Summary


PRSUBD20200599
Public Infrastructure
Final Acceptance
CMH PARKS INC
DEVELOPMENT COMPLETE
Hawthorne Ridge 2nd Plat - subdivision development
03/06/2020
04/20/2020
04/22/2024
07/20/2023
Locations
Contacts
CMH PARKS INC, Address:5000 CLAYTON RD  
REDFORD CONSTRUCTION INC, Address:PO BOX 1065, Phone:(816) 540-2030  
Reviews
Review Type Outcome Est. Completion Date Completed
Licensed Contractors Approved 03/06/2020 04/20/2020
Dawn Bell
Fees
Paid Fees Amount Paid Owing Date Paid
Sanitary Sewer Insp Fees $7,400.55 $7,400.55 Paid 03/06/2020
Water Insp Fee $6,104.83 $6,104.83 Paid 03/06/2020
Water Test Fee $600.00 $600.00 Paid 03/06/2020
Storm Sewer Inspection Fee $9,355.45 $9,355.45 Paid 03/06/2020
Paved Surface Inspection Fee $11,644.91 $11,644.91 Paid 03/06/2020
Site Grading Fee $15,685.94 $15,685.94 Paid 03/06/2020
$15,685.95
Right of Way Permit Fee $80.00 $80.00 Paid 03/06/2020
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Water Line - Valve Partial 07/27/2020
Misc
Informational
07/27/2020
On Friday, 7-24-2020. Redford Excavating completed at water shut to install (1) Valve tap where the new water line will take off to tie in the end of phase 1 an go to the beginning of phase 2.
Misc
Informational
10/08/2020
On Tuesday, 10-06-2020 and Wednesday, 10-07-2020. Redford Excavating installed hydrant valves and main valves at waterline crossings at the intersections SW Arboridge Drive and Buckthorn St., Buckthorn St. & Arbor Tree Drive and Arbor Ridge Dr. and Arborway Terrace.
Sanitary Sewer Construction Inspection Partial 07/27/2020
Misc
Informational
07/08/2020
On Wednesday, 7-08-2020. Redford Construction resumed Sanitary Sewer installation, installing 8” sewer from manhole 1–2 sta.13+36 to18+00. MH—1-3 also was set on line #1. (5) y’s were installed for private taps.
Misc
Informational
07/13/2020
On Thursday, 7-09-2020. Redford Excavating resumed Sanitary Sewer installation. Contractor installed (3) laterals.
Misc
Informational
07/13/2020
Contractor resumed placement of the service laterals on Arbor lane dr.
Misc
Informational
07/15/2020
On Tuesday, 7-14-2020. Redford Excavating resumed installation of the Sanitary Sewer. Installed All remaining Laterals through sta. 18+00.
Misc
Informational
07/15/2020
On Wednesday, 7-15-2020. Redford Excavating resumed Sanitary Sewer installation. Completed approx. 100 LF of 8” Sewer until rain forced contractor to stop work for the day.
Misc
Informational
07/17/2020
On Friday, 7-17-2020. Redford Construction is installing 8” Sanitary Sewers. Because they encountered rock fill, they could only place 40 LF of sewer. The stop working early today because of the heat.
Misc
Informational
07/23/2020
On Thursday, 7-23-2020. Redford Excavating resumed Sanitary Sewer installation. MH - 5 and approx. 100’ of 8” sewer was placed continuing on line 1. Also crew #2 installed Laterial between station 16+40 and 18+70 east side of street.
Misc
Informational
07/27/2020
On Friday 7-24-2020. Redford Excavating resumed Sanitary Sewer installation of line #1 and installed MH - 1-6 Lateral lines lines at sta. 21+05, 21+76 and approx. 170 LF of 8” sewer. Crew #2 installaed laterals between sta. 16+00 thru 19+00.
Misc
Informational
07/27/2020
On Saturday, 7-25-2020. Redford Excavating “s crew #2 finished installing laterals for line #1. Contractor placed flowable fill over laterals and completed back fill of line #1 before the expected rain Monday!
Misc
Informational
07/30/2020
On Tuesday, 7-28-2020. Redford worked (2) crews and installed portions of line #2 and #3. MH 2-1 was installed with approx. 200 LF of 8” sewer line on line #2. Also the contractor installed approx. 100 LF of 8” sewer on line #3.
Misc
Informational
07/30/2020
On Thursday, 7-29-2020. Redford Excavating resumed Sanitary Sewer installation on Line #2 & #3. Lataerals were installed on line # 2 and on line #3 MH 4-1 was installed.
