND ABOVE-CEILING SYSTEMS AT PHASE 1 AREA
Misc
Partial Correction
11/14/2012
OK TO COVER WHEN READY GWB CEILING FRAMING AND ABOVE-CEILING SYSTEMS AT: UPPER CEILING FRAMING AT PHASE 2A CORRIDOR; STERILE STORAGE ROOM 153; 157; 157A; 159; SERPENTINE SOFFIT @ 101; SOFFIT @ 193; SOFFIT @ 194 EAST WALL;
Misc
Partial Correction
11/14/2012
OK TO COVER WHEN READY ACT CEILING FRAMING + ABOVE-CEILING SYSTEMS @ FOLLOWING PHASE 2A SPACES: 182( ); 183( ) ; 183A; 183B; 183H; 183J; 184; 185; 186; 187; 188; 189; 190( ); 191; 191A; 192; 192A; 193; 194; 194A-H;
Alarm Test Passed 11/20/2012 at 7:30 AM 11/20/2012
Above Ceiling Inspection Partial 11/20/2012 11/20/2012 at 12:00 AM 11/20/2012
Misc
Partial Correction
11/15/2012
OK TO COVER WHEN READY ALL ACT AND GWB CEILING FRAMING AND ABOVE-CEILING SYSTEMS AT PHASE 1 AREA;
Misc
Partial Correction
11/15/2012
OK TO COVER WHEN READY GWB CEILING FRAMING AND ABOVE-CEILING SYSTEMS AT: UPPER CEILING FRAMING AT PHASE 2A CORRIDOR; STERILE STORAGE ROOM 153; 157; 157A; 159; SERPENTINE SOFFIT @ 101; SOFFIT @ 193; SOFFIT @ 194 EAST WALL
Misc
Partial Correction
11/15/2012
OK TO COVER WHEN READY ACT CEILING FRAMING + ABOVE-CEILING SYSTEMS @ FOLLOWING PHASE 2A SPACES: 182( ); 183( ) ; 183A; 183B; 183H; 183J; 184; 185; 186; 187; 188; 189; 190( ); 191; 191A; 192; 192A; 193; 194; 194A-H; PHASE 2A AREA COMPLETE AFTER ITEMS POINTED OUT TO BEN ARE CORRECTED
In-wall Inspection Partial 11/20/2012 11/20/2012 at 12:00 AM 11/20/2012
Misc
Resolved
11/20/2012
OK TO COVER WHEN READY WALL FRAMING AND IN-WALL SYSTEMS AT PHASE 2 WALLS @ FOLLOWING LOCATIONS: 157; 157A; 159; 162; 149 (OR-4) W WALL AFTER TWO E-BOX STAND-OFFS ARE EXTENDED; 150 (OR-3) AFTER DOORS JAMB STUDS ARE SCREWED TO BASE TRACK AND APPARENTLY-ABANDONED ELECTRICAL WIRING IS REMOVED OR SECURED;
Misc
Partial Correction
11/06/2012
OK TO COVER WHEN READY WALL FRAMING AND IN-WALL SYSTEMS @ PHASE 2; PHASE 2A ; PHASE 2B COMPRISING 167A & 167B BOTH FACES
Occupancy Inspection - Codes Commercial Partial 11/30/2012 11/30/2012 at 12:00 AM 11/30/2012
Misc
Corrective Action Required
10/19/2012
FOLLOWING PHASES/SPACES OK FOR TEMPORARY OCCUPANCY & USE: PHASE 1; PHASE 2F; RESOLVE ANY ISSUES WITH FIRE DEPARTMENT
Misc
Resolved
11/30/2012
PROVIDE CERTIFICATION OF LIGHTNING PROTECTION SYSTEM
Misc
Corrective Action Required
10/19/2012
SPACES NOT READY FOR FINAL INSPECTION: - OR#4 - ROOFTOPS (SOME WORK NOT COMPLETED)
Misc
Corrective Action Required
10/19/2012
ROOFTOPS: - IFGC 404.8: EXPOSED METALLIC PIPING MUST BE PERMANENTLY PROTECTED WITH PAINT OR BY OTHER APPROVED MEANS. - FINAL CLEANUP: REMOVE ALL DEBRIS AND UNUSED MATERIAL
Misc
Corrective Action Required
11/30/2012
PHASE 2A AREA OK TO SET UP FOR BUSINESS; NO PATIENTS NOR PUBLIC PRIOR TO APPROVAL
Occupancy Inspection - Fire Temporary C of O 11/30/2012 at 12:00 AM 11/30/2012
Misc
Corrective Action Required
08/29/2012
