Permit Application Status

PRSITE20244163


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary


PRSITE20244163
Development - Site
Final Completion
CURRY INVESTMENT COMPANY
DEVELOPMENT COMPLETE
Replacement of private water line
08/08/2024
08/09/2024
01/10/2025
Locations
Contacts
CURRY INVESTMENT COMPANY, Address:2700 KENDALLWOOD PKWY STE 208  
Levi Bernard, Stark Boring Co., Inc.  
STARK BORING COMPANY INC, Address:202 SW OUTER RD, Phone:(816) 293-5289  
Reviews
Review Type Outcome Est. Completion Date Completed
Licensed Contractors Approved 08/08/2024 08/08/2024
Grant White
Fees
Paid Fees Amount Paid Owing Date Paid
Water Insp Fee $11,190.00 $11,190.00 Paid 08/15/2024
Water Test Fee $200.00 $200.00 Paid 08/15/2024
Right of Way Permit Fee $85.00 $85.00 Paid 08/15/2024
Outstanding Fees Amount Paid Owing Date Paid
After Hours Inspection (Building Codes)(Per Hour) $275.00 $0.00 $275.00 Not Paid
After Hours Inspections (Public Works)(Per Hour) $500.00 $0.00 $500.00 Not Paid


$775.00    Add Fees to My Cart
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Site Visit Partial 8/21/2024 8/21/2024 08/21/2024
Misc
Informational
08/21/2024
08/21/24 Wednesday JMJ Contractor not on site as of today.
Water Line - Construction Inspection Partial 9/6/2024 9/6/2024 09/06/2024
Misc
Informational
09/06/2024
09/06/24 Friday JMJ (Stark Boring-Scott) Contractor started yesterday began to excavate site to began installation of waterline. The contractor is planning a night shut for Monday. I will inform water of the shut on the private waterline & the fire hydrants that will effected.
Water Line - Construction Inspection Partial 9/10/2024 9/10/2024 09/10/2024
Misc
Informational
09/06/2024
09/06/24 Friday JMJ (Stark Boring-Scott) Contractor started yesterday began to excavate site to began installation of waterline. The contractor is planning a night shut for Monday. I will inform water of the shut on the private waterline & the fire hydrants that will effected. 09/10/24 Tuesday JMJ (Stark Boring-Scoot) Contractor throttle down water @ Summit Shopping Center @ 1:30AM for a night shut to construct tie-in location. The removal of existing 90 degree bend for a 6"X6" tee 2/90 deg bends with stainless steel all-threads to establish new grade. Water line was flushed after tie-in was completed.
Water Line - Construction Inspection Partial 9/11/2024 9/11/2024 09/11/2024
Misc
Informational
09/10/2024
09/06/24 Friday JMJ (Stark Boring-Scott) Contractor started yesterday began to excavate site to began installation of waterline. The contractor is planning a night shut for Monday. I will inform water of the shut on the private waterline & the fire hydrants that will effected. 09/10/24 Tuesday JMJ (Stark Boring-Scott) Contractor throttle down water @ Summit Shopping Center @ 1:30AM for a night shut to construct tie-in location. The removal of existing 90 degree bend for a 6"X6" tee 2/90 deg bends with stainless steel all-threads to establish new grade. Water line was flushed after tie-in was completed. The 6" gate was installed after the 90 degree bend on the high side. 09/11/24 Wednesday JMJ (Stark Boring-Scott) Contractor installed approximately 25' of 6" PVC water main 2/45 degree bends used all-threads on the 45 degree point down to obtain space from existing RCP storm pipe. Contractor place steel plates over trench excavation for the water line parking lot area.
Water Line - Construction Inspection Partial 9/12/2024 9/12/2024 09/12/2024
Misc
Informational
09/11/2024
09/06/24 Friday JMJ (Stark Boring-Scott) Contractor started yesterday began to excavate site to began installation of waterline. The contractor is planning a night shut for Monday. I will inform water of the shut on the private waterline & the fire hydrants that will effected. 09/10/24 Tuesday JMJ (Stark Boring-Scott) Contractor throttle down water @ Summit Shopping Center @ 1:30AM for a night shut to construct tie-in location. The removal of existing 90 degree bend for a 6"X6" tee 2/90 deg bends with stainless steel all-threads to establish new grade. Water line was flushed after tie-in was completed. The 6" gate was installed after the 90 degree bend on the high side. 09/11/24 Wednesday JMJ (Stark Boring-Scott) Contractor installed approximately 25' of 6" PVC water main 2/45 degree bends used all-threads on the 45 degree point down to obtain space from existing RCP storm pipe. Contractor place steel plates over trench excavation for the water line parking lot area. Backing blocks were poured. 09/12/24 Thursday JMJ (Stark Boring-Scott) Contractor installed approximately 120' of 6" PVC water main.
Water Line - Construction Inspection Partial 9/13/2024 9/13/2024 09/13/2024
Misc
Informational
09/12/2024
09/06/24 Friday JMJ (Stark Boring-Scott) Contractor started yesterday began to excavate site to began installation of waterline. The contractor is planning a night shut for Monday. I will inform water of the shut on the private waterline & the fire hydrants that will effected. 09/10/24 Tuesday JMJ (Stark Boring-Scott) Contractor throttle down water @ Summit Shopping Center @ 1:30AM for a night shut to construct tie-in location. The removal of existing 90 degree bend for a 6"X6" tee 2/90 deg bends with stainless steel all-threads to establish new grade. Water line was flushed after tie-in was completed. The 6" gate was installed after the 90 degree bend on the high side. 09/11/24 Wednesday JMJ (Stark Boring-Scott) Contractor installed approximately 25' of 6" PVC water main 2/45 degree bends used all-threads on the 45 degree point down to obtain space from existing RCP storm pipe. Contractor place steel plates over trench excavation for the water line parking lot area. Backing blocks were poured. 09/12/24 Thursday JMJ (Stark Boring-Scott) Contractor installed approximately 120' of 6" PVC water main. 09/13/24 Friday JMJ (Stark Boring-Scoot) Contractor installed approximately 40' of 6" PVC water main. The contractor clean up the construction site and covered excavated trench for water line.
Water Line - Construction Inspection Partial 9/16/2024 9/16/2024 09/16/2024
Misc
Informational
09/13/2024
09/06/24 Friday JMJ (Stark Boring-Scott) Contractor started yesterday began to excavate site to began installation of waterline. The contractor is planning a night shut for Monday. I will inform water of the shut on the private waterline & the fire hydrants that will effected. 09/10/24 Tuesday JMJ (Stark Boring-Scott) Contractor throttle down water @ Summit Shopping Center @ 1:30AM for a night shut to construct tie-in location. The removal of existing 90 degree bend for a 6"X6" tee 2/90 deg bends with stainless steel all-threads to establish new grade. Water line was flushed after tie-in was completed. The 6" gate was installed after the 90 degree bend on the high side. 09/11/24 Wednesday JMJ (Stark Boring-Scott) Contractor installed approximately 25' of 6" PVC water main 2/45 degree bends used all-threads on the 45 degree point down to obtain space from existing RCP storm pipe. Contractor place steel plates over trench excavation for the water line parking lot area. Backing blocks were poured. 09/12/24 Thursday JMJ (Stark Boring-Scott) Contractor installed approximately 120' of 6" PVC water main. 09/13/24 Friday JMJ (Stark Boring-Scott) Contractor installed approximately 40' of 6" PVC water main. The contractor clean up the construction site and covered excavated trench for water line. 09/16/24 Monday JMJ (Stark Boring-Scott) Contractor installed approximately 100' of PVC water main. The contractor clean up the construction site and covered excavated trench for water line.
Water Line - Construction Inspection Partial 9/18/2024 9/18/2024 09/18/2024
Misc
Informational
09/16/2024
09/06/24 Friday JMJ (Stark Boring-Scott) Contractor started yesterday began to excavate site to began installation of waterline. The contractor is planning a night shut for Monday. I will inform water of the shut on the private waterline & the fire hydrants that will effected. 09/10/24 Tuesday JMJ (Stark Boring-Scott) Contractor throttle down water @ Summit Shopping Center @ 1:30AM for a night shut to construct tie-in location. The removal of existing 90 degree bend for a 6"X6" tee 2/90 deg bends with stainless steel all-threads to establish new grade. Water line was flushed after tie-in was completed. The 6" gate was installed after the 90 degree bend on the high side. 09/11/24 Wednesday JMJ (Stark Boring-Scott) Contractor installed approximately 25' of 6" PVC water main 2/45 degree bends used all-threads on the 45 degree point down to obtain space from existing RCP storm pipe. Contractor place steel plates over trench excavation for the water line parking lot area. Backing blocks were poured. 09/12/24 Thursday JMJ (Stark Boring-Scott) Contractor installed approximately 120' of 6" PVC water main. 09/13/24 Friday JMJ (Stark Boring-Scott) Contractor installed approximately 40' of 6" PVC water main. The contractor clean up the construction site and covered excavated trench for water line. 09/16/24 Monday JMJ (Stark Boring-Scott) Contractor installed approximately 100' of 6" PVC water main. The contractor clean up the construction site and covered excavated trench for water line. 09/18/24 Wednesday JMJ (Stark Boring-Scott) Contractor installed approximately 120' of 6" PVC water main.