Misc
Informational
08/04/2020
Contractor rained out Friday 7-31-2020
Misc
Informational
08/04/2020
On Monday 8-03-2020. Redford Excavating resumed Sanitary Sewer installation. Rain on friday made for a messy day. All holes left opened are filled with water and pumping is needed at both sewer line installation areas being installed for line #4. The man hole 4-1 was installed. Also on line #3 MH 3-1 was installed with approx. 100 LF of 8” sewer.
Misc
Informational
08/04/2020
On Tuesday, 8-04-2020. Redford Excavating resumed Sanitary Sewer installation. Laterals 11 + 46 and 11+ 50 are installed for crew number (1). Crew #2 installed 8” sanitary sewer for line # 3 between sta. 20+85 to MH- 3-2
Misc
Informational
08/12/2020
On Wednesday 8-05-2020. Redford Excavating continued Sanitary Sewer installation for line #3. Crew #2 Set MH 3-2 & installed approximately 200 LF of 8” pipe. Crew #1 worked line #4towards MH 4-2 installing laterals between MN 4-1 to 4-2.
Misc
Informational
08/12/2020
On Friday, 8-07-2020. Contractor worked installing laterals between MH 4-2 and 4-1 also set MH 4-2. Second crew did not work.
Misc
Informational
08/12/2020
On Monday 8-10-2020, Contractor resumed Sanitary Sewer installation. Crew #1 placed 100’ of 8” sewer east of MH #4 on line #3. Crew #2 installed 2 laterals in rock on line #3.
Misc
Informational
08/12/2020
On Tuesday, 8-11-2020. Contractor resumed Sanitary Sewer installation at line #3. Crew #1 Sat MH 4-3 and installed approx. 240 LF of 8” sewer. Crew #2 worked on laterals for lots 106 & 107.
Misc
Informational
08/12/2020
On Wednesday, 8-12-2020. Redford Excavating installed laterals on line #3 for lots 146,147,111,112,113 &114. Crew #2 did laterals for lot’s 131 & 132 and placed flowable fill over them.
Misc
Informational
08/17/2020
On Thursday, 8-13-2020. The contractor installed laterals for line C - long side. Then placed flowable fill. Only worked with (1) crew.
Misc
Informational
08/17/2020
On Monday 8-17-2020. The contractor on friday worked backfilling laterals placed on yesterday. Also today Sanitary Sewer line were installed on line C. Appro. 100 LF was laid.
Misc
Informational
08/18/2020
Redford Excavating resumed Sanitary Sewer installation for line C Installed approx. 100 LF of sewer and 100 LF of 8” sewers and laterals for lots 133, 134,104 and 103. Completed some back fill and placed flowable fill.
Misc
Informational
08/21/2020
On Thursday, 8-20-2020. Redford Excavating resumed Sanitary Sewer Installation. Contractor completed laterals for lots 134,135, &136. Contractor placed flowable fill over laterals and backfilled laterals.
Storm - Material Verification Passed 09/01/2020
Misc
Informational
09/01/2020
Materials delivered to project all meet city specifications and are exceptable for use.
Storm - Outlet Structure Partial 09/01/2020
Misc
Informational
09/01/2020
On Tuesday, 9-01-2020. Redford Excavating began installation of the storm sewer. CI 2-4 Bottom section was installed and excavating was completed for pipe towards CI 2-5.
Misc
Informational
09/04/2020
On 9-03-2020. Redford installed structures 2-6,and CI 2-7 with 47 LF of 42” HDPE pipe. And poured concrete collars.
Misc
Informational
09/28/2020
Contractor installed structures CI 4-4, CI 7-1 and poured inverts and dog houses for storm sewer for line #6 on 9-24-2020.
Storm - Pipe Partial 09/09/2020
Misc
Informational
09/09/2020
On Tuesday, 9-08-2020. Redford Excavating resumed Storm Sewer installation. Contractor worked on Line #2 installing 42.5 LF of 42” HDPE pipe and set CI 2-8. Contractor also placed 60 LF of 36” storm pipe for line #4.
Misc
Informational
09/09/2020
On Wednesday, 9-09-2020. Contractor resumed Storm Sewer installation. Contractor installed structure CI 2-9 and placed 30 LF of line #2 and backfilled.
Misc
Informational
09/15/2020
On Monday, 9-14-2020. Redford Excavating worked (2) crews installing Storm line #1 at sta. 10+00 tapping into existing MH with 15” HDPE pipe placing pipe to CI 1-1. Approx. 250 LF of pipe was installed. Crew #(I) set structure 2-10 through 2-11 and installed 205LF of 15” HDPE Pipe.
