Planning Application Status

PL2022373




 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PL2022373
Lee's Summit High School West - Robotics Facility
Commercial Final Development Plan
Commercial Final Development Plan
Approved
10/21/2022
REORGANIZED SCHOOL DIST NO 7
Build new 7,100 square foot robotics facility
Locations
Contacts
REORGANIZED SCHOOL DIST NO 7, Address:301 NE Tudor Rd  
MULTISTUDIO, Address:4200 PENNSYLVANIA AVE  
KAW VALLEY ENGINEERING INC, Address:14700 W 114TH TERR, Phone:(913) 894-5150  
Reviews
Review Type Outcome Est. Completion Date Completed
Engineering Review Approved with Conditions 12/02/2022 12/02/2022
Gene Williams, P.E.
DE Engineers Estimate
Corrective Action Required
12/02/2022

The Engineer’s Estimate of Probable Construction Costs has been accepted for this project, and the Engineering Plan Review and Inspection Fee (which is calculated as 3% of the total infrastructure cost plus a water test inspection fee(s)), and the water tap and meter setup fee/sanitary sewer impact fee have been included. These must be paid prior to the issuance of an infrastructure permit and/or the final processing of a building permit. $27,353.55
DE Contact Field Eng. Inspector
Corrective Action Required
12/02/2022

Prior to the commencement of any construction activities, the Contractor shall contact Field Engineering Inspections at (816) 969-1200 to coordinate a preconstruction meeting / conference with the assigned Field Engineering Inspector.
Misc.
Corrective Action Required
12/02/2022

The stormwater waiver is currently under review. Staff is recommending approval of the waiver, but in the event the waiver is not approved, revisions to the Final Development Plan may be required.
Planning Review No Comments 12/02/2022 11/28/2022
Hector Soto Jr.
Building Codes Review No Comments 12/02/2022 11/23/2022
Joe Frogge
Miscellaneous Correction
Resolved
11/23/2022

Water service backflow to be inside building. 11/17/22 - still shown on C800-A
Miscellaneous Correction
Resolved
11/23/2022

Specify size, type, and location of water meter. 11/17/22 - Not found on plans.
Fire Review Approved with Conditions 12/02/2022 11/23/2022
Mike Weisenborn
Code Statement
Corrective Action Required
11/23/2022

All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2018 International Fire Code.
Imposed Loads
Corrective Action Required
11/23/2022

IFC 503.2.3 - Fire apparatus access roads shall be designed and maintained to support the imposed loads of fire apparatus and shall be surfaced so as to provide all-weather driving capabilities. The sidewalk FD Acess shall support the weight of a fire apparatus (75,000-pounds).
Traffic Review No Comments 12/02/2022 11/23/2022
Mike Weisenborn
Fire Review Approved with Conditions 11/18/2022 11/21/2022
Mike Weisenborn
Code Statement
Corrective Action Required
11/11/2022

All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2018 International Fire Code.
Imposed Loads
Corrective Action Required
11/11/2022

IFC 503.2.3 - Fire apparatus access roads shall be designed and maintained to support the imposed loads of fire apparatus and shall be surfaced so as to provide all-weather driving capabilities. The sidewalk FD Acess shall support the weight of a fire apparatus (75,000-pounds).
Planning Review Corrections 11/18/2022 11/17/2022
Hector Soto Jr.
Corrective Action Required
11/17/2022

SITE DATA TABLE (Sheet C100-A). - Correct the listed property zoning from PO to AG (Agricultural). - Fill in the setback information for Front (30' per plat); Rear (50'); and side (50'). - Provide building square footage for the existing school; the proposed robotics building; and total (existing + proposed). - List the number of existing classrooms; the number of proposed classrooms (from the addition); and total classrooms (existing + proposed). - List the number of existing parking parking spaces and the number of required parking spaces. The number of required parking spaces for a high school is calculated at a rate of 6 spaces per total classrooms. The comments listed above were previously made but not addressed on the resubmittal. The FDP response letter indicates that they have been addressed on Sheet C100-A, but they have not been.
Building Codes Review Corrections 11/18/2022 11/17/2022
Joe Frogge
Miscellaneous Correction
Resolved
11/17/2022

Sanitary connection at manhole not allowed.
Miscellaneous Correction
Corrective Action Required
11/11/2022

Water service backflow to be inside building. 11/17/22 - still shown on C800-A
Miscellaneous Correction
Corrective Action Required
11/11/2022

Specify size, type, and location of water meter. 11/17/22 - Not found on plans.
Engineering Review Corrections 11/18/2022 11/17/2022
Gene Williams, P.E.
Corrective Action Required
11/17/2022

Sheet C800-A: Backflow vault is shown on the domestic line rather than the fire line. Backflow devices for domestic service lines shall be located within the building, not outside the building and not within a vault.
Corrective Action Required
11/17/2022

Sheet C500-A: Please see above comment. The same comment applies to this sheet. Please revise.
Corrective Action Required
11/17/2022

The location and sizing of the water meter shall be shown on the utility sheet. Please show the location and sizing of the meter. Please revise.
Corrective Action Required
11/17/2022