-uncover all sprinkler heads throughout phased areas - label sprinkler system valves in stairway, 1st and 2nd floors -permanent room labeling - med-gas line certification test -label all med-gas valving as to area served - test all exit lights room/corridor lighting, outlets with generator power - test the 1st floor stairway flow alarm
Misc
Corrective Action Required
11/30/2012
11/30/12, Phase-2A PRCOM20110184 1st floor -remove all dust covers from smoke detectors - certify all medgas lines -label all areas with suite designation from the corridor - verify generator power to outlets and light switches
Occupancy Inspection - Codes Commercial Partial 12/5/2012 12/5/2012 at 12:00 AM 12/05/2012
Misc
Corrective Action Required
11/30/2012
FOLLOWING PHASES/SPACES OK FOR TEMPORARY OCCUPANCY & USE: PHASE 1; PHASE 2F; RESOLVE ANY ISSUES WITH FIRE DEPARTMENT
Misc
Resolved
12/05/2012
SPACES NOT READY FOR FINAL INSPECTION: - ROOFTOPS (SOME WORK NOT COMPLETED)
Misc
Corrective Action Required
11/30/2012
ROOFTOPS: - IFGC 404.8: EXPOSED METALLIC PIPING MUST BE PERMANENTLY PROTECTED WITH PAINT OR BY OTHER APPROVED MEANS. - FINAL CLEANUP: REMOVE ALL DEBRIS AND UNUSED MATERIAL
Misc
Partial Correction
12/05/2012
PHASES 2A & 2D AREAS OK TO SET UP FOR BUSINESS; NO PATIENTS NOR PUBLIC PRIOR TO APPROVAL
Misc
Corrective Action Required
12/05/2012
MED GAS PIPING TEST CERTS REQUIRED FOR PHASE 2D AREA FOR TCO STATUS TO BE APPROVED
Occupancy Inspection - Codes Commercial Partial 12/5/2012 at 12:00 AM 12/05/2012
Misc
Corrective Action Required
12/05/2012
FOLLOWING PHASES/SPACES OK FOR TEMPORARY OCCUPANCY & USE: PHASE 1; PHASE 2F; 2D; RESOLVE ANY ISSUES WITH FIRE DEPARTMENT
Misc
Corrective Action Required
12/05/2012
ROOFTOPS: - IFGC 404.8: EXPOSED METALLIC PIPING MUST BE PERMANENTLY PROTECTED WITH PAINT OR BY OTHER APPROVED MEANS. - FINAL CLEANUP: REMOVE ALL DEBRIS AND UNUSED MATERIAL
Misc
Partial Correction
12/05/2012
PHASE 2A AREA OK TO SET UP FOR BUSINESS; NO PATIENTS NOR PUBLIC PRIOR TO APPROVAL
Misc
Corrective Action Required
12/05/2012
MED GAS PIPING TEST CERTS REQUIRED FOR PHASE 2A AREA FOR TCO STATUS TO BE APPROVED
Occupancy Inspection - Fire Temporary C of O 12/5/2012 at 12:00 AM 12/05/2012
Misc
Corrective Action Required
11/30/2012
-uncover all sprinkler heads throughout phased areas - label sprinkler system valves in stairway, 1st and 2nd floors -permanent room labeling - med-gas line certification test -label all med-gas valving as to area served - test all exit lights room/corridor lighting, outlets with generator power - test the 1st floor stairway flow alarm
Misc
Corrective Action Required
11/30/2012
11/30/12, Phase-2A PRCOM20110184 1st floor -remove all dust covers from smoke detectors - certify all medgas lines -label all areas with suite designation from the corridor - verify generator power to outlets and light switches
