Review Type |
Outcome |
Est. Completion Date |
Completed |
Engineering Review
|
Approved with Conditions
|
03/15/2024
|
03/14/2024
|
|
Gene Williams, P.E.
|
|
DE Engineers Estimate
Corrective Action Required
The Engineer’s Estimate of Probable Construction Costs has been accepted for this project, and the Engineering Plan Review and Inspection Fee (which is calculated as 3% of the total infrastructure cost plus a water test inspection fee(s)), sanitary sewer fee, and the water tap and meter setup fee have been included. These must be paid prior to the issuance of an infrastructure permit and/or the final processing of a building permit. $58,572.76
|
|
DE Contact Field Eng. Inspector
Corrective Action Required
Prior to the commencement of any construction activities, the Contractor shall contact Field Engineering Inspections at (816) 969-1200 to coordinate a project coordination meeting with the assigned Field Engineering Inspector.
|
|
DE Future Repair Work
Corrective Action Required
Please be aware that any future repair work to public infrastructure (e.g., water main repair, sanitary sewer repair, storm sewer repair, etc.) within public easements will not necessarily include the repair of pavement, curbing, landscaping, or other private improvements which are located within the easement.
|
|
|
Building Codes Review
|
No Comments
|
03/15/2024
|
03/08/2024
|
|
Mike Weisenborn
|
|
|
Traffic Review
|
No Comments
|
03/15/2024
|
03/08/2024
|
|
Mike Weisenborn
|
|
|
Fire Review
|
Approved with Conditions
|
03/15/2024
|
03/08/2024
|
|
Mike Weisenborn
|
|
Code Statement
Corrective Action Required
All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2018 International Fire Code and local amendments.
|
|
Fire Lanes - Marking
Corrective Action Required
IFC 503.3 - 503.3 Marking. Where required by the fire code official, approved signs or other approved notices or markings that include the words NO PARKING—FIRE LANE shall be provided for fire apparatus access roads to identify such roads or prohibit the obstruction thereof. The means by which fire lanes are designated shall be maintained in a clean and legible condition at all times and be replaced or repaired when necessary to provide adequate visibility.
Fire lanes may be marked in one or a combination of methods as approved by the fire code official. Curbs. All curbs and curb ends shall be painted red with four inch (4") white lettering stating "FIRE LANE—NO PARKING". Wording may not be spaced more than fifteen feet (15') apart. Where no curb exists or a rolled curb is installed, a 6-inch (6") wide painted red stripe applied to the concrete or asphalt with four inch (4") white lettering stating "FIRE LANE—NO PARKING. "Signs. In areas where fire lanes are required, but no continuous curb is available, one of the following methods shall be used to indicate the fire lane. Option 1 : A sign twelve inches (12") wide and eighteen inches (18") in height shall be mounted on a metal post set in concrete a minimum of depth of eighteen inches (18") set back one foot (1') in from the edge of the roadway with the bottom of the sign being seven feet (7') from finished grade. Signs shall face oncoming traffic. Spacing of signs shall not exceed fifty feet (50') between signs. Signs shall be reflective material with a white color background with symbols, letters and border in red color. "FIRE LANE—NO PARKING". Option 2 : A sign twelve inches (12") wide and eighteen inches (18") in height shall be mounted on the side of a structure or other permanent fixture approved by the Fire Code Official. The bottom of the sign being seven feet (7') from finished grade. Spacing of signs shall not exceed fifty feet (50') between signs. Signs shall be reflective material with a white color background with symbols, letters and border in red color. "FIRE LANE—NO PARKING".
|
|
|
Planning Review
|
No Comments
|
03/15/2024
|
03/08/2024
|
|
Mike Weisenborn
|
|
|
Fire Review
|
Approved with Conditions
|
03/04/2024
|
03/05/2024
|
|
Jim Eden
|
|
Code Statement
Corrective Action Required
All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2018 International Fire Code and local amendments.
|
|
Water Supply
IFC 507.1 - An approved water supply capable of supplying the required fire flow for fire protection shall be provided to premises upon which facilities, buildings or portions of buildings are hereafter constructed or moved into or within the jurisdiction.
