Planning Application Status

PL2019414




 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PL2019414
MAIN ORCHARD - MASTER DRAINAGE PLAN
Engineering Plan Review
Engineering Plan Review
Approved
12/12/2019
FIVE THIRTY LLC
6 Lot single family development
Locations
Contacts
FIVE THIRTY LLC, Address:50 SE 30TH ST  
ENGINEERING SOLUTIONS, Address:50 SE 30TH ST, Phone:(816) 623-9888  
ENGINEERING SOLUTIONS, Address:50 SE 30TH ST, Phone:(816) 623-9888  
Reviews
Review Type Outcome Est. Completion Date Completed
Engineering Review Approved with Conditions 01/22/2020 01/22/2020
Gene Williams, P.E.
Engineering Review Corrections 01/13/2020 01/10/2020
Gene Williams, P.E.
Corrective Action Required
01/10/2020

The plans show a lack of detail concerning the construction of the detention pits. Although the overall concept appears acceptable, detailed design drawings were missing. Missing items include the following: 1) a 12 inch drain pipe is shown entering the pit, without any reference to minimum slope, connection to the downspout header, pipe type, and bedding, 2) the 1 inch outlet pipe is shown without any concrete flared section at the end, which we feel is required due to the fragile nature of this small pipe, and overall longevity of the pipe where it daylights, 3) inconsistent material call-outs for the rock (i.e., the report specifies 1.5 inch to 2.5 inch clean rock, but the plan calls for 1 foot of 6 inch river rock, which does not appear to make sense), 4) a 12 inch round grate top is specified, but no other information is provided (we recommend a cast iron grate for this application), 5) plantings are specified, but no further information is supplied concerning the type of plantings, 6) 12 inch drain pipe appears to be installed near the surface, 7) the elevation view shows 12 inches (i.e., 1 foot) of topsoil, but this does not scale properly when examining the elevation view (i.e., when adding up the thickness of 1 foot of topsoil, this would force the 1 inch outlet pipe to be placed immediately beneath the topsoil, thus rendering it useless in terms of draining the clean rock within the detention pit).
Corrective Action Required
01/10/2020

It would appear the 1 inch outlet pipe will need to be placed at a much lower elevation than shown on the elevation view. This will increase the distance needed to reach a daylight condition.
Corrective Action Required
01/10/2020

A plan and profile view is required for the outlet pipe.
Corrective Action Required
01/10/2020

A plan and profile view is required for the 12 inch drain pipe.
Corrective Action Required
01/10/2020

The 12 inch drain pipe material must be specified, along with the slope.
Corrective Action Required
01/10/2020

the 1 inch outlet pipe must show the slope and daylight location.
Corrective Action Required
01/10/2020

Shouldn't the detention pit outlet pipe located on the extreme southwest lot be directed more toward the right of way?
Corrective Action Required
01/10/2020

Shouldn't the detention pit outlet pipe located on the lot immediately north of the lot previously discussed, be directed more northerly to align with the existing swale?
Corrective Action Required
01/10/2020

Sheet C.201: It was our understanding that the detention pits were going to be placed in a sump condition. It does not appear any information in the form of contours or finish elevations were provided showing how this will be accomplished.
Corrective Action Required
01/10/2020

Sheet C.201: Existing elevations were provided for the lot corners, but finish elevations are also required, even if the existing elevation will not change.
Corrective Action Required
01/10/2020

The Engineer's Estimate of Probable Construction Costs appeared low for the following unit prices: 1) detention pit and grading. The unit price of $1,200 appears extremely low based on the fact that these pits will consist of 12 inch stormwater pipe, grate, tees, rock, filter fabric, outlet pipe, plantings, and end of outlet pipe treatment.
Engineering Review Corrections 12/27/2019 12/26/2019
Gene Williams, P.E.
Corrective Action Required
12/26/2019

The Master Drainage Plan was submitted in conjunction with the sanitary sewer extension plans. The Master Drainage Plan should be a separate, standalone plan. As discussed in previous phone calls, construction of the detention pits shall be performed during individual home construction, and as such, a standalone plan is required.
Corrective Action Required
12/26/2019

No detail whatsoever was provided concerning the construction of the detention pits. Dimensions were missing, materials, depth, etc.
Corrective Action Required
12/26/2019

No further review is being conducted at this time, due to the incomplete nature of these plans. Detention pits are not even called-out, nor are there any notes concerning the deferred construction during the construction of individual homes.
Hearings
Title Location Date Time
Documents & Images
Date Uploaded File Type Document Name
12/12/2019 Letter Routing Sheet - FDP
12/12/2019 Receipt Receipt for transaction: 2019-007697
12/12/2019 Plans C.001
12/12/2019 Plans C.050
12/12/2019 Plans C.051
12/12/2019 Plans C.052
12/12/2019 Plans C.100
12/12/2019 Plans C.200
12/12/2019 Plans C.201
12/12/2019 Plans C.202
12/12/2019 Plans C.400
12/12/2019 Plans C.401
12/12/2019 Plans C.402
12/12/2019 Plans C.403
12/12/2019 Plans FDP Storm Water Letter 191211
12/26/2019 Letter DE-Comment Letter (Engineering Plans)
12/27/2019 Letter Resubmittal Routing Sheet
12/27/2019 Plans C.200
12/27/2019 Plans C.201
12/27/2019 Plans C.202
12/27/2019 Plans MAIN ORACHARD MDP
12/27/2019 Plans C.001
12/27/2019 Plans C.100
01/10/2020 Letter DE-Comment Letter (Engineering Plans)
01/14/2020 Plans CIVIL PLANS 1-13-20
01/14/2020 Letter Resubmittal Routing Sheet
01/22/2020 FeeWorksheetMDP
01/29/2020 Plans CIVIL PLANS 1-13-20
01/30/2020 Plans Drainage Study 191029
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New license, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home