Occupancy Inspection - Codes Commercial Temporary C of O 12/6/2012 at 12:00 AM 12/06/2012
Misc
Corrective Action Required
12/05/2012
FOLLOWING PHASES/SPACES OK FOR TEMPORARY OCCUPANCY & USE: PHASE 1; PHASE 2F; 2D; RESOLVE ANY ISSUES WITH FIRE DEPARTMENT
Misc
Resolved
12/06/2012
ROOFTOPS: - IFGC 404.8: EXPOSED METALLIC PIPING MUST BE PERMANENTLY PROTECTED WITH PAINT OR BY OTHER APPROVED MEANS. - FINAL CLEANUP: REMOVE ALL DEBRIS AND UNUSED MATERIAL
Misc
Partial Correction
12/05/2012
PHASE 2A AREA OK TO SET UP FOR BUSINESS; NO PATIENTS NOR PUBLIC PRIOR TO APPROVAL
Misc
Corrective Action Required
12/05/2012
MED GAS PIPING TEST CERTS REQUIRED FOR PHASE 2A AREA FOR TCO STATUS TO BE APPROVED
Above Ceiling Inspection Partial 12/13/2012 12/13/2012 at 12:00 AM 12/13/2012
Misc
Partial Correction
11/20/2012
OK TO COVER WHEN READY ALL ACT AND GWB CEILING FRAMING AND ABOVE-CEILING SYSTEMS AT PHASE 1 AREA;
Misc
Partial Correction
11/20/2012
OK TO COVER WHEN READY GWB CEILING FRAMING AND ABOVE-CEILING SYSTEMS AT: UPPER CEILING FRAMING AT PHASE 2A CORRIDOR; STERILE STORAGE ROOM 153; 157; 157A; 159; SERPENTINE SOFFIT @ 101; SOFFIT @ 193; SOFFIT @ 194 EAST WALL
Misc
Partial Correction
11/20/2012
OK TO COVER WHEN READY ACT CEILING FRAMING + ABOVE-CEILING SYSTEMS @ FOLLOWING PHASE 2A SPACES: 182( ); 183( ) ; 183A; 183B; 183H; 183J; 184; 185; 186; 187; 188; 189; 190( ); 191; 191A; 192; 192A; 193; 194; 194A-H; PHASE 2A; WOMEN'S LOCKER RM 157;
Above Ceiling Inspection Partial 12/13/2012 at 12:00 AM 12/13/2012
Misc
Partial Correction
12/13/2012
OK TO COVER WHEN READY ALL ACT AND GWB CEILING FRAMING AND ABOVE-CEILING SYSTEMS AT PHASE 1 AREA;
Misc
Partial Correction
12/13/2012
OK TO COVER WHEN READY GWB CEILING FRAMING AND ABOVE-CEILING SYSTEMS AT: UPPER CEILING FRAMING AT PHASE 2A CORRIDOR; STERILE STORAGE ROOM 153; 157; 157A; 159; SERPENTINE SOFFIT @ 101; SOFFIT @ 193; SOFFIT @ 194 EAST WALL
Misc
Partial Correction
12/13/2012
OK TO COVER WHEN READY ACT CEILING FRAMING + ABOVE-CEILING SYSTEMS @ FOLLOWING PHASE 2A SPACES: 182( ); 183( ) ; 183A; 183B; 183H; 183J; 184; 185; 186; 187; 188; 189; 190( ); 191; 191A; 192; 192A; 193; 194; 194A-H; PHASE 2A; WOMEN'S LOCKER RM 167;
Occupancy Inspection - Codes Commercial Temporary C of O 12/14/2012 12/14/2012 at 12:00 AM 12/14/2012
Misc
Partial Correction
12/14/2012
FOLLOWING PHASES/SPACES OK FOR TEMPORARY OCCUPANCY & USE: PHASE 1; PHASE 2F; 2D; PHASE 2A; WOMEN'S LOCKER RM 167; RESOLVE ANY ISSUES WITH FIRE DEPARTMENT
Underslab Plumbing Inspection - Commercial Partial 12/19/2012 12/19/2012 at 12:00 AM 12/19/2012
Misc
Partial Correction
11/12/2012
OK TO COVER WHEN READY UNDER-SLAB DWV PIPING AT FOLLOWING LOCATIONS: 107; 184; 185; 188; 189; 191; 191A; 192; 192A; 193; 194E&F; 153; 159; 167; 104; 105; 174;
Underslab Plumbing Inspection - Commercial Partial 12/27/2012 12/27/2012 at 12:00 AM 12/27/2012
Misc
Partial Correction
12/19/2012