Misc
Informational
09/15/2020
On Tuesday, 9-15-2020. Redford excavating resumed storm Sewer installation. Crew #1 installed CI 4-1 also crew #2 placed MH 3-1 FI 3-2
Misc
Informational
09/15/2020
Contractor placed 140 LF 18” HDPE Pipe for line #3 and 100 LF of 36”pipe fo line #4. Back field placed pipe.
Misc
Informational
09/22/2020
On Monday, 9-21-2020. Redford Excavating resumed Storm Sewer installation installing MH 4-3, CI 4-4 and approx. 144LF of 30” HDPE pipe. Also layer 100LF of 24” HDPE pipe and back filled pipe on line #4.
Misc
Informational
09/22/2020
On Tuesday 9-22-2020. Redford Excavating placed CI’s 4-5 & 4-6 and placed 40LF of 24” and 142 LF of 18” HDPE pipe. Also contractor Poured dog houses for MH 4-3, CI 4-4 & CI 4-5
Misc
Informational
09/25/2020
On Wednesday 9-23-2020, Redford excavating performed there own camera testing on the Sanitary Sewer. Contractor found MH 1-3 had entry and exit sewer pipe with bends . They dug up the MH 1-3 an made repairs to the pipe and or structure.
Misc
Informational
09/25/2020
On Thursday, 9-24-2020. Redford Excavating Installed CI 6-1,6-2 and placed approx. 140LF of 24” HDPE pipe and pour concrete dog houses for each structure. Contractor also installed FI 9-1 with 94LF of 15” HDPE pipe.
Misc
Informational
09/28/2020
On Friday, 9-25-2020. Red Ford Excavating installed approx. 145 LF of 24” HDPE pipe for lines 7 & 4
Misc
Informational
09/29/2020
On Monday, 9-28-2020. Red Ford Excavating installed 35 LF of 15” HDPE pipe on line #10 and 74 LF of of 24” for line #11. Contractor back filled and completed dog houses.
Sanitary Sewer - Air Test Passed 10/01/2020
Misc
Informational
10/01/2020
On Wednesday, 9-30-2020. Redford excavating completed all Sanitary Sewer air testing of city mains and also completed Vacuum testing of all sanitary sewer man holes. All testing passed inspections.
Sanitary Sewer - Mandrel Passed 10/01/2020
Misc
Informational
10/01/2020
On Thursday, 10-01-2020. Redford Excavating completed All mandrel testing of Sanitary Sewers and passed inspections.
Sanitary Sewer - Vacuum Passed 10/01/2020
Misc
Informational
10/01/2020
On Wednesday, 9-30-2020. Redford Excavating completed all Man Hole Vacuum testing for all Sanitary Manholes. All test passed inspections.
Water Line - Fire Hydrant Partial 10/08/2020
Misc
Informational
10/08/2020
On Tuesday, 10-06-2020. Redford Excavating installed (2) hydrants located - (1) on Buckthorn st. At sta. 11+56 line 3 and at Sta.15+27 line 1.
Water - Material Verification Passed 10/08/2020
Misc
Informational
10/08/2020
On Friday, 10-02-2020. A field review of Water Materials brought to project was performed and all materials met cities specifications.
Pavement-Stabilized Subgrade Partial 11/03/2020
Misc
Informational
10/22/2020
On Thursday, 10-22-2020. Spalding Excavating finished the Portland sub-grade stabilization and compaction installation. Kansas City Testing provided all density testing that passed with reading from 95% to 100% compaction.
Misc
Informational
11/03/2020
On Tuesday, 11-03-2020. Spalding Excavating installed type 5 aggr. Base and compacted to sub-grade.
Curb - Proof Roll Partial 11/17/2020
Misc
Informational
11/16/2020
On Monday, 11-16-2020. JK Concrete set curb string line for curb placement tomorrow.
Misc
Informational
11/17/2020
On Tuesday, 11-17-2020. JK Concrete installed CG-1 (curb machine) throughout project.
Misc
Informational
11/18/2020
On Wednesday, 11-18-2020 JK Concrete resumed curb installation. (Curb Machine) Contractor placed remaining CS curb and also formed and poured throats for the CG-1 curb poured day prior.
Site Visit Partial 11/20/2020
Misc
Informational
10/20/2020
On Tuesday, 10-20-2020. Spalding Construction is preparing SW Arbor Ridge for sub grade stabilization. Cutting sub-grade for fly ash/lime.
