Summary
PL2015180
LEE'S SUMMIT HONDA PARKING LOT ADDITION
Commercial Final Development Plan
Commercial Final Development Plan
Approved
11/20/2015
JOHN OHRAZDA
NOTE: FDP & BUILDING PERMITS CANNOT BE ISSUED UNTIL: 1. A FULLY EXECUTED LEASE AGREEMENT HAS BEEN SIGNED BY THE CITY/AIRPORT AND LS HONDA. - Lease executed 8/22/16 and by Ordinance #7942. 2. THE SUP APPLCIATION PL2015197 HAS BEEN APPROVED BY COUNCIL. CHRIS HUGHEY 11/24/2015
Locations
Contacts
DAVIDSON ARCHITECTURE & ENGINEERING, Address:4301 INDIAN CREEK PKWY, Phone:(913) 451-9390  
JOHN OHRAZDA, Address:LEE'S SUMMIT AIRPORT, Phone:(816) 969-1180  
DAVIDSON ARCHITECTURE & ENGINEERING - PAUL MILLER, Address:4301 INDIAN CREEK PKWY, Phone:(913) 451-9390  
DAVIDSON ARCHITECTURE & ENGINEERING, Address:4301 INDIAN CREEK PKWY, Phone:(913) 451-9390  
Reviews
Review Type Outcome Est. Completion Date Completed
Engineering Review Approved with Conditions 10/14/2016 10/14/2016
Gene Williams, P.E.
DE Engineers Estimate
Corrective Action Required
10/14/2016

The Engineer’s Estimate of Probable Construction Costs has been accepted for this project, and the Public Works Review and Inspection Fee of $1,144.52 (which is based on 3% of the total infrastructure cost) must be paid prior to the issuance of an infrastructure permit and/or the final processing of a building permit from the Codes Administration Department. Please be aware that a $9,323.50 credit was applied for payment already tendered.
DE Contact Field Eng. Inspector
Corrective Action Required
10/14/2016

Contact Public Works Inspections at (816) 969-1800 at least 48 hours prior to the onset of construction.
DE Contact ROW Inspector
Corrective Action Required
10/14/2016

Contact a Right-of-Way Inspector at (816) 969-1800 prior to any land disturbance within the right-of-way. These activities may require a permit.
DE C&O #12 Cut & Fill
Corrective Action Required
10/14/2016

Any cut and / or fill operations, which cause public infrastructure to exceed the maximum / minimum depths of cover shall be mitigated by relocating the infrastructure vertically and / or horizontally to meet the specifications contained within the City’s Design and Construction Manual.
DE Future Repair Work
Corrective Action Required
10/14/2016

Please be aware that any future repair work to public infrastructure (e.g., water main repair, sanitary sewer repair, storm sewer repair, etc.) within public easements will not necessarily include the repair of pavement, curbing, landscaping, or other private improvements which are located within the easement.
PW Submit Land Disturbance (DELETE)
Corrective Action Required
10/14/2016

Submit a Land Disturbance Permit application and the required attachments to the City prior to any land disturbance activities on the site.
Planning Review No Comments 10/06/2016 10/10/2016
Hector Soto Jr.
Engineering Review Corrections 10/06/2016 10/06/2016
Gene Williams, P.E.
Corrective Action Required
10/06/2016

Please refer to the previous applicant letter dated Sept. 27, 2016. Is the stormwater system sufficient to manage stormwater on a 2.8 acre site? It would appear an additional inlet would be required since all of the stormwater will be directed to the northwest corner of the site. The response dated Sept. 28, 2016 made reference to Sheet C3.1, but this sheet shows calculations for the stormwater detention system. In general, an inlet should be positioned to capture no more than 2 acres of drainage area. Otherwise, there is concern that the system will be overloaded.
Fire Review No Comments 10/06/2016 10/05/2016
Jim Eden
Traffic Review No Comments 10/06/2016 10/05/2016
Michael Park
Engineering Review Corrections 09/27/2016 09/27/2016
Hector Soto Jr.
Corrective Action Required
09/27/2016