OK TO COVER WHEN READY UNDER-SLAB DWV PIPING AT FOLLOWING LOCATIONS: 107; 184; 185; 188; 189; 191; 191A; 192; 192A; 193; 194E&F; 153; 159; 167; 104; 105; 174; MENS LOCKER ROOM UNDERSLAB APPROVED
In-wall Inspection Partial 1/2/2013 (8:00 to 5:00) 1/2/2013 at 12:00 AM 01/02/2013
Misc
Partial Correction
11/20/2012
OK TO COVER WHEN READY WALL FRAMING AND IN-WALL SYSTEMS @ PHASE 2; PHASE 2A ; PHASE 2B COMPRISING 167A & 167B BOTH FACES PHASE 3 (WAITING AREA, OFFICES) OKAY TO COVER. 2B (MENS LOCKER ROOM) OKAY TO COVER
Occupancy Inspection - Codes Commercial Temporary C of O 1/10/2013 at 12:00 AM 01/10/2013
In-wall Inspection Passed 1/11/2013 1/11/2013 at 12:00 AM 01/11/2013
Misc
Resolved
01/11/2013
OK TO COVER WHEN READY WALL FRAMING + IN-WALL SYSTEMS AT PHASE 2C SPACES 154 & 156 EXISTING OR's 1 & 2
Above Ceiling Inspection Failed 1/22/2013 1/22/2013 at 12:00 AM 01/22/2013
Misc
Partial Correction
12/13/2012
OK TO COVER WHEN READY ALL ACT AND GWB CEILING FRAMING AND ABOVE-CEILING SYSTEMS AT PHASE 1 AREA;
Misc
Partial Correction
12/13/2012
OK TO COVER WHEN READY GWB CEILING FRAMING AND ABOVE-CEILING SYSTEMS AT: UPPER CEILING FRAMING AT PHASE 2A CORRIDOR; STERILE STORAGE ROOM 153; 157; 157A; 159; SERPENTINE SOFFIT @ 101; SOFFIT @ 193; SOFFIT @ 194 EAST WALL
Misc
Partial Correction
12/13/2012
OK TO COVER WHEN READY ACT CEILING FRAMING + ABOVE-CEILING SYSTEMS @ FOLLOWING PHASE 2A SPACES: 182( ); 183( ) ; 183A; 183B; 183H; 183J; 184; 185; 186; 187; 188; 189; 190( ); 191; 191A; 192; 192A; 193; 194; 194A-H; PHASE 2A; WOMEN'S LOCKER RM 167;
Misc
Corrective Action Required
01/22/2013
PHASE 2B MEN'S LOCKER AREA + PHASE 3: - REMOVE ANY ABANDONED HANGERS AND LIGHT-GAUGE FRAMING - REPAIR DAMAGED HVAC DUCT INSULATION - SPACE 178: INSULATE COPPER WATER PIPING OR CLARIFY; CAP DISCONTINUOUS C.I. PIPE OR CLARIFY - SUPPORT L.V. CABLE MIN 18" ABOVE GRID - FIRE-SEAL RATED WALL ALONG C/L (F) - CLOSE ALL ELECT J.B.s - PLUG ANY UNUSED OPENINGS @ ELECT BOXES
Above Ceiling Inspection Partial 1/23/2013 at 12:00 AM 01/23/2013
Misc
Partial Correction
01/22/2013
OK TO COVER WHEN READY ALL ACT AND GWB CEILING FRAMING AND ABOVE-CEILING SYSTEMS AT PHASE 1 AREA; PHASE 2B MEN'S LOCKER AREA; PHASE 3 EXCEPT ELECT RM 172;
Misc
Partial Correction
01/22/2013
OK TO COVER WHEN READY GWB CEILING FRAMING AND ABOVE-CEILING SYSTEMS AT: UPPER CEILING FRAMING AT PHASE 2A CORRIDOR; STERILE STORAGE ROOM 153; 157; 157A; 159; SERPENTINE SOFFIT @ 101; SOFFIT @ 193; SOFFIT @ 194 EAST WALL
Misc
Partial Correction
01/22/2013
OK TO COVER WHEN READY ACT CEILING FRAMING + ABOVE-CEILING SYSTEMS @ FOLLOWING PHASE 2A SPACES: 182( ); 183( ) ; 183A; 183B; 183H; 183J; 184; 185; 186; 187; 188; 189; 190( ); 191; 191A; 192; 192A; 193; 194; 194A-H; PHASE 2A; WOMEN'S LOCKER RM 167;
Misc
Resolved
01/23/2013