Work with Water Utilities to provide information on available fire flow in the area. Fire flow shall meet the requirements of IFC Table B105.1(2) for a V-B or V-A construction. A 50% reduction in fire flow is allowed per local amendment for the sprinkler system.
|
|
Hydrants
IFC 507.5.1 - Where a portion of the facility or building hereafter constructed or moved into or within the jurisdiction is more than 300 feet from a hydrant on a fire apparatus access road, as measured by an approved route around the exterior of the facility or building, on-site fire hydrants and mains shall be provided where required by the fire code official.
Show all available hydrants to meet the 300' requirement
and required fire flow.
|
|
Imposed Loads
IFC 503.2.3 - Fire apparatus access roads shall be designed and maintained to support the imposed loads of fire apparatus and shall be surfaced so as to provide all-weather driving capabilities.
Confirm the medium duty pavement will support 75,000-pounds.
|
|
Obstructions
IFC 503.4 - Fire apparatus access roads shall not be obstructed in any manner, including the parking of vehicles. The minimum widths and clearances established in Section 503.2.1 shall be maintained at all times.
How will access to be maintained to B building hydrant and FDC?
|
|
Fire Lanes - Marking
Corrective Action Required
IFC 503.3 - 503.3 Marking. Where required by the fire code official, approved signs or other approved notices or markings that include the words NO PARKING—FIRE LANE shall be provided for fire apparatus access roads to identify such roads or prohibit the obstruction thereof. The means by which fire lanes are designated shall be maintained in a clean and legible condition at all times and be replaced or repaired when necessary to provide adequate visibility.
Fire lanes may be marked in one or a combination of methods as approved by the fire code official. Curbs. All curbs and curb ends shall be painted red with four inch (4") white lettering stating "FIRE LANE—NO PARKING". Wording may not be spaced more than fifteen feet (15') apart. Where no curb exists or a rolled curb is installed, a 6-inch (6") wide painted red stripe applied to the concrete or asphalt with four inch (4") white lettering stating "FIRE LANE—NO PARKING. "Signs. In areas where fire lanes are required, but no continuous curb is available, one of the following methods shall be used to indicate the fire lane. Option 1 : A sign twelve inches (12") wide and eighteen inches (18") in height shall be mounted on a metal post set in concrete a minimum of depth of eighteen inches (18") set back one foot (1') in from the edge of the roadway with the bottom of the sign being seven feet (7') from finished grade. Signs shall face oncoming traffic. Spacing of signs shall not exceed fifty feet (50') between signs. Signs shall be reflective material with a white color background with symbols, letters and border in red color. "FIRE LANE—NO PARKING". Option 2 : A sign twelve inches (12") wide and eighteen inches (18") in height shall be mounted on the side of a structure or other permanent fixture approved by the Fire Code Official. The bottom of the sign being seven feet (7') from finished grade. Spacing of signs shall not exceed fifty feet (50') between signs. Signs shall be reflective material with a white color background with symbols, letters and border in red color. "FIRE LANE—NO PARKING".
|
|
|
Building Codes Review
|
No Comments
|
03/04/2024
|
03/04/2024
|
|
Joe Frogge
|
|
Miscellaneous Correction
Water piping from main to 10' past meter must be copper.
|
|
Miscellaneous Correction
Provide cleanout near where sanitary exits building.
|
|
|
Engineering Review
|
Corrections
|
03/04/2024
|
03/04/2024
|
|
Gene Williams, P.E.
|
|
Corrective Action Required
A SWPPP is required prior to formal approval of the plans.
|
|
Corrective Action Required
Notes to facilitate drainage within the backflow vault are vague. The note states that a 2 foot diameter hole will be created, lined with geofabric and 3/4 inch clean rock. However, no other details are provided such as the depth. It is important to note, however, we have recetnly seen this method of drainage to be ineffective even if the depth of the hole is shown on the plans. It is recommended that a small diameter pipe be installed and drained to a curb inlet or other junction, or daylight if possible. Please revise as appropriate.
