Planning Application Status

PL2021451




 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PL2021451
Pergola Park 5th Plat
Final Plat
Final Plat
Recorded
11/17/2021
NLV PERGOLA PARK LLC
Locations
Address
3246 SW PERGOLA PARK DR, LEES SUMMIT, MO 64081

Address
3250 SW PERGOLA PARK DR, LEES SUMMIT, MO 64081

Address
3254 SW PERGOLA PARK DR, LEES SUMMIT, MO 64081

Address
3258 SW PERGOLA PARK DR, LEES SUMMIT, MO 64081

Address
3262 SW PERGOLA PARK DR, LEES SUMMIT, MO 64081

Address
1121 SW CORINTHIAN LN, LEES SUMMIT, MO 64081

Address
1117 SW CORINTHIAN LN, LEES SUMMIT, MO 64081

Address
1113 SW CORINTHIAN LN, LEES SUMMIT, MO 64081

Address
1109 SW CORINTHIAN LN, LEES SUMMIT, MO 64081

Address
1105 SW CORINTHIAN LN, LEES SUMMIT, MO 64081

Address
1101 SW CORINTHIAN LN, LEES SUMMIT, MO 64081

Address
1063 SW CORINTHIAN LN, LEES SUMMIT, MO 64081

Address
1059 SW CORINTHIAN LN, LEES SUMMIT, MO 64081

Address
1055 SW CORINTHIAN LN, LEES SUMMIT, MO 64081

Address
3266 SW PERGOLA PARK DR, LEES SUMMIT, MO 64081

Address
1125 SW CORINTHIAN LN, LEES SUMMIT, MO 64081

Address
3267 SW PERGOLA PARK DR, LEES SUMMIT, MO 64081

Address
3270 SW PERGOLA PARK DR, LEES SUMMIT, MO 64081

Property
62430995000000000

Property
62430996300000000

Property
62430996800000000

Property
62430996700000000

Property
62430996600000000

Property
62430996500000000

Property
62430996400000000

Property
62430996200000000

Property
62430996000000000

Property
62430995800000000

Property
62430995900000000

Property
62430995700000000

Property
62430995500000000

Property
62430995600000000

Property
62430995400000000

Property
62430995200000000

Property
62430995300000000

Property
62430995100000000

Property
62430996101000000

Address
1051 SW CORINTHIAN LN, LEES SUMMIT, MO 64081

Contacts
RUSSELL PEARSON, Address:3152 GRANDSTAND CIR, Phone:(913) 735-9861  
DAVID RINNE, Address:SCHLAGEL ASSOCIATES  
Scott Ready, Phone: 8169691225  
NLV PERGOLA PARK LLC, Address:3152 SW GRANDSTAND CIR  
CASTLE SEAN DUANE & KRISTIN MARIE, Address:1051 SW CORINTHIAN LN  
LAUGHLIN MEGAN, Address:4335 MCGEE ST  
BELLAH HOMES LLC, Address:PO BOX 346  
PARRISH BRYAN & CASEY, Address:1121 SW CORINTHIAN LN  
PARRISH DAVID, Address:3246 SW PERGOLA PARK DR  
MCCLARAN REVOCABLE LIVING TRUST DATED 8-1-2023, Address:3254 SW PERGOLA PARK DR  
JULICH PETER & ANN, Address:3258 SW PEGOLA DR  
Reviews
Review Type Outcome Est. Completion Date Completed
Planning Review No Comments 01/03/2023 01/03/2023
Hector Soto Jr.
GIS Review No Comments 01/03/2023 12/22/2022
Scott Ready
Traffic Review No Comments 01/03/2023 12/22/2022
Scott Ready
Fire Review No Comments 01/03/2023 12/22/2022
Scott Ready
Engineering Review Approved with Conditions 01/03/2023 12/22/2022
Scott Ready
DE C&O #01 Eng Plans – FP/PP
Corrective Action Required
12/22/2022

