Permit Application Status

PRSUBD20224825


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary


PRSUBD20224825
Public Infrastructure
Final Acceptance
WOODLAND OAKS LLC
DEVELOPMENT COMPLETE
WOODLAND OAKS - LOW PRESSURE SANITARY ONSITE AND OFFSITE
09/28/2022
10/04/2022
10/24/2024
Locations
Address
1751 NE WOODLAND SHORES DR, LEES SUMMIT, MO 64086

Address
2624 NE WOODLAND OAK DR, LEES SUMMIT, MO 64086

Address
2620 NE WOODLAND OAK DR, LEES SUMMIT, MO 64086

Address
2616 NE WOODLAND OAK DR, LEES SUMMIT, MO 64086

Address
2612 NE WOODLAND OAK DR, LEES SUMMIT, MO 64086

Address
2608 NE WOODLAND OAK DR, LEES SUMMIT, MO 64086

Address
2604 NE WOODLAND OAK DR, LEES SUMMIT, MO 64086

Address
2536 NE WOODLAND OAK CIR, LEES SUMMIT, MO 64086

Address
2532 NE WOODLAND OAK CIR, LEES SUMMIT, MO 64086

Address
2528 NE WOODLAND OAK CIR, LEES SUMMIT, MO 64086

Address
2524 NE WOODLAND OAK CIR, LEES SUMMIT, MO 64086

Address
2520 NE WOODLAND OAK CIR, LEES SUMMIT, MO 64086

Address
2516 NE WOODLAND OAK CIR, LEES SUMMIT, MO 64086

Address
2512 NE WOODLAND OAK CIR, LEES SUMMIT, MO 64086

Address
2508 NE WOODLAND OAK CIR, LEES SUMMIT, MO 64086

Address
2504 NE WOODLAND OAK CIR, LEES SUMMIT, MO 64086

Address
2500 NE WOODLAND OAK CIR, LEES SUMMIT, MO 64086

Address
2505 NE WOODLAND OAK CIR, LEES SUMMIT, MO 64086

Address
2509 NE WOODLAND OAK CIR, LEES SUMMIT, MO 64086

Address
2513 NE WOODLAND OAK CIR, LEES SUMMIT, MO 64086

Address
2517 NE WOODLAND OAK CIR, LEES SUMMIT, MO 64086

Address
2531 NE WOODLAND OAK CIR, LEES SUMMIT, MO 64086

Address
2533 NE WOODLAND OAK CIR, LEES SUMMIT, MO 64086

Address
2535 NE WOODLAND OAK CIR, LEES SUMMIT, MO 64086

Address
1812 NE LASHBROOK CIR, LEES SUMMIT, MO 64086

Address
1816 NE LASHBROOK CIR, LEES SUMMIT, MO 64086

Address
1820 NE LASHBROOK CIR, LEES SUMMIT, MO 64086

Address
1817 NE LASHBROOK CIR, LEES SUMMIT, MO 64086

Address
1813 NE LASHBROOK CIR, LEES SUMMIT, MO 64086

Address
1809 NE LASHBROOK CIR, LEES SUMMIT, MO 64086

Address
2603 NE WOODLAND OAK DR, LEES SUMMIT, MO 64086

Address
2607 NE WOODLAND OAK DR, LEES SUMMIT, MO 64086

Address
2611 NE WOODLAND OAK DR, LEES SUMMIT, MO 64086

Address
2615 NE WOODLAND OAK DR, LEES SUMMIT, MO 64086

Address
1810 NE CHERRYBARK CT, LEES SUMMIT, MO 64086

Address
1812 NE CHERRYBARK CT, LEES SUMMIT, MO 64086

Address
1816 NE CHERRYBARK CT, LEES SUMMIT, MO 64086

Address
1820 NE CHERRYBARK CT, LEES SUMMIT, MO 64086

Address
1817 NE CHERRYBARK CT, LEES SUMMIT, MO 64086

Address
1813 NE CHERRYBARK CT, LEES SUMMIT, MO 64086

Address
1809 NE CHERRYBARK CT, LEES SUMMIT, MO 64086

Address
1805 NE CHERRYBARK CT, LEES SUMMIT, MO 64086

Address
1801 NE LASHBROOK DR, LEES SUMMIT, MO 64086

Address
2600 NE COLBERN RD, LEES SUMMIT, MO 64086

Address
1652 NE WOODLAND SHORES CIR, LEES SUMMIT, MO 64086

Address
1653 NE WOODLAND SHORES CIR, LEES SUMMIT, MO 64086

Property
53440222000000000

Property
53440221900000000

Property
53440221800000000

Property
53440221700000000

Property
53440221600000000

Property
53440221500000000

Property
53440221400000000

Property
53440221300000000

Property
53440253900000000

Property
53440254000000000

Property
53440254100000000

Property
53440254200000000

Property
53440254300000000

Property
53440254400000000

Property
53440254500000000

Property
53440255200000000

Property
53440254600000000

Property
53440255100000000

Property
53440254700000000

Property
53440255000000000

Property
53440254800000000

Property
53440254900000000

Property
53440256200000000

Property
53440256300000000

Property
53440255500000000

Property
53440255400000000

Property
53440255300000000

Property
53440256100000000

Property
53440255600000000

Property
53440256000000000

Property
53440255900000000

Property
53440255700000000

Property
53440255800000000

Property
53440257300000000

