Summary


PRSUBD20200031
Public Infrastructure
Final Acceptance
FIVE THIRTY LLC
DEVELOPMENT COMPLETE
Public sanitary sewer
01/06/2020
01/30/2020
04/03/2023
04/24/2020
Locations
Contacts
FIVE THIRTY LLC, Address:50 SE 30TH ST  
REDFORD CONSTRUCTION INC, Address:PO BOX 1065, Phone:(816) 540-2030  
Reviews
Review Type Outcome Est. Completion Date Completed
Licensed Contractors Approved 01/06/2020 03/03/2020
Mike Weisenborn
Fees
Paid Fees Amount Paid Owing Date Paid
91100C8-Sanitary Sewer Insp Fees $676.96 $676.96 Paid 01/06/2020
9110073-Right of Way Permit Fee $80.00 $80.00 Paid 01/06/2020
9110081-Paved Surface Inspection Fee $456.43 $456.43 Paid 01/29/2020
9110068-Storm Fee $367.53 $367.53 Paid 01/29/2020
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Sanitary Sewer Construction Inspection Partial 2/18/2020 02/18/2020
Misc
Informational
02/18/2020
MH A-1 has been installed. The existing 8" line was cut and the MH was dropped in, a new 8" pipe was ran through the MH and the A-lok's and a fernco stainless steel strongback was installed to connect the new pipe on both sides of the MH. I spoke with Brent at water and he was ok with the pipe staying in as long as they cut the top off and kept the bottom for the flow line. This is not a doghouse MH because the botton of the MH is already in, they will pour the inverts aroud the pipe and cut off the top of the pipe.
Sanitary Sewer Construction Inspection Partial 2/18/2020 02/18/2020
Misc
Informational
02/18/2020
Installed the first service line , installed trench check, anode and tracer wire for lot 1. They also wrapped the MH and have backfilled, they were installing the lid and ring as I left.Steve Robbins 02/18/2020 4:16 PM
Sanitary Sewer Construction Inspection Partial 3/21/2020 02/28/2020
Misc
Informational
02/28/2020
MH -2 has been installed, wrapped and has been backfilled. The service line have been connected with wyes, they have anodes, tracer wire and the trench checks have all been poured. All the 8" pipe hase been installed and has been backfilled. We will be able to do the testing on Monday March 23.
Sanitary Sewer - Invert Passed 2/21/2020 02/28/2020
PW-Misc
Informational
02/28/2020
The inverts for the 2 MH's that were installed have been poured.
Erosion Control Inspection Passed 2/28/2020 02/28/2020
Sanitary - Material Verification Passed 2/13/2020 02/28/2020
Sanitary Sewer - Vacuum Passed 03/25/2020
Misc
Informational
03/25/2020
I observed the vacuum test for both north and south manholes. The north MH was approx 12’ deep and it held at 10 on the gauge with no drop for 2.5 minutes. Test Passed. The south MH was less than 10’ deep and it held at 10 on the gauge with no drop for 2 minutes. Test Passed.
Sanitary Sewer - Air Test Passed 03/25/2020
Misc
Informational
03/25/2020
I observed the air pressure test for the 8” line segment between the two manholes. The line is approximately 300’ ft and it held at 4psi for 8 minutes with no drop. Test passed.
Misc
Informational
03/25/2020
I observed the air pressure test for the 8” line segment between the two manholes. The line is approximately 300’ ft and it held at 4psi for 8 minutes with no drop. Test passed.
Misc
Informational
03/25/2020
I observed the air pressure test for the 8” line segment between the two manholes. The line is approximately 300’ ft and it held at 4psi for 8 minutes with no drop. Test passed.
Sanitary Sewer - Mandrel Passed 03/25/2020
Misc
Informational
03/25/2020
I observed the mandrel pull through the 8” sanitary sewer line with no deflection. I verified the correct mandrel size. Test passed.
Grading/Excavation/Fill Inspection Passed 04/03/2020
Sanitary - Material Verification Passed 04/03/2020
Sanitary Sewer Construction Inspection Passed 3/23/2020 04/03/2020
Misc
Informational
04/03/2020
The line has been constructed and all the testing has been completed and passed. The camera test has also passed.
Sanitary Sewer - Camera Test Passed 4/2/2020 04/03/2020
Misc
Informational
04/03/2020
The camera test has been completed and the sanitary lines have been accepted by the water department.
Documents & Images
Date Uploaded File Type Document Name
01/06/2020 Receipt Receipt for transaction: 2020-000063
01/29/2020 Receipt Receipt for transaction: 2020-000352
01/30/2020 Letter DE-Permit
02/18/2020 Letter DE-Daily Inspection Summary
02/18/2020 Letter DE-Daily Inspection Summary
02/28/2020 Letter DE-Daily Inspection Summary
02/28/2020 Letter DE-Daily Inspection Summary
03/25/2020 Letter INSPECTION SUMMARY
03/25/2020 Letter INSPECTION SUMMARY
03/25/2020 Letter INSPECTION SUMMARY
03/26/2020 MAIN ORCHARD ASBUILTS
04/03/2020 Letter DE-Daily Inspection Summary
04/09/2020 Activity Document Main-Orchard Public Sanitary Sewer Extention-Punch List
04/09/2020 Activity Document Main-Orchard Public Sanitary Sewer Substantial Completion
04/14/2020 Activity Document Main Orchard Sanitary LSMO Maint Bond
04/24/2020 Letter DE-Certificate of Final Acceptance (Commercial)
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home