Planning Application Status

PL2020082




 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PL2020082
LSMC Hybrid OR Addition
Commercial Final Development Plan
Commercial Final Development Plan
Approved
03/25/2020
MIDWEST DIVISION LSH LLC
Locations
Contacts
MIDWEST DIVISION LSH LLC, Address:PO BOX 80610  
ACI BOLAND, Address:1421 EAST 104TH ST; SUITE 100, Phone:(816) 763-9600  
GBA ARCHITECTS ENGINEERS , Address:9801 RENNER BLVD, Phone:(913) 492-0400  
Reviews
Review Type Outcome Est. Completion Date Completed
Engineering Review Approved with Conditions 04/22/2020 04/22/2020
Sue Pyles, P.E.
DE C&O #11 Pavement Thickness
Corrective Action Required
04/22/2020

Private parking lots shall follow Article 8 of the Unified Development Ordinance for pavement thickness and base requirements.
DE Contact Field Eng. Inspector
Corrective Action Required
04/22/2020

Contact the Field Engineering Inspector at (816) 969-1200 at least 48 hours prior to the onset of construction.
DE Engineers Estimate
Corrective Action Required
04/22/2020

The Engineer’s Estimate of Probable Construction Costs has been accepted for this project, and the Engineering Plan Review and Inspection Fee (which is calculated as 3% of the total infrastructure cost plus a water test inspection fee(s)), and the water tap and meter setup fee have been included. These must be paid prior to the issuance of an infrastructure permit and/or the final processing of a building permit. $433.15
Planning Review No Comments 04/22/2020 04/22/2020
Hector Soto Jr.
Traffic Review No Comments 04/22/2020 04/21/2020
Michael Park
Building Codes Review No Comments 04/22/2020 04/17/2020
Joe Frogge
Fire Review Approved with Conditions 04/22/2020 04/16/2020
Jim Eden
Code Statement
Informational
04/16/2020

All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2018 International Fire Code.
Misc.
Informational
04/16/2020

Fire hydrants and the FDC for the hosptal shall remain accessible at all times during construction.
Engineering Review Corrections 04/09/2020 04/08/2020
Sue Pyles, P.E.
Corrective Action Required
04/08/2020

Label the pipe that is being rerouted. Is it roof drain, storm sewer, or something else? Our mapping information shows a 24" storm sewer pipe running north-south under the existing building and a water service line connecting to the nrth side of the existing building at this location. Neither of those are addressed. Please revise to clearly show all utilities and how they will be handled.
Planning Review Corrections 04/09/2020 04/08/2020
Hector Soto Jr.
Corrective Action Required
04/08/2020

SITE DATA TABLE. Add a table that lists the following information: - Existing zoning; - Site area; - Existing, proposed and total building area (sq. ft.); - Existing, proposed and total floor area ratio (FAR); - Existing, proposed and total parking spaces; - Existing, proposed and total hospital beds; - Existing, proposed and total site impervious coverage; and - Existing, proposed and total site open space.
Corrective Action Required
04/08/2020

PARKING SPACE WIDTH. Dimension the width of the two parking spaces to the west and the parking space to the immediate east of the new landscape island in order to verify that they comply with minimum parking space widths. Parking spaces shall be a minimum 9' in width. Where a parking space is bounded by curbing on one or both sides, the width shall be measured from the curb face.
Corrective Action Required
04/08/2020

LIGHT FIXTURES. Provide cut sheets for the proposed wall pack light fixtures for review. The proposed light fixtures shall comply with the standards under UDO Section 8.260.
Corrective Action Required
04/08/2020

LANDSCAPING. The two ornamental trees to be removed for the addition shall be relocated elsewhere on site.
Building Codes Review No Comments 04/09/2020 04/07/2020
Joe Frogge
Traffic Review No Comments 04/09/2020 04/01/2020
Michael Park
Fire Review Approved with Conditions 04/09/2020 03/30/2020
Jim Eden
Code Statement
Informational
03/30/2020

All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2018 International Fire Code.
Misc.
Informational
04/16/2020

Fire hydrants and the FDC for the hosptal shall remain accessible at all times during construction.
Fees
Paid Fees Amount Paid Owing Date Paid
9110077-Final Development Plan fee $600.00 $600.00 Paid 03/26/2020
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Hearings

There are no hearings for this planning application.

Documents & Images
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New license, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home