Property
53440256500000000

Property
53440257200000000

Property
53440256600000000

Property
53440256400000000

Property
53440257100000000

Property
53440256700000000

Property
53440256800000000

Property
53440257000000000

Property
53440256900000000

Property
53440257400000000

Property
53440080100000000

Property
53440083700000000

Property
53440083600000000

Address
2628 NE WOODLAND OAK DR, LEES SUMMIT, MO 64086

Contacts
WOODLAND OAKS LLC, Address:656 BAYBERRY LN STE 101  
REDFORD CONSTRUCTION INC, Address:PO BOX 1065, Phone:(816) 540-2030  
WOODLAND OAKS LLC, Address:656 BAYBERRY LN STE 101  
WALKER CUSTOM HOMES LLC, Address:PO BOX 247  
WEGNER FAMILY TRUST AGREEMENT DATED SEPTEMBER 24, 2009, Address:5718 NE SAPPHIRE PL  
TRUMARK CUSTOM HOMES LLC, Address:2924 NW THOREAU DR  
JFE CONSTRUCTION INC, Address:1314 SW MARKET ST  
JFE HOMES LLC, Address:1314 SW MARKET ST  
STONE CHASE PROPERTIES LLC, Address:240 STONE CHASE  
BELLAH HOMES LLC, Address:PO BOX 346  
WOODLAND SHORES HOMES ASSOCIATION INC, Address:1800 NE BLUE HERON DR  
MASTERS PAXTON, Address:1653 NE WOODLAND SHORES CIR  
SADASIVAN THERESA DENISE & RAJ, Address:1652 NE WOODLAND SHORES CIR  
Reviews
Review Type Outcome Est. Completion Date Completed
Licensed Contractors Approved 09/28/2022 10/04/2022
Dawn Bell
Fees
Paid Fees Amount Paid Owing Date Paid
91100C8-Sanitary Sewer Insp Fees $4,373.92 $4,373.92 Paid 10/03/2022
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Sanitary Sewer Construction Inspection Partial 10/07/2022
Misc
Informational
10/07/2022
10-4-22 AN we now have approved plans. Redford has begun trenching to start laying the low pressure sewer main 10-5-22 AN spoke with Patrick from Redford, need tracer wire on sewer main and services . 10-5-22 AN crew is installing the tracer wire on the main and to the check valve . Pic of check valve attached
Sanitary Sewer Construction Inspection Partial 10/07/2022
Misc
Informational
10/07/2022
10-4-22 AN we now have approved plans. Redford has begun trenching to start laying the low pressure sewer main 10-5-22 AN spoke with Patrick from Redford, need tracer wire on sewer main and services . 10-5-22 AN crew is installing the tracer wire on the main and to the check valve . Pic of check valve attached
Sanitary Sewer Construction Inspection Partial 10/07/2022
Misc
Informational
10/07/2022
10-4-22 AN we now have approved plans. Redford has begun trenching to start laying the low pressure sewer main 10-5-22 AN spoke with Patrick from Redford, need tracer wire on sewer main and services . 10-5-22 AN crew is installing the tracer wire on the main and to the check valve . Pic of check valve attached 10-6-22 AN still laying the the low pressure main and services
Sanitary Sewer Construction Inspection Partial 10/07/2022
Misc
Informational
10/07/2022
10-4-22 AN we now have approved plans. Redford has begun trenching to start laying the low pressure sewer main 10-5-22 AN spoke with Patrick from Redford, need tracer wire on sewer main and services . 10-5-22 AN crew is installing the tracer wire on the main and to the check valve . Pic of check valve attached 10-6-22 AN still laying the the low pressure main and services 10-7-22 AN crew is fusing pipe for install next week
Sanitary - Material Verification Partial 10/07/2022
Misc
Informational
10/07/2022
10-7-22 AN. 3” pvc hdpe sdr-11 force main 2” pvc hdpe sdr-11 force main 1.25” pvc hdpe sdr-11. Service lines
Sanitary Sewer Construction Inspection Partial 10/10/2022
Misc
Informational
10/07/2022
10-4-22 AN we now have approved plans. Redford has begun trenching to start laying the low pressure sewer main 10-5-22 AN spoke with Patrick from Redford, need tracer wire on sewer main and services . 10-5-22 AN crew is installing the tracer wire on the main and to the check valve . Pic of check valve attached 10-6-22 AN still laying the the low pressure main and services 10-7-22 AN crew is fusing pipe for install next week 10-10-22 AN crew has all of line 1 installed sta 10, 9,8,7,6,5,4,3,2,1,0
