Planning Application Status

PL2022391




 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PL2022391
Market Street Center Lot 2 - Westlake Ace Hardware
Commercial Final Development Plan
Commercial Final Development Plan
Approved
11/04/2022
LEES SUMMIT RETAIL PARTNERS LLC
Locations
Contacts
Scott Ready, Phone: 8169691225  
Dan Finn, Address:Phelps Engineering, Inc., Phone:(913) 393-1155  
POWELL MINNIS, Address:DAVIDSON A+E, Phone:(913) 451-9390  
Lee's Summit Retail Partners, LLC, Address:4706 Broadway Blvd, Phone:(816) 285-9550  
LEES SUMMIT RETAIL PARTNERS LLC, Address:4706 BROADWAY STE 260  
Reviews
Review Type Outcome Est. Completion Date Completed
Engineering Review Approved with Conditions 03/29/2023 03/23/2023
Sue Pyles, P.E.
DE Contact Field Eng. Inspector
Corrective Action Required
03/23/2023

Prior to the commencement of any construction activities, the Contractor shall contact Field Engineering Inspections at (816) 969-1200 to coordinate a preconstruction meeting / conference with the assigned Field Engineering Inspector.
DE Engineers Estimate
Corrective Action Required
03/23/2023

The Engineer’s Estimate of Probable Construction Costs has been accepted for this project, and the Engineering Plan Review and Inspection Fee (which is calculated as 3% of the total infrastructure cost plus a water test inspection fee(s)), water tap and meter setup fee, and the sanitary sewer development fee have been included. These must be paid prior to the issuance of an infrastructure permit and/or the final processing of a building permit. $29,103.83
DE Future Repair Work
Corrective Action Required
03/23/2023

Please be aware that any future repair work to public infrastructure (e.g., water main repair, sanitary sewer repair, storm sewer repair, etc.) within public easements will not necessarily include the repair of pavement, curbing, landscaping, or other private improvements which are located within the easement.
Building Codes Review No Comments 03/29/2023 03/23/2023
Scott Ready
Traffic Review No Comments 03/29/2023 03/23/2023
Scott Ready
Fire Review Approved with Conditions 03/29/2023 03/23/2023
Scott Ready
Code Statement
Corrective Action Required
03/23/2023

All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2018 International Fire Code.
Hazmat
Corrective Action Required
03/23/2023

IFC 105.6.20 - A Hazardous materials permit is required for the using, dispensing, transporting, handling, and/or storing of extremely hazardous substances. “Extremely Hazardous Substances (EHS) Facilities” are defined as facilities subject to the provisions of Superfund Amendments and Reauthorization Act of 1986 (SARA TITLE III), Section 302, for storing, dispensing, using, or handling of listed chemicals in excess of their threshold planning quantities (TPQ). See amended Section 5001.4 of the 2018 International Fire Code. A Haz Mat permit is also required for propane (LPG) filling and exchange. Complete a Hazardous Materials Permit application. Include quantites and specifications for the filling operation and employee training.
Planning Review No Comments 03/29/2023 03/23/2023
Scott Ready
Engineering Review Corrections 03/23/2023 03/23/2023
Sue Pyles, P.E.
Corrective Action Required
03/23/2023

Please update the estimate to include items for the backflow vault and 1.25" domestic water line.
Building Codes Review No Comments 03/23/2023 03/16/2023
Scott Ready
Traffic Review No Comments 03/23/2023 03/16/2023
Scott Ready
Fire Review Approved with Conditions 03/23/2023 03/16/2023
Scott Ready
Code Statement
Corrective Action Required
03/16/2023

All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2018 International Fire Code.
Hazmat
Corrective Action Required
03/16/2023

IFC 105.6.20 - A Hazardous materials permit is required for the using, dispensing, transporting, handling, and/or storing of extremely hazardous substances. “Extremely Hazardous Substances (EHS) Facilities” are defined as facilities subject to the provisions of Superfund Amendments and Reauthorization Act of 1986 (SARA TITLE III), Section 302, for storing, dispensing, using, or handling of listed chemicals in excess of their threshold planning quantities (TPQ). See amended Section 5001.4 of the 2018 International Fire Code. A Haz Mat permit is also required for propane (LPG) filling and exchange. Complete a Hazardous Materials Permit application. Include quantites and specifications for the filling operation and employee training.
Planning Review No Comments 03/23/2023 03/16/2023
Scott Ready
Engineering Review Corrections 03/15/2023 03/16/2023
Sue Pyles, P.E.
Corrective Action Required
03/16/2023

