Summary


PRSUBD20192368
Public Infrastructure
Final Acceptance
GOPPERT DUSTY L & KRISTINA N
DEVELOPMENT COMPLETE
Full subdivision infrustructure.
08/26/2019
09/03/2019
06/17/2023
01/12/2021
Locations
Contacts
GOPPERT DUSTY L & KRISTINA N, Address:708 SW SCHERER RD  
Dusty Goppert, Phone:(816) 942-7595  
Reviews
Review Type Outcome Est. Completion Date Completed
Master Draingage As-built Review Approved 05/12/2020 09/29/2020
Mike Weisenborn
Licensed Contractors Approved 08/26/2019 08/26/2019
Mike Weisenborn
Fees
Paid Fees Amount Paid Owing Date Paid
Sanitary Sewer Insp Fees $1,045.02 $1,045.02 Paid 08/26/2019
Water Insp Fee $477.54 $477.54 Paid 08/26/2019
Water Test Fee $200.00 $200.00 Paid 08/26/2019
Storm Sewer Inspection Fee $212.73 $212.73 Paid 08/26/2019
Paved Surface Inspection Fee $2,307.60 $2,307.60 Paid 08/26/2019
Site Grading Fee $461.37 $461.37 Paid 08/26/2019
Right of Way Permit Fee $80.00 $80.00 Paid 08/26/2019
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Erosion Control Inspection Passed 10/22/2019
Misc
Informational
10/22/2019
SEPTEMBER 5, 2019 Silt fence is installed. Portal Potty is onsite. Concrete wash out pit is also on site.
Sanitary Sewer Construction Inspection Partial 10/22/2019
Misc
Informational
10/22/2019
SEPTEMBER 9, 2019 Brian Snow and crew are starting to install Sanitary Sewer at existing manhole A1 0+00. Crew has the correct amount of gravel at the bottom and top of pipe.
Misc
Corrective Action Required
04/15/2020
On Tuesday, 4-14-2020, I completed a inspection that had failed from Water Services. A video was taken to view the new sanitary sewer line and the inspection failed. Debris was found in the line and needed to be washed out. Also grouting needed to be completed on all (4) MH and lift ring. In was determined. None of the MH were exceptable and (1) had not been done at all. The owner was notified the work had not passed and he needed to get some else to jet the system and recover the debris.
Sanitary Sewer Construction Inspection Partial 10/22/2019
Misc
Informational
10/22/2019
SEPTEMBER 10, 2019 Brian Snow and crew have cored into the existing stub at 0+00 and all gasket have been installed.
Sanitary Sewer Construction Inspection Partial 10/22/2019
Misc
Informational
10/22/2019
SEPTEMBER 12, 2019 Starting Stubb @ 0+00 to Manhole A2 has been complete and backfilled.
Sanitary Sewer Construction Inspection Partial 10/22/2019
Misc
Informational
10/22/2019
SEPTEMBER 13, 2019 Brian Snow and crew are installing 8” Sanitary Line from MH A2 and on. Crew also has hooked up Sanitary Line to cored stubb @ 0+00.
Sanitary Sewer Construction Inspection Partial 10/22/2019
Misc
Informational
10/22/2019
SEPTEMBER 13, 2019 Brian Snow and crew are installing 8” Sanitary Line from MH A2 and on. Crew also has hooked up Sanitary Line to cored stubb @ 0+00.
Misc
Informational
10/22/2019
SEPTEMBER 16, 2019 Upon Inspectors arrival, Brian Snow and crew had set MH A3 and were heading to set last ManHole by the end of the day which is Manhole A4 @ 5+37.89
Storm - Pipe Partial 10/22/2019
Misc
Informational
10/22/2019
SEPTEMBER 19, 2019 Brian Snow and crews were installing storm sewers . Inspector advised crews to make sure storm sewer pipes were installed straight.
Misc
Partial Correction
06/01/2020
On Monday, 6-01-2020. Developer (Dusty) Hired 2 - guy’s to re install the 15” storm sewer that was laid flat in elevation. Guy’s saw cut CI structure for re installment of pipe and dug up old 15” HDPE Pipe for re placement.
Water Line - Construction Inspection Partial 10/22/2019
Misc
Informational
10/22/2019
SEPTEMBER 19, 2019 Brian Snow and Crew are also installing 6” water line.
Water Line - Construction Inspection Partial 10/22/2019
Misc
Informational
10/22/2019
SEPTEMBER 24, 2019 70 LF OF 36’ PVC C900 has been installed and wrapped per revised plans.