Sheet C3.1: Proposed and existing grades do not appear to have shown up on the profile view. Please correct.
Corrective Action Required
09/27/2016

Is the stormwater system sufficient to manage stormwater on a 2.8 acre site? It would appear an additional inlet would be required.
Corrective Action Required
09/27/2016

An Engineer's Estimate of Probable Construction Costs (revised) should be submitted along with your final submittal drawings.
Planning Review No Comments 09/27/2016 09/27/2016
Hector Soto Jr.
Fire Review No Comments 09/27/2016 09/27/2016
Jim Eden
Traffic Review No Comments 09/27/2016 09/21/2016
Michael Park
Engineering Review Corrections 09/02/2016 09/02/2016
Gene Williams, P.E.
Corrective Action Required
09/02/2016

Sheet C3.1: Proposed and existing grades do not appear to have shown up on the profile view. Please correct.
Corrective Action Required
09/02/2016

Is the stormwater system sufficient to manage stormwater on a 2.8 acre site? It would appear an additional inlet would be required.
Corrective Action Required
09/02/2016

An Engineer's Estimate of Probable Construction Costs (revised) should be submitted along with your final submittal drawings.
Planning Review Corrections 09/02/2016 09/01/2016
Ron Seyl
Corrective Action Required
09/01/2016

Label the width of the southern most drive isle on Sheet C1.1
Corrective Action Required
09/01/2016

Label the parking lot setback from the south property line.
Corrective Action Required
09/01/2016

- Submit a revised photometric plan that includes the proposed lighting for the additional portion of the parking lot. The photometric diagram shall indicate the foot candle levels throughout the site and at the property lines. - The revised photometric plan shall include the location, height, intensity and type of outside lighting fixtures for the entire parking lot addition. - Include additional specification sheets if the light fixtures and wattage on the addtional parking lot area differ from what was proposed on the intial parking lot.
Traffic Review No Comments 09/02/2016 08/30/2016
Michael Park
Fire Review Complete 09/02/2016 08/29/2016
Jim Eden
Traffic Review No Comments 09/01/2016 08/25/2016
Ron Seyl
Fire Review No Comments 09/01/2016 08/25/2016
Ron Seyl
Engineering Review Approved with Conditions 09/01/2016 08/25/2016
Ron Seyl
DE Engineers Estimate
Corrective Action Required
08/25/2016

The Engineer’s Estimate of Probable Construction Costs has been accepted for this project, and the Public Works Review and Inspection Fee of $9,323.50 (which is based on 3% of the total infrastructure cost) must be paid prior to the issuance of an infrastructure permit and/or the final processing of a building permit from the Codes Administration Department.
DE Contact Field Eng. Inspector
Corrective Action Required
08/25/2016

Contact Public Works Inspections at (816) 969-1800 at least 48 hours prior to the onset of construction.
DE Contact ROW Inspector
Corrective Action Required
08/25/2016

Contact a Right-of-Way Inspector at (816) 969-1800 prior to any land disturbance within the right-of-way. These activities may require a permit.
DE Future Repair Work
Corrective Action Required
08/25/2016

Please be aware that any future repair work to public infrastructure (e.g., water main repair, sanitary sewer repair, storm sewer repair, etc.) within public easements will not necessarily include the repair of pavement, curbing, landscaping, or other private improvements which are located within the easement.
PW Submit Land Disturbance (DELETE)
Corrective Action Required
08/25/2016

Submit a Land Disturbance Permit application and the required attachments to the Erosion Control Specialist prior to any land disturbance activities.
DE C&O #12 Cut & Fill
Corrective Action Required
08/25/2016

Any cut and / or fill operations, which cause public infrastructure to exceed the maximum / minimum depths of cover shall be mitigated by relocating the infrastructure vertically and / or horizontally to meet the specifications contained within the City’s Design and Construction Manual.
Planning Review No Comments 09/01/2016 08/25/2016
Ron Seyl
Planning Review Corrections 06/15/2016 06/15/2016
Ron Seyl
Corrective Action Required
06/14/2016