Please include the following note on the plat: Sidewalks where shown on this this plat, which are required by ordinance, are the developer’s responsibility and shall either be installed with the construction of the public street infrastructure as shown on this plat, or developer shall deposit a cash escrow with the City prior to the issuance of any building permits for structures on this plat, in the amount required by the Unified Development Ordinance.
DE C&O #02 Master Drainage Plan
Corrective Action Required
12/22/2022

All required engineering plans and studies, including water lines, sanitary sewers, storm drainage, streets and erosion and sediment control shall be submitted along with the final plat and approved prior to the approval of the final plat. All public infrastructure must be substantially complete, prior to the issuance of any building permits.
DE C&O #03 Eng & Insp Fees
Corrective Action Required
12/22/2022

A Master Drainage Plan (MDP) shall be submitted and approved in accordance with the City’s Design and Construction Manual for all areas of the development, including all surrounding impacted areas, along with the engineering plans for the development. The MDP shall address drainage level of service issues on an individual lot basis.
DE C&O #04 Cert FA or Escrow
Corrective Action Required
12/22/2022

All Engineering Plan Review and Inspection Fees shall be paid prior to approval of the associated engineering plans and prior to the issuance of any site development permits or the start of construction (excluding land disturbance permit).
DE C&O #05 As-Graded MDP
Corrective Action Required
12/22/2022

All subdivision-related public improvements must have a Certificate of Final Acceptance prior to approval of the final plat, unless security is provided in the manner set forth in the City's Unified Development Ordinance (UDO) Section 7.340. If security is provided, building permits may be issued upon issuance of a Certificate of Substantial Completion of the public infrastructure as outlined in Article 3, Division V, Sections 3.540 and 3.550 and Article 3, Division IV, Section 3.475 of the UDO, respectively.
DE C&O #07 Easements
Corrective Action Required
12/22/2022

The As-graded Master Drainage Plan shall be submitted to and accepted by the City prior to the issuance of a Certificate of Substantial Completion and prior to the issuance of any building permits for the development.
DE C&O #08 Changes to MDP
Corrective Action Required
12/22/2022

All permanent off-site easements, in a form acceptable to the City, shall be executed and recorded with the Jackson County Recorder of Deeds prior to the issuance of a Certificate of Substantial Completion or approval of the final plat. A certified copy shall be submitted to the City for verification.
DE C&O #12 Cut & Fill
Corrective Action Required
12/22/2022

A restriction note shall be included on the final plat stating: “Individual lot owner(s) shall not change or obstruct the drainage flow paths on the lots, as shown on the Master Drainage Plan, unless specific application is made and approved by the City Engineer."
DE C&O #13 ADA Sidewalk Ramps
Corrective Action Required
12/22/2022

Any cut and / or fill operations, which cause public infrastructure to exceed the maximum / minimum depths of cover shall be mitigated by relocating the infrastructure vertically and / or horizontally to meet the specifications contained within the City’s Design and Construction Manual.
GIS Review No Comments 12/15/2022 12/15/2022
Scott Ready
Fire Review No Comments 12/15/2022 12/14/2022
Scott Ready
Planning Review Corrections 12/15/2022 12/13/2022
Hector Soto Jr.
Corrective Action Required
12/13/2022

STREET NAME. Provide a street name for the stub labeled Street A for review. Include the "SW" quadrant prefix to the proposed street name.
Corrective Action Required
12/13/2022

CC&Rs. Provide a copy of the CCR's for review to ensure that said document includes the common property verbiage required under UDO Section 4.290. Staff can provide a template of said language for your use upon request.
Traffic Review No Comments 12/15/2022 12/12/2022
Brad Cooley, P.E., RSPI
Engineering Review Approved with Conditions 12/15/2022 12/09/2022
Sue Pyles, P.E.
DE C&O #01 Eng Plans – FP/PP
Corrective Action Required
12/08/2022