Misc
Informational
11/10/2020
On Monday, 11-09-2020. Redford Excavating installed 4” under drains for the CI’s throughout the project.
Misc
Informational
11/18/2020
On Tuesday, 11-17-2020. I got Sanitary Sewer test results back for the video camera from Water Dept. Sewers passed inspections, However Water has not looked at the Man Holes and will get me that info when it’s done.
Misc
Informational
11/20/2020
On Friday, 11-20-2020. Spalding Excavating began cutting finish roadway grading for asphalt overlay. They also began backfilling curb and completed some mass finish grading throughout project.
Pavement-Stabilized Subgrade Partial 12/01/2020
Water Line - Coliform Test 1 Partial 01/12/2021
Misc
Informational
01/12/2021
On Monday, 1-11-2020. Redford Excavating provided the first water sample for testing.
Water Line - Coliform Test 2 Passed 01/18/2021
Misc
Informational
01/12/2021
On Tuesday, 1-12-2021, Redford Excavating provided 2nd water sample and are still waiting on results for first sample.
Misc
Informational
01/18/2021
On Friday 1-15-2021. The test results for the water samples taken earlier in week tested negative for bacteria and passed all water installation.
Water Line - Construction Inspection Passed 01/18/2021
Misc
Informational
10/08/2020
On Tuesday and Wednesday, 10-06 and 10-07-2020. Redford Excavating installed 8” waterline at project site crossing throughout project. All intersections were water lines crossed the contractor installed hydrants, Valves, and 8” piping. Poured thrust blocks and all restraints at bends and “t”s
Misc
Informational
12/16/2020
On Wednesday, 12-16-2020. Redford Excavating began installation of the 8” pvc waterline. Began at sta. 10+00 installing hydrants and fitting heading up the base line. Contractor back filled pipe at the end of the day. Prepared thrust restraints as they went.
Misc
Informational
12/28/2020
On Thursday, 12-17-2020, thru Monday, 12-28-2020. Redford excavating is working installing the 8” waterline and fire hydrants. Contractor has approx 100 LF of pipe and (1) hydrant left to complete water system, all restraints and thrust blocks have been poured and contractor has completed backing,
Misc
Informational
01/18/2021
On Monday, 1-18-2021. Red Ford Excavating tied in at (2) locations the 8” water main where the test samples were taken. This is the final testing and water line installation needed the complete and accept the service.
Install Street and Stop Signs Passed 01/28/2021
Misc
Informational
01/28/2021
On Thursday, 1-28-2020, The signage was installed for the project by K&G Stripping.
Site Visit Complete 03/05/2021
Misc
Informational
10/20/2020
On Tuesday, 10-20-2020. Spalding Construction is preparing SW Arbor Ridge for sub grade stabilization. Cutting sub-grade for fly ash/lime.
Misc
Informational
01/12/2021
On Tuesday, 1-12-2021. JK Concrete began installing ADA Ramps throughout project. Intersections at Buckhorn and Arbor Ridge and Arbor Arbor Tree where poured.
Misc
Informational
01/25/2021
On Monday, 1-25-2021. A walk through punchlist for occupancy was conducted. Steve Robbins, Bob Berch and I represented the city of Lee’s Summit. Spalding Excavating, Redford Excavating, and Summit Homes development as was represented. Punch list items include curb replacement, CI grouting with lift cables cutting, erosion materials to be installed, water services completion Tracer tones and final inspections. Gutter buddies need concrete blocks installed in front of the buddies. Dirt piles need to be removed and a master drainage plan needs to be submitted.
Misc
Informational
03/05/2021
On Thursday, 3-04-2021. JK Concrete completed the ADA repairs needed to comply with what the city has requested to bring the ramps into compliance.
Misc
Informational
03/08/2021
On Monday, 3-08-2021. Spalding Contractors placed seeding and straw on project subgrade.
Sanitary Sewer Construction Inspection Passed 07/20/2023
Misc
Informational
07/06/2020
On Monday, 7-06-2020. Redford Construction began installing 8” sanitary pipe. They start on line #1 at sta. 10+00. 5 y’s lateral sewer taps where installed and approx. 200 LF of 8” sewer was installed as well.
Misc
Informational
07/06/2020
On Monday, 7-06-2020. Redford Construction began installing 8” sanitary pipe. They start on line #1 at sta. 10+00. 5 y’s lateral sewer taps where installed and approx. 200 LF of 8” sewer was installed as well.