A separately-recorded easement may need to be submitted for the new water meter to be installed. If required by Water Utilities, it should extend 5 feet around the perimeter of the water meter pit. Please use our standard template for water line easement, and provide a courtesy review copy with an 8.5 inch by 11 inch exhibit showing the limits of the easement in graphic format prior to execution and recording.
Corrective Action Required
11/17/2022

The Design Criteria Modification Request template form was submitted without the summary sheet and exhibits. Please submit the template form, summary sheet, and exhibits as one (1) single pdf file.
Corrective Action Required
11/18/2022

It appears a water meter already exists on the west side of the service entrance, and it may be possible to install a tee to this existing domestic service line. Please evaluate, as this will enable the elimination of the water meter and tap on the east side of the service drive.
Traffic Review No Comments 11/18/2022 11/11/2022
Scott Ready
Traffic Review No Comments 11/04/2022 11/04/2022
Brad Cooley, P.E., RSPI
Fire Review Approved with Conditions 11/04/2022 11/01/2022
Jim Eden
Code Statement
Corrective Action Required
11/01/2022

All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2018 International Fire Code.
Imposed Loads
Corrective Action Required
11/01/2022

IFC 503.2.3 - Fire apparatus access roads shall be designed and maintained to support the imposed loads of fire apparatus and shall be surfaced so as to provide all-weather driving capabilities. The sidewalk FD Acess shall support the weight of a fire apparatus (75,000-pounds).
Planning Review Corrections 11/04/2022 11/01/2022
Hector Soto Jr.
Corrective Action Required
10/31/2022

SITE DATA TABLE (Sheet C100-A). - Correct the listed property zoning from PO to AG (Agricultural). - Fill in the setback information for Front (30' per plat); Rear (50'); and side (50'). - Provide building square footage for the existing school; the proposed robotics building; and total (existing + proposed). - List the number of existing classrooms; the number of proposed classrooms (from the addition); and total classrooms (existing + proposed). - List the number of existing parking parking spaces and the number of required parking spaces. The number of required parking spaces for a high school is calculated at a rate of 6 spaces per total classrooms.
Corrective Action Required
11/01/2022

ROOF-TOP UNITS. In order to comply with City ordinances, all RTUs shall be fully screened from view by raising building parapet heights at least equal to the height of the units being screened.
Corrective Action Required
11/01/2022

EXTERIOR MATERIALS. Label the proposed exterior building material colors.
Corrective Action Required
11/01/2022

LIGHTING. Identify which light fixture(s) listed on the fixture schedule on Sheet E700 will be used on the building exterior. All exterior lighting fixtures shall comply with UDO Sections 8.220 and 8.260.
Engineering Review Corrections 11/04/2022 11/01/2022
Gene Williams, P.E.
Corrective Action Required
11/04/2022

Please add the project number to the waiver request form (i.e., PL2022373).
Building Codes Review Corrections 11/04/2022 10/26/2022
Joe Frogge
Miscellaneous Correction
Corrective Action Required
10/26/2022

Sanitary connection at manhole not allowed.
Miscellaneous Correction
Corrective Action Required
10/26/2022

Water service backflow to be inside building.
Miscellaneous Correction
Corrective Action Required
10/26/2022

Specify size, type, and location of water meter.
Fees
Paid Fees Amount Paid Owing Date Paid
9110077-Final Development Plan fee $725.00 $725.00 Paid 11/07/2022
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Hearings
Title Location Date Time
Documents & Images
Date Uploaded File Type Document Name
10/21/2022 Application Form Final Development Plan_LSW_Signed
10/21/2022 Plans 220909_LSW_LSN Bid Set_REDUX
10/21/2022 Engineer Report/Study 20220909 LSWHS Robotics Stormwater Compliance Letter (R0)
11/04/2022 Letter Applicant Letter - FDP (DFDP)
11/07/2022 Receipt Receipt for transaction: 2022-008759
11/11/2022 Engineer Report/Study 22-5547 LS West High School Robotics Building Geotech Report
11/11/2022 Plans 221110 LSW Permit Set
11/11/2022 Letter Lee's Summit West FDP Responses
11/11/2022 Letter LSR7 Robotics - ASI 001-ISS 003 - LSW Narrative
11/11/2022 Letter LSW DCM Design Waiver Request 11-08-2022
11/17/2022 Activity Document FEEWorksheet_MissingMeter
11/17/2022 Engineers Estimate LSWHS Robotics -EPEOPCC 20221027
11/21/2022 Letter Applicant Letter - FDP (DFDP)
11/23/2022 Letter 22-1123_Lee Summit West FDP Comments
11/23/2022 Waiver/Modification Document 20221122 LSWHS Robotics Stormwater Compliance Letter (R1)
11/23/2022 Engineers Estimate LSWHS Robotics -EPEOPCC 20221122
11/23/2022 Plans 221123 LSW Permit Set
12/02/2022 Activity Document FeeWSLSWestHSRoboticsFDP
12/02/2022 Waiver/Modification Document 20221122 LSWHS Robotics Stormwater Compliance Letter (R1)
12/02/2022 Letter Applicant Letter - FDP (DFDP)
12/02/2022 Approved Plans APPROVED LS WEST ROBOTICS - CIVIL
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New license, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home