Water Line - Construction Inspection Partial 9/20/2024 9/20/2024 09/20/2024
Misc
Informational
09/18/2024
09/06/24 Friday JMJ (Stark Boring-Scott) Contractor started yesterday began to excavate site to began installation of waterline. The contractor is planning a night shut for Monday. I will inform water of the shut on the private waterline & the fire hydrants that will effected. 09/10/24 Tuesday JMJ (Stark Boring-Scott) Contractor throttle down water @ Summit Shopping Center @ 1:30AM for a night shut to construct tie-in location. The removal of existing 90 degree bend for a 6"X6" tee 2/90 deg bends with stainless steel all-threads to establish new grade. Water line was flushed after tie-in was completed. The 6" gate was installed after the 90 degree bend on the high side. 09/11/24 Wednesday JMJ (Stark Boring-Scott) Contractor installed approximately 25' of 6" PVC water main 2/45 degree bends used all-threads on the 45 degree point down to obtain space from existing RCP storm pipe. Contractor place steel plates over trench excavation for the water line parking lot area. Backing blocks were poured. 09/12/24 Thursday JMJ (Stark Boring-Scott) Contractor installed approximately 120' of 6" PVC water main. 09/13/24 Friday JMJ (Stark Boring-Scott) Contractor installed approximately 40' of 6" PVC water main. The contractor clean up the construction site and covered excavated trench for water line. 09/16/24 Monday JMJ (Stark Boring-Scott) Contractor installed approximately 100' of 6" PVC water main. The contractor clean up the construction site and covered excavated trench for water line. 09/18/24 Wednesday JMJ (Stark Boring-Scott) Contractor installed approximately 120' of 6" PVC water main. 09/20/24 Friday JMJ (Stark Boring-Scott) Contractor continued 6" PVC water installation with a tee 6"X6" & valve the will run to Freddy's restaurant yesterday it was inspected by (BR).Today contractor cleaned parking lot area and broke through rock. Contractor preparing for weekend rain condition.
Water Line - Construction Inspection Partial 9/25/2024 9/25/2024 09/25/2024
Misc
Informational
09/20/2024
09/06/24 Friday JMJ (Stark Boring-Scott) Contractor started yesterday began to excavate site to began installation of waterline. The contractor is planning a night shut for Monday. I will inform water of the shut on the private waterline & the fire hydrants that will effected. 09/10/24 Tuesday JMJ (Stark Boring-Scott) Contractor throttle down water @ Summit Shopping Center @ 1:30AM for a night shut to construct tie-in location. The removal of existing 90 degree bend for a 6"X6" tee 2/90 deg bends with stainless steel all-threads to establish new grade. Water line was flushed after tie-in was completed. The 6" gate was installed after the 90 degree bend on the high side. 09/11/24 Wednesday JMJ (Stark Boring-Scott) Contractor installed approximately 25' of 6" PVC water main 2/45 degree bends used all-threads on the 45 degree point down to obtain space from existing RCP storm pipe. Contractor place steel plates over trench excavation for the water line parking lot area. Backing blocks were poured. 09/12/24 Thursday JMJ (Stark Boring-Scott) Contractor installed approximately 120' of 6" PVC water main. 09/13/24 Friday JMJ (Stark Boring-Scott) Contractor installed approximately 40' of 6" PVC water main. The contractor clean up the construction site and covered excavated trench for water line. 09/16/24 Monday JMJ (Stark Boring-Scott) Contractor installed approximately 100' of 6" PVC water main. The contractor clean up the construction site and covered excavated trench for water line. 09/18/24 Wednesday JMJ (Stark Boring-Scott) Contractor installed approximately 120' of 6" PVC water main. 09/20/24 Friday JMJ (Stark Boring-Scott) Contractor continued 6" PVC water installation with a tee 6"X6" & valve the will run to Freddy's restaurant yesterday it was inspected by (BR).Today contractor cleaned parking lot area and broke through rock. Contractor preparing for weekend rain condition. 09/25/24 Wednesday JMJ (Stark Boring-Scott) Contractor continued to install 6" water main but rain into heavy rock only 100' for today and yesterday.
Water Line - Construction Inspection Partial 9/27/2024 9/27/2024 09/27/2024
Misc
Informational
09/25/2024
09/06/24 Friday JMJ (Stark Boring-Scott) Contractor started yesterday began to excavate site to began installation of waterline. The contractor is planning a night shut for Monday. I will inform water of the shut on the private waterline & the fire hydrants that will effected. 09/10/24 Tuesday JMJ (Stark Boring-Scott) Contractor throttle down water @ Summit Shopping Center @ 1:30AM for a night shut to construct tie-in location. The removal of existing 90 degree bend for a 6"X6" tee 2/90 deg bends with stainless steel all-threads to establish new grade. Water line was flushed after tie-in was completed. The 6" gate was installed after the 90 degree bend on the high side. 09/11/24 Wednesday JMJ (Stark Boring-Scott) Contractor installed approximately 25' of 6" PVC water main 2/45 degree bends used all-threads on the 45 degree point down to obtain space from existing RCP storm pipe. Contractor place steel plates over trench excavation for the water line parking lot area. Backing blocks were poured. 09/12/24 Thursday JMJ (Stark Boring-Scott) Contractor installed approximately 120' of 6" PVC water main. 09/13/24 Friday JMJ (Stark Boring-Scott) Contractor installed approximately 40' of 6" PVC water main. The contractor clean up the construction site and covered excavated trench for water line. 09/16/24 Monday JMJ (Stark Boring-Scott) Contractor installed approximately 100' of 6" PVC water main. The contractor clean up the construction site and covered excavated trench for water line. 09/18/24 Wednesday JMJ (Stark Boring-Scott) Contractor installed approximately 120' of 6" PVC water main. 09/20/24 Friday JMJ (Stark Boring-Scott) Contractor continued 6" PVC water installation with a tee 6"X6" & valve the will run to Freddy's restaurant yesterday it was inspected by (BR).Today contractor cleaned parking lot area and broke through rock. Contractor preparing for weekend rain condition. 09/25/24 Wednesday JMJ (Stark Boring-Scott) Contractor continued to install 6" water main, but ran into heavy rock only 100' for today and yesterday. 09/27/24 Friday JMJ (Stark Boring-Scott) Contractor continued to install 6" water main only 2 stick pipe were laid yesterday. Contractor will install another stick pipe and a 90 degree bend on the water pipe. Contractor will installed the 6''X6" tee as-per project plan.
Water Line - Construction Inspection Partial 10/1/2024 10/1/2024 10/01/2024
Misc
Informational
09/27/2024
09/06/24 Friday JMJ (Stark Boring-Scott) Contractor started yesterday began to excavate site to began installation of waterline. The contractor is planning a night shut for Monday. I will inform water of the shut on the private waterline & the fire hydrants that will effected. 09/10/24 Tuesday JMJ (Stark Boring-Scott) Contractor throttle down water @ Summit Shopping Center @ 1:30AM for a night shut to construct tie-in location. The removal of existing 90 degree bend for a 6"X6" tee 2/90 deg bends with stainless steel all-threads to establish new grade. Water line was flushed after tie-in was completed. The 6" gate was installed after the 90 degree bend on the high side. 09/11/24 Wednesday JMJ (Stark Boring-Scott) Contractor installed approximately 25' of 6" PVC water main 2/45 degree bends used all-threads on the 45 degree point down to obtain space from existing RCP storm pipe. Contractor place steel plates over trench excavation for the water line parking lot area. Backing blocks were poured. 09/12/24 Thursday JMJ (Stark Boring-Scott) Contractor installed approximately 120' of 6" PVC water main. 09/13/24 Friday JMJ (Stark Boring-Scott) Contractor installed approximately 40' of 6" PVC water main. The contractor clean up the construction site and covered excavated trench for water line. 09/16/24 Monday JMJ (Stark Boring-Scott) Contractor installed approximately 100' of 6" PVC water main. The contractor clean up the construction site and covered excavated trench for water line. 09/18/24 Wednesday JMJ (Stark Boring-Scott) Contractor installed approximately 120' of 6" PVC water main. 09/20/24 Friday JMJ (Stark Boring-Scott) Contractor continued 6" PVC water installation with a tee 6"X6" & valve the will run to Freddy's restaurant yesterday it was inspected by (BR).Today contractor cleaned parking lot area and broke through rock. Contractor preparing for weekend rain condition. 09/25/24 Wednesday JMJ (Stark Boring-Scott) Contractor continued to install 6" water main, but ran into heavy rock only 100' for today and yesterday. 09/27/24 Friday JMJ (Stark Boring-Scott) Contractor continued to install 6" water main only 2 stick pipe were laid yesterday. Contractor will install another stick pipe and a 90 degree bend on the water pipe. Contractor will installed the 6''X6" tee as-per project plan. 10/01/24 Monday JMJ (Stark Boring-Scott) Contractor installed only 60' of 6" water main because of breaking heavy rock.
Water Line - Construction Inspection Partial 10/2/2024 10/2/2024 10/02/2024
Misc
Informational
10/01/2024
09/06/24 Friday JMJ (Stark Boring-Scott) Contractor started yesterday began to excavate site to began installation of waterline. The contractor is planning a night shut for Monday. I will inform water of the shut on the private waterline & the fire hydrants that will effected. 09/10/24 Tuesday JMJ (Stark Boring-Scott) Contractor throttle down water @ Summit Shopping Center @ 1:30AM for a night shut to construct tie-in location. The removal of existing 90 degree bend for a 6"X6" tee 2/90 deg bends with stainless steel all-threads to establish new grade. Water line was flushed after tie-in was completed. The 6" gate was installed after the 90 degree bend on the high side. 09/11/24 Wednesday JMJ (Stark Boring-Scott) Contractor installed approximately 25' of 6" PVC water main 2/45 degree bends used all-threads on the 45 degree point down to obtain space from existing RCP storm pipe. Contractor place steel plates over trench excavation for the water line parking lot area. Backing blocks were poured. 09/12/24 Thursday JMJ (Stark Boring-Scott) Contractor installed approximately 120' of 6" PVC water main. 09/13/24 Friday JMJ (Stark Boring-Scott) Contractor installed approximately 40' of 6" PVC water main. The contractor clean up the construction site and covered excavated trench for water line. 09/16/24 Monday JMJ (Stark Boring-Scott) Contractor installed approximately 100' of 6" PVC water main. The contractor clean up the construction site and covered excavated trench for water line. 09/18/24 Wednesday JMJ (Stark Boring-Scott) Contractor installed approximately 120' of 6" PVC water main. 09/20/24 Friday JMJ (Stark Boring-Scott) Contractor continued 6" PVC water installation with a tee 6"X6" & valve the will run to Freddy's restaurant yesterday it was inspected by (BR).Today contractor cleaned parking lot area and broke through rock. Contractor preparing for weekend rain condition. 09/25/24 Wednesday JMJ (Stark Boring-Scott) Contractor continued to install 6" water main, but ran into heavy rock only 100' for today and yesterday. 09/27/24 Friday JMJ (Stark Boring-Scott) Contractor continued to install 6" water main only 2 stick pipe were laid yesterday. Contractor will install another stick pipe and a 90 degree bend on the water pipe. Contractor will installed the 6''X6" tee as-per project plan. 10/01/24 Monday JMJ (Stark Boring-Scott) Contractor installed only 60' of 6" water main because of breaking heavy rock. 10/02/24 Tuesday JMJ ( Stark Boring-Scott) Contractor was able to install two sticks on Monday & two on Tuesday. Contractor continued to to break rock to install the 6" water main.
