Review Type |
Outcome |
Est. Completion Date |
Completed |
Engineering Review
|
Approved with Conditions
|
04/22/2020
|
04/22/2020
|
|
Sue Pyles, P.E.
|
|
DE C&O #11 Pavement Thickness
Corrective Action Required
Private parking lots shall follow Article 8 of the Unified Development Ordinance for pavement thickness and base requirements.
|
|
DE Contact Field Eng. Inspector
Corrective Action Required
Contact the Field Engineering Inspector at (816) 969-1200 at least 48 hours prior to the onset of construction.
|
|
DE Engineers Estimate
Corrective Action Required
The Engineer’s Estimate of Probable Construction Costs has been accepted for this project, and the Engineering Plan Review and Inspection Fee (which is calculated as 3% of the total infrastructure cost plus a water test inspection fee(s)), and the water tap and meter setup fee have been included. These must be paid prior to the issuance of an infrastructure permit and/or the final processing of a building permit. $433.15
|
|
|
Planning Review
|
No Comments
|
04/22/2020
|
04/22/2020
|
|
Hector Soto Jr.
|
|
|
Traffic Review
|
No Comments
|
04/22/2020
|
04/21/2020
|
|
Michael Park
|
|
|
Building Codes Review
|
No Comments
|
04/22/2020
|
04/17/2020
|
|
Joe Frogge
|
|
|
Fire Review
|
Approved with Conditions
|
04/22/2020
|
04/16/2020
|
|
Jim Eden
|
|
Code Statement
All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2018 International Fire Code.
|
|
Misc.
Fire hydrants and the FDC for the hosptal shall remain accessible at all times during construction.
|
|
|
Engineering Review
|
Corrections
|
04/09/2020
|
04/08/2020
|
|
Sue Pyles, P.E.
|
|
Corrective Action Required
Label the pipe that is being rerouted. Is it roof drain, storm sewer, or something else? Our mapping information shows a 24" storm sewer pipe running north-south under the existing building and a water service line connecting to the nrth side of the existing building at this location. Neither of those are addressed. Please revise to clearly show all utilities and how they will be handled.
|
|
|
Planning Review
|
Corrections
|
04/09/2020
|
04/08/2020
|
|
Hector Soto Jr.
|
|
Corrective Action Required
SITE DATA TABLE. Add a table that lists the following information:
- Existing zoning;
- Site area;
- Existing, proposed and total building area (sq. ft.);
- Existing, proposed and total floor area ratio (FAR);
- Existing, proposed and total parking spaces;
- Existing, proposed and total hospital beds;
- Existing, proposed and total site impervious coverage; and
- Existing, proposed and total site open space.
|
|
Corrective Action Required
PARKING SPACE WIDTH. Dimension the width of the two parking spaces to the west and the parking space to the immediate east of the new landscape island in order to verify that they comply with minimum parking space widths. Parking spaces shall be a minimum 9' in width. Where a parking space is bounded by curbing on one or both sides, the width shall be measured from the curb face.
|
|
Corrective Action Required
LIGHT FIXTURES. Provide cut sheets for the proposed wall pack light fixtures for review. The proposed light fixtures shall comply with the standards under UDO Section 8.260.
|
|
Corrective Action Required
LANDSCAPING. The two ornamental trees to be removed for the addition shall be relocated elsewhere on site.
|
|
|
Building Codes Review
|
No Comments
|
04/09/2020
|
04/07/2020
|
|
Joe Frogge
|
|
|
Traffic Review
|
No Comments
|
04/09/2020
|
04/01/2020
|
|
Michael Park
|
|
|
Fire Review
|
Approved with Conditions
|
04/09/2020
|
03/30/2020
|
|
Jim Eden
|
|
Code Statement
All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2018 International Fire Code.
|
|
Misc.
Fire hydrants and the FDC for the hosptal shall remain accessible at all times during construction.
|
|
|