|
|
Corrective Action Required
Why is the backflow vault shown within the paved area? It appears the backflow vault can be installed elsewhere outside of paved areas. In accordance with the Design and Construction Manual, backflow vaults shall be placed outside of paved areas unless there are no other alternatives available. It will also require the installation of alternative traffic-rated accessway. Please evaluate and revise as appropriate.
|
|
|
Planning Review
|
No Comments
|
03/04/2024
|
03/04/2024
|
|
Hector Soto Jr.
|
|
|
Traffic Review
|
No Comments
|
03/04/2024
|
02/26/2024
|
|
Mike Weisenborn
|
|
|
Building Codes Review
|
Corrections
|
12/19/2023
|
12/19/2023
|
|
Joe Frogge
|
|
Miscellaneous Correction
Corrective Action Required
Water piping from main to 10' past meter must be copper.
|
|
Miscellaneous Correction
Corrective Action Required
Provide cleanout near where sanitary exits building.
|
|
|
Engineering Review
|
Corrections
|
12/19/2023
|
12/19/2023
|
|
Gene Williams, P.E.
|
|
Corrective Action Required
A SWPPP is required for site disturbance over 1 acre. Please provide a SWPPP for the project.
|
|
Corrective Action Required
Even though the sanitary sewer is a private line, it has the potential to serve upstream developments that are not part of John Knox Village. There is concern about re-routing the 8 inch line around the building by providing an oversized 10 inch line (for the reason to make-up the needed slope of 0.8%), so this issue will need to be reviewed by Water Utilities. We expect an answer soon.
|
|
Corrective Action Required
Utility Plan: Copper is required from the water main to the meter, and a minimum of 10 feet beyond the meter. Please revise.
|
|
Corrective Action Required
Utility Sheet: Show a gate valve immediately prior to the backflow vault. Please revise.
|
|
Corrective Action Required
Utility Sheet: W14 note calls for connection of domestic service to building. This implies the line in question is the domestic service line from the water main, which is not the case. W6 denotes where the domestic service enters the building, not W14. W14 appears to be a separate line from the building to the dog park drinking fountain. Please clarify to eliminate any confusion.
|
|
Corrective Action Required
Utility Sheet: The exterior backflow vault is not required since the building appears to be within 50 feet of the main. A gate valve is still required, however, on the private fire line. Please revise as appropriate.
|
|
Corrective Action Required
Utility Sheet: If private fire hydrants are required as per Fire Department comments, they may require a backflow vault exterior to the buidling. Based on what is show, however, exterior backflow vaults would not be required on the two (2) fire hydrants shown. Please evaluate Fire Department comments, and if additional hydrants are necessary, please evaluate whether exterior backflow vaults are necessary and revise as appropriate.
|
|
Corrective Action Required
Please show the HGL for the design storm on the profile view of all storm lines greater than 10 inches diameter. If the pipe cannot manage the 100 year event without surcharging, a suitable overflow route shall be shown, and the HGL shall be a minimum of 2.0 feet below the lowest opening in any building. Please revise as appropriate.
|
|
Corrective Action Required
Please label all storm lines as "PRIVATE" on the profile views. Please label all sanitary sewer lines as "PRIVATE" on the profile views. This will enable our GIS technicians to enter the data appropriately.
|
|
Corrective Action Required
Curb and gutter section view should be revised to show the subgrade material (i.e., aggregate and geogrid or chemcially-stabilized subgrade) a minimum of 1.0 feet beyond the back of curb. This can be done on the typical pavement section, or by revising the City standard detail for curb and gutter to show the extension of the subgrade a minimum of 1.0 feet beyond the back of curb. Please revise as appropriate.
|
|
Corrective Action Required
Pipe bedding detail for HDPE should be revised to show a minimum of 12 inches of aggregate cover over the top of pipe rather than 6 inches as shown. This requirement took effect in July 2020. Please revise as appropriate.
|
|
Corrective Action Required
Recommend a thorough review of the storm line being re-routed to ensure it can manage infrequent storm events. It appears a severe flooding event has the potential to flood buildings since there does not appear to be any overflow route. Please evaluate and revise the design if appropriate.
|
|
Corrective Action Required
Utility Plan: Sanitary sewer connections show a tee. This is not allowed in the City of Lee's Summit. A wye shall be installed as per the City of Lee's Summit standard detail. Please revise.