Sanitary Sewer Construction Inspection Partial 10/10/2022
Misc
Informational
10/10/2022
10-4-22 AN we now have approved plans. Redford has begun trenching to start laying the low pressure sewer main 10-5-22 AN spoke with Patrick from Redford, need tracer wire on sewer main and services . 10-5-22 AN crew is installing the tracer wire on the main and to the check valve . Pic of check valve attached 10-6-22 AN still laying the the low pressure main and services 10-7-22 AN crew is fusing pipe for install next week 10-10-22 AN crew has all of line 1 installed sta 10, 9,8,7,6,5,4,3,2,1,0 10-10-22 AN working on line 3 sta 23 - 11
Sanitary Sewer Construction Inspection Partial 12/14/2022
Misc
Informational
10/10/2022
10-4-22 AN we now have approved plans. Redford has begun trenching to start laying the low pressure sewer main 10-5-22 AN spoke with Patrick from Redford, need tracer wire on sewer main and services . 10-5-22 AN crew is installing the tracer wire on the main and to the check valve . Pic of check valve attached 10-6-22 AN still laying the the low pressure main and services 10-7-22 AN crew is fusing pipe for install next week 10-10-22 AN crew has all of line 1 installed sta 10, 9,8,7,6,5,4,3,2,1,0 10-10-22 AN working on line 3 sta 23 - 11 10-4-22 AN we now have approved plans. Redford has begun trenching to start laying the low pressure sewer main 10-5-22 AN spoke with Patrick from Redford, need tracer wire on sewer main and services . 10-5-22 AN crew is installing the tracer wire on the main and to the check valve . Pic of check valve attached 10-20-22 AN. Redford is still working on the sewer by the entrance of blackwell. All three cul de sac are now completed 11-9-22 AN boring company has began boring on blackwell 11-10-22AN. Still boring 11-14-22 AN. All the boring is completed and we will test the line before it is connected to the main 11-16-22 AN. Crew has began to dig up the front yard for their sewer tie in 11-16-22 AN low pressure sewer is now tied into the gravity main. 2 pic attached
Sanitary Sewer - Mandrel Passed 12/14/2022
Misc
Informational
12/14/2022
12-14-22 AN low pressure main so no mandrel
Sanitary Sewer Construction Inspection Partial 1/12/2023 1/12/2023 01/12/2023
Misc
Informational
12/14/2022
10-4-22 AN we now have approved plans. Redford has begun trenching to start laying the low pressure sewer main 10-5-22 AN spoke with Patrick from Redford, need tracer wire on sewer main and services . 10-5-22 AN crew is installing the tracer wire on the main and to the check valve . Pic of check valve attached 10-6-22 AN still laying the the low pressure main and services 10-7-22 AN crew is fusing pipe for install next week 10-10-22 AN crew has all of line 1 installed sta 10, 9,8,7,6,5,4,3,2,1,0 10-10-22 AN working on line 3 sta 23 - 11 10-4-22 AN we now have approved plans. Redford has begun trenching to start laying the low pressure sewer main 10-5-22 AN spoke with Patrick from Redford, need tracer wire on sewer main and services . 10-5-22 AN crew is installing the tracer wire on the main and to the check valve . Pic of check valve attached 10-20-22 AN. Redford is still working on the sewer by the entrance of blackwell. All three cul de sac are now completed 11-9-22 AN boring company has began boring on blackwell 11-10-22AN. Still boring 11-14-22 AN. All the boring is completed and we will test the line before it is connected to the main 11-16-22 AN. Crew has began to dig up the front yard for their sewer tie in 11-16-22 AN low pressure sewer is now tied into the gravity main. 2 pic attached 1-12-23 DP crew was exposing utilities at the location for the air relief valve. The approved area will not work due to utilities, they are taking the information back to their Engineers.