Water Line - Construction Inspection Partial 10/3/2024 10/3/2024 10/03/2024
Misc
Informational
10/02/2024
09/06/24 Friday JMJ (Stark Boring-Scott) Contractor started yesterday began to excavate site to began installation of waterline. The contractor is planning a night shut for Monday. I will inform water of the shut on the private waterline & the fire hydrants that will effected. 09/10/24 Tuesday JMJ (Stark Boring-Scott) Contractor throttle down water @ Summit Shopping Center @ 1:30AM for a night shut to construct tie-in location. The removal of existing 90 degree bend for a 6"X6" tee 2/90 deg bends with stainless steel all-threads to establish new grade. Water line was flushed after tie-in was completed. The 6" gate was installed after the 90 degree bend on the high side. 09/11/24 Wednesday JMJ (Stark Boring-Scott) Contractor installed approximately 25' of 6" PVC water main 2/45 degree bends used all-threads on the 45 degree point down to obtain space from existing RCP storm pipe. Contractor place steel plates over trench excavation for the water line parking lot area. Backing blocks were poured. 09/12/24 Thursday JMJ (Stark Boring-Scott) Contractor installed approximately 120' of 6" PVC water main. 09/13/24 Friday JMJ (Stark Boring-Scott) Contractor installed approximately 40' of 6" PVC water main. The contractor clean up the construction site and covered excavated trench for water line. 09/16/24 Monday JMJ (Stark Boring-Scott) Contractor installed approximately 100' of 6" PVC water main. The contractor clean up the construction site and covered excavated trench for water line. 09/18/24 Wednesday JMJ (Stark Boring-Scott) Contractor installed approximately 120' of 6" PVC water main. 09/20/24 Friday JMJ (Stark Boring-Scott) Contractor continued 6" PVC water installation with a tee 6"X6" & valve the will run to Freddy's restaurant yesterday it was inspected by (BR).Today contractor cleaned parking lot area and broke through rock. Contractor preparing for weekend rain condition. 09/25/24 Wednesday JMJ (Stark Boring-Scott) Contractor continued to install 6" water main, but ran into heavy rock only 100' for today and yesterday. 09/27/24 Friday JMJ (Stark Boring-Scott) Contractor continued to install 6" water main only 2 stick pipe were laid yesterday. Contractor will install another stick pipe and a 90 degree bend on the water pipe. Contractor will installed the 6''X6" tee as-per project plan. 10/01/24 Monday JMJ (Stark Boring-Scott) Contractor installed only 60' of 6" water main because of breaking heavy rock. 10/02/24 Tuesday JMJ (Stark Boring-Scott) Contractor was able to install two sticks on Monday & two on Tuesday. Contractor continued to to break rock to install the 6" water main. 10/03/24 Wednesday JMJ (Stark Boring-Scott) Contractor installed 170' of 6" water main plus a 6"X6" tee. Contractor backfilled and used a vibration plate to compact excavation trench. Contractor cleaned up area around excavation and used plates.
Water Line - Construction Inspection Partial 10/15/2024 10/15/2024 10/15/2024
Misc
Informational
10/03/2024
09/06/24 Friday JMJ (Stark Boring-Scott) Contractor started yesterday began to excavate site to began installation of waterline. The contractor is planning a night shut for Monday. I will inform water of the shut on the private waterline & the fire hydrants that will effected. 09/10/24 Tuesday JMJ (Stark Boring-Scott) Contractor throttle down water @ Summit Shopping Center @ 1:30AM for a night shut to construct tie-in location. The removal of existing 90 degree bend for a 6"X6" tee 2/90 deg bends with stainless steel all-threads to establish new grade. Water line was flushed after tie-in was completed. The 6" gate was installed after the 90 degree bend on the high side. 09/11/24 Wednesday JMJ (Stark Boring-Scott) Contractor installed approximately 25' of 6" PVC water main 2/45 degree bends used all-threads on the 45 degree point down to obtain space from existing RCP storm pipe. Contractor place steel plates over trench excavation for the water line parking lot area. Backing blocks were poured. 09/12/24 Thursday JMJ (Stark Boring-Scott) Contractor installed approximately 120' of 6" PVC water main. 09/13/24 Friday JMJ (Stark Boring-Scott) Contractor installed approximately 40' of 6" PVC water main. The contractor clean up the construction site and covered excavated trench for water line. 09/16/24 Monday JMJ (Stark Boring-Scott) Contractor installed approximately 100' of 6" PVC water main. The contractor clean up the construction site and covered excavated trench for water line. 09/18/24 Wednesday JMJ (Stark Boring-Scott) Contractor installed approximately 120' of 6" PVC water main. 09/20/24 Friday JMJ (Stark Boring-Scott) Contractor continued 6" PVC water installation with a tee 6"X6" & valve the will run to Freddy's restaurant yesterday it was inspected by (BR).Today contractor cleaned parking lot area and broke through rock. Contractor preparing for weekend rain condition. 09/25/24 Wednesday JMJ (Stark Boring-Scott) Contractor continued to install 6" water main, but ran into heavy rock only 100' for today and yesterday. 09/27/24 Friday JMJ (Stark Boring-Scott) Contractor continued to install 6" water main only 2 stick pipe were laid yesterday. Contractor will install another stick pipe and a 90 degree bend on the water pipe. Contractor will installed the 6''X6" tee as-per project plan. 10/01/24 Monday JMJ (Stark Boring-Scott) Contractor installed only 60' of 6" water main because of breaking heavy rock. 10/02/24 Tuesday JMJ (Stark Boring-Scott) Contractor was able to install two sticks on Monday & two on Tuesday. Contractor continued to to break rock to install the 6" water main. 10/03/24 Wednesday JMJ (Stark Boring-Scott) Contractor installed 170' of 6" water main plus a 6"X6" tee. Contractor backfilled and used a vibration plate to compact excavation trench. Contractor cleaned up area around excavation and used plates. 10/15/24 Tuesday JMJ (Stark Boring-Scott) 2 hour Hydrostatic passed for 6" private waterline. Contractor is chlorinating 6" private waterline.
Water Line - Construction Inspection Partial 10/16/2024 10/16/2024 10/16/2024
Misc
Informational
10/15/2024
09/06/24 Friday JMJ (Stark Boring-Scott) Contractor started yesterday began to excavate site to began installation of waterline. The contractor is planning a night shut for Monday. I will inform water of the shut on the private waterline & the fire hydrants that will effected. 09/10/24 Tuesday JMJ (Stark Boring-Scott) Contractor throttle down water @ Summit Shopping Center @ 1:30AM for a night shut to construct tie-in location. The removal of existing 90 degree bend for a 6"X6" tee 2/90 deg bends with stainless steel all-threads to establish new grade. Water line was flushed after tie-in was completed. The 6" gate was installed after the 90 degree bend on the high side. 09/11/24 Wednesday JMJ (Stark Boring-Scott) Contractor installed approximately 25' of 6" PVC water main 2/45 degree bends used all-threads on the 45 degree point down to obtain space from existing RCP storm pipe. Contractor place steel plates over trench excavation for the water line parking lot area. Backing blocks were poured. 09/12/24 Thursday JMJ (Stark Boring-Scott) Contractor installed approximately 120' of 6" PVC water main. 09/13/24 Friday JMJ (Stark Boring-Scott) Contractor installed approximately 40' of 6" PVC water main. The contractor clean up the construction site and covered excavated trench for water line. 09/16/24 Monday JMJ (Stark Boring-Scott) Contractor installed approximately 100' of 6" PVC water main. The contractor clean up the construction site and covered excavated trench for water line. 09/18/24 Wednesday JMJ (Stark Boring-Scott) Contractor installed approximately 120' of 6" PVC water main. 09/20/24 Friday JMJ (Stark Boring-Scott) Contractor continued 6" PVC water installation with a tee 6"X6" & valve the will run to Freddy's restaurant yesterday it was inspected by (BR).Today contractor cleaned parking lot area and broke through rock. Contractor preparing for weekend rain condition. 09/25/24 Wednesday JMJ (Stark Boring-Scott) Contractor continued to install 6" water main, but ran into heavy rock only 100' for today and yesterday. 09/27/24 Friday JMJ (Stark Boring-Scott) Contractor continued to install 6" water main only 2 stick pipe were laid yesterday. Contractor will install another stick pipe and a 90 degree bend on the water pipe. Contractor will installed the 6''X6" tee as-per project plan. 10/01/24 Monday JMJ (Stark Boring-Scott) Contractor installed only 60' of 6" water main because of breaking heavy rock. 10/02/24 Tuesday JMJ (Stark Boring-Scott) Contractor was able to install two sticks on Monday & two on Tuesday. Contractor continued to to break rock to install the 6" water main. 10/03/24 Wednesday JMJ (Stark Boring-Scott) Contractor installed 170' of 6" water main plus a 6"X6" tee. Contractor backfilled and used a vibration plate to compact excavation trench. Contractor cleaned up area around excavation and used plates. 10/15/24 Tuesday JMJ (Stark Boring-Scott) 2 hour Hydrostatic passed for 6" private waterline. Contractor is chlorinating 6" private waterline. 10/16/24 Wednesday JMJ (Stark Boring-Scott) Contractor plans to de-chlorinated 6" private waterline today @ 3:00PM.