FDP APPROVAL Please note that the final development plan cannot be approved, nor can any necessary building permits be issued, for the parking lot addition until such time as the following items are completed: 1. A fully executed lease agreement for the subject parking lot site shall be signed by the City/Airport and Lee’s Summit Honda.
Engineering Review Approved with Conditions 06/15/2016 06/15/2016
Ron Seyl
DE Engineers Estimate
Corrective Action Required
06/15/2016

The Engineer’s Estimate of Probable Construction Costs has been accepted for this project, and the Public Works Review and Inspection Fee of $9,323.50 (which is based on 3% of the total infrastructure cost) must be paid prior to the issuance of an infrastructure permit and/or the final processing of a building permit from the Codes Administration Department.
DE Contact Field Eng. Inspector
Corrective Action Required
06/15/2016

Contact Public Works Inspections at (816) 969-1800 at least 48 hours prior to the onset of construction.
DE Contact ROW Inspector
Corrective Action Required
06/15/2016

Contact a Right-of-Way Inspector at (816) 969-1800 prior to any land disturbance within the right-of-way. These activities may require a permit.
DE Future Repair Work
Corrective Action Required
06/15/2016

Please be aware that any future repair work to public infrastructure (e.g., water main repair, sanitary sewer repair, storm sewer repair, etc.) within public easements will not necessarily include the repair of pavement, curbing, landscaping, or other private improvements which are located within the easement.
PW Submit Land Disturbance (DELETE)
Corrective Action Required
06/15/2016

Submit a Land Disturbance Permit application and the required attachments to the Erosion Control Specialist prior to any land disturbance activities.
DE C&O #12 Cut & Fill
Corrective Action Required
06/15/2016

Any cut and / or fill operations, which cause public infrastructure to exceed the maximum / minimum depths of cover shall be mitigated by relocating the infrastructure vertically and / or horizontally to meet the specifications contained within the City’s Design and Construction Manual.
Traffic Review No Comments 06/15/2016 06/15/2016
Michael Park
Fire Review No Comments 06/15/2016 06/09/2016
Jim Eden
Fire Review No Comments 05/02/2016 05/04/2016
Jim Eden
Planning Review Corrections 05/02/2016 05/02/2016
Ron Seyl
Corrective Action Required
05/01/2016

OPEN YARD SHRUBS Based on the Landscape Plan, 30 open yard shrubs are required but only 12 open yard shrubs are shown on the Plan. Please add an additional 18 open yard shrubs.
Corrective Action Required
05/02/2016

STREET FRONTAGE TREES Please submit a revised Landscaping Plan that show trees a minimum of five (5) feet from the existing 30" water transmission main, as measured from the outside of the transmission main, to the outside of the mature tree trunk. Indicate the location of the transmission main on the landscape plan, as well a note stating that all trees to be planted along NE Colbern Rd are to be planted a minimum of five (5) feet from the existing main. Please submit the normal number of copies of this plan for attachment to the existing plans.
Corrective Action Required
05/02/2016

FDP APPROVAL Please note that the final development plan cannot be approved, nor can any necessary building permits be issued, for the parking lot addition until such time as the following items are completed: 1. A fully executed lease agreement for the subject parking lot site shall be signed by the City/Airport and Lee’s Summit Honda.
Corrective Action Required
05/03/2016

All drive aisles shall be a minimum of 28' wide (back -of-curb to back-of-curb). All drives are shown as being 26' wide.
Traffic Review Approved with Conditions 05/02/2016 04/28/2016
Michael Park
Corrective Action Required
04/28/2016

Consider lowering the overall site elevation. There is unstable soil in the area, evident by adjacent land slide occurring. A lower site elevation would also eliminate future needs to regrade for adjacent trailways and coordination with borrow material for the airport expansion project.
Engineering Review Approved with Conditions 05/02/2016 04/28/2016
Gene Williams, P.E.
Corrective Action Required
04/28/2016

Please submit a revised Landscaping Plan that show trees a minimum of five (5) feet from the existing 30" water transmission main, as measured from the outside of the transmission main, to the outside of the mature tree trunk. It appears the trees are shown directly on top of this line. Please submit the normal number of copies of this plan for attachment to the existing plans.
DE Engineers Estimate
Corrective Action Required
04/28/2016

