Review Type |
Outcome |
Est. Completion Date |
Completed |
Traffic Review
|
No Comments
|
06/03/2019
|
06/03/2019
|
|
Mike Weisenborn
|
|
|
Engineering Review
|
No Comments
|
06/03/2019
|
06/03/2019
|
|
Gene Williams, P.E.
|
|
|
Traffic Review
|
Corrections
|
03/21/2019
|
03/27/2019
|
|
Michael Park
|
|
Corrective Action Required
Include additional construction sequencing notes on the Signal General Notes Sheet, for example:
1. The traffic signal shall remain fully operational with exception of the hourly period for relocation of poles/equipment as described on the traffic control plans.
2. All signal installation and relocation work must be completed prior to construction of roadway improvements due to the removals of existing signal boxes and foundations associated with roadway improvements.
3. Prior to any signal pole or post relocation all new foundations or bases, conduits, pull boxes and cabling/wiring shall be installed for an expedient relocation process that minimizes separation and reconnection time (or downtime of signal operations).
|
|
Corrective Action Required
The existing pedestrian push buttons are not ADA compliant and should be replaced if/where the pole is relocated.
|
|
Corrective Action Required
The signal quantities sheet is missing some information (e.g. ground rods, estimate of lighting cable, ground wire, video/power cabling). Also field verify the type of cables required for the existing video system and note on the plans.
|
|
|
Engineering Review
|
No Comments
|
03/21/2019
|
03/21/2019
|
|
Gene Williams, P.E.
|
|
|
Traffic Review
|
Corrections
|
12/26/2018
|
12/26/2018
|
|
Gene Williams, P.E.
|
|
Corrective Action Required
Add a R2-1 (25 mph) on westbound NW O’Brien Rd at an appropriate distance from NW Pryor Rd.
|
|
Corrective Action Required
The three lane section on NW O’Brien Rd should be extended to approximately 29+50 in order to plan for the future commercial entrances into West Village.
|
|
Corrective Action Required
On NW O’Brien, transition from CG2 to CG1 over a distance of ten feet from the PC at the intersection of NW O’Brien Rd and NW Ambersham Dr.
|
|
Corrective Action Required
Provide a traffic control plan for any impacts to NW Pryor Rd and / or NW O’Brien Rd.
|
|
|
Engineering Review
|
Corrections
|
12/26/2018
|
12/26/2018
|
|
Gene Williams, P.E.
|
|
Corrective Action Required
Sheet 1: Please delete the Public Works "Utility Service Number", and replace it with "Development Services 816-969-1200".
|
|
Corrective Action Required
Sheet 5 and 6: CG-2 curb and gutter is called-out. O'Brien is a commercial local road. Please show CG-1 curb and gutter. Also, show where the CG-1 curb and gutter will transition to the CG-2 curb and gutter on the plan view.
|
|
Corrective Action Required
Sheet 5 and 6: Label each typical section for O'Brien as "Commercial Local".
|
|
Corrective Action Required
Sheet 5 and 6: A commercial local street requires 7.5 inch base course asphaltic concrete, not 5.5 inches. Also, the surface course should be specified as Type 5 or 6, and the base course Type 5. Finally, the widened portion on typical section view from station 31+40 to 33+74 shows a 6 inch concrete strip, capped with a surface course of asphaltic concrete. The minimum thickness for the concrete should be specified as 8 inches KCMMB, and also clarify the subgrade design. It is not defined for that portion.
|
|
Corrective Action Required
Sheet 6: Please label the Pryor Rd. section view as "Arterial Roadway Section".
|
|
Corrective Action Required
Sheet 6: Arterial street widening projects require the developer to match existing conditions. Were Record Drawings consulted to determine the original design? Where is the pavement jointing and sawcut plan? Where are the existing pavement joints in relation to these?
|
|
Corrective Action Required
As commented above, a plan must be provided showing existing joints and sawcuts along Tudor Rd., and the joint patterns and sawcuts to be established with this project, along with any dowels or rebar. We will not allow a field-design.
|
|
Corrective Action Required
The ADA-accessible ramps on the west side of Pryor Rd. do not appear to match-up with the existing ADA-accessible route across Pryor Rd. How will this be addressed?
|
|
Corrective Action Required
What is the existing cross-slope and width across O'Brien at the intersection of Pryor Rd. and O'Brien, and how will this stop-controlled intersection be designed to maintain no greater than 1.5% cross-slope, and 5 feet minimum width?
|
|
Corrective Action Required
Is the intent to re-use the existing ADA-accessible ramps on the west side of Pryor Rd. as the ADA-accessible route across Pryor Rd.? If so, do these ramps meet current City requirements in terms of cross-slope and running slope of the ramp? Width of the ramp? If not, then these must be upgraded with these improvements.
|
|
Corrective Action Required
Sheet 11: The City has adopted a more stringent standard for design than PROWAG. Please see Section 5304.8 of the Design and Construction Manual for details, including the bullet point items needed for plans, with design criteria listed on Table LS-5 of the same section. In general, the City requires no more than a design cross-slope of 1.5% in all directions of an ADA-accessible ramp, and no more than 7.5% running slope. A minimum 5.0 feet width is also required. It appears there are instances on this sheet where the design criteria are not met.
|
|
Corrective Action Required
Sheet 11: Please see the above comments concerning the ADA-accessible ramp details. Section 5304.8 requires that plans include the bullet point items in the design, including cross-sections along the long axis, width, and curb opening of the ramp.
|
|
Corrective Action Required
Please delete the standard ADA-accessible ramp details from the plans. These are only used in retrofit cases, where site-specific designs are not provided. In the case of this project, site-specific designs for the ADA-accessible ramps and ADA-accessible routes across stop-control intersections are required.
|
|
Corrective Action Required
What is the cross-slope of Pryor Rd. across the ADA-accessible routes? No more than 1.5% cross-slope is allowed at this stop-controlled intersection. A minimum width of 5 feet is required. Please show this on the plans.
|
|
Corrective Action Required
Sheet 16: This is supposed to be an erosion and sediment control plan, but nothing is shown other than a plan view of the project.
|
|
Corrective Action Required
O'Brien Rd. is well over 400 feet in length, and a storm sewer should be installed to collect stormwater, and tie into the storm sewer of Woodside Ridge 1st Plat. It appears that a minimum of two (2) curb inlets are required along O'Brien Rd., on each side of the street.
|
|
Corrective Action Required
Sheet 8: It is not clear what is being done to modify the existing curb inlet within the widened portion of the turn lane. Is the existing curb inlet being removed? Please provide sufficient details for this portion of the project so there is no uncertainty concerning expectations of the contractor.
|
|
Corrective Action Required
Sheet 8: A note is provided stating "relocate signal". Wouldn't it be a good idea to provide the sheet number where details concerning this relocation are provided?
|
|
Corrective Action Required
General CommentP: Please go over the plans and ensure missing items necessary to construct this project are provided. From our standpoint, the plans are incomplete.
|
|
|