Water Line - Construction Inspection Partial 10/22/2019
Misc
Informational
10/22/2019
SEPTEMBER 24, 2019 70 LF OF 36’ PVC C900 has been installed and wrapped per revised plans.
Misc
Informational
10/22/2019
SEPTEMBER 24, 2019 Construction Taps have been made by water department but no Valve checks have been done.
Water Line - Thrust Restraint Partial 10/22/2019
Misc
Informational
10/22/2019
SEPTEMBER 26, 2019 All kickers and restraints have been poured and formed.
Water Line - Hydrostatic Test Passed 10/22/2019
Misc
Informational
10/22/2019
OCTOBER 1, 2019 Inspector observed hydrostatic test performed by Brian Snow. Test was ran at 150 PSI from 130pm to 330pm.
Site Visit Complete 10/22/2019
Misc
Informational
10/22/2019
OCTOBER 1, 2019 OCTOBER 2, 2019 Inspector visually watched Brian Snow chlorinate water line on Oct 1, 2019 Inspector visually watched Brian Snow dechlorinate water line from 930 am to 11:00am. Inspector verified de chlorination with test strips. Inspector will take sample to Keystone Labs on 10/3/19.
Water Line - Coliform Test 1 Passed 10/22/2019
Misc
Corrective Action Required
10/22/2019
PASSED
Water Line - Coliform Test 2 Passed 10/22/2019
Misc
Informational
10/22/2019
PASSED
Sanitary Sewer - Air Test Passed 10/22/2019
Misc
Informational
10/22/2019
OCTOBER 15, 2019 Existing Manhole to A2= PASSED Manhole A2 to A3 = PASSED Manhole A3 to A4= PASSED
Sanitary Sewer - Mandrel Passed 10/22/2019
Misc
Informational
10/22/2019
OCTOBER 15, 2019 Existing to A2 = Pass A4 to A3 to A2 = one pull all the way through = Pass
Curb - Proof Roll Passed 11/07/2019
Misc
Informational
11/07/2019
NOVEMBER 7, 2019 PASSED Along with Dusty Goppert and his wife, Inspector visually observed a proof roll on CURBS AND CUL-DE-SAC. All areas passed proof roll. Quality Aggregates provided a tandem axle truck for proof roll with the appropriate weight in the truck.
Site Visit Partial 12/03/2019
Misc
Informational
12/03/2019
DECEMBER 3, 2019 Inspector arrived onsite to meet contractors pouring curbs. Contractor asked how many cylinders HE was suppose to make for compression testing on the curbs. Inspector notified contractor that HE was not supposed to make any. Inspector also said to contractors that a 3rd party testing company was suppose to make the cylinders as well as test for slump and air content and cylinders, due to weather, were suppose to be left onsite until they reached 3500 PSI. Inspector then called Dusty Goppert and told him that he needed a 3rd party testing lab to test and make cylinders. Dusty informed Inspector that the job would be moved to December 4, 2019 and all parties would be on site to follow city procedures.
Pavement-Curb Construction Partial 12/04/2019
Misc
Informational
12/04/2019
NOVEMBER 4, 2019 Concrete crews are onsite installing curbs. Curbs are being installed with a paving machine due to there being 800 ft of curb. Terracon was onsite to make compression strength cylinders and to check temp, slump, and air. Inspector also told crews to make sure they white cure and blanket.
Pavement-Surface Partial 01/10/2020
Misc
Informational
01/10/2020
DECEMBER 12, 2019 Advanced Asphalt was onsite installing the base layer of Asphalt to the project.
Street - Surface Course Passed 03/25/2020
Misc
Informational
03/25/2020
Advanced Asphalt Paving Company installed the surface lift for the street. I verified the correct equipment, mix type and temperature of the install. Terrecon testing lab is on site. The preliminary density testing results were in compliance with 96 percent or better.
Sanitary Sewer - Vacuum Passed 04/03/2020
Misc
Informational
10/22/2019
OCTOBER 15, 2019 Manhole A4=PASSED Manhole A3=PASSED Manhole A2 FAILED
Misc
Corrective Action Required
03/10/2020
I observed the Vac test for MH A-2. Test failed. The gauge dropped from 10 to below 9 at 82 seconds. The crew is going to make corrections then call back for another test at a later date.