Sheet C3: • Specify fire line material. • Locate the water meter as required by Design and Construction Manual Section 6901.L.1, which in this case is in the R/W within 1’ of the R/W line. • Design and Construction Manual Section 6901.I.3 requires buildings located more than 50’ from the public water main to include a BFPD located in a buried vault located within 5’ of the R/W on the private side. Please revise the plans accordingly, and include the sump drainage as previously requested. Please update the estimate as needed.
Planning Review No Comments 03/15/2023 03/15/2023
Shannon McGuire
Building Codes Review No Comments 03/15/2023 03/08/2023
Scott Ready
Traffic Review No Comments 03/15/2023 03/08/2023
Scott Ready
Fire Review Approved with Conditions 03/15/2023 03/08/2023
Scott Ready
Code Statement
Corrective Action Required
03/08/2023

All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2018 International Fire Code.
Hazmat
Corrective Action Required
03/08/2023

IFC 105.6.20 - A Hazardous materials permit is required for the using, dispensing, transporting, handling, and/or storing of extremely hazardous substances. “Extremely Hazardous Substances (EHS) Facilities” are defined as facilities subject to the provisions of Superfund Amendments and Reauthorization Act of 1986 (SARA TITLE III), Section 302, for storing, dispensing, using, or handling of listed chemicals in excess of their threshold planning quantities (TPQ). See amended Section 5001.4 of the 2018 International Fire Code. A Haz Mat permit is also required for propane (LPG) filling and exchange. Complete a Hazardous Materials Permit application. Include quantites and specifications for the filling operation and employee training.
Planning Review Corrections 02/21/2023 02/24/2023
Shannon McGuire
Corrective Action Required
02/24/2023

Please provide a Completed application form with signatures and a completed ownership affidavit form.
Corrective Action Required
02/24/2023

On the cover page please include the legal description of the property and include the area of land in sq. ft. and acres.
Corrective Action Required
02/24/2023

Will there be any ground mounted mechanical equipment? If so please provide the location, size, and type of material to be used in all screening of ground mounted mechanical equipment. Also provide the manufacturer’s specification sheets for proposed mechanical equipment to be used.
Corrective Action Required
02/24/2023

It looks like you are proposing no curbing along the sidewalk adjacent to the front (north side) of the store. How will this area be protected from vehicles? As curb block are only allowed as part of ADA stalls I would recommend installing bollards.
Engineering Review Corrections 02/21/2023 02/21/2023
Sue Pyles, P.E.
Corrective Action Required
02/21/2023

General: • Submit an Engineer's Estimate of Probable Construction Costs. • Submit the SWPPP and a copy of the MDNR Land Disturbance Permit. • The plans label the lot as Lot 2A. Please verify if this is correct or revise to Lot 2 throughout the plan set.
Corrective Action Required
02/21/2023

Sheet C1: The scale appears incorrect. Please revise.
Corrective Action Required
02/21/2023

Sheets C2-C2.4: • Label the retaining wall and include Top of Wall and Bottom of Wall elevations where appropriate. • The City recommends that the sidewalk design slopes be 1.5% for cross-slope and 7.5% for running-slope to allow for construction tolerance in the field. The slopes shown at the west end of the crosswalk exceed these design slopes.
Corrective Action Required
02/21/2023

Sheet C3: • The method of draining the backflow vault sump shall be shown. We have seen the following methods used in the past: 1) daylighting with a small diameter pipe, 2) connection to a storm box, or 3) construction of an infiltration gallery in the form of a 2 foot diameter hole lined with permeable geotextile and filled with clean 3/4 inch rock. In lieu of the above, a sump pump could be installed. Please evaluate and revise as appropriate. • Will there be an irrigation meter? If so, please include in the plan set. • Specify fire line material.
Corrective Action Required
02/21/2023

