Review Type |
Outcome |
Est. Completion Date |
Completed |
Planning Review
|
No Comments
|
07/13/2017
|
07/14/2017
|
|
Christina Stanton
|
|
|
Engineering Review
|
Approved with Conditions
|
07/13/2017
|
07/14/2017
|
|
Sue Pyles, P.E.
|
|
DE C&O #11 Pavement Thickness
Corrective Action Required
Private pavement sections shall either follow Article 12 of the UDO or Table LS-2 or LS-3 of the Design & Construction Manual for pavement thickness and base requirements.
|
|
DE Contact Field Eng. Inspector
Corrective Action Required
Contact Public Works Inspections at (816) 969-1800 at least 48 hours prior to the onset of construction.
|
|
DE Contact ROW Inspector
Corrective Action Required
Contact a Right-of-Way Inspector at (816) 969-1800 prior to any land disturbance within the right-of-way. These activities may require a permit.
|
|
DE Engineers Estimate
Corrective Action Required
The Engineer’s Estimate of Probable Construction Costs has been accepted for this project, and the Public Works Review and Inspection Fee of $12,662.84 (which is based on 3% of the total infrastructure cost plus a water test inspection fee) must be paid prior to the issuance of an infrastructure permit and/or the final processing of a building permit from the Codes Administration Department.
|
|
DE Future Repair Work
Corrective Action Required
Please be aware that any future repair work to public infrastructure (e.g., water main repair, sanitary sewer repair, storm sewer repair, etc.) within public easements will not necessarily include the repair of pavement, curbing, landscaping, or other private improvements which are located within the easement.
|
|
|
Fire Review
|
Approved with Conditions
|
07/13/2017
|
07/13/2017
|
|
Jim Eden
|
|
Misc.
Corrective Action Required
Any fencing or barrier around the facility shall not prevent immediate access to a hydrant from the parking lot.
For information only.
|
|
|
Traffic Review
|
No Comments
|
07/13/2017
|
07/07/2017
|
|
Michael Park
|
|
|
Fire Review
|
Approved with Conditions
|
06/27/2017
|
06/27/2017
|
|
Jim Eden
|
|
Misc.
Corrective Action Required
Any fencing or barrier around the facility shall not prevent immediate access to a hydrant from the parking lot.
For information only.
|
|
|
Engineering Review
|
Corrections
|
06/27/2017
|
06/27/2017
|
|
Sue Pyles, P.E.
|
|
Corrective Action Required
Revise the Storm Water Drainage Analysis report to address the 40-hour extended detention of runoff from the local 90% mean annual event (1.37"/24-hour rainfall), per the Design and Construction Manual Section 5608.
|
|
Corrective Action Required
Sheet 4: Revise the Berm Section A-A to meet the requirements of APWA ESC-05.
|
|
Corrective Action Required
Sheet 5: Include the joint details and notes from Standard Detail GEN-3A on this sheet. Label the thickness and include the tie-bars in Section A-A.
|
|
Corrective Action Required
Sheet 8: Include a note requiring trench checks at the sanitary sewer service lines.
|
|
Corrective Action Required
Sheet 8: Label the wye connection to the existing main to a "cut-in."
|
|
Corrective Action Required
Sheet 10: Revise the APWA ESC detail numbers to match current standard details. Revise the erosion control methods for the swale, silt fence is not allowed for that use.
|
|
Corrective Action Required
Sheets 12-13: Delete GEN 3A & 3B, they are for retrofit only.
|
|
Corrective Action Required
Include sanitary sewer standard detail SAN-1 in the plan set.
|
|
Corrective Action Required
Submit a revised Engineer's Estimate of Probable Construction Costs per all review comments.
|
|
|
Traffic Review
|
No Comments
|
06/27/2017
|
06/27/2017
|
|
Michael Park
|
|
|
Planning Review
|
Approved with Conditions
|
06/27/2017
|
06/27/2017
|
|
Christina Stanton
|
|
Corrective Action Required
Provide a copy of the spec sheets for the mechanical units. The units shall be screened per Section 7.180.F of the UDO, "...by landscaping or masonry wall up to a height of the units to be screened."
Provide details of the gates used elsewhere on the site and the screening wall.
|
|
|
Engineering Review
|
Corrections
|
06/07/2017
|
06/08/2017
|
|
Sue Pyles, P.E.
|
|
Corrective Action Required
Sheet 3: Revise the General Notes to remove references to future Final Development Plans, as this is the FDP.
|
|
Corrective Action Required
Sheet 3: Revise "Oldham Road" to "SE Oldham Parkway" in the "Streets" note.
|
|
Corrective Action Required
Sheet 4: Grading Plan must include all proposed grading. Revise to show the swale grading on the west side.
|
|
Corrective Action Required
Sheet 4: Include a legend to identify the different dashed lines included in the drawing.
|
|
Corrective Action Required
Include ADA-accessible sidewak ramp details and information to meet the Design and Construction Manual Section 5300 requirements. Include all information required by 5304.8 and Table LS-5.
