Permit Application Status

PRSUBD20214936


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary


PRSUBD20214936
Public Infrastructure
Final Acceptance
WHITANCE DAVID E & NANCY L
DEVELOPMENT COMPLETE
Construction of a new 15" public sanitary sewer main
09/21/2021
04/04/2022
10/26/2023
Locations
Contacts
WHITANCE DAVID E & NANCY L, Address:1720 SE RANSON RD  
SCHOOL DISTRICT 7 REORGANIZED, Address:301 NE TUDOR RD  
CITY OF LEES SUMMIT, Address:207 SW MARKET ST  
THE CITY OF LEES SUMMIT, Address:220 SE GREEN ST  
MCCOWN GORDON CONSTRUCTION LLC, Address:850 MAIN ST, Phone:(816) 960-1111  
SITE RITE CONSTRUCTON CO, Address:1601 BELLEFONTAINE AVE, Phone:(816) 561-4890  
Reviews
Review Type Outcome Est. Completion Date Completed
Licensed Contractors Approved 09/21/2021 09/21/2021
Mike Weisenborn
Fees
Paid Fees Amount Paid Owing Date Paid
91100C8-Sanitary Sewer Insp Fees $6,559.65 $6,559.65 Paid 10/04/2021
9110071-Site Grading Fee $615.00 $615.00 Paid 10/04/2021
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Erosion Control Inspection Partial 04/07/2022
Misc
Informational
04/07/2022
On Wednesday 4-06-2022. Site Rite Construction began grading and tree removal for sewer location. Contractor mobilized machinery and rock for roadway entrance. We reviewed the erosion plan and found we need to altar some of the silt fencing out of the creek and change some of the locations the plans suggested fencing should go. On Thursday and Friday, 4-07 & 4-08-2022. Contractor resumed clearing and mobilizing. MH’s and pipe and rock.
Sanitary Sewer Construction Inspection Partial 04/12/2022
Misc
Informational
04/12/2022
On Monday, 4-11-2022, Site Rite Construction broke ground installing MH A-2 and approx 20 LF of 15” sanitary pipe. On Tuesday, 4-12-2022, Site Rite resumes sewer installation. Contractor placed approx 140 LF of sanitary pipe and back filled small area. Contractor breaking approx 1’ of rock. On Wednesday, 4-13-2022. Site Rite Construction resumed sanitary sewer installation. Very wet but contractor did place A-3 and approx 120 LF of sewer between MH-A-2 and A-4. On Thursday, 4-14-2022. Contractor resumes sewer install. Contractor can only install about 70 LF of pipe due to rock excavation. On Friday, 4-15-2022. Site Rite Construction began work but only installed 2 stick of sanitary pipe before left for the day as per General Contractor Mc Cown Gordon. They had reach their hours for the week and it is Good Friday.
Misc
Informational
04/18/2022
On Monday, 4-18-2022. Site Rite Construction resumes Sanitary Sewer installation. Contract installs approx 100 LF of 15” pvc sewer and back fill pipe. On Tuesday thru Thursday,4-21-2022. Site Rite Excavating have installed approx 100 LF and A-4 Man Hole. Contractor also broke breaker bit. Took (4) hour to get up and going. On Friday 4-22-2022. Contractor resumes Sewer installation. Contractor installed 3 sections or 42 LF of 15” pvc pipe and backfilled trench.
Misc
Informational
04/26/2022
On Monday, 4-25-2022, Site Rite Construction resumes sewer installation. Contractor installed approx 80LF of 8” pvc pipe and back filled trench. On Tuesday, 4-26-2022. The contractor resumed Sanitary Sewer installation. Contractor has begun to come out of the rock demo. Should get more production with less rock removal. Installed approx 80 ft of pipe and back filled.
Misc
Informational
05/09/2022
On Monday, 5-09-2022 Site Rite resumed sanitary Sewer installation. Contractor. Install pipe to structure A-6 and back filled pipe installed for the day.
Misc
Informational
05/16/2022
On Monday, 5-16-2022. Site Rite Contractors resumed Sanitary Sewer installation. The contractor set MH-5 and approx 40 LF of 15’ plastic pipe.
Misc
Informational
05/19/2022
On Thursday, 5-19-2022. Site Rite resumes Sanitary Sewer installation. The contractor moving very slow due to heavy rock demolition. Approx 60 LF per day. On Friday 5-20-2022. Contractor resumes sewer installation. Placed approx 80 LF of sewer and backfilled.