|
|
Corrective Action Required
ADA-accessible ramp details: please remove the "wings" on the ADA-accessible ramps. Please grade to the ramp rather than constructing a concrete "wing". Please revise the plans as appropriate.
|
|
Corrective Action Required
Calculations in the form of a table for the storm lines appeared to be missing from the plans. Please provide storm line calculations in table format within the plans. Ensure the HGL for the design storm is transcribed to the profile views of all storm lines greater than 10 inches diameter.
|
|
Corrective Action Required
Recommend at an absolute minimum the new storm line being re-routed around the building be sized to manage the 100 year event for the gravity condition. Otherwise, the potential for structure flooding appears possible. Please evaluate and revise as appropriate.
|
|
Corrective Action Required
Pavement design does not meet the Unified Development Ordinance (UDO) in terms of pavement thickness, aggregate base, or chemically-stabilized subgrade/geogrid. Please see the UDO for specific requirements. In lieu of using the standard pavement section specified in the UDO, a geotechnical study using on-site sampling may be used to show the alternate design is at least as good as the UDO version. If interested, please contact me and I will provide the specific parameters needed for a geotechnical study and report.
|
|
Corrective Action Required
Please be aware the UDO does not distinguish between parking aisles and drive aisles. The only distinction in pavement design is between: 1) normal duty pavement including drive aisles and parking stalls, and 2) heavy duty pavement to support garbage trucks, emergency vehicles, etc. Please review and show on the site plan where heavy duty and light duty asphaltic concrete pavement will be constructed.
|
|
Corrective Action Required
Sheet C7.0: Please remove the "wings" from the ADA-accessible ramp. As previously discussed in this comment letter, wings are not necessary as the area shown can be graded to the ramp. Please revise the detail as appropriate.
|
|
Corrective Action Required
Sheet C4.0: It is extremely difficult to determine where the retaining walls are located on this sheet. The legend shows a solid line. There appear to be several solid lines on this sheet. Please review and revise as appropriate so it is clear to everyone reading the plans where the retaning wall(s) are located.
|
|
Corrective Action Required
Utility Sheet: SS-06 shows the new sanitary service line connecting directly to a manhole. This is not allowed in the City of Lee's Summit unless it is an 8 inch line. Please connect to the relocated line with a wye connection in accordance with the Lee's Summit standard detail. Please revise as appropriate.
|
|
Corrective Action Required
The City standard detail for sanitary sewer connection appeared to be missing from the plans. Please provide the City standard detail SAN-1.
|
|
Corrective Action Required
Truncated domes appeared to be missing from the ADA-accessible ramps along Moore St. Although this is a private road, it would appear truncated domes would be appropriate given the nature of the development. Please revise as appropriate.
|
|
Corrective Action Required
An itemized and sealed Engineer's Estimate of Probable Construction Costs should accompany your final submittal drawings. Please do not include items such as the buiilding, lighting, railing, trees, shrubs, or retaining walls.
|
|
|
Traffic Review
|
No Comments
|
12/19/2023
|
12/19/2023
|
|
Susan Barry, P.E.
|
|
|
Fire Review
|
Corrections
|
12/19/2023
|
12/18/2023
|
|
Jim Eden
|
|
Code Statement
All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2018 International Fire Code and local amendments.
|
|
Water Supply
IFC 507.1 - An approved water supply capable of supplying the required fire flow for fire protection shall be provided to premises upon which facilities, buildings or portions of buildings are hereafter constructed or moved into or within the jurisdiction.
Work with Water Utilities to provide information on available fire flow in the area. Fire flow shall meet the requirements of IFC Table B105.1(2) for a V-B or V-A construction. A 50% reduction in fire flow is allowed per local amendment for the sprinkler system.
To be confirmed with Water Utilities.
|
|
Hydrants
IFC 507.5.1 - Where a portion of the facility or building hereafter constructed or moved into or within the jurisdiction is more than 300 feet from a hydrant on a fire apparatus access road, as measured by an approved route around the exterior of the facility or building, on-site fire hydrants and mains shall be provided where required by the fire code official.