Water Line - Construction Inspection Partial 10/23/2024
Misc
Informational
10/16/2024
09/06/24 Friday JMJ (Stark Boring-Scott) Contractor started yesterday began to excavate site to began installation of waterline. The contractor is planning a night shut for Monday. I will inform water of the shut on the private waterline & the fire hydrants that will effected. 09/10/24 Tuesday JMJ (Stark Boring-Scott) Contractor throttle down water @ Summit Shopping Center @ 1:30AM for a night shut to construct tie-in location. The removal of existing 90 degree bend for a 6"X6" tee 2/90 deg bends with stainless steel all-threads to establish new grade. Water line was flushed after tie-in was completed. The 6" gate was installed after the 90 degree bend on the high side. 09/11/24 Wednesday JMJ (Stark Boring-Scott) Contractor installed approximately 25' of 6" PVC water main 2/45 degree bends used all-threads on the 45 degree point down to obtain space from existing RCP storm pipe. Contractor place steel plates over trench excavation for the water line parking lot area. Backing blocks were poured. 09/12/24 Thursday JMJ (Stark Boring-Scott) Contractor installed approximately 120' of 6" PVC water main. 09/13/24 Friday JMJ (Stark Boring-Scott) Contractor installed approximately 40' of 6" PVC water main. The contractor clean up the construction site and covered excavated trench for water line. 09/16/24 Monday JMJ (Stark Boring-Scott) Contractor installed approximately 100' of 6" PVC water main. The contractor clean up the construction site and covered excavated trench for water line. 09/18/24 Wednesday JMJ (Stark Boring-Scott) Contractor installed approximately 120' of 6" PVC water main. 09/20/24 Friday JMJ (Stark Boring-Scott) Contractor continued 6" PVC water installation with a tee 6"X6" & valve the will run to Freddy's restaurant yesterday it was inspected by (BR).Today contractor cleaned parking lot area and broke through rock. Contractor preparing for weekend rain condition. 09/25/24 Wednesday JMJ (Stark Boring-Scott) Contractor continued to install 6" water main, but ran into heavy rock only 100' for today and yesterday. 09/27/24 Friday JMJ (Stark Boring-Scott) Contractor continued to install 6" water main only 2 stick pipe were laid yesterday. Contractor will install another stick pipe and a 90 degree bend on the water pipe. Contractor will installed the 6''X6" tee as-per project plan. 10/01/24 Monday JMJ (Stark Boring-Scott) Contractor installed only 60' of 6" water main because of breaking heavy rock. 10/02/24 Tuesday JMJ (Stark Boring-Scott) Contractor was able to install two sticks on Monday & two on Tuesday. Contractor continued to to break rock to install the 6" water main. 10/03/24 Wednesday JMJ (Stark Boring-Scott) Contractor installed 170' of 6" water main plus a 6"X6" tee. Contractor backfilled and used a vibration plate to compact excavation trench. Contractor cleaned up area around excavation and used plates. 10/15/24 Tuesday JMJ (Stark Boring-Scott) 2 hour Hydrostatic passed for 6" private waterline. Contractor is chlorinating 6" private waterline. 10/16/24 Wednesday JMJ (Stark Boring-Scott) Contractor plans to de-chlorinated 6" private waterline today @ 3:00PM. 10/23/24 Wednesday JMJ (Stark Boring-Scott) Both bacterial samples passed.
Erosion Control Inspection Partial 10/25/2024 10/25/2024 10/25/2024
Misc
Informational
10/25/2024
Erosion Control functioning at site.
Site Visit Partial 10/25/2024 10/25/2024 10/25/2024
Misc
Informational
08/21/2024
08/21/24 Wednesday JMJ Contractor not on site as of today. 10/25/24 Friday JMJ Contractor not on site as of today.
Water Line - Construction Inspection Partial 10/30/2024 10/30/2024 10/30/2024
Misc
Informational
10/23/2024
09/06/24 Friday JMJ (Stark Boring-Scott) Contractor started yesterday began to excavate site to began installation of waterline. The contractor is planning a night shut for Monday. I will inform water of the shut on the private waterline & the fire hydrants that will effected. 09/10/24 Tuesday JMJ (Stark Boring-Scott) Contractor throttle down water @ Summit Shopping Center @ 1:30AM for a night shut to construct tie-in location. The removal of existing 90 degree bend for a 6"X6" tee 2/90 deg bends with stainless steel all-threads to establish new grade. Water line was flushed after tie-in was completed. The 6" gate was installed after the 90 degree bend on the high side. 09/11/24 Wednesday JMJ (Stark Boring-Scott) Contractor installed approximately 25' of 6" PVC water main 2/45 degree bends used all-threads on the 45 degree point down to obtain space from existing RCP storm pipe. Contractor place steel plates over trench excavation for the water line parking lot area. Backing blocks were poured. 09/12/24 Thursday JMJ (Stark Boring-Scott) Contractor installed approximately 120' of 6" PVC water main. 09/13/24 Friday JMJ (Stark Boring-Scott) Contractor installed approximately 40' of 6" PVC water main. The contractor clean up the construction site and covered excavated trench for water line. 09/16/24 Monday JMJ (Stark Boring-Scott) Contractor installed approximately 100' of 6" PVC water main. The contractor clean up the construction site and covered excavated trench for water line. 09/18/24 Wednesday JMJ (Stark Boring-Scott) Contractor installed approximately 120' of 6" PVC water main. 09/20/24 Friday JMJ (Stark Boring-Scott) Contractor continued 6" PVC water installation with a tee 6"X6" & valve the will run to Freddy's restaurant yesterday it was inspected by (BR).Today contractor cleaned parking lot area and broke through rock. Contractor preparing for weekend rain condition. 09/25/24 Wednesday JMJ (Stark Boring-Scott) Contractor continued to install 6" water main, but ran into heavy rock only 100' for today and yesterday. 09/27/24 Friday JMJ (Stark Boring-Scott) Contractor continued to install 6" water main only 2 stick pipe were laid yesterday. Contractor will install another stick pipe and a 90 degree bend on the water pipe. Contractor will installed the 6''X6" tee as-per project plan. 10/01/24 Monday JMJ (Stark Boring-Scott) Contractor installed only 60' of 6" water main because of breaking heavy rock. 10/02/24 Tuesday JMJ (Stark Boring-Scott) Contractor was able to install two sticks on Monday & two on Tuesday. Contractor continued to to break rock to install the 6" water main. 10/03/24 Wednesday JMJ (Stark Boring-Scott) Contractor installed 170' of 6" water main plus a 6"X6" tee. Contractor backfilled and used a vibration plate to compact excavation trench. Contractor cleaned up area around excavation and used plates. 10/15/24 Tuesday JMJ (Stark Boring-Scott) 2 hour Hydrostatic passed for 6" private waterline. Contractor is chlorinating 6" private waterline. 10/16/24 Wednesday JMJ (Stark Boring-Scott) Contractor plans to de-chlorinated 6" private waterline today @ 3:00PM. 10/23/24 Wednesday JMJ (Stark Boring-Scott) Both bacterial samples passed. 10/30/24 Wednesday JMJ (Stark Boring-Scott) Contractor is doing the water tie-in to the newly installed line. Newly installed private line and the old water main will be active until the water service are all transferred.
Water Line - Construction Inspection Partial 10/31/2024 10/31/2024 10/31/2024
Misc
Informational
10/30/2024
09/06/24 Friday JMJ (Stark Boring-Scott) Contractor started yesterday began to excavate site to began installation of waterline. The contractor is planning a night shut for Monday. I will inform water of the shut on the private waterline & the fire hydrants that will effected. 09/10/24 Tuesday JMJ (Stark Boring-Scott) Contractor throttle down water @ Summit Shopping Center @ 1:30AM for a night shut to construct tie-in location. The removal of existing 90 degree bend for a 6"X6" tee 2/90 deg bends with stainless steel all-threads to establish new grade. Water line was flushed after tie-in was completed. The 6" gate was installed after the 90 degree bend on the high side. 09/11/24 Wednesday JMJ (Stark Boring-Scott) Contractor installed approximately 25' of 6" PVC water main 2/45 degree bends used all-threads on the 45 degree point down to obtain space from existing RCP storm pipe. Contractor place steel plates over trench excavation for the water line parking lot area. Backing blocks were poured. 09/12/24 Thursday JMJ (Stark Boring-Scott) Contractor installed approximately 120' of 6" PVC water main. 09/13/24 Friday JMJ (Stark Boring-Scott) Contractor installed approximately 40' of 6" PVC water main. The contractor clean up the construction site and covered excavated trench for water line. 09/16/24 Monday JMJ (Stark Boring-Scott) Contractor installed approximately 100' of 6" PVC water main. The contractor clean up the construction site and covered excavated trench for water line. 09/18/24 Wednesday JMJ (Stark Boring-Scott) Contractor installed approximately 120' of 6" PVC water main. 09/20/24 Friday JMJ (Stark Boring-Scott) Contractor continued 6" PVC water installation with a tee 6"X6" & valve the will run to Freddy's restaurant yesterday it was inspected by (BR).Today contractor cleaned parking lot area and broke through rock. Contractor preparing for weekend rain condition. 09/25/24 Wednesday JMJ (Stark Boring-Scott) Contractor continued to install 6" water main, but ran into heavy rock only 100' for today and yesterday. 09/27/24 Friday JMJ (Stark Boring-Scott) Contractor continued to install 6" water main only 2 stick pipe were laid yesterday. Contractor will install another stick pipe and a 90 degree bend on the water pipe. Contractor will installed the 6''X6" tee as-per project plan. 10/01/24 Monday JMJ (Stark Boring-Scott) Contractor installed only 60' of 6" water main because of breaking heavy rock. 10/02/24 Tuesday JMJ (Stark Boring-Scott) Contractor was able to install two sticks on Monday & two on Tuesday. Contractor continued to to break rock to install the 6" water main. 10/03/24 Wednesday JMJ (Stark Boring-Scott) Contractor installed 170' of 6" water main plus a 6"X6" tee. Contractor backfilled and used a vibration plate to compact excavation trench. Contractor cleaned up area around excavation and used plates. 10/15/24 Tuesday JMJ (Stark Boring-Scott) 2 hour Hydrostatic passed for 6" private waterline. Contractor is chlorinating 6" private waterline. 10/16/24 Wednesday JMJ (Stark Boring-Scott) Contractor plans to de-chlorinated 6" private waterline today @ 3:00PM. 10/23/24 Wednesday JMJ (Stark Boring-Scott) Both bacterial samples passed. 10/30/24 Wednesday JMJ (Stark Boring-Scott) Contractor is doing the water tie-in to the newly installed line. Newly installed private line and the old water main will be active until the water service are all transferred. 10/31/24 Thursday JMJ (Stark Boring-Scott) Contractor transferred to water services to the newly installed private water main. (Benjamin Moore Spectrum Paint, and Box Drop Mattress & Furniture).