Erosion Control Inspection Partial 6/1/2023 06/01/2023
Misc
Informational
06/01/2023
6-1-23 NS No erosion control issues
Grading/Excavation/Fill Inspection Passed 12/20/2023 12/20/2023
Misc
Informational
12/20/2023
12-20-23 NS Site Visited and it appears grading is done passed
Sanitary - Material Verification Passed 12/20/2023 12/20/2023
Misc
Informational
10/07/2022
10-7-22 AN. 3” pvc hdpe sdr-11 force main 2” pvc hdpe sdr-11 force main 1.25” pvc hdpe sdr-11. Service lines 12-20-23 NS Site Visited and it appears sewer has passed
Erosion Control Inspection Failed 12/28/2023
Misc
Corrective Action Required
12/28/2023
6-1-23 NS No erosion control issues 12-28-23 NS Site visited and the erosion control has failed
Sanitary Sewer Construction Inspection Passed 1/5/2024 01/05/2024
Misc
Informational
01/12/2023
10-4-22 AN we now have approved plans. Redford has begun trenching to start laying the low pressure sewer main 10-5-22 AN spoke with Patrick from Redford, need tracer wire on sewer main and services . 10-5-22 AN crew is installing the tracer wire on the main and to the check valve . Pic of check valve attached 10-6-22 AN still laying the the low pressure main and services 10-7-22 AN crew is fusing pipe for install next week 10-10-22 AN crew has all of line 1 installed sta 10, 9,8,7,6,5,4,3,2,1,0 10-10-22 AN working on line 3 sta 23 - 11 10-4-22 AN we now have approved plans. Redford has begun trenching to start laying the low pressure sewer main 10-5-22 AN spoke with Patrick from Redford, need tracer wire on sewer main and services . 10-5-22 AN crew is installing the tracer wire on the main and to the check valve . Pic of check valve attached 10-20-22 AN. Redford is still working on the sewer by the entrance of blackwell. All three cul de sac are now completed 11-9-22 AN boring company has began boring on blackwell 11-10-22AN. Still boring 11-14-22 AN. All the boring is completed and we will test the line before it is connected to the main 11-16-22 AN. Crew has began to dig up the front yard for their sewer tie in 11-16-22 AN low pressure sewer is now tied into the gravity main. 2 pic attached 1-12-23 DP crew was exposing utilities at the location for the air relief valve. The approved area will not work due to utilities, they are taking the information back to their Engineers. 1-5-24 NS Site visited and it appears all work is complete and test passed.
Erosion Control Inspection Partial 1/23/2024 01/23/2024
Misc
Corrective Action Required
12/28/2023
6-1-23 NS No erosion control issues 12-28-23 NS Site visited and the erosion control has failed 1-3-24 NS Site Visited erosion con 1-23-24 NS Site Visited and erosion control has been fixed
Erosion Control Inspection Partial 2/28/2024 02/28/2024
Misc
Corrective Action Required
01/23/2024
6-1-23 NS No erosion control issues 12-28-23 NS Site visited and the erosion control has failed 1-3-24 NS Site Visited erosion con 1-23-24 NS Site Visited and erosion control has been fixed 2-28-24 NS Site Visited and no erosion control issues
Erosion Control Inspection Partial 3/29/2024 03/29/2024
Misc
Corrective Action Required
02/28/2024
6-1-23 NS No erosion control issues 12-28-23 NS Site visited and the erosion control has failed 1-3-24 NS Site Visited erosion con 1-23-24 NS Site Visited and erosion control has been fixed 2-28-24 NS Site Visited and no erosion control issues 3-29-24 NS Site Visited and no erosion control issues
Erosion Control Inspection Partial 4/18/2024 04/18/2024
Misc
Corrective Action Required
03/29/2024