Please include the following note on the plat: Sidewalks where shown on this this plat, which are required by ordinance, are the developer’s responsibility and shall either be installed with the construction of the public street infrastructure as shown on this plat, or developer shall deposit a cash escrow with the City prior to the issuance of any building permits for structures on this plat, in the amount required by the Unified Development Ordinance.
DE C&O #02 Master Drainage Plan
Corrective Action Required
12/08/2022

All required engineering plans and studies, including water lines, sanitary sewers, storm drainage, streets and erosion and sediment control shall be submitted along with the final plat and approved prior to the approval of the final plat. All public infrastructure must be substantially complete, prior to the issuance of any building permits.
DE C&O #03 Eng & Insp Fees
Corrective Action Required
12/08/2022

A Master Drainage Plan (MDP) shall be submitted and approved in accordance with the City’s Design and Construction Manual for all areas of the development, including all surrounding impacted areas, along with the engineering plans for the development. The MDP shall address drainage level of service issues on an individual lot basis.
DE C&O #04 Cert FA or Escrow
Corrective Action Required
12/08/2022

All Engineering Plan Review and Inspection Fees shall be paid prior to approval of the associated engineering plans and prior to the issuance of any site development permits or the start of construction (excluding land disturbance permit).
DE C&O #05 As-Graded MDP
Corrective Action Required
12/08/2022

All subdivision-related public improvements must have a Certificate of Final Acceptance prior to approval of the final plat, unless security is provided in the manner set forth in the City's Unified Development Ordinance (UDO) Section 7.340. If security is provided, building permits may be issued upon issuance of a Certificate of Substantial Completion of the public infrastructure as outlined in Article 3, Division V, Sections 3.540 and 3.550 and Article 3, Division IV, Section 3.475 of the UDO, respectively.
DE C&O #07 Easements
Corrective Action Required
12/08/2022

The As-graded Master Drainage Plan shall be submitted to and accepted by the City prior to the issuance of a Certificate of Substantial Completion and prior to the issuance of any building permits for the development.
DE C&O #08 Changes to MDP
Corrective Action Required
12/08/2022

All permanent off-site easements, in a form acceptable to the City, shall be executed and recorded with the Jackson County Recorder of Deeds prior to the issuance of a Certificate of Substantial Completion or approval of the final plat. A certified copy shall be submitted to the City for verification.
DE C&O #12 Cut & Fill
Corrective Action Required
12/08/2022

A restriction note shall be included on the final plat stating: “Individual lot owner(s) shall not change or obstruct the drainage flow paths on the lots, as shown on the Master Drainage Plan, unless specific application is made and approved by the City Engineer."
DE C&O #13 ADA Sidewalk Ramps
Corrective Action Required
12/08/2022

Any cut and / or fill operations, which cause public infrastructure to exceed the maximum / minimum depths of cover shall be mitigated by relocating the infrastructure vertically and / or horizontally to meet the specifications contained within the City’s Design and Construction Manual.
Engineering Review Approved with Conditions 12/22/2021 04/21/2022
Sue Pyles, P.E.
Corrective Action Required
12/21/2021

Please include the following note on the plat: Sidewalks where shown on this this plat, which are required by ordinance, are the developer’s responsibility and shall either be installed with the construction of the public street infrastructure as shown on this plat, or developer shall deposit a cash escrow with the City prior to the issuance of any building permits for structures on this plat, in the amount required by the Unified Development Ordinance.
DE C&O #01 Eng Plans – FP/PP
Corrective Action Required
04/21/2022

All required engineering plans and studies, including water lines, sanitary sewers, storm drainage, streets and erosion and sediment control shall be submitted along with the final plat and approved prior to the approval of the final plat. All public infrastructure must be substantially complete, prior to the issuance of any building permits.
DE C&O #02 Master Drainage Plan
Corrective Action Required
04/21/2022

A Master Drainage Plan (MDP) shall be submitted and approved in accordance with the City’s Design and Construction Manual for all areas of the development, including all surrounding impacted areas, along with the engineering plans for the development. The MDP shall address drainage level of service issues on an individual lot basis.
DE C&O #03 Eng & Insp Fees
Corrective Action Required
04/21/2022