|
|
Corrective Action Required
Include a Drainage Area Map and storm sewer calculations in the plan set.
|
|
Corrective Action Required
Storm Water Drainage Analysis: Include a Drainage Area Map as well as enough information in the summary to indicate that all requirements of the Design and Construction Manual Section 5608, including Section 5608.4.C.1, have been met.
|
|
Corrective Action Required
Storm Water Drainage Analysis: Include design information and summarize drainage addressed with the proposed swale.
|
|
Corrective Action Required
Include swale cross section design in the plan set.
|
|
Corrective Action Required
Include standard details for all storm drinage structures.
|
|
Corrective Action Required
Include structural details for construction of all non-standard structures, which include the Baffle Box Structures 1A & 1C.
|
|
Corrective Action Required
Include required storm sewer riprap dimensions in the plan set.
|
|
Corrective Action Required
Engineer's Estimate of Probable Construction Costs: Provide separate items for storm sewer riprap and ESC construction entrance.
|
|
Corrective Action Required
Sheet 8: Provide erosion and sediment control for the proposed swale as well as proposed storm sewer structures.
|
|
Corrective Action Required
Sheet 5 shows Str. 2B as a 5' Dia. MH, but the cost estimate includes a 4' Dia. MH. Revise as needed.
|
|
Corrective Action Required
Sheet 5 shows Str. 2D as a 12" HDPE End Section, but the cost estimate includes a 15" HDPE End Section (which matches the storm pipe size). Revise as needed.
|
|
Corrective Action Required
Sheet 6: Show the water meter location, which must be located within the easement.
|
|
Corrective Action Required
Sheet 6: Provide enough information to verify the proposed alignment for the relocated sanitary sewer line for Skate Center will meet the minimum slope requirements.
|
|
|
Planning Review
|
Corrections
|
06/07/2017
|
06/07/2017
|
|
Christina Stanton
|
|
Corrective Action Required
Clean up comments on the Dimension Plan (Sheet 3 of 9). Several of the "General Notes" refer to things being updated at/on the final development plan. In addition, correct Oldham "Road" to "Parkway" under "Streets".
|
|
Corrective Action Required
Provide spec sheets for the roof-mounted units (RTUs).
|
|
Corrective Action Required
Staff recommends providing a variety of different species of trees and shrubs.
|
|
|
Fire Review
|
Corrections
|
06/07/2017
|
06/07/2017
|
|
Jim Eden
|
|
Code Statement
Corrective Action Required
All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2012 International Fire Code .
|
|
Fire Lanes
Corrective Action Required
IFC 503.2.1 - Fire apparatus access roads shall have an unobstructed width of not less than 20 feet (6096 mm), exclusive of shoulders, except for approved security gates in accordance with Section 503.6, and an unobstructed vertical clearance of not less than 13 feet 6 inches (4115 mm)
Action required: The drive (Oldham Court) shall have a 20 foot drive surface.
|
|
Knox Locks
Corrective Action Required
IFC 506.1 -Where access to or within a structure or an area is restricted because of secured openings or where immediate access is necessary for life-saving or fire-fighting purposes, the fire code official is authorized to require a key box to be installed in an approved location. The key box shall be of an approved type listed in accordance with UL 1037, and shall contain keys to gain necessary access as required by the fire code official.506.1.1 Locks.An approved lock shall be installed on gates or similar barriers when required by the fire code official.
Action required: Knox padlocks shall be provided on the gates
|
|
Fire Lanes - Marking
Corrective Action Required
IFC 503.3- Where required by the fire code official, approved signs or other approved notices or markings that include the words NO PARKING—FIRE LANE shall be provided for fire apparatus access roads to identify such roads or prohibit the obstruction thereof. The means by which fire lanes are designated shall be maintained in a clean and legible condition at all times and be replaced or repaired when necessary to provide adequate visibility.
Action required: The lane towards the fire hydrant shall be posted. It is recommended that the hydrant be moved to the lane fronting the building to keep the hydrant from being obstructed and would allow for future development of the lot to the west.
|
|
Hydrants
Corrective Action Required
IFC 507.5.1- Where a portion of the facility or building hereafter constructed or moved into or within the jurisdiction is more than 300 feet from a hydrant on a fire apparatus access road, as measured by an approved route around the exterior of the facility or building, on-site fire hydrants and mains shall be provided where required by the fire code official.
It is recommended that the hydrant be moved to the lane fronting the building to keep the hydrant from being obstructed and allow for future development of the lot to the west.
|
|
Imposed Loads
Corrective Action Required
IFC 503.2.3 -Fire apparatus access roads shall be designed and maintained to support the imposed loads of fire apparatus and shall be surfaced so as to provide all-weather driving capabilities.
Action required: Confirm paving type on the fire lane.
|
|
|
Traffic Review
|
Approved with Conditions
|
06/07/2017
|
06/06/2017
|
|
Michael Park
|
|
Suggest providing a sidewalk connection from the site to the public sidewalk.
|
|
|