Water Line - Construction Inspection Partial 11/4/2024 11/4/2024 11/04/2024
Misc
Informational
10/31/2024
09/06/24 Friday JMJ (Stark Boring-Scott) Contractor started yesterday began to excavate site to began installation of waterline. The contractor is planning a night shut for Monday. I will inform water of the shut on the private waterline & the fire hydrants that will effected. 09/10/24 Tuesday JMJ (Stark Boring-Scott) Contractor throttle down water @ Summit Shopping Center @ 1:30AM for a night shut to construct tie-in location. The removal of existing 90 degree bend for a 6"X6" tee 2/90 deg bends with stainless steel all-threads to establish new grade. Water line was flushed after tie-in was completed. The 6" gate was installed after the 90 degree bend on the high side. 09/11/24 Wednesday JMJ (Stark Boring-Scott) Contractor installed approximately 25' of 6" PVC water main 2/45 degree bends used all-threads on the 45 degree point down to obtain space from existing RCP storm pipe. Contractor place steel plates over trench excavation for the water line parking lot area. Backing blocks were poured. 09/12/24 Thursday JMJ (Stark Boring-Scott) Contractor installed approximately 120' of 6" PVC water main. 09/13/24 Friday JMJ (Stark Boring-Scott) Contractor installed approximately 40' of 6" PVC water main. The contractor clean up the construction site and covered excavated trench for water line. 09/16/24 Monday JMJ (Stark Boring-Scott) Contractor installed approximately 100' of 6" PVC water main. The contractor clean up the construction site and covered excavated trench for water line. 09/18/24 Wednesday JMJ (Stark Boring-Scott) Contractor installed approximately 120' of 6" PVC water main. 09/20/24 Friday JMJ (Stark Boring-Scott) Contractor continued 6" PVC water installation with a tee 6"X6" & valve the will run to Freddy's restaurant yesterday it was inspected by (BR).Today contractor cleaned parking lot area and broke through rock. Contractor preparing for weekend rain condition. 09/25/24 Wednesday JMJ (Stark Boring-Scott) Contractor continued to install 6" water main, but ran into heavy rock only 100' for today and yesterday. 09/27/24 Friday JMJ (Stark Boring-Scott) Contractor continued to install 6" water main only 2 stick pipe were laid yesterday. Contractor will install another stick pipe and a 90 degree bend on the water pipe. Contractor will installed the 6''X6" tee as-per project plan. 10/01/24 Monday JMJ (Stark Boring-Scott) Contractor installed only 60' of 6" water main because of breaking heavy rock. 10/02/24 Tuesday JMJ (Stark Boring-Scott) Contractor was able to install two sticks on Monday & two on Tuesday. Contractor continued to to break rock to install the 6" water main. 10/03/24 Wednesday JMJ (Stark Boring-Scott) Contractor installed 170' of 6" water main plus a 6"X6" tee. Contractor backfilled and used a vibration plate to compact excavation trench. Contractor cleaned up area around excavation and used plates. 10/15/24 Tuesday JMJ (Stark Boring-Scott) 2 hour Hydrostatic passed for 6" private waterline. Contractor is chlorinating 6" private waterline. 10/16/24 Wednesday JMJ (Stark Boring-Scott) Contractor plans to de-chlorinated 6" private waterline today @ 3:00PM. 10/23/24 Wednesday JMJ (Stark Boring-Scott) Both bacterial samples passed. 10/30/24 Wednesday JMJ (Stark Boring-Scott) Contractor is doing the water tie-in to the newly installed line. Newly installed private line and the old water main will be active until the water service are all transferred. 10/31/24 Thursday JMJ (Stark Boring-Scott) Contractor transferred to water services to the newly installed private water main. (Benjamin Moore Spectrum Paint, and Box Drop Mattress & Furniture). 11/01/24 Friday JMJ (Stark Boring-Scott) Only on service was transferred and another was exposed but not completed.
Water Line - Construction Inspection Partial 11/5/2024 11/5/2024 11/05/2024
Misc
Informational
11/04/2024
09/06/24 Friday JMJ (Stark Boring-Scott) Contractor started yesterday began to excavate site to began installation of waterline. The contractor is planning a night shut for Monday. I will inform water of the shut on the private waterline & the fire hydrants that will effected. 09/10/24 Tuesday JMJ (Stark Boring-Scott) Contractor throttle down water @ Summit Shopping Center @ 1:30AM for a night shut to construct tie-in location. The removal of existing 90 degree bend for a 6"X6" tee 2/90 deg bends with stainless steel all-threads to establish new grade. Water line was flushed after tie-in was completed. The 6" gate was installed after the 90 degree bend on the high side. 09/11/24 Wednesday JMJ (Stark Boring-Scott) Contractor installed approximately 25' of 6" PVC water main 2/45 degree bends used all-threads on the 45 degree point down to obtain space from existing RCP storm pipe. Contractor place steel plates over trench excavation for the water line parking lot area. Backing blocks were poured. 09/12/24 Thursday JMJ (Stark Boring-Scott) Contractor installed approximately 120' of 6" PVC water main. 09/13/24 Friday JMJ (Stark Boring-Scott) Contractor installed approximately 40' of 6" PVC water main. The contractor clean up the construction site and covered excavated trench for water line. 09/16/24 Monday JMJ (Stark Boring-Scott) Contractor installed approximately 100' of 6" PVC water main. The contractor clean up the construction site and covered excavated trench for water line. 09/18/24 Wednesday JMJ (Stark Boring-Scott) Contractor installed approximately 120' of 6" PVC water main. 09/20/24 Friday JMJ (Stark Boring-Scott) Contractor continued 6" PVC water installation with a tee 6"X6" & valve the will run to Freddy's restaurant yesterday it was inspected by (BR).Today contractor cleaned parking lot area and broke through rock. Contractor preparing for weekend rain condition. 09/25/24 Wednesday JMJ (Stark Boring-Scott) Contractor continued to install 6" water main, but ran into heavy rock only 100' for today and yesterday. 09/27/24 Friday JMJ (Stark Boring-Scott) Contractor continued to install 6" water main only 2 stick pipe were laid yesterday. Contractor will install another stick pipe and a 90 degree bend on the water pipe. Contractor will installed the 6''X6" tee as-per project plan. 10/01/24 Monday JMJ (Stark Boring-Scott) Contractor installed only 60' of 6" water main because of breaking heavy rock. 10/02/24 Tuesday JMJ (Stark Boring-Scott) Contractor was able to install two sticks on Monday & two on Tuesday. Contractor continued to to break rock to install the 6" water main. 10/03/24 Wednesday JMJ (Stark Boring-Scott) Contractor installed 170' of 6" water main plus a 6"X6" tee. Contractor backfilled and used a vibration plate to compact excavation trench. Contractor cleaned up area around excavation and used plates. 10/15/24 Tuesday JMJ (Stark Boring-Scott) 2 hour Hydrostatic passed for 6" private waterline. Contractor is chlorinating 6" private waterline. 10/16/24 Wednesday JMJ (Stark Boring-Scott) Contractor plans to de-chlorinated 6" private waterline today @ 3:00PM. 10/23/24 Wednesday JMJ (Stark Boring-Scott) Both bacterial samples passed. 10/30/24 Wednesday JMJ (Stark Boring-Scott) Contractor is doing the water tie-in to the newly installed line. Newly installed private line and the old water main will be active until the water service are all transferred. 10/31/24 Thursday JMJ (Stark Boring-Scott) Contractor transferred to water services to the newly installed private water main. (Benjamin Moore Spectrum Paint, and Box Drop Mattress & Furniture). 11/01/24 Friday JMJ (Stark Boring-Scott) Only on service was transferred and another was exposed but not completed. 11/05/24 Tuesday JMJ (Stark Boring-Scott) Contractor restarted the transferring water service from old water main to the newly installed water main. The contractor had shoring delivered to the site for excavation. The trench or depth and the rains have weaken the sides.