Show all available hydrants to meet the 300' requirement
and required fire flow.
|
|
Imposed Loads
IFC 503.2.3 - Fire apparatus access roads shall be designed and maintained to support the imposed loads of fire apparatus and shall be surfaced so as to provide all-weather driving capabilities.
Confirm the medium duty pavement will support 75,000-pounds.
|
|
Obstructions
IFC 503.4 - Fire apparatus access roads shall not be obstructed in any manner, including the parking of vehicles. The minimum widths and clearances established in Section 503.2.1 shall be maintained at all times.
How will access to be maintained to B building hydrant and FDC?
|
|
Fire Lanes - Marking
IFC 503.3 - 503.3 Marking. Where required by the fire code official, approved signs or other approved notices or markings that include the words NO PARKING—FIRE LANE shall be provided for fire apparatus access roads to identify such roads or prohibit the obstruction thereof. The means by which fire lanes are designated shall be maintained in a clean and legible condition at all times and be replaced or repaired when necessary to provide adequate visibility.
Fire lanes may be marked in one or a combination of methods as approved by the fire code official. Curbs. All curbs and curb ends shall be painted red with four inch (4") white lettering stating "FIRE LANE—NO PARKING". Wording may not be spaced more than fifteen feet (15') apart. Where no curb exists or a rolled curb is installed, a 6-inch (6") wide painted red stripe applied to the concrete or asphalt with four inch (4") white lettering stating "FIRE LANE—NO PARKING. "Signs. In areas where fire lanes are required, but no continuous curb is available, one of the following methods shall be used to indicate the fire lane. Option 1 : A sign twelve inches (12") wide and eighteen inches (18") in height shall be mounted on a metal post set in concrete a minimum of depth of eighteen inches (18") set back one foot (1') in from the edge of the roadway with the bottom of the sign being seven feet (7') from finished grade. Signs shall face oncoming traffic. Spacing of signs shall not exceed fifty feet (50') between signs. Signs shall be reflective material with a white color background with symbols, letters and border in red color. "FIRE LANE—NO PARKING". Option 2 : A sign twelve inches (12") wide and eighteen inches (18") in height shall be mounted on the side of a structure or other permanent fixture approved by the Fire Code Official. The bottom of the sign being seven feet (7') from finished grade. Spacing of signs shall not exceed fifty feet (50') between signs. Signs shall be reflective material with a white color background with symbols, letters and border in red color. "FIRE LANE—NO PARKING".
|
|
|
Planning Review
|
Corrections
|
12/19/2023
|
12/18/2023
|
|
Hector Soto Jr.
|
|
Corrective Action Required
DRIVE AISLE. Dimension the pavement width (excluding curb and gutter) of the proposed parking lot drive aisles. The drive aisles serving two-way traffic require a minimum 24' pavement width, whereas aisles serving one-way traffic require a minimum 10' pavement width.
|
|
Corrective Action Required
PAVEMENT DESIGN DETAIL. The asphalt pavement details provided on Sheet C7.0 do not meet City requirements. The City's light duty asphalt requirement is 1.5" surface course and 4" base course. The heavy duty asphalt requirement is 1.5" surface course and 5" base course.
|
|
Corrective Action Required
TRASH ENCLOSURE. Please confirm that the proposed development will not include an exterior trash dumpster site. If an exterior dumpster will be located on the site, show and label the proposed location. Each trash enclosure shall be constructed of masonry walls or steel architecturally designed walls with either a solid steel opaque gate painted to be compatible with the color of the masonry or steel walls and building it is to serve or a steel framed semi-opaque gate with a screen mesh material approved by the Director that provides an appropriate visual barrier.
|
|
Corrective Action Required
COLORS. Label the proposed exterior building material colors on Sheet A5.1A.
|
|
Corrective Action Required
LIGHTING.
- Show the proposed location of the relocated light poles.
- Provide manufacturer specifications for all proposed exterior wall-mounted light fixtures for review. All exterior fixtures shall comply with the requirements of UDO Sections 8.220, 8.260 and 8.270.
- Provide a photometric plan in accordance with UDO Section 8.230.
|
|
|