Misc
Informational
07/07/2020
On Monday, 7-06-2020. Redford Construction began installing 8” sanitary pipe. They start on line #1 at sta. 10+00. 5 y’s lateral sewer taps where installed and approx. 200 LF of 8” sewer was installed as well.
Misc
Informational
07/07/2020
On Tuesday, 7-07-2020. Redford construction resumed Sanitary Sewer installation. Starting at sta. 12+00 to sta. 13+36 installing MH - 1. Laterals at sta. 12+14,12+18 & 13+02 were installed. Contractor also completed face fill over sewer.
Documents & Images
Date Uploaded File Type Document Name
03/06/2020 Receipt Receipt for transaction: 2020-001014
03/06/2020 Receipt Receipt for transaction: 2020-001015
03/06/2020 Receipt Receipt for transaction: 2020-001024
04/17/2020 Approved Set Hawthorne Ridge 2nd Sanitary Sewer Plans 4.17.20
04/17/2020 Approved Set Hawthorne Ridge 2nd Street & Storm Sewer Plans 4.17.20
04/17/2020 Approved Set Hawthorne Ridge 2nd Water Main Plans 4.17.20
10/23/2020 Approved Plans Hawthorn Ridge 2nd Plat Street & Storm Revisions Approved 10.23.20
01/07/2021 Letter DE-Permit
03/17/2021 2021-03-17_HR2 As-Built Sanitary Sewer Plans
03/18/2021 2021-03-17_HR2 As-Built Water Plans
03/18/2021 Accepted As-Built Street & Storm Sewer Plans
04/21/2021 Letter INSPECTION SUMMARY
04/21/2021 Letter INSPECTION SUMMARY
04/21/2021 Letter INSPECTION SUMMARY
04/21/2021 Letter INSPECTION SUMMARY
04/21/2021 Letter INSPECTION SUMMARY
04/21/2021 Letter INSPECTION SUMMARY
04/21/2021 Letter INSPECTION SUMMARY
04/21/2021 Letter INSPECTION SUMMARY
04/21/2021 Letter INSPECTION SUMMARY
04/21/2021 Letter INSPECTION SUMMARY
04/21/2021 Letter INSPECTION SUMMARY
04/21/2021 Letter INSPECTION SUMMARY
04/21/2021 Letter INSPECTION SUMMARY
04/21/2021 Letter INSPECTION SUMMARY
04/21/2021 Letter INSPECTION SUMMARY
04/21/2021 Letter INSPECTION SUMMARY
04/21/2021 Letter INSPECTION SUMMARY
04/21/2021 Letter INSPECTION SUMMARY
04/21/2021 Letter INSPECTION SUMMARY
04/21/2021 Letter INSPECTION SUMMARY
04/21/2021 Letter INSPECTION SUMMARY
04/21/2021 Letter INSPECTION SUMMARY
04/21/2021 Letter INSPECTION SUMMARY
04/21/2021 Letter INSPECTION SUMMARY
04/21/2021 Letter INSPECTION SUMMARY
04/21/2021 Letter INSPECTION SUMMARY
04/21/2021 Letter INSPECTION SUMMARY
04/21/2021 Letter INSPECTION SUMMARY
04/21/2021 Letter INSPECTION SUMMARY
04/21/2021 Letter INSPECTION SUMMARY
04/21/2021 Letter INSPECTION SUMMARY
04/21/2021 Letter INSPECTION SUMMARY
04/21/2021 Letter INSPECTION SUMMARY
04/21/2021 Letter INSPECTION SUMMARY
04/21/2021 Letter INSPECTION SUMMARY
04/21/2021 Letter INSPECTION SUMMARY
04/21/2021 Letter INSPECTION SUMMARY
04/21/2021 Letter INSPECTION SUMMARY
04/21/2021 Letter INSPECTION SUMMARY
04/21/2021 Letter INSPECTION SUMMARY
04/21/2021 Letter INSPECTION SUMMARY
04/21/2021 Letter INSPECTION SUMMARY
04/21/2021 Letter INSPECTION SUMMARY
04/22/2021 Hawthorne Ridge 2nd Plat Substantial Completion
04/22/2021 Hawthore Ridge 2nd Plat Punch List
06/02/2021 Security Document Hawthorne Ridge 2nd Plat - 3 yr maintenance bond
02/16/2023 Security Document Hawthorn Ridge 2nd Final Affidavit
07/20/2023 Letter DE-Certificate of Final Acceptance (Commercial)
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home