Water Line - Construction Inspection Partial 11/6/2024 11/6/2024 11/06/2024
Misc
Informational
11/05/2024
09/06/24 Friday JMJ (Stark Boring-Scott) Contractor started yesterday began to excavate site to began installation of waterline. The contractor is planning a night shut for Monday. I will inform water of the shut on the private waterline & the fire hydrants that will effected. 09/10/24 Tuesday JMJ (Stark Boring-Scott) Contractor throttle down water @ Summit Shopping Center @ 1:30AM for a night shut to construct tie-in location. The removal of existing 90 degree bend for a 6"X6" tee 2/90 deg bends with stainless steel all-threads to establish new grade. Water line was flushed after tie-in was completed. The 6" gate was installed after the 90 degree bend on the high side. 09/11/24 Wednesday JMJ (Stark Boring-Scott) Contractor installed approximately 25' of 6" PVC water main 2/45 degree bends used all-threads on the 45 degree point down to obtain space from existing RCP storm pipe. Contractor place steel plates over trench excavation for the water line parking lot area. Backing blocks were poured. 09/12/24 Thursday JMJ (Stark Boring-Scott) Contractor installed approximately 120' of 6" PVC water main. 09/13/24 Friday JMJ (Stark Boring-Scott) Contractor installed approximately 40' of 6" PVC water main. The contractor clean up the construction site and covered excavated trench for water line. 09/16/24 Monday JMJ (Stark Boring-Scott) Contractor installed approximately 100' of 6" PVC water main. The contractor clean up the construction site and covered excavated trench for water line. 09/18/24 Wednesday JMJ (Stark Boring-Scott) Contractor installed approximately 120' of 6" PVC water main. 09/20/24 Friday JMJ (Stark Boring-Scott) Contractor continued 6" PVC water installation with a tee 6"X6" & valve the will run to Freddy's restaurant yesterday it was inspected by (BR).Today contractor cleaned parking lot area and broke through rock. Contractor preparing for weekend rain condition. 09/25/24 Wednesday JMJ (Stark Boring-Scott) Contractor continued to install 6" water main, but ran into heavy rock only 100' for today and yesterday. 09/27/24 Friday JMJ (Stark Boring-Scott) Contractor continued to install 6" water main only 2 stick pipe were laid yesterday. Contractor will install another stick pipe and a 90 degree bend on the water pipe. Contractor will installed the 6''X6" tee as-per project plan. 10/01/24 Monday JMJ (Stark Boring-Scott) Contractor installed only 60' of 6" water main because of breaking heavy rock. 10/02/24 Tuesday JMJ (Stark Boring-Scott) Contractor was able to install two sticks on Monday & two on Tuesday. Contractor continued to to break rock to install the 6" water main. 10/03/24 Wednesday JMJ (Stark Boring-Scott) Contractor installed 170' of 6" water main plus a 6"X6" tee. Contractor backfilled and used a vibration plate to compact excavation trench. Contractor cleaned up area around excavation and used plates. 10/15/24 Tuesday JMJ (Stark Boring-Scott) 2 hour Hydrostatic passed for 6" private waterline. Contractor is chlorinating 6" private waterline. 10/16/24 Wednesday JMJ (Stark Boring-Scott) Contractor plans to de-chlorinated 6" private waterline today @ 3:00PM. 10/23/24 Wednesday JMJ (Stark Boring-Scott) Both bacterial samples passed. 10/30/24 Wednesday JMJ (Stark Boring-Scott) Contractor is doing the water tie-in to the newly installed line. Newly installed private line and the old water main will be active until the water service are all transferred. 10/31/24 Thursday JMJ (Stark Boring-Scott) Contractor transferred to water services to the newly installed private water main. (Benjamin Moore Spectrum Paint, and Box Drop Mattress & Furniture). 11/01/24 Friday JMJ (Stark Boring-Scott) Only on service was transferred and another was exposed but not completed. 11/05/24 Tuesday JMJ (Stark Boring-Scott) Contractor restarted the transferring water service from old water main to the newly installed water main. The contractor had shoring delivered to the site for excavation. The trench or depth and the rains have weaken the sides. 11/06/24 Wednesday JMJ (Stark Boring-Scott) Contractor was able to complete only one water service transfer to the new main. Contractor will continue water transfer tomorrow.
Water Line - Construction Inspection Partial 11/8/2024 11/8/2024 11/08/2024
Misc
Informational
11/06/2024
09/06/24 Friday JMJ (Stark Boring-Scott) Contractor started yesterday began to excavate site to began installation of waterline. The contractor is planning a night shut for Monday. I will inform water of the shut on the private waterline & the fire hydrants that will effected. 09/10/24 Tuesday JMJ (Stark Boring-Scott) Contractor throttle down water @ Summit Shopping Center @ 1:30AM for a night shut to construct tie-in location. The removal of existing 90 degree bend for a 6"X6" tee 2/90 deg bends with stainless steel all-threads to establish new grade. Water line was flushed after tie-in was completed. The 6" gate was installed after the 90 degree bend on the high side. 09/11/24 Wednesday JMJ (Stark Boring-Scott) Contractor installed approximately 25' of 6" PVC water main 2/45 degree bends used all-threads on the 45 degree point down to obtain space from existing RCP storm pipe. Contractor place steel plates over trench excavation for the water line parking lot area. Backing blocks were poured. 09/12/24 Thursday JMJ (Stark Boring-Scott) Contractor installed approximately 120' of 6" PVC water main. 09/13/24 Friday JMJ (Stark Boring-Scott) Contractor installed approximately 40' of 6" PVC water main. The contractor clean up the construction site and covered excavated trench for water line. 09/16/24 Monday JMJ (Stark Boring-Scott) Contractor installed approximately 100' of 6" PVC water main. The contractor clean up the construction site and covered excavated trench for water line. 09/18/24 Wednesday JMJ (Stark Boring-Scott) Contractor installed approximately 120' of 6" PVC water main. 09/20/24 Friday JMJ (Stark Boring-Scott) Contractor continued 6" PVC water installation with a tee 6"X6" & valve the will run to Freddy's restaurant yesterday it was inspected by (BR).Today contractor cleaned parking lot area and broke through rock. Contractor preparing for weekend rain condition. 09/25/24 Wednesday JMJ (Stark Boring-Scott) Contractor continued to install 6" water main, but ran into heavy rock only 100' for today and yesterday. 09/27/24 Friday JMJ (Stark Boring-Scott) Contractor continued to install 6" water main only 2 stick pipe were laid yesterday. Contractor will install another stick pipe and a 90 degree bend on the water pipe. Contractor will installed the 6''X6" tee as-per project plan. 10/01/24 Monday JMJ (Stark Boring-Scott) Contractor installed only 60' of 6" water main because of breaking heavy rock. 10/02/24 Tuesday JMJ (Stark Boring-Scott) Contractor was able to install two sticks on Monday & two on Tuesday. Contractor continued to to break rock to install the 6" water main. 10/03/24 Wednesday JMJ (Stark Boring-Scott) Contractor installed 170' of 6" water main plus a 6"X6" tee. Contractor backfilled and used a vibration plate to compact excavation trench. Contractor cleaned up area around excavation and used plates. 10/15/24 Tuesday JMJ (Stark Boring-Scott) 2 hour Hydrostatic passed for 6" private waterline. Contractor is chlorinating 6" private waterline. 10/16/24 Wednesday JMJ (Stark Boring-Scott) Contractor plans to de-chlorinated 6" private waterline today @ 3:00PM. 10/23/24 Wednesday JMJ (Stark Boring-Scott) Both bacterial samples passed. 10/30/24 Wednesday JMJ (Stark Boring-Scott) Contractor is doing the water tie-in to the newly installed line. Newly installed private line and the old water main will be active until the water service are all transferred. 10/31/24 Thursday JMJ (Stark Boring-Scott) Contractor transferred to water services to the newly installed private water main. (Benjamin Moore Spectrum Paint, and Box Drop Mattress & Furniture). 11/01/24 Friday JMJ (Stark Boring-Scott) Only on service was transferred and another was exposed but not completed. 11/05/24 Tuesday JMJ (Stark Boring-Scott) Contractor restarted the transferring water service from old water main to the newly installed water main. The contractor had shoring delivered to the site for excavation. The trench or depth and the rains have weaken the sides. 11/06/24 Wednesday JMJ (Stark Boring-Scott) Contractor was able to complete only one water service transfer to the new main. Contractor will continue water transfer tomorrow. 11/08/24 Friday JMJ (Stark Boring-Scott) Contractor continued the transfer of services to the new water main. One on Thursday and One on Friday.
Water Line - Construction Inspection Partial 11/12/2024 11/12/2024 11/12/2024
Misc
Informational
11/08/2024
09/06/24 Friday JMJ (Stark Boring-Scott) Contractor started yesterday began to excavate site to began installation of waterline. The contractor is planning a night shut for Monday. I will inform water of the shut on the private waterline & the fire hydrants that will effected. 09/10/24 Tuesday JMJ (Stark Boring-Scott) Contractor throttle down water @ Summit Shopping Center @ 1:30AM for a night shut to construct tie-in location. The removal of existing 90 degree bend for a 6"X6" tee 2/90 deg bends with stainless steel all-threads to establish new grade. Water line was flushed after tie-in was completed. The 6" gate was installed after the 90 degree bend on the high side. 09/11/24 Wednesday JMJ (Stark Boring-Scott) Contractor installed approximately 25' of 6" PVC water main 2/45 degree bends used all-threads on the 45 degree point down to obtain space from existing RCP storm pipe. Contractor place steel plates over trench excavation for the water line parking lot area. Backing blocks were poured. 09/12/24 Thursday JMJ (Stark Boring-Scott) Contractor installed approximately 120' of 6" PVC water main. 09/13/24 Friday JMJ (Stark Boring-Scott) Contractor installed approximately 40' of 6" PVC water main. The contractor clean up the construction site and covered excavated trench for water line. 09/16/24 Monday JMJ (Stark Boring-Scott) Contractor installed approximately 100' of 6" PVC water main. The contractor clean up the construction site and covered excavated trench for water line. 09/18/24 Wednesday JMJ (Stark Boring-Scott) Contractor installed approximately 120' of 6" PVC water main. 09/20/24 Friday JMJ (Stark Boring-Scott) Contractor continued 6" PVC water installation with a tee 6"X6" & valve the will run to Freddy's restaurant yesterday it was inspected by (BR).Today contractor cleaned parking lot area and broke through rock. Contractor preparing for weekend rain condition. 09/25/24 Wednesday JMJ (Stark Boring-Scott) Contractor continued to install 6" water main, but ran into heavy rock only 100' for today and yesterday. 09/27/24 Friday JMJ (Stark Boring-Scott) Contractor continued to install 6" water main only 2 stick pipe were laid yesterday. Contractor will install another stick pipe and a 90 degree bend on the water pipe. Contractor will installed the 6''X6" tee as-per project plan. 10/01/24 Monday JMJ (Stark Boring-Scott) Contractor installed only 60' of 6" water main because of breaking heavy rock. 10/02/24 Tuesday JMJ (Stark Boring-Scott) Contractor was able to install two sticks on Monday & two on Tuesday. Contractor continued to to break rock to install the 6" water main. 10/03/24 Wednesday JMJ (Stark Boring-Scott) Contractor installed 170' of 6" water main plus a 6"X6" tee. Contractor backfilled and used a vibration plate to compact excavation trench. Contractor cleaned up area around excavation and used plates. 10/15/24 Tuesday JMJ (Stark Boring-Scott) 2 hour Hydrostatic passed for 6" private waterline. Contractor is chlorinating 6" private waterline. 10/16/24 Wednesday JMJ (Stark Boring-Scott) Contractor plans to de-chlorinated 6" private waterline today @ 3:00PM. 10/23/24 Wednesday JMJ (Stark Boring-Scott) Both bacterial samples passed. 10/30/24 Wednesday JMJ (Stark Boring-Scott) Contractor is doing the water tie-in to the newly installed line. Newly installed private line and the old water main will be active until the water service are all transferred. 10/31/24 Thursday JMJ (Stark Boring-Scott) Contractor transferred to water services to the newly installed private water main. (Benjamin Moore Spectrum Paint, and Box Drop Mattress & Furniture). 11/01/24 Friday JMJ (Stark Boring-Scott) Only on service was transferred and another was exposed but not completed. 11/05/24 Tuesday JMJ (Stark Boring-Scott) Contractor restarted the transferring water service from old water main to the newly installed water main. The contractor had shoring delivered to the site for excavation. The trench or depth and the rains have weaken the sides. 11/06/24 Wednesday JMJ (Stark Boring-Scott) Contractor was able to complete only one water service transfer to the new main. Contractor will continue water transfer tomorrow. 11/08/24 Friday JMJ (Stark Boring-Scott) Contractor continued the transfer of services to the new water main. One on Thursday and One on Friday. 11/12/24 Tuesday JMJ (Stark Boring-Scott) Contractor continued the transfer of services to the new water main. One was completed yesterday service on Veterans day (which was a holiday) contractor message photo of the water service. Contractor installed 5 services today.