Misc
Informational
06/08/2022
On Monday, 6-06-2022, The contractor resumed Sanitary Sewer installation. Contractor placed MH-5. Contractor had to remove approx 4’ of rock to set man hole. On Tuesday, 6-07-2022, The contractor set approx 40 LF of 15” PVC sewer pipe and backfilled pipe. On Wednesday, 6-08-2022 the contractor laid 4 sections of 15” pvc pipe. Rained last night roadway to muddy to get to the project site. On Thursday, 6-08-2022. Site Rite Construction resumed Sanitary Sewer installation. Contractor installs approx 3 sections of 15” pvc sewer and backfilled.
Misc
Informational
06/13/2022
On Monday, 6-13-2022. Site Rite Excavating resumed Sanitary sewer installation. Contractor installed approx 3 sticks or 60 LF of 15” pvc pipe and compacted. Contractor still moving slow due to rock removal. On Tuesday, 6-14-2022, contractor resumed sewer installation. Contractor installed MH-#7 and approx 30 LF of 15” pvc. On Wednesday, 6-15-2022. Site Rite Excavating Set last MH-#8 and back filled . On Thursday, 6-16-2022 the contractor installed the last section of ductile 15” pipe. Contractor found debris in the existing sewer the She Diggs it installed. Pipe and MH was jetted before Site Rite could tie-in there sewer.
Water Line - Construction Inspection Partial 04/22/2022
Sanitary Sewer Construction Inspection Partial 05/11/2022
Misc
Informational
04/12/2022
On Monday, 4-11-2022, Site Rite Construction broke ground installing MH A-2 and approx 20 LF of 15” sanitary pipe. On Tuesday, 4-12-2022, Site Rite resumes sewer installation. Contractor placed approx 140 LF of sanitary pipe and back filled small area. Contractor breaking approx 1’ of rock.
Misc
Informational
05/11/2022
Site Rite is installing pipe ; they are hitting a lot of rock getting about 4 sticks of pipe a day.
Misc
Informational
06/06/2022
On 6-06-2022. Site Rite Excavating resumed Sanitary Sewer installation. Contractor set CI #8 and approx 60 LF of 15” pipe.
Sanitary Sewer Construction Inspection Partial 05/17/2022
Misc
Informational
05/11/2022
On Monday, 4-11-2022, Site Rite Construction broke ground installing MH A-2 and approx 20 LF of 15” sanitary pipe. On Tuesday, 4-12-2022, Site Rite resumes sewer installation. Contractor placed approx 140 LF of sanitary pipe and back filled small area. Contractor breaking approx 1’ of rock.
Misc
Informational
05/11/2022
Site Rite is installing pipe ; they are hitting a lot of rock getting about 4 sticks of pipe a day.
Misc
Informational
05/17/2022
Site rite is still hitting a lot of rock. Just installed a MH. Are expecting 3-4 sticks of 15” pipe today.
Grading/Excavation/Fill Inspection Partial 06/10/2022
Misc
Informational
06/10/2022
On Friday, 6-10-2022. A proof roll was performed by Third party testing, the prime contractor the sub-contractor and myself. The locations were in front of the school and the (2) Cape St intersections. All locations passed proof roll for the contractor to place rock fill. Both Cape St locations will receive 14” of 3” base rock with geo-grid and then 12” of type 5 base rock. The lane installations are ready for curb and 1st lift of base asphalt. Some areas are to narrow to place asphalt and will have concrete pavement poured in Lou of asphalt pavement. On Friday, 6-10-2022 Kat excavating cut fill for roadway installation on SW Heartwood Drive. Contractor remove approx 30’ of existing curbing and prepared extended roadway to the south for the extended roadway.
Sanitary Sewer - Mandrel Passed 06/20/2022
Misc
Informational
06/20/2022
On Monday, 6-20-2022. Site Rite performed and passed Mandrel test on the 15” sewer for this project.
Sanitary Sewer - Vacuum Passed 06/21/2022
Misc
Informational
06/21/2022
On Monday and Tuesday, 6-21-2022 the contractor completed and passed air an vacuum testing for the 15” sewer system. On Tuesday 6-21-2022 Contractor completed and passed all vacuums test for all man holes and completed the grouting of lift rings and completed the flushing of the sewer.
Misc
Informational
06/29/2022
31 day date for sewer to be tested/video by City of Lee’s Summits Water Service will by JULY 21, 2022
Sanitary Sewer Construction Inspection Partial 06/29/2022
Misc
Informational
05/17/2022
On Monday, 4-11-2022, Site Rite Construction broke ground installing MH A-2 and approx 20 LF of 15” sanitary pipe. On Tuesday, 4-12-2022, Site Rite resumes sewer installation. Contractor placed approx 140 LF of sanitary pipe and back filled small area. Contractor breaking approx 1’ of rock.