6-1-23 NS No erosion control issues 12-28-23 NS Site visited and the erosion control has failed 1-3-24 NS Site Visited erosion con 1-23-24 NS Site Visited and erosion control has been fixed 2-28-24 NS Site Visited and no erosion control issues 3-29-24 NS Site Visited and no erosion control issues 4-18-24 NS Site Visited and no erosion control issues
Erosion Control Inspection Partial 4/30/2024 04/30/2024
Misc
Corrective Action Required
04/18/2024
6-1-23 NS No erosion control issues 12-28-23 NS Site visited and the erosion control has failed 1-3-24 NS Site Visited erosion con 1-23-24 NS Site Visited and erosion control has been fixed 2-28-24 NS Site Visited and no erosion control issues 3-29-24 NS Site Visited and no erosion control issues 4-18-24 NS Site Visited and no erosion control issues 4-30-24 NS Site Visited and no erosion control issues
Erosion Control Inspection Partial 6/28/2024 06/28/2024
Misc
Corrective Action Required
04/30/2024
6-1-23 NS No erosion control issues 12-28-23 NS Site visited and the erosion control has failed 1-3-24 NS Site Visited erosion con 1-23-24 NS Site Visited and erosion control has been fixed 2-28-24 NS Site Visited and no erosion control issues 3-29-24 NS Site Visited and no erosion control issues 4-18-24 NS Site Visited and no erosion control issues 4-30-24 NS Site Visited and no erosion control issues 6-28-24 NS Site Visited and no erosion control issues
Erosion Control Inspection Partial 7/25/2024 07/25/2024
Misc
Corrective Action Required
06/28/2024
6-1-23 NS No erosion control issues 12-28-23 NS Site visited and the erosion control has failed 1-3-24 NS Site Visited erosion con 1-23-24 NS Site Visited and erosion control has been fixed 2-28-24 NS Site Visited and no erosion control issues 3-29-24 NS Site Visited and no erosion control issues 4-18-24 NS Site Visited and no erosion control issues 4-30-24 NS Site Visited and no erosion control issues 6-28-24 NS Site Visited and no erosion control issues 7-25-24 NS Site Visited and no erosion control issues
Erosion Control Inspection Partial 8/6/2024 08/06/2024
Misc
Corrective Action Required
07/25/2024
6-1-23 NS No erosion control issues 12-28-23 NS Site visited and the erosion control has failed 1-3-24 NS Site Visited erosion con 1-23-24 NS Site Visited and erosion control has been fixed 2-28-24 NS Site Visited and no erosion control issues 3-29-24 NS Site Visited and no erosion control issues 4-18-24 NS Site Visited and no erosion control issues 4-30-24 NS Site Visited and no erosion control issues 6-28-24 NS Site Visited and no erosion control issues 7-25-24 NS Site Visited and no erosion control issues
Erosion Control Inspection Partial 8/8/2024 08/08/2024
Misc
Corrective Action Required
08/06/2024
6-1-23 NS No erosion control issues 12-28-23 NS Site visited and the erosion control has failed 1-3-24 NS Site Visited erosion con 1-23-24 NS Site Visited and erosion control has been fixed 2-28-24 NS Site Visited and no erosion control issues 3-29-24 NS Site Visited and no erosion control issues 4-18-24 NS Site Visited and no erosion control issues 4-30-24 NS Site Visited and no erosion control issues 6-28-24 NS Site Visited and no erosion control issues 7-25-24 NS Site Visited and no erosion control issues 8-8-24 NS Site Visited and no erosion control issues
Site Visit Partial 08/08/2024
Misc
Informational
08/08/2024
8-8-24 NS Site Visited and no one is working due to rain.
Erosion Control Inspection Partial 8/22/2024 08/22/2024
Misc
Corrective Action Required
08/08/2024
6-1-23 NS No erosion control issues 12-28-23 NS Site visited and the erosion control has failed 1-3-24 NS Site Visited erosion con 1-23-24 NS Site Visited and erosion control has been fixed 2-28-24 NS Site Visited and no erosion control issues 3-29-24 NS Site Visited and no erosion control issues 4-18-24 NS Site Visited and no erosion control issues 4-30-24 NS Site Visited and no erosion control issues 6-28-24 NS Site Visited and no erosion control issues 7-25-24 NS Site Visited and no erosion control issues 8-8-24 NS Site Visited and no erosion control issues 8-22-24 NS Site Visited and no erosion issues