Water Line - Construction Inspection Partial 11/14/2024 11/14/2024 11/14/2024
Misc
Informational
11/12/2024
09/06/24 Friday JMJ (Stark Boring-Scott) Contractor started yesterday began to excavate site to began installation of waterline. The contractor is planning a night shut for Monday. I will inform water of the shut on the private waterline & the fire hydrants that will effected. 09/10/24 Tuesday JMJ (Stark Boring-Scott) Contractor throttle down water @ Summit Shopping Center @ 1:30AM for a night shut to construct tie-in location. The removal of existing 90 degree bend for a 6"X6" tee 2/90 deg bends with stainless steel all-threads to establish new grade. Water line was flushed after tie-in was completed. The 6" gate was installed after the 90 degree bend on the high side. 09/11/24 Wednesday JMJ (Stark Boring-Scott) Contractor installed approximately 25' of 6" PVC water main 2/45 degree bends used all-threads on the 45 degree point down to obtain space from existing RCP storm pipe. Contractor place steel plates over trench excavation for the water line parking lot area. Backing blocks were poured. 09/12/24 Thursday JMJ (Stark Boring-Scott) Contractor installed approximately 120' of 6" PVC water main. 09/13/24 Friday JMJ (Stark Boring-Scott) Contractor installed approximately 40' of 6" PVC water main. The contractor clean up the construction site and covered excavated trench for water line. 09/16/24 Monday JMJ (Stark Boring-Scott) Contractor installed approximately 100' of 6" PVC water main. The contractor clean up the construction site and covered excavated trench for water line. 09/18/24 Wednesday JMJ (Stark Boring-Scott) Contractor installed approximately 120' of 6" PVC water main. 09/20/24 Friday JMJ (Stark Boring-Scott) Contractor continued 6" PVC water installation with a tee 6"X6" & valve the will run to Freddy's restaurant yesterday it was inspected by (BR).Today contractor cleaned parking lot area and broke through rock. Contractor preparing for weekend rain condition. 09/25/24 Wednesday JMJ (Stark Boring-Scott) Contractor continued to install 6" water main, but ran into heavy rock only 100' for today and yesterday. 09/27/24 Friday JMJ (Stark Boring-Scott) Contractor continued to install 6" water main only 2 stick pipe were laid yesterday. Contractor will install another stick pipe and a 90 degree bend on the water pipe. Contractor will installed the 6''X6" tee as-per project plan. 10/01/24 Monday JMJ (Stark Boring-Scott) Contractor installed only 60' of 6" water main because of breaking heavy rock. 10/02/24 Tuesday JMJ (Stark Boring-Scott) Contractor was able to install two sticks on Monday & two on Tuesday. Contractor continued to to break rock to install the 6" water main. 10/03/24 Wednesday JMJ (Stark Boring-Scott) Contractor installed 170' of 6" water main plus a 6"X6" tee. Contractor backfilled and used a vibration plate to compact excavation trench. Contractor cleaned up area around excavation and used plates. 10/15/24 Tuesday JMJ (Stark Boring-Scott) 2 hour Hydrostatic passed for 6" private waterline. Contractor is chlorinating 6" private waterline. 10/16/24 Wednesday JMJ (Stark Boring-Scott) Contractor plans to de-chlorinated 6" private waterline today @ 3:00PM. 10/23/24 Wednesday JMJ (Stark Boring-Scott) Both bacterial samples passed. 10/30/24 Wednesday JMJ (Stark Boring-Scott) Contractor is doing the water tie-in to the newly installed line. Newly installed private line and the old water main will be active until the water service are all transferred. 10/31/24 Thursday JMJ (Stark Boring-Scott) Contractor transferred to water services to the newly installed private water main. (Benjamin Moore Spectrum Paint, and Box Drop Mattress & Furniture). 11/01/24 Friday JMJ (Stark Boring-Scott) Only on service was transferred and another was exposed but not completed. 11/05/24 Tuesday JMJ (Stark Boring-Scott) Contractor restarted the transferring water service from old water main to the newly installed water main. The contractor had shoring delivered to the site for excavation. The trench or depth and the rains have weaken the sides. 11/06/24 Wednesday JMJ (Stark Boring-Scott) Contractor was able to complete only one water service transfer to the new main. Contractor will continue water transfer tomorrow. 11/08/24 Friday JMJ (Stark Boring-Scott) Contractor continued the transfer of services to the new water main. One on Thursday and One on Friday. 11/12/24 Tuesday JMJ (Stark Boring-Scott) Contractor continued the transfer of services to the new water main. One was completed yesterday service on Veterans day (which was a holiday) contractor message photo of the water service. Contractor installed 5 services today. 11/14/24 Thursday JMJ (Stark Boring-Scott) Contractor continued the transfer of services to the new main. One service was completed today. The contractor did not work yesterday.
Erosion Control Inspection Partial 11/14/2024 11/14/2024 11/14/2024
Misc
Informational
10/25/2024
No work on site. 11/14/24 Thursday JMJ Contractor did general clean up of site.
Water Line - Construction Inspection Partial 11/19/2024 11/19/2024 11/19/2024
Misc
Informational
11/14/2024
09/06/24 Friday JMJ (Stark Boring-Scott) Contractor started yesterday began to excavate site to began installation of waterline. The contractor is planning a night shut for Monday. I will inform water of the shut on the private waterline & the fire hydrants that will effected. 09/10/24 Tuesday JMJ (Stark Boring-Scott) Contractor throttle down water @ Summit Shopping Center @ 1:30AM for a night shut to construct tie-in location. The removal of existing 90 degree bend for a 6"X6" tee 2/90 deg bends with stainless steel all-threads to establish new grade. Water line was flushed after tie-in was completed. The 6" gate was installed after the 90 degree bend on the high side. 09/11/24 Wednesday JMJ (Stark Boring-Scott) Contractor installed approximately 25' of 6" PVC water main 2/45 degree bends used all-threads on the 45 degree point down to obtain space from existing RCP storm pipe. Contractor place steel plates over trench excavation for the water line parking lot area. Backing blocks were poured. 09/12/24 Thursday JMJ (Stark Boring-Scott) Contractor installed approximately 120' of 6" PVC water main. 09/13/24 Friday JMJ (Stark Boring-Scott) Contractor installed approximately 40' of 6" PVC water main. The contractor clean up the construction site and covered excavated trench for water line. 09/16/24 Monday JMJ (Stark Boring-Scott) Contractor installed approximately 100' of 6" PVC water main. The contractor clean up the construction site and covered excavated trench for water line. 09/18/24 Wednesday JMJ (Stark Boring-Scott) Contractor installed approximately 120' of 6" PVC water main. 09/20/24 Friday JMJ (Stark Boring-Scott) Contractor continued 6" PVC water installation with a tee 6"X6" & valve the will run to Freddy's restaurant yesterday it was inspected by (BR).Today contractor cleaned parking lot area and broke through rock. Contractor preparing for weekend rain condition. 09/25/24 Wednesday JMJ (Stark Boring-Scott) Contractor continued to install 6" water main, but ran into heavy rock only 100' for today and yesterday. 09/27/24 Friday JMJ (Stark Boring-Scott) Contractor continued to install 6" water main only 2 stick pipe were laid yesterday. Contractor will install another stick pipe and a 90 degree bend on the water pipe. Contractor will installed the 6''X6" tee as-per project plan. 10/01/24 Monday JMJ (Stark Boring-Scott) Contractor installed only 60' of 6" water main because of breaking heavy rock. 10/02/24 Tuesday JMJ (Stark Boring-Scott) Contractor was able to install two sticks on Monday & two on Tuesday. Contractor continued to to break rock to install the 6" water main. 10/03/24 Wednesday JMJ (Stark Boring-Scott) Contractor installed 170' of 6" water main plus a 6"X6" tee. Contractor backfilled and used a vibration plate to compact excavation trench. Contractor cleaned up area around excavation and used plates. 10/15/24 Tuesday JMJ (Stark Boring-Scott) 2 hour Hydrostatic passed for 6" private waterline. Contractor is chlorinating 6" private waterline. 10/16/24 Wednesday JMJ (Stark Boring-Scott) Contractor plans to de-chlorinated 6" private waterline today @ 3:00PM. 10/23/24 Wednesday JMJ (Stark Boring-Scott) Both bacterial samples passed. 10/30/24 Wednesday JMJ (Stark Boring-Scott) Contractor is doing the water tie-in to the newly installed line. Newly installed private line and the old water main will be active until the water service are all transferred. 10/31/24 Thursday JMJ (Stark Boring-Scott) Contractor transferred to water services to the newly installed private water main. (Benjamin Moore Spectrum Paint, and Box Drop Mattress & Furniture). 11/01/24 Friday JMJ (Stark Boring-Scott) Only on service was transferred and another was exposed but not completed. 11/05/24 Tuesday JMJ (Stark Boring-Scott) Contractor restarted the transferring water service from old water main to the newly installed water main. The contractor had shoring delivered to the site for excavation. The trench or depth and the rains have weaken the sides. 11/06/24 Wednesday JMJ (Stark Boring-Scott) Contractor was able to complete only one water service transfer to the new main. Contractor will continue water transfer tomorrow. 11/08/24 Friday JMJ (Stark Boring-Scott) Contractor continued the transfer of services to the new water main. One on Thursday and One on Friday. 11/12/24 Tuesday JMJ (Stark Boring-Scott) Contractor continued the transfer of services to the new water main. One was completed yesterday service on Veterans day (which was a holiday) contractor message photo of the water service. Contractor installed 5 services today. 11/14/24 Thursday JMJ (Stark Boring-Scott) Contractor continued the transfer of services to the new main. One service was completed today. The contractor did not work yesterday. 11/19/24 Tuesday JMJ (Stark Boring-Scott) Contractor continued the transfer of services to the new main.