The Engineer’s Estimate of Probable Construction Costs has been accepted for this project, and the Public Works Review and Inspection Fee of $9,323.50 (which is based on 3% of the total infrastructure cost) must be paid prior to the issuance of an infrastructure permit and/or the final processing of a building permit from the Codes Administration Department.
DE Contact Field Eng. Inspector
Corrective Action Required
04/28/2016

Contact Development Inspections at (816) 969-1800 at least 48 hours prior to the onset of construction.
DE Contact ROW Inspector
Corrective Action Required
04/28/2016

Contact a Right-of-Way Inspector at (816) 969-1800 prior to any land disturbance within the right-of-way. These activities may require a permit.
DE Future Repair Work
Corrective Action Required
04/28/2016

Please be aware that any future repair work to public infrastructure (e.g., water main repair, sanitary sewer repair, storm sewer repair, etc.) within public easements will not necessarily include the repair of pavement, curbing, landscaping, or other private improvements which are located within the easement.
PW Submit Land Disturbance (DELETE)
Corrective Action Required
04/28/2016

Submit a Land Disturbance Permit application and the required plan, fees, and attachments to the Development Inspector. Since there is no building permit associated with this application, a separate Land Disturbance permit from the City shall be required.
DE C&O #12 Cut & Fill
Corrective Action Required
04/28/2016

Any cut and / or fill operations, which cause public infrastructure to exceed the maximum / minimum depths of cover shall be mitigated by relocating the infrastructure vertically and / or horizontally to meet the specifications contained within the City’s Design and Construction Manual.
Engineering Review Corrections 02/02/2016 02/02/2016
John Barker
Corrective Action Required
02/02/2016

Provide a detail of the orifice plate and attachment
Corrective Action Required
02/02/2016

Show proposed and existing grade on the profiles
Corrective Action Required
02/02/2016

Show crossing utilities on the profiles.
Corrective Action Required
02/02/2016

Corrective Action Required
02/02/2016

In the pavement sections, 12" compacted native subrade is not allowed.
Corrective Action Required
02/02/2016

Submit an sealed Engineer's Estimate of Probable Construction Cost, including all site work included in the project. The subgrade treatment included in the estimate should go to at least 1 foot beyond the back of curb.
Corrective Action Required
02/02/2016

The outlet structure orifice plate does not appear to match that which is shown in the report. It would appear the report is showing a 3.6 feet orifice plate, and the plans call for a 3.5 foot orifice plate.
Corrective Action Required
02/02/2016

What is meant by “orifice plate”? Is this circular? Is it rectangular?
Corrective Action Required
02/02/2016

The report and plans do not appear to show any 40 hour extended detention either within the discussion or calculations or the drawings.
Planning Review Corrections 02/02/2016 01/28/2016
Ron Seyl
Corrective Action Required
01/28/2016

STREET ADDRESS Correct the street address on Sheet C1.0 to: 301 NE Colbern Rd Lee's Summit, Jackson County, Missouri 64063
Corrective Action Required
01/28/2016

PROJECT SUMMARY TABLE In the project summary table, correct the site area to cover the entire parcel lease area of 2.78 acres. Correct the impervious surface calculation also.
Corrective Action Required
01/28/2016

SIDEWALK Label the sidewalk and sidewalk width of the sidewalk on the south side of NE Colbern Rd.
Corrective Action Required
01/28/2016

STREETS Label the centerline of NE Colbern Rd.
Corrective Action Required
01/28/2016

OIL/GAS WELLS Display the location of all oil and/or gas wells within the subject property. If none exist, please note that fact. Also, please note the source of information regarding the wells.
Corrective Action Required
01/28/2016

PARKING Periodically label the width and depth of the parking stalls on Sheet C1.1.
Corrective Action Required
02/01/2016

LINE WEIGHTS The line weights on the plans do not seem to match what is shown on the Property Legend on Sheet C1.1. Please correct.
Corrective Action Required
02/01/2016