PHASE 2B MEN'S LOCKER AREA + PHASE 3: - REMOVE ANY ABANDONED HANGERS AND LIGHT-GAUGE FRAMING - REPAIR DAMAGED HVAC DUCT INSULATION - SPACE 178: INSULATE COPPER WATER PIPING OR CLARIFY; CAP DISCONTINUOUS C.I. PIPE OR CLARIFY - SUPPORT L.V. CABLE MIN 18" ABOVE GRID - FIRE-SEAL RATED WALL ALONG C/L (F) - CLOSE ALL ELECT J.B.s - PLUG ANY UNUSED OPENINGS @ ELECT BOXES
Alarm Test Passed 1/24/2013 at 12:00 AM 01/24/2013
Occupancy Inspection - Codes Commercial Partial 1/30/2013 1/30/2013 at 12:00 AM 01/30/2013
Misc
Partial Correction
01/30/2013
OK FOR OCCUPANCY AT FOLLOWING SPACES: PHASE 2B; PHASE 2C; PHASE 3;
Occupancy Inspection - Fire Temporary C of O 02/01/2013
Misc
Corrective Action Required
12/05/2012
-uncover all sprinkler heads throughout phased areas - label sprinkler system valves in stairway, 1st and 2nd floors -permanent room labeling - med-gas line certification test -label all med-gas valving as to area served - test all exit lights room/corridor lighting, outlets with generator power - test the 1st floor stairway flow alarm
Misc
Corrective Action Required
12/05/2012
11/30/12, Phase-2A PRCOM20110184 1st floor -remove all dust covers from smoke detectors - certify all medgas lines -label all areas with suite designation from the corridor - verify generator power to outlets and light switches
Above Ceiling Inspection Passed 2/14/2013 at 12:00 AM 02/14/2013
Misc
Resolved
02/14/2013
OK TO COVER WHEN READY ALL ACT AND GWB CEILING FRAMING AND ABOVE-CEILING SYSTEMS AT PHASE 1 AREA; PHASE 2B MEN'S LOCKER AREA; PHASE 3 EXCEPT ELECT RM 172;
Misc
Resolved
02/14/2013
OK TO COVER WHEN READY GWB CEILING FRAMING AND ABOVE-CEILING SYSTEMS AT: UPPER CEILING FRAMING AT PHASE 2A CORRIDOR; STERILE STORAGE ROOM 153; 157; 157A; 159; SERPENTINE SOFFIT @ 101; SOFFIT @ 193; SOFFIT @ 194 EAST WALL
Misc
Resolved
02/14/2013
OK TO COVER WHEN READY ACT CEILING FRAMING + ABOVE-CEILING SYSTEMS @ FOLLOWING PHASE 2A SPACES: 182( ); 183( ) ; 183A; 183B; 183H; 183J; 184; 185; 186; 187; 188; 189; 190( ); 191; 191A; 192; 192A; 193; 194; 194A-H; PHASE 2A; WOMEN'S LOCKER RM 167;
Rated Assembly Inspection Passed 2/14/2013 at 12:00 AM 02/14/2013
Misc
Resolved
02/14/2013
COMPONENTS OF RATED ASSEMBLIES OK TO COVER AT FOLLOWING LOCATIONS: PHASE 1 COMPLETE; PHASE 2 SPACES 157; 157A; 159 OK TO TAPE, MUD & FIRE-SEAL 5/8" TYPE X GWB; 185 INSIDE & OUTSIDE FACES FULL HEIGHT; 194 FROM 3/C.3 TO A/3.0 TO A/4.0
Underslab Plumbing Inspection - Commercial Passed 2/14/2013 at 12:00 AM 02/14/2013
Misc
Resolved
02/14/2013
OK TO COVER WHEN READY UNDER-SLAB DWV PIPING AT FOLLOWING LOCATIONS: 107; 184; 185; 188; 189; 191; 191A; 192; 192A; 193; 194E&F; 153; 159; 167; 104; 105; 174; MENS LOCKER ROOM UNDERSLAB APPROVED
Occupancy Inspection - Codes Commercial Full C of O 2/15/2013 at 12:00 AM 02/15/2013
Misc
Resolved
02/15/2013
OK FOR OCCUPANCY AT FOLLOWING SPACES: PHASE 2B; PHASE 2C; PHASE 3;
Documents & Images
Date Uploaded File Type Document Name
02/21/2012 Letter Plan Review Conditions