Water Line - Construction Inspection Partial 11/21/2024 11/21/2024 11/21/2024
Misc
Informational
11/19/2024
09/06/24 Friday JMJ (Stark Boring-Scott) Contractor started yesterday began to excavate site to began installation of waterline. The contractor is planning a night shut for Monday. I will inform water of the shut on the private waterline & the fire hydrants that will effected. 09/10/24 Tuesday JMJ (Stark Boring-Scott) Contractor throttle down water @ Summit Shopping Center @ 1:30AM for a night shut to construct tie-in location. The removal of existing 90 degree bend for a 6"X6" tee 2/90 deg bends with stainless steel all-threads to establish new grade. Water line was flushed after tie-in was completed. The 6" gate was installed after the 90 degree bend on the high side. 09/11/24 Wednesday JMJ (Stark Boring-Scott) Contractor installed approximately 25' of 6" PVC water main 2/45 degree bends used all-threads on the 45 degree point down to obtain space from existing RCP storm pipe. Contractor place steel plates over trench excavation for the water line parking lot area. Backing blocks were poured. 09/12/24 Thursday JMJ (Stark Boring-Scott) Contractor installed approximately 120' of 6" PVC water main. 09/13/24 Friday JMJ (Stark Boring-Scott) Contractor installed approximately 40' of 6" PVC water main. The contractor clean up the construction site and covered excavated trench for water line. 09/16/24 Monday JMJ (Stark Boring-Scott) Contractor installed approximately 100' of 6" PVC water main. The contractor clean up the construction site and covered excavated trench for water line. 09/18/24 Wednesday JMJ (Stark Boring-Scott) Contractor installed approximately 120' of 6" PVC water main. 09/20/24 Friday JMJ (Stark Boring-Scott) Contractor continued 6" PVC water installation with a tee 6"X6" & valve the will run to Freddy's restaurant yesterday it was inspected by (BR).Today contractor cleaned parking lot area and broke through rock. Contractor preparing for weekend rain condition. 09/25/24 Wednesday JMJ (Stark Boring-Scott) Contractor continued to install 6" water main, but ran into heavy rock only 100' for today and yesterday. 09/27/24 Friday JMJ (Stark Boring-Scott) Contractor continued to install 6" water main only 2 stick pipe were laid yesterday. Contractor will install another stick pipe and a 90 degree bend on the water pipe. Contractor will installed the 6''X6" tee as-per project plan. 10/01/24 Monday JMJ (Stark Boring-Scott) Contractor installed only 60' of 6" water main because of breaking heavy rock. 10/02/24 Tuesday JMJ (Stark Boring-Scott) Contractor was able to install two sticks on Monday & two on Tuesday. Contractor continued to to break rock to install the 6" water main. 10/03/24 Wednesday JMJ (Stark Boring-Scott) Contractor installed 170' of 6" water main plus a 6"X6" tee. Contractor backfilled and used a vibration plate to compact excavation trench. Contractor cleaned up area around excavation and used plates. 10/15/24 Tuesday JMJ (Stark Boring-Scott) 2 hour Hydrostatic passed for 6" private waterline. Contractor is chlorinating 6" private waterline. 10/16/24 Wednesday JMJ (Stark Boring-Scott) Contractor plans to de-chlorinated 6" private waterline today @ 3:00PM. 10/23/24 Wednesday JMJ (Stark Boring-Scott) Both bacterial samples passed. 10/30/24 Wednesday JMJ (Stark Boring-Scott) Contractor is doing the water tie-in to the newly installed line. Newly installed private line and the old water main will be active until the water service are all transferred. 10/31/24 Thursday JMJ (Stark Boring-Scott) Contractor transferred to water services to the newly installed private water main. (Benjamin Moore Spectrum Paint, and Box Drop Mattress & Furniture). 11/01/24 Friday JMJ (Stark Boring-Scott) Only on service was transferred and another was exposed but not completed. 11/05/24 Tuesday JMJ (Stark Boring-Scott) Contractor restarted the transferring water service from old water main to the newly installed water main. The contractor had shoring delivered to the site for excavation. The trench or depth and the rains have weaken the sides. 11/06/24 Wednesday JMJ (Stark Boring-Scott) Contractor was able to complete only one water service transfer to the new main. Contractor will continue water transfer tomorrow. 11/08/24 Friday JMJ (Stark Boring-Scott) Contractor continued the transfer of services to the new water main. One on Thursday and One on Friday. 11/12/24 Tuesday JMJ (Stark Boring-Scott) Contractor continued the transfer of services to the new water main. One was completed yesterday service on Veterans day (which was a holiday) contractor message photo of the water service. Contractor installed 5 services today. 11/14/24 Thursday JMJ (Stark Boring-Scott) Contractor continued the transfer of services to the new main. One service was completed today. The contractor did not work yesterday. 11/19/24 Tuesday JMJ (Stark Boring-Scott) Contractor continued the transfer of services to the new main. 11/21/24 Thursday JMJ (Stark Boring-Scott) Yesterday during transferring of services there was a spider tap of three different taps, which resulted in pressure still being on the abandoned copper line. Retail store owners were notified about the circumstance and contractor continued to transfer services today.
Water Line - Construction Inspection Partial 11/22/2024 11/22/2024 11/22/2024
Misc
Informational
11/21/2024
09/06/24 Friday JMJ (Stark Boring-Scott) Contractor started yesterday began to excavate site to began installation of waterline. The contractor is planning a night shut for Monday. I will inform water of the shut on the private waterline & the fire hydrants that will effected. 09/10/24 Tuesday JMJ (Stark Boring-Scott) Contractor throttle down water @ Summit Shopping Center @ 1:30AM for a night shut to construct tie-in location. The removal of existing 90 degree bend for a 6"X6" tee 2/90 deg bends with stainless steel all-threads to establish new grade. Water line was flushed after tie-in was completed. The 6" gate was installed after the 90 degree bend on the high side. 09/11/24 Wednesday JMJ (Stark Boring-Scott) Contractor installed approximately 25' of 6" PVC water main 2/45 degree bends used all-threads on the 45 degree point down to obtain space from existing RCP storm pipe. Contractor place steel plates over trench excavation for the water line parking lot area. Backing blocks were poured. 09/12/24 Thursday JMJ (Stark Boring-Scott) Contractor installed approximately 120' of 6" PVC water main. 09/13/24 Friday JMJ (Stark Boring-Scott) Contractor installed approximately 40' of 6" PVC water main. The contractor clean up the construction site and covered excavated trench for water line. 09/16/24 Monday JMJ (Stark Boring-Scott) Contractor installed approximately 100' of 6" PVC water main. The contractor clean up the construction site and covered excavated trench for water line. 09/18/24 Wednesday JMJ (Stark Boring-Scott) Contractor installed approximately 120' of 6" PVC water main. 09/20/24 Friday JMJ (Stark Boring-Scott) Contractor continued 6" PVC water installation with a tee 6"X6" & valve the will run to Freddy's restaurant yesterday it was inspected by (BR).Today contractor cleaned parking lot area and broke through rock. Contractor preparing for weekend rain condition. 09/25/24 Wednesday JMJ (Stark Boring-Scott) Contractor continued to install 6" water main, but ran into heavy rock only 100' for today and yesterday. 09/27/24 Friday JMJ (Stark Boring-Scott) Contractor continued to install 6" water main only 2 stick pipe were laid yesterday. Contractor will install another stick pipe and a 90 degree bend on the water pipe. Contractor will installed the 6''X6" tee as-per project plan. 10/01/24 Monday JMJ (Stark Boring-Scott) Contractor installed only 60' of 6" water main because of breaking heavy rock. 10/02/24 Tuesday JMJ (Stark Boring-Scott) Contractor was able to install two sticks on Monday & two on Tuesday. Contractor continued to to break rock to install the 6" water main. 10/03/24 Wednesday JMJ (Stark Boring-Scott) Contractor installed 170' of 6" water main plus a 6"X6" tee. Contractor backfilled and used a vibration plate to compact excavation trench. Contractor cleaned up area around excavation and used plates. 10/15/24 Tuesday JMJ (Stark Boring-Scott) 2 hour Hydrostatic passed for 6" private waterline. Contractor is chlorinating 6" private waterline. 10/16/24 Wednesday JMJ (Stark Boring-Scott) Contractor plans to de-chlorinated 6" private waterline today @ 3:00PM. 10/23/24 Wednesday JMJ (Stark Boring-Scott) Both bacterial samples passed. 10/30/24 Wednesday JMJ (Stark Boring-Scott) Contractor is doing the water tie-in to the newly installed line. Newly installed private line and the old water main will be active until the water service