Review Type |
Outcome |
Est. Completion Date |
Completed |
Planning Review
|
No Comments
|
06/19/2020
|
06/19/2020
|
|
Shannon McGuire
|
|
|
Engineering Review
|
Approved with Conditions
|
06/19/2020
|
06/18/2020
|
|
Gene Williams, P.E.
|
|
DE Engineers Estimate
Corrective Action Required
The Engineer’s Estimate of Probable Construction Costs did not appear to be submitted with the application. The Engineering Plan Review and Inspection Fee will be based on the approved estimate. Fee to be determined.
|
|
DE Contact Field Eng. Inspector
Corrective Action Required
Contact Field Engineering Inspections at (816) 969-1200 at least 48 hours prior to the onset of construction.
|
|
DE Contact ROW Inspector
Corrective Action Required
Prior to any activities within the right-of-way that are not directly associated with a specific infrastructure or building permit, a separate right-of-way permit may be required. Contact a Right-of-Way Inspector at (816) 969-1800 to obtain the required permit.
|
|
DE Future Repair Work
Corrective Action Required
Please be aware that any future repair work to public infrastructure (e.g., water main repair, sanitary sewer repair, storm sewer repair, etc.) within public easements will not necessarily include the repair of pavement, curbing, landscaping, or other private improvements which are located within the easement.
|
|
DE C&O #12 Cut & Fill
Corrective Action Required
Any cut and / or fill operations, which cause public infrastructure to exceed the maximum / minimum depths of cover shall be mitigated by relocating the infrastructure vertically and / or horizontally to meet the specifications contained within the City’s Design and Construction Manual.
|
|
|
Building Codes Review
|
No Comments
|
06/19/2020
|
06/16/2020
|
|
Joe Frogge
|
|
|
Traffic Review
|
No Comments
|
06/19/2020
|
06/16/2020
|
|
Michael Park
|
|
|
Fire Review
|
Approved with Conditions
|
06/19/2020
|
06/15/2020
|
|
Jim Eden
|
|
Code Statement
All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2018 International Fire Code.
|
|
|
Building Codes Review
|
Corrections
|
03/06/2020
|
03/05/2020
|
|
Joe Frogge
|
|
Corrective Action Required
2018 IPC 708.1.2 Building sewers. Building sewers smaller than 8 inches shall have cleanouts located at intervals of not more than 100 feet. Building sewers 8 inches and larger shall have a manhole located not more than 200 feet from the junction of the building drain and the building sewer and at intervals of not more than 400 feet. The interval length shall be measured from the cleanout or manhole opening, along the developed length of the piping to the next drainage fitting providing access for cleaning, a manhole or the end of the building sewer.
Action required: Provide additional cleanouts in sanitary sewer piping to comply.
|
|
|
Planning Review
|
Corrections
|
03/06/2020
|
03/05/2020
|
|
Shannon McGuire
|
|
Corrective Action Required
All plan sheets should be a maximum of 24” x 36” with one inch border. Sheet L1 exceeds this requirement.
|
|
Corrective Action Required
Please submit a photometric diagram that shows the foot candle levels throughout the site and at the property lines.
|
|
Corrective Action Required
Is any ground or roof mounted equipment being proposed? If so please provide the location, size, and type of material to be used in all screening of mechanical equipment. Also, please submit the manufacturer’s specification sheets for proposed mechanical equipment to be used.
|
|
Corrective Action Required
Please add the total impervious coverage to the site data table.
|
|
Corrective Action Required
1 tree shall be planted for each 30 feet of street frontage. 9 trees are required along NW Ambersham Dr. You graphically show 9 trees but the not stated you are only providing 8. This may be a typo. Please confirm you will be providing the required 9 trees.
|
|
Corrective Action Required
The plat that covers this tract must be recorded prior to the issuance of building permits.
|
|
|
Traffic Review
|
Corrections
|
03/06/2020
|
03/03/2020
|
|
Michael Park
|
|
Corrective Action Required
Recommend the inclusion of a bicycle rack installation as previously considered during the PDP approval.
|
|
|
Fire Review
|
Approved with Conditions
|
03/06/2020
|
03/02/2020
|
|
Jim Eden
|
|
Code Statement
Corrective Action Required
All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2018 International Fire Code.
|
|
|
Engineering Review
|
Corrections
|
03/06/2020
|
02/27/2020
|
|
Gene Williams, P.E.
|
|
Corrective Action Required
Sheet C04: How does the proposed grading on this project fit with the approved Master Drainage Plan for Woodside Ridge 1st Plat? Has this been checked to ensure the grading is in accordance with the Master Drainage Plan for Woodside Ridge 1st, and in particular, along the western boundary?
|
|
Corrective Action Required
Sheet C08: It appears Note 14 is calling-out a shade structure, in what actually appears to be an ADA-accessible ramp. Please reconcile.
|
|
Corrective Action Required
Sheet C09: A plan and profile is required for all storm lines greater than 6 inches diameter.
|
|
Corrective Action Required
Sheet C10: Inlet protection is shown in a very critical location (i.e., the sump). In addition, it is not clear what form of inlet protection is being proposed. Please clarify, and ensure the inlet protection is not going to act as a dam during rain events, creating a flood hazard in the sump condition.
|
|
Corrective Action Required
Sheet C11: Stabilized subgrade is called-out on the typical section views of the pavement. To eliminate any confusion on this requirement, please add the word "chemically" in front of "stabilized subgrade". In lieu of chemically-stabilized subgrade, you may also want to consider geogrid.
|
|
Corrective Action Required
Landscape Plan: The landscape plan does not show the water line in reference to the tree placement. However, it appears certain there are conflicts in regard to the minimum five (5) foot distance between the outside of the water main, and the outside of the mature tree trunk. Most of the trees along Ambersham Dr. are directly on top of the water main, which is considered an encroachment.
|
|
Corrective Action Required
An itemized and sealed Engineer's Estimate of Probable Construction Costs should accompany your final submittal drawings. The Engineering Plan Review and Inspection Fee is based on this estimate, and calculated at 3% of the total, plus a right of way fee in the amount of $80. Items to include on the estimate include: 1) grading to establish proper drainage, 2) grading for parking lot, 3) pavement, 3) subgrade preparation either chemically-stabilized or geogrid, including the area one (1) foot beyond the back of curb, 4) aggregate base, including the area one (1) foot beyond the back of curb, 5) curb and gutter, 6) storm lines greater than 6 inches in diameter, 7) storm structures, including inlets, 8) private sanitary sewer lines and tracer wire and box, 9) private water lines, 10) erosion and sediment control measures and devices, 11) final restoration, including sodding, seeding, topsoil, fertilizer, mulch.
|
|
|