All Engineering Plan Review and Inspection Fees shall be paid prior to approval of the associated engineering plans and prior to the issuance of any site development permits or the start of construction (excluding land disturbance permit).
DE C&O #04 Cert FA or Escrow
Corrective Action Required
04/21/2022

All subdivision-related public improvements must have a Certificate of Final Acceptance prior to approval of the final plat, unless security is provided in the manner set forth in the City's Unified Development Ordinance (UDO) Section 7.340. If security is provided, building permits may be issued upon issuance of a Certificate of Substantial Completion of the public infrastructure as outlined in Article 3, Division V, Sections 3.540 and 3.550 and Article 3, Division IV, Section 3.475 of the UDO, respectively.
DE C&O #05 As-Graded MDP
Corrective Action Required
04/21/2022

The As-graded Master Drainage Plan shall be submitted to and accepted by the City prior to the issuance of a Certificate of Substantial Completion and prior to the issuance of any building permits for the development.
DE C&O #07 Easements
Corrective Action Required
04/21/2022

All permanent off-site easements, in a form acceptable to the City, shall be executed and recorded with the Jackson County Recorder of Deeds prior to the issuance of a Certificate of Substantial Completion or approval of the final plat. A certified copy shall be submitted to the City for verification.
DE C&O #08 Changes to MDP
Corrective Action Required
04/21/2022

A restriction note shall be included on the final plat stating: “Individual lot owner(s) shall not change or obstruct the drainage flow paths on the lots, as shown on the Master Drainage Plan, unless specific application is made and approved by the City Engineer."
DE C&O #12 Cut & Fill
Corrective Action Required
04/21/2022

Any cut and / or fill operations, which cause public infrastructure to exceed the maximum / minimum depths of cover shall be mitigated by relocating the infrastructure vertically and / or horizontally to meet the specifications contained within the City’s Design and Construction Manual.
DE C&O #13 ADA Sidewalk Ramps
Corrective Action Required
04/21/2022

All ADA sidewalk ramps shall be constructed by the developer at the time the street is constructed.
DE C&O #14 Common Area Sidewalks
Corrective Action Required
04/21/2022

All sidewalks adjacent to a common area tract, unplatted land or any land where no structure is intended to be built, and is required, shall be constructed by the developer at the time the street is constructed.
GIS Review No Comments 12/22/2021 12/28/2021
Kathy Kraemer
Planning Review Corrections 12/22/2021 12/22/2021
Jennifer Thompson
Corrective Action Required
12/22/2021

The plat dedication within the City signature section reflects the previous plat, please revise.
Corrective Action Required
12/22/2021

Provide the CCR's for review.
Corrective Action Required
12/22/2021

Addresses will be forthcoming.
Corrective Action Required
12/22/2021

Still need to discuss with Fire Dept. the street name change from Mary to Lumberman's Row.
Traffic Review No Comments 12/22/2021 12/20/2021
Brad Cooley, P.E., RSPI
Fire Review No Comments 12/22/2021 12/15/2021
Scott Ready
GIS Review Corrections 12/03/2021 12/07/2021
Kathy Kraemer
Corrective Action Required
12/07/2021

Please change the dedication to "Pegola Park 5th Plat"
Corrective Action Required
12/07/2021

Please provide an ITB for centerline on one end of tract 11-5 (alley). Also, as a clarification: does the total arc length of 508.57 include the 25' to SW Pergola Pk Dr?
Planning Review Corrections 12/03/2021 12/06/2021
Jennifer Thompson
Corrective Action Required
12/06/2021

Revise plat title to include Tract S.
Corrective Action Required
12/06/2021

Revise the dedications to reflect the correct plat title. The plat dedication and the city dedication areas.
Corrective Action Required
12/06/2021

Correct the spelling for SIDE in the encroachment section.
Corrective Action Required
12/06/2021

Label the 5' sidewalk on the plat besides referencing it in the legend.
Corrective Action Required
12/06/2021