Misc
Informational
05/17/2022
Site Rite is installing pipe ; they are hitting a lot of rock getting about 4 sticks of pipe a day.
Misc
Informational
05/17/2022
Site rite is still hitting a lot of rock. Just installed a MH. Are expecting 3-4 sticks of 15” pipe today.
Sanitary Sewer - Air Test Passed 06/29/2022
Misc
Informational
06/21/2022
On Monday, 6-20-2022, Site Rite Construction performed Vacuum testing and pressure testing on Sanitary sewers for this project. All testing passed except Man Hole #5. Man Hole did not hold required vacuum. Contractor will review and correct vacuum issue.
Sanitary Sewer Construction Inspection Partial 07/20/2022
Misc
Informational
06/29/2022
On Monday, 4-11-2022, Site Rite Construction broke ground installing MH A-2 and approx 20 LF of 15” sanitary pipe. On Tuesday, 4-12-2022, Site Rite resumes sewer installation. Contractor placed approx 140 LF of sanitary pipe and back filled small area. Contractor breaking approx 1’ of rock.
Misc
Informational
06/29/2022
Site Rite is installing pipe ; they are hitting a lot of rock getting about 4 sticks of pipe a day.
Misc
Informational
06/29/2022
Site rite is still hitting a lot of rock. Just installed a MH. Are expecting 3-4 sticks of 15” pipe today.
Sanitary Sewer Construction Inspection Passed 08/19/2022
Misc
Informational
07/20/2022
On Monday, 4-11-2022, Site Rite Construction broke ground installing MH A-2 and approx 20 LF of 15” sanitary pipe. On Tuesday, 4-12-2022, Site Rite resumes sewer installation. Contractor placed approx 140 LF of sanitary pipe and back filled small area. Contractor breaking approx 1’ of rock.
Misc
Informational
07/20/2022
Site Rite is installing pipe ; they are hitting a lot of rock getting about 4 sticks of pipe a day.
Misc
Informational
07/20/2022
Site rite is still hitting a lot of rock. Just installed a MH. Are expecting 3-4 sticks of 15” pipe today.
Misc
Informational
08/19/2022
On Friday 8-19-2022 received the passing video results from Water Services for the 15” sanitary sewer Installed by Site Rite Excavating. McCown Gordon notified school can surge sewer system through pipe.
Documents & Images
Date Uploaded File Type Document Name
09/21/2021 Email PL2021114 LSR7 Middle School on Bailey Rd_ - Off-Site Sanitary Sewer Segment No_ 1
10/04/2021 Receipt Receipt for transaction: 2021-007753
12/30/2021 Approved Plans East Trails Middle School Interceptor Sewer Upsizing Revision Approved 12.30.21
04/04/2022 Permit DE-Permit
04/07/2022 Letter INSPECTION SUMMARY
04/07/2022 Letter INSPECTION SUMMARY
04/12/2022 Letter INSPECTION SUMMARY
04/14/2022 Letter INSPECTION SUMMARY
04/22/2022 Letter INSPECTION SUMMARY
04/22/2022 Letter INSPECTION SUMMARY
05/11/2022 Letter INSPECTION SUMMARY
05/17/2022 Letter INSPECTION SUMMARY
06/10/2022 Letter INSPECTION SUMMARY
06/10/2022 Letter INSPECTION SUMMARY
06/16/2022 Letter INSPECTION SUMMARY
06/21/2022 Letter INSPECTION SUMMARY
06/21/2022 Letter INSPECTION SUMMARY
06/29/2022 Letter INSPECTION SUMMARY
06/29/2022 Letter INSPECTION SUMMARY
07/21/2022 Letter INSPECTION SUMMARY
07/21/2022 Letter INSPECTION SUMMARY
08/11/2022 Letter INSPECTION SUMMARY
08/19/2022 Letter INSPECTION SUMMARY
11/04/2022 Letter DE-Certificate of Substantial Completion Single Lot
11/04/2022 Letter East Trails Middle School -Public Sanitary Main Extension- Substantial Completion
11/04/2022 Letter DE-Punch List
11/04/2022 Letter East Trails Middle School -Public Sanitary Main Extension - Punch List
11/07/2022 Security Document Maintenance Bond
02/27/2023 Plans 21_09_22 LSMS SS EXTENSION ASI33-AS-BUILT-SURVEY MU
02/27/2023 Plans 2023_02_21 AS-BUILT 020_0103 LSMS
10/26/2023 Security Document SiteRite Affidavit
10/26/2023 Letter DE-Certificate of Final Acceptance (Commercial)
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.