Sheet C4: • Provide details for lowering the existing junction box, Structure 11. • Provide details for connecting proposed curb inlet Structure 10A with the existing storm sewer. • Review the flowlines at Structure 10A, there appears to be a typo.
Corrective Action Required
02/21/2023

Sheet C4.1: Provide details for lowering and converting the existing junction box to a curb inlet, Structure 20.
Corrective Action Required
02/21/2023

Sheet C4.2: • Please show the hydraulic grade line for the design storm on the profile view of the storm system. If the pipe cannot manage the 100 year event without surcharging, then a suitable overflow route must be established for the excess. • Include the following note: “Compacted Fill shall be placed to a minimum 18” above the top of the pipe prior to installation.” Show and label the limits of the compacted fill placement in the Profile view. Use hatching for clarity.
Corrective Action Required
02/21/2023

Sheet C5: Please include inlet calculations. • Sheets C7.2-C7.3: Please revise all trench and backfill details to show 12” fill above the pipe, rather than 6”.
Fire Review Approved with Conditions 02/21/2023 02/17/2023
Jim Eden
Code Statement
Corrective Action Required
02/24/2023

All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2018 International Fire Code.
Hazmat
Corrective Action Required
02/17/2023

IFC 105.6.20 - A Hazardous materials permit is required for the using, dispensing, transporting, handling, and/or storing of extremely hazardous substances. “Extremely Hazardous Substances (EHS) Facilities” are defined as facilities subject to the provisions of Superfund Amendments and Reauthorization Act of 1986 (SARA TITLE III), Section 302, for storing, dispensing, using, or handling of listed chemicals in excess of their threshold planning quantities (TPQ). See amended Section 5001.4 of the 2018 International Fire Code. A Haz Mat permit is also required for propane (LPG) filling and exchange. Complete a Hazardous Materials Permit application. Include quantites and specifications for the filling operation and employee training.
Building Codes Review No Comments 02/21/2023 02/16/2023
Joe Frogge
Traffic Review No Comments 02/21/2023 02/08/2023
Brad Cooley, P.E., RSPI
Fees
Paid Fees Amount Paid Owing Date Paid
9110077-Final Development Plan fee $725.00 $725.00 Paid 12/27/2022
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Hearings
Title Location Date Time
Documents & Images
Date Uploaded File Type Document Name
12/27/2022 Receipt Receipt for transaction:2022-009649
02/06/2023 Engineer Report/Study 2023-02-04 Final Stormwater Management Plan
02/06/2023 Application Form Final Development Plan Application
02/06/2023 Letter Legal Description
02/06/2023 Plans 2023-02-04 Market Street Center - Lot 2 FDP
02/06/2023 Engineer Report/Study Structure #30 - Riprap Sizing
02/24/2023 Letter Applicant Letter - FDP (DFDP)
03/08/2023 Engineers Estimate 220695 FDP - OPC
03/08/2023 Letter 2023-03-08 Response to FDP Comments
03/08/2023 Plans 2023-03-08 Market Street Center - Lot 2 FDP
03/08/2023 Engineer Report/Study SWPPP
03/16/2023 Letter Applicant Letter - FDP (DFDP)
03/16/2023 Plans 2023-03-16 Market Street Center - Lot 2 FDP
03/16/2023 Letter 2023-03-16 Response to FDP Comments
03/23/2023 Letter Applicant Letter - FDP (DFDP)
03/23/2023 Engineers Estimate 220695 FDP - OPC
03/23/2023 Activity Document Fees PL2022391 Market Street Center Lot 2 Westlake Ace FDP
03/23/2023 Approved Plans Approved FDP_032323_2023-03-16 Market Street Center - Lot 2 FDP
03/23/2023 Letter Applicant Letter - FDP (DFDP)
06/15/2023 Plans 2023-06-08 Westlake LS Updated Civil Drawings
06/15/2023 Approved Plans FDP APPROVED CIVIL REVISIONS_2023-06-08 Westlake LS Updated Civil Drawings
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New license, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home