Revise the drainage note to reflect correct plat title.
Corrective Action Required
12/06/2021

Provide a copy of the CCR's.
Corrective Action Required
12/06/2021

Addresses will be forthcoming.
Corrective Action Required
12/06/2021

I need to discuss with Fire Dept. regarding the street name changes between Mary and Lumberman's Row.
Engineering Review Corrections 12/03/2021 12/03/2021
Sue Pyles, P.E.
Corrective Action Required
12/01/2021

Please revise “Tracts Q – R” to “Tracts Q – S” in the plat title.
Corrective Action Required
12/01/2021

Please revise the plat referenced in the Drainage Note.
Corrective Action Required
12/03/2021

Sidewalks that are required to be constructed as part of this plat, and by ordinance are the developer’s responsibility, shall either be installed with the construction of the public street infrastructure or have a cash escrow deposited, by the developer, with the City, due to future developable adjacent property.
Traffic Review Corrections 12/03/2021 12/01/2021
Brad Cooley, P.E., RSPI
Corrective Action Required
12/01/2021

Additional callouts should be added to clearly delineate the proposed sidewalk.
Fire Review No Comments 12/03/2021 11/30/2021
Jim Eden
Fees
Paid Fees Amount Paid Owing Date Paid
Final Plat fee $850.00 $850.00 Paid 11/22/2021
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Hearings
Title Location Date Time
Planning Commission Meeting 04/28/2022 5:00 PM Council Chambers 04/28/2022 05:00 PM
Public Hearing Review
Approved
04/28/2022
City Council Ordinance 1st Reading 05/10/2022 6:00 PM Council Chambers 05/10/2022 06:00 PM
Public Hearing Review
Approved
City Council Ordinance 2nd Reading 01/17/2023 6:00 PM Council Chambers 01/17/2023 06:00 PM
Public Hearing Review
Approved
Documents & Images
Date Uploaded File Type Document Name
11/17/2021 Application Form Application and Affidavit - Signed
11/17/2021 Plans 2020-10-26 20-189F-Plat-24x36
11/17/2021 Engineer Report/Study DESCRIPTION - PERGOLA PARTK - 5TH PLAT 11-17-2021
11/17/2021 Engineer Report/Study PERGOLA 5TH BOUNDARY REPORT
11/17/2021 Application Form Pages from Final Plat Checklist
11/22/2021 Receipt Receipt for transaction:2021-008881
12/08/2021 Letter Applicant Letter - FP (DRCF)
12/13/2021 Letter Applicant Letter - FP (DRCF)
12/15/2021 Letter Response to Staff Comments dated 12-8-2021
12/15/2021 Plans 2021-12-14-189F-Plat-24x36
12/28/2021 Letter Applicant Letter - FP (DRCF)
04/22/2022 Letter Staff Report
12/08/2022 Plans 2022-12-08 20-189F-Plat-24x36
12/15/2022 Letter Applicant Letter - FP (DRCF)
12/21/2022 Letter Declaration of Community Association and Covenants, Conditions, Restrictions of Pergola Park 5th Plat
12/22/2022 Engineers Estimate SIGNED 20-189-REMAINING Engineers Cost Estimate as of 11-8-22
12/22/2022 Plans 2022-12-22 20-189F-Plat-24x36
01/03/2023 Letter Applicant Letter - FP (DRCF)
01/04/2023 Engineers Estimate Engineers Cost Estimate for remainder of site work_for Packet Letter
01/06/2023 Letter LOC_Original hard copy doc
01/11/2023 Letter County Recorded Document_Off-Site Sanitary Easement
01/23/2023 Letter Pergola Park 5th Plat - Recorded
01/23/2023 Ordinance/Resolution Plat Ordinance - Recorded
01/23/2023 Ordinance/Resolution 9581
02/09/2023 Plans Pergola Park 5th plat
08/28/2023 Letter Pergola Park 5th Certificate of Substantial Completion Multiple Lot
08/28/2023 Letter DE-Punch List1
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.