03/27/2012 Letter Plan Review Conditions
04/10/2012 Letter Building Permit
04/10/2012 Letter Plan Review Conditions
04/11/2012 Letter Inspection Summary
04/17/2012 Letter Inspection Summary
04/17/2012 Letter Inspection Summary
04/24/2012 Letter Inspection Summary
05/11/2012 Letter Inspection Summary
05/17/2012 Letter Inspection Summary
05/22/2012 Letter Inspection Summary
05/31/2012 Letter Inspection Summary
06/01/2012 Letter Inspection Summary
06/07/2012 Letter Inspection Summary
06/08/2012 Letter Inspection Summary
06/12/2012 Letter Inspection Summary
06/18/2012 Letter Inspection Summary
06/21/2012 Letter Inspection Summary
06/26/2012 Letter Inspection Summary
06/27/2012 Letter Inspection Summary
06/28/2012 Letter Inspection Summary
07/05/2012 Letter Inspection Summary
07/09/2012 Letter Inspection Summary
07/12/2012 Letter Inspection Summary
07/12/2012 Letter Inspection Summary
07/13/2012 Letter Inspection Summary
07/16/2012 Letter Inspection Summary
07/18/2012 Letter Inspection Summary
07/18/2012 Letter Inspection Summary
07/19/2012 Letter Inspection Summary
08/08/2012 Letter Inspection Summary
08/09/2012 Letter Inspection Summary
08/14/2012 Letter Inspection Summary
08/16/2012 Letter Inspection Summary
08/16/2012 Letter Inspection Summary
08/16/2012 Letter Inspection Summary
08/16/2012 Letter Inspection Summary
08/21/2012 Letter Inspection Summary
08/23/2012 Letter Fire Loss Reduction Form
08/23/2012 Letter Inspection Summary
08/29/2012 Letter Temporary Certificate of Occupancy
09/19/2012 Letter Inspection Summary
09/25/2012 Letter Inspection Summary
09/28/2012 Letter Inspection Summary
09/28/2012 Letter Inspection Summary
10/03/2012 Letter Inspection Summary
10/12/2012 Letter Inspection Summary
10/15/2012 Letter Inspection Summary
10/17/2012 Letter Inspection Summary
10/17/2012 Letter Temporary Certificate of Occupancy
10/19/2012 Letter Temporary Certificate of Occupancy
10/23/2012 Letter Inspection Summary
11/06/2012 Letter Inspection Summary
11/12/2012 Letter Inspection Summary
11/15/2012 Letter Inspection Summary
11/20/2012 Letter Inspection Summary
11/26/2012 Letter DOC112612-001.pdf
11/30/2012 Letter Inspection Summary
11/30/2012 Letter Fire Loss Reduction Form
12/05/2012 Letter Inspection Summary
12/13/2012 Letter Inspection Summary
12/14/2012 Letter Temporary Certificate of Occupancy
12/19/2012 Letter Inspection Summary
12/27/2012 Letter Inspection Summary
01/02/2013 Letter Inspection Summary
01/11/2013 Letter Inspection Summary
01/22/2013 Letter Inspection Summary
01/23/2013 Letter Inspection Summary
01/30/2013 Letter Inspection Summary
02/15/2013 Letter Field Certificate of Occupancy
02/19/2013 Letter Final Certificate of Occupancy
06/25/2013 Letter Fire Building Plan Review
06/26/2013 Letter Fire Building Plan Review
08/28/2013 Letter Temporary Certificate of Occupancy
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home