Site Visit Partial 08/22/2024
Misc
Informational
08/08/2024
8-8-24 NS Site Visited and no one is working due to rain. 8-22-24 NS Site Visited and crews are pouring concrete curb.
Site Visit Partial 8/27/2024 08/27/2024
Misc
Informational
08/22/2024
8-8-24 NS Site Visited and no one is working due to rain. 8-22-24 NS Site Visited and crews are pouring concrete curb. 8-27-24 NS Site Visited no work is being done.
Site Visit Partial 9/4/2024 09/04/2024
Misc
Informational
08/27/2024
8-8-24 NS Site Visited and no one is working due to rain. 8-22-24 NS Site Visited and crews are pouring concrete curb. 8-27-24 NS Site Visited no work is being done. 9-4-24 NS Site visited and it appears base asphalt has been put down and islands poured
Site Visit Partial 9/17/2024 09/17/2024
Misc
Informational
09/04/2024
8-8-24 NS Site Visited and no one is working due to rain. 8-22-24 NS Site Visited and crews are pouring concrete curb. 8-27-24 NS Site Visited no work is being done. 9-4-24 NS Site visited and it appears base asphalt has been put down and islands poured 9-17-24 NS Site visited and it appears no work is being done today. While I was gone the Fire curb was installed. Paint and stop signs as well.
Site Visit Partial 9/18/2024 09/18/2024
Misc
Informational
09/17/2024
8-8-24 NS Site Visited and no one is working due to rain. 8-22-24 NS Site Visited and crews are pouring concrete curb. 8-27-24 NS Site Visited no work is being done. 9-4-24 NS Site visited and it appears base asphalt has been put down and islands poured 9-17-24 NS Site visited and it appears no work is being done today. While I was gone the Fire curb was installed. Paint and stop signs as well. 9-18-24 NS Site visited and they put up road signs
Site Visit Partial 9/19/2024 09/19/2024
Misc
Informational
09/18/2024
Colbern Road Investment. 8-8-24 NS Site Visited and no one is working due to rain. 8-22-24 NS Site Visited and crews are pouring concrete curb. 8-27-24 NS Site Visited no work is being done. 9-4-24 NS Site visited and it appears base asphalt has been put down and islands poured 9-17-24 NS Site visited and it appears no work is being done today. While I was gone the Fire curb was installed. Paint and stop signs as well. 9-18-24 NS Site visited and they put up road signs 9-19-24 NS Site visited and the signs are still up and no work today.
Erosion Control Inspection Partial 9/30/2024 09/30/2024
Misc
Corrective Action Required
08/22/2024
6-1-23 NS No erosion control issues 12-28-23 NS Site visited and the erosion control has failed 1-3-24 NS Site Visited erosion con 1-23-24 NS Site Visited and erosion control has been fixed 2-28-24 NS Site Visited and no erosion control issues 3-29-24 NS Site Visited and no erosion control issues 4-18-24 NS Site Visited and no erosion control issues 4-30-24 NS Site Visited and no erosion control issues 6-28-24 NS Site Visited and no erosion control issues 7-25-24 NS Site Visited and no erosion control issues 8-8-24 NS Site Visited and no erosion control issues 8-22-24 NS Site Visited and no erosion issues 9-30-24 NS Site Visited and no erosion control issues
Site Visit Partial 9/30/2024 09/30/2024
Misc
Informational
09/19/2024
Colbern Road Investment. 8-8-24 NS Site Visited and no one is working due to rain. 8-22-24 NS Site Visited and crews are pouring concrete curb. 8-27-24 NS Site Visited no work is being done. 9-4-24 NS Site visited and it appears base asphalt has been put down and islands poured 9-17-24 NS Site visited and it appears no work is being done today. While I was gone the Fire curb was installed. Paint and stop signs as well. 9-18-24 NS Site visited and they put up road signs 9-19-24 NS Site visited and the signs are still up and no work today. 9-30-24 NS Site Visited and sidewalks are being put in.
