Summary


PRSUBD20226053
Public Infrastructure
Issued
HD DEVELOPMENT OF MARYLAND INC
DEVELOPMENT COMPLETE
LP Mart - Hamblen Rd Turn lanes on Hamblen Rd
12/09/2022
05/14/2024
Locations
Contacts
HD DEVELOPMENT OF MARYLAND INC, Address:PO BOX 105842  
ENGINEERING SOLUTIONS, Address:50 SE 30TH ST, Phone:(816) 623-9888  
MID-WEST ASSOCIATED CONTRACTORS CORPORATION, Address:900 NW HUNTER DR STE 25, Phone:(816) 229-6090  
  
Reviews
Review Type Outcome Est. Completion Date Completed
Licensed Contractors Approved 04/05/2024 04/15/2024
Mike Weisenborn
LION PETROLEUM CONVIENCE STORE
Fees
Paid Fees Amount Paid Owing Date Paid
9110073-Right of Way Permit Fee $85.00 $85.00 Paid 05/14/2024
9110068-Storm Fee $114.00 $114.00 Paid 05/14/2024
9110081-Paved Surface Inspection Fee $270.64 $270.64 Paid 05/14/2024
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Pavement-Proof Roll Pending
Grading/Excavation/Fill Inspection Pending
Install Street and Stop Signs Pending
Install Street and Stop Signs Pending
Pavement-Aggregate Base Pending
Pavement-Curb Construction Pending
Pavement-Stabilized Subgrade Pending
Storm Sewer Construction Inspection Pending
Site Visit Pending
Misc
Informational
08/07/2024
08/07/24 Wednesday JMJ Gas tanks were being installed a state inspector was onsite observing operation.
Erosion Control Inspection Pending
Misc
Informational
11/14/2024
11-14-24 BR Erosion control is up and working order.
Pavement-Surface Pending
Misc
Informational
12/16/2024
12-16-24 BR Contractor (Blacktop Paving Maintenance) poured 4'' of KCMMB A-3 on SE Hamblen Rd. turn lane section.
Install Street and Stop Signs Pending
Pavement-Aggregate Base Pending
Pavement-Curb Construction Pending
Pavement-Stabilized Subgrade Pending
Storm Sewer Construction Inspection Pending
Storm Sewer Construction Inspection Partial 11/13/2024 11/13/2024 11/13/2024
Misc
Informational
10/28/2024
10-28-24 BR Contractor excavated existing storm box on SE Hamblen Rd. to lower storm cover. Also contractor excavated for new storm box location with installing rebar for storm box floor. 10-31-24 BR Contractor poured storm box walls and invert on new storm box. 11-5-24 BR Contractor installed storm box lid on new storm box structure. The existing storm box was cut down to street level and existing 15'' RCP pipe is being excavated. 11-6-24 BR Contractor poured inverts on 1st storm junction box and installed 25' of 15'' RCP pipe coming out of storm box. 11-7-24 BR Contractor installed 25' of 15'' RCP pipe to 2nd storm junction box with box structure installed. 11-8-24 BR Contractor formed walls & lids on both storm junction boxes with #5 rebar. Ready for concrete. 11-12-24 BR Contractor poured lids for both storm junction boxes and back fill pipe.
Erosion Control Inspection Partial 11/14/2024 11/14/2024 11/14/2024
Misc
Informational
11/14/2024
11-14-24 BR Erosion control is up and working order.
Site Visit Complete 8/7/2024 8/7/2024 11/14/2024
Misc
Informational
08/07/2024
08/07/24 Wednesday JMJ Gas tanks were being installed a state inspector was onsite observing operation.
Pavement-Stabilized Subgrade Partial 12/3/2024 12/3/2024 12/03/2024
Misc
Informational
11/25/2024
11-25-24 BR Contractor started excavations on turn lane section on SE Hamblen Rd 12-3-24 BR Contractor installed 9'' of aggerate on turn lane section on SE Hamblen Rd.
Pavement-Curb Construction Partial 12/9/2024 12/9/2024 12/09/2024
Misc
Informational
12/09/2024
12-5-24 BR Contractor formed up for curb with aggregate place and compacted ready for concrete. 12-6-24 BR Contractor poured 4k KCMMB concrete curb on SE Hamblen Rd section to LS specifications.
Pavement-Aggregate Base Passed 12/9/2024 12/9/2024 12/16/2024
Misc
Informational
12/09/2024
12-9-24 BR Contractor installed 9'' aggerate base on turn lane SE Hamblen Rd.
Pavement-Surface Partial 12/17/2024 12/17/2024 12/17/2024
Misc
Informational
12/16/2024
12-16-24 BR Contractor (Blacktop Paving Maintenance) poured 4'' of KCMMB A-3 on SE Hamblen Rd. turn lane section. There was no 3rd party tester for compaction on site. 12-17-24 BR Contractor (Blacktop Paving Maintenance) poured 2'' KCMMB A-2 on SE Hamblen Rd turn lane section. The 3rd party tester (Geotech) is on site testing surface.
Documents & Images
Date Uploaded File Type Document Name
04/04/2023 Approved Plans LP Mart - Hamblen Turn Lane Approved 04 04 23
04/04/2023 Activity Document Fees PL2022403 LP Mart - Hamblen Rd Turn Lane
03/21/2023 Engineers Estimate COST ESTIMATE PUBLIC ROAD 2023-3-21
05/14/2024 Receipt Receipt for transaction: 2024-003321
05/14/2024 Letter DE-Permit
08/07/2024 Letter INSPECTION SUMMARY
10/28/2024 Letter INSPECTION SUMMARY
10/31/2024 Letter INSPECTION SUMMARY
11/05/2024 Letter INSPECTION SUMMARY
11/06/2024 Letter INSPECTION SUMMARY
11/07/2024 Letter INSPECTION SUMMARY
11/08/2024 Letter INSPECTION SUMMARY
11/08/2024 Letter INSPECTION SUMMARY
11/08/2024 Letter INSPECTION SUMMARY
11/08/2024 Letter INSPECTION SUMMARY
11/13/2024 Letter INSPECTION SUMMARY
11/13/2024 Letter INSPECTION SUMMARY
11/14/2024 Letter INSPECTION SUMMARY
11/14/2024 Letter INSPECTION SUMMARY
11/14/2024 Letter INSPECTION SUMMARY
11/14/2024 Letter INSPECTION SUMMARY
11/25/2024 Letter INSPECTION SUMMARY
12/03/2024 Letter INSPECTION SUMMARY
12/03/2024 Letter INSPECTION SUMMARY
12/09/2024 Letter INSPECTION SUMMARY
12/09/2024 Letter INSPECTION SUMMARY
12/16/2024 Letter INSPECTION SUMMARY
12/16/2024 Letter INSPECTION SUMMARY
12/16/2024 Letter INSPECTION SUMMARY
12/16/2024 Letter INSPECTION SUMMARY
12/17/2024 Letter INSPECTION SUMMARY
04/07/2025 Letter DE-Certificate of Substantial Completion Single Lot
04/07/2025 Letter SUBD Punch List
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home