LIGHTPOLE BASE Provide detail on the lightpole pedestal. Concrete pedestals/bases for parking lot lighting shall not exceed three (3) feet in height and shall be included in the maximum overall height.
Corrective Action Required
02/01/2016

LIGHTING WATTAGE Include a column on the Lumenaire Schedule that shows the wattage for each individual fixture. Per the City's Unified Development Ordinance, all fixtures on developments that adjoin commercial, uses and/or districts shall be limited to 400-Watts maximum per head, and the total aggregate wattage for multiple headed fixtures mounted on a single pole shall be limited to 800-Watts maximum. It appears that the wattage on a number of the proposed fixtures may exceed the 400-Watt maximum per head limit.
Corrective Action Required
02/01/2016

EXTERIOR DISPLAY LIGHTING 1. The display area lighting shall not exceed 25.0 footcandles with an average illumination to minimum illumination of not greater than 5.0:1. It appears that the footcandle levels shown on the photometric plan exceed the 25.0 footcandle maximum for the area of the lot just south of NE Colbern Rd. Revise the light fixtures and photometric plan to meet the City's exterior display lighting requirements. Also, submit lighting specification sheets for any new lighting being proposed.
Corrective Action Required
02/01/2016

FIXTURE HEIGHT Pole mounted fixtures shall not exceed 20 feet as measured from finish grade to the top of the light fixture. Concrete pedestals/bases shall not exceed three (3) feet in height and shall be included in the overall height. Is the "MH 21" shown below the fixture label indicating the height of the fixtures? If so, the fixture height needs to be lowered to meet UDO requirements.
Corrective Action Required
02/01/2016

FORM 7460 For any property within two miles of the airport, a Form 7460 shall be completed and submitted to the FAA, and comments received back prior to any construction.
Corrective Action Required
02/01/2016

LANDSCAPE ISLANDS on the Landscape Plan, provide the square footage of the landscape islands. Per UDO Section 14.110.A, landscape islands, strips or other planting areas shall be located within the parking lot and shall constitute at least five percent (5%) of the entire area devoted to parking spaces, aisles and driveways. The island shall be planted in trees, shrubs, grass, or ground cover, except for those areas that are mulched. Please indicate proposed island landscaping methods on the Landscape Plan.
Corrective Action Required
02/02/2016

LANDSCAPING REQUIREMENTS 1. The landscape plan shows that 26 trees are required for the street frontage and open yard. However, 25 trees are what is required based upon calculations from the City's Landscaping Worksheet. A copy of the worksheet will be provided along with the Applicant's Letter. 2. Ten street frontage trees are required, but only nine are shown on the Landscaping Plan. Please revise.
Corrective Action Required
02/02/2016

PARKING LOT SCREENING Based upon the Landscaping Plan, the City's parking lot screening requirements have not been met. Per Unified Development Ordinance Section 14.120 - Parking Lot Screening - For any parking lot designed or intended to accommodate five (5) cars or more and any area set aside for loading or unloading of trucks or vans, if such parking lot or loading area is visible from a street right-of-way, a visual screen shall be provided as required below: A. Screening to a height of two-and-one-half (2.5) feet must be provided along the edge of the parking lot or loading area closest to and parallel to the street. B. Screening shall be decorative and 100% opaque to a height of two-and-one-half (2.5) feet above the elevation of the parking/loading area or the street, whichever is highest. C. Screening may be provided in any of the following ways: 1. Planted only. A hedge consisting of at least twelve (12) shrubs per forty (40) linear feet that will spread into a continuous visual screen within two (2) growing seasons. Shrubs must be at least eighteen (18) inches tall at the time of planting and be of a species that will normally grow to at least two-and-one-half (2.5) feet in height at maturity and be suitable for the parking lot application. 2. Earthen berm. An earthen berm constructed to a height of two-and-one-half (2.5) feet above the adjacent elevation of the street or parking/loading area, whichever is highest, shall not exceed a slope of 3:1 and shall have a crown of at least two (2) feet. The berm shall be planted in ground covers and other plant materials to achieve a decorative effect to the satisfaction of the Director. 3. Wall. A wall of brick, stone, PVC plastic fencing or finished and textured concrete may be constructed to a height of two-and-one-half (2.5) feet and 100% opacity and landscaped with plant material to achieve a decorative effect to the satisfaction of the Director. 4. Combination. Any combination of hedge, berm or wall that effectively provides a visual screen of the parking lot or loading area to a height of two-and-one-half (2.5) feet and achieves a decorative effect through appropriate use of landscaping and plant material. D. The street-side screening treatment may be located within the landscape strip required under this Article along the front yard of the property. E. Berming and/or screening shall not encroach into the required sight triangle of streets or access drives. Please submit a revised Landscaping Plan that shows how the parking lot screening requirement will be met.
Corrective Action Required
02/02/2016

FDP APPROVAL Please note that the final development plan cannot be approved, nor can any necessary building permits be issued, for the parking lot addition until such time as the following items are completed: 1. A fully executed lease agreement for the subject parking lot site shall be signed by the City/Airport and Lee’s Summit Honda. 2. The special use permit (Appl. #PL2015-197) for auto sales on the subject parking lot site has been approved by the City Council. The special use permit application is currently scheduled to be heard by the City Council on February 18, 2016.
Fire Review No Comments 02/02/2016 01/26/2016
Jim Eden
Traffic Review No Comments 02/02/2016 01/19/2016
Michael Park
Planning Review Corrections 12/08/2015 01/19/2016
Chris Hughey
See incomplete letter.
Engineering Review Corrections 12/08/2015 01/19/2016
Chris Hughey
LEE'S SUMMIT HONDA PARKING LOT ADDITION See incomplete letter.
Fire Review Complete 12/08/2015 12/01/2015
Jim Eden
Code Statement
Corrective Action Required
12/01/2015

All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2012 International Fire Code .
See incomplete letter.
Traffic Review No Comments 12/08/2015 11/24/2015
Michael Park
See incomplete letter.
Fees
Paid Fees Amount Paid Owing Date Paid
9110077-Final Development Plan fee $600.00 $600.00 Paid 11/20/2015
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Hearings
Title Location Date Time
Documents & Images
Date Uploaded File Type Document Name
11/20/2015 Receipt Receipt for transaction: 2015-006214
11/20/2015 Letter Routing Sheet - FDP
12/10/2015 Letter PL2015-180 FDP LS Honda parking lot addition incomplete letter
01/19/2016 Letter Routing Sheet - FDP
02/02/2016 Letter Applicant Letter - FDP (DFDP)
04/25/2016 Letter Resubmittal Routing Sheet - FDP
05/04/2016 Letter Applicant Letter - FDP (DFDP)
06/08/2016 Letter Resubmittal Routing Sheet - FDP
06/15/2016 Letter Applicant Letter - FDP (DFDP)
08/25/2016 Agreement (executed) Lease with BFRE, LLC 8-22-2016
08/25/2016 Letter Applicant Letter - FDP (DFDP)
08/26/2016 Letter Resubmittal Routing Sheet - FDP
09/06/2016 Letter Applicant Letter - FDP (DFDP)
09/20/2016 Letter Resubmittal Routing Sheet - FDP
09/20/2016 Plans C1.1 - Civil Site Plan & Cover Sheet
09/20/2016 Plans Lee's Summit Honda Photometric plan
09/27/2016 Letter Applicant Letter - FDP (DFDP)
09/30/2016 Letter Resubmittal Routing Sheet - FDP
09/30/2016 Plans C1.0 - 13132Cbase-2
09/30/2016 Plans C2.1 - 13132Cbase-2
09/30/2016 Plans C3.1 - 13132C3Dbase
10/10/2016 Letter Applicant Letter - FDP (DFDP)
12/19/2016 Letter Applicant Letter - FDP (DFDP)
11/10/2017 Activity Document Fee WorksheetUpdatedDevCenter
11/10/2017 Activity Document Fee WorksheetUpdatedDevCenterREVISED
09/11/2019 LS Honda Building - Parking Lot Addition
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New license, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home