Erosion Control Inspection Failed 10/11/2024 10/14/2024
Misc
Corrective Action Required
09/30/2024
6-1-23 NS No erosion control issues 12-28-23 NS Site visited and the erosion control has failed 1-3-24 NS Site Visited erosion con 1-23-24 NS Site Visited and erosion control has been fixed 2-28-24 NS Site Visited and no erosion control issues 3-29-24 NS Site Visited and no erosion control issues 4-18-24 NS Site Visited and no erosion control issues 4-30-24 NS Site Visited and no erosion control issues 6-28-24 NS Site Visited and no erosion control issues 7-25-24 NS Site Visited and no erosion control issues 8-8-24 NS Site Visited and no erosion control issues 8-22-24 NS Site Visited and no erosion issues 9-30-24 NS Site Visited and no erosion control issues 10-14-24 NS clean gutter buddies and clean the road from dirt and gravel
Site Visit Partial 10/10/2024 10/14/2024
Misc
Informational
09/30/2024
Colbern Road Investment. 8-8-24 NS Site Visited and no one is working due to rain. 8-22-24 NS Site Visited and crews are pouring concrete curb. 8-27-24 NS Site Visited no work is being done. 9-4-24 NS Site visited and it appears base asphalt has been put down and islands poured 9-17-24 NS Site visited and it appears no work is being done today. While I was gone the Fire curb was installed. Paint and stop signs as well. 9-18-24 NS Site visited and they put up road signs 9-19-24 NS Site visited and the signs are still up and no work today. 9-30-24 NS Site Visited and sidewalks are being put in. 10-14-24 NS Site visited and the sidewalk are being put in again today and will be the second to last sidewalk being put in. I talked to Jamie and they are waiting for utilities to be moved so they can put in the sidewalk and turn lanes.
Documents & Images
Date Uploaded File Type Document Name
10/03/2022 Receipt Receipt for transaction: 2022-007984
10/03/2022 Approved Plans Woodland Oaks LPS Sanitary Set Approved 10.3.22
10/07/2022 Letter INSPECTION SUMMARY
10/07/2022 Letter INSPECTION SUMMARY
10/07/2022 Letter INSPECTION SUMMARY
10/07/2022 Letter INSPECTION SUMMARY
10/07/2022 Letter INSPECTION SUMMARY
10/10/2022 Letter INSPECTION SUMMARY
10/10/2022 Letter INSPECTION SUMMARY
12/14/2022 Letter INSPECTION SUMMARY
12/14/2022 Letter INSPECTION SUMMARY
12/28/2023 Letter INSPECTION SUMMARY
01/05/2024 Letter INSPECTION SUMMARY
01/05/2024 Letter INSPECTION SUMMARY
01/05/2024 Letter INSPECTION SUMMARY
01/05/2024 Letter INSPECTION SUMMARY
01/08/2024 WOODLAND OAKS Water District 13
01/23/2024 Letter INSPECTION SUMMARY
02/23/2024 Letter DE-Certificate of Substantial Completion Single Lot Old
02/23/2024 Letter DE-Punch List Old
02/23/2024 Letter DE-Certificate of Substantial Completion Multiple Lot
02/23/2024 Letter DE-Punch List
03/29/2024 Letter INSPECTION SUMMARY
04/18/2024 Letter INSPECTION SUMMARY
04/30/2024 Letter INSPECTION SUMMARY
07/25/2024 Letter INSPECTION SUMMARY
08/22/2024 Letter INSPECTION SUMMARY
08/22/2024 Letter INSPECTION SUMMARY
08/27/2024 Letter INSPECTION SUMMARY
09/04/2024 Letter INSPECTION SUMMARY
09/17/2024 Letter INSPECTION SUMMARY
09/18/2024 Letter INSPECTION SUMMARY
09/19/2024 Letter INSPECTION SUMMARY
09/30/2024 Letter INSPECTION SUMMARY
10/14/2024 Letter INSPECTION SUMMARY
10/14/2024 Letter INSPECTION SUMMARY
10/24/2024 Letter DE-Certificate of Final Acceptance (Commercial)
09/30/2024 Letter INSPECTION SUMMARY
08/08/2024 Letter INSPECTION SUMMARY
08/08/2024 Letter INSPECTION SUMMARY
08/06/2024 Letter INSPECTION SUMMARY
06/28/2024 Letter INSPECTION SUMMARY
02/28/2024 Letter INSPECTION SUMMARY
01/12/2023 Letter INSPECTION SUMMARY
10/04/2022 Letter DE-Permit
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home