Misc
Resolved
04/03/2020
On Friday 4-03-2020 I inspected a vacuum test for MH #2. The vacuum test held for 2 min, and lose (1) lb of air passing the vacuum test.
Sanitary Sewer - Vacuum Passed 05/26/2020
Misc
Informational
10/22/2019
OCTOBER 15, 2019 Manhole A4=PASSED Manhole A3=PASSED Manhole A2 FAILED
Misc
Resolved
04/03/2020
On Friday 4-03-2020 I inspected the vacuum testing of MH #2. Which held for (2) minutes from 10lbs only losing (1lb) MH passes vacuum test.
Storm - Swales Passed 06/04/2020
Misc
Informational
06/04/2020
On 6-03-2020. The contractor reconstructed the Storm Sewer swale because it was not right and would not pass inspection. New swale passes inspection
Storm - Rip Rap Passed 06/04/2020
Misc
Informational
06/04/2020
On Thursday, 6-04-2020. The contractor re installed rip rap at the end of the storm sewer. This is the redo due to placing the pipe to low.
Storm - Pipe Passed 06/04/2020
Misc
Informational
10/22/2019
SEPTEMBER 19, 2019 Brian Snow and crews were installing storm sewers . Inspector advised crews to make sure storm sewer pipes were installed straight.
Misc
Informational
06/04/2020
On Wednesday 6-03-2020. The contractor re-installed the 15” storm sewer pipe and end section from the CI to the to the end section. This was redone because the pipe was installed at the wrong elevation the first time.
Sanitary Sewer - Vacuum Passed 06/17/2020
Pavement-Curb Construction Passed 06/17/2020
Misc
Informational
12/04/2019
NOVEMBER 4, 2019 Concrete crews are onsite installing curbs. Curbs are being installed with a paving machine due to there being 800 ft of curb. Terracon was onsite to make compression strength cylinders and to check temp, slump, and air. Inspector also told crews to make sure they white cure and blanket.
Site Visit Complete 06/17/2020
Misc
Informational
12/03/2019
DECEMBER 3, 2019 Inspector arrived onsite to meet contractors pouring curbs. Contractor asked how many cylinders HE was suppose to make for compression testing on the curbs. Inspector notified contractor that HE was not supposed to make any. Inspector also said to contractors that a 3rd party testing company was suppose to make the cylinders as well as test for slump and air content and cylinders, due to weather, were suppose to be left onsite until they reached 3500 PSI. Inspector then called Dusty Goppert and told him that he needed a 3rd party testing lab to test and make cylinders. Dusty informed Inspector that the job would be moved to December 4, 2019 and all parties would be on site to follow city procedures.
Water Line - Thrust Restraint Passed 06/17/2020
Misc
Informational
10/22/2019
SEPTEMBER 26, 2019 All kickers and restraints have been poured and formed.
Water Line - Construction Inspection Passed 06/17/2020
Misc
Informational
10/22/2019
SEPTEMBER 24, 2019 70 LF OF 36’ PVC C900 has been installed and wrapped per revised plans.
Misc
Informational
10/22/2019
SEPTEMBER 24, 2019 Construction Taps have been made by water department but no Valve checks have been done.
Pavement-Surface Passed 06/17/2020
Misc
Informational
01/10/2020
DECEMBER 12, 2019 Advanced Asphalt was onsite installing the base layer of Asphalt to the project.
Sanitary Sewer Construction Inspection Passed 06/17/2020
Misc
Informational
10/22/2019
SEPTEMBER 13, 2019 Brian Snow and crew are installing 8” Sanitary Line from MH A2 and on. Crew also has hooked up Sanitary Line to cored stubb @ 0+00.
Misc
Informational
10/22/2019
SEPTEMBER 16, 2019 Upon Inspectors arrival, Brian Snow and crew had set MH A3 and were heading to set last ManHole by the end of the day which is Manhole A4 @ 5+37.89
Misc
Informational
06/17/2020
The water dept. did a camera test and found a sag, after it was repaired it sat for 30 days and they came out again and everything has now passed and sanitary.
Sanitary Sewer - Camera Test Passed 7/17/2020 06/17/2020
Storm - Material Verification Passed 06/17/2020
Water - Material Verification Partial 06/17/2020
Storm - Outlet Structure Passed 6/17/2020 06/17/2020
Misc
Informational
06/17/2020
The strorm outlet structure was installed incorrectly, there was no fall going into the pond and the water was going back into the pipe the wrong way. This problem has now been corrected and the water is flowing into the pond and they also installed rip rap at the end of the outlet structure. This has been accepted.
Storm - Inlets Clean Passed 06/17/2020
Documents & Images
Date Uploaded File Type Document Name
08/26/2019 Receipt Receipt for transaction: 2019-005783
08/30/2019 Letter DE-Permit
09/10/2019 scan_99845_2019-09-10-07-42-55
10/22/2019 SEPTEMBER 9, 2019 Sanitary Sewer Line @ 0+00
10/22/2019 gaskets
10/22/2019 Gaskets
10/22/2019 SEPTEMBER 12, 2019 Sanitary Line from 0+00 to 3+35.38 Manhole
10/22/2019 SEPTEMBER 13, 2019 Manhole A2 and SS Line
10/22/2019 SEPTEMBER 13, 2019 Cored Connection @ stub 0+00
10/22/2019 SEPTEMBER 16, 2019 MH A3 TO MH A4
10/22/2019 SEPTEMBER 19, 2019 Storm
10/22/2019 SEPTEMBER 19, 2019 6” Waterline Installation
10/22/2019 SEPTEMBER 19, 2019 6” Waterline Installation0
10/22/2019 SEPTEMBER 19, 2019 6” Waterline Installation1
10/22/2019 SEPTEMBER 24, 2019 70 LF OF 36’ PVC 900
10/22/2019 SEPTEMBER 24, 2019 Construction Taps
10/22/2019 SEPTEMBER 24, 2019 Construction Taps
10/22/2019 RESTRAINTS
10/22/2019 RESTRAINT
10/22/2019 RESTRAINTS0
10/22/2019 RESTRAINTS1
10/22/2019 RESTRAINTS2
10/22/2019 RESTRAINTS3
10/22/2019 RESTRAINTS4
10/22/2019 Letter INSPECTION SUMMARY
10/22/2019 Letter INSPECTION SUMMARY
10/22/2019 Letter INSPECTION SUMMARY
10/22/2019 Letter INSPECTION SUMMARY
10/22/2019 Letter INSPECTION SUMMARY
10/22/2019 Letter INSPECTION SUMMARY
10/22/2019 Letter INSPECTION SUMMARY
10/22/2019 Letter INSPECTION SUMMARY
10/22/2019 Letter INSPECTION SUMMARY
10/22/2019 Letter INSPECTION SUMMARY
10/22/2019 Letter INSPECTION SUMMARY
10/22/2019 Letter INSPECTION SUMMARY
10/22/2019 Letter INSPECTION SUMMARY
10/22/2019 Letter INSPECTION SUMMARY
10/22/2019 Letter INSPECTION SUMMARY
10/22/2019 Letter INSPECTION SUMMARY
10/22/2019 Letter INSPECTION SUMMARY
10/22/2019 Letter INSPECTION SUMMARY
10/22/2019 Letter INSPECTION SUMMARY
10/22/2019 Letter INSPECTION SUMMARY
11/07/2019 Letter INSPECTION SUMMARY
12/03/2019 Letter INSPECTION SUMMARY
12/04/2019 NOVEMBER 4, 2019 CURB INSTALLATION
03/10/2020 Letter INSPECTION SUMMARY
03/25/2020 Letter INSPECTION SUMMARY
05/27/2020 Goppert Acres- Storm Revisions approved 5.27.20
06/02/2020 Topo-Lots 1A&1B-6-2-20
06/15/2020 Plans GOPPERT GRADING REVISED 061520
06/16/2020 Goppert Acres As-graded MDP Accepted 6.16.20
06/17/2020 Letter DE-Daily Inspection Summary
06/17/2020 Letter DE-Daily Inspection Summary
06/17/2020 Letter DE-Punch List
06/17/2020 Goppert Acres Substantial Completion
06/17/2020 Goppert Acres Punch List
07/09/2020 Plans 18028 AB3-WATER
09/15/2020 Maintenance Bond
10/16/2020 Activity Document Final Affidavit
10/16/2020 Drawing Sanitary As-built
10/16/2020 Plans 18028 AB-SANITARY
11/04/2020 Plans 18028 GOPPERT AS BUILT - Street
11/04/2020 Plans 18028 GOPPERT AS BUILT - Street
10/16/2020 Plans 18028 AB-SANITARY
07/09/2020 Plans 18028 AB3-WATER
01/12/2021 Letter DE-Certificate of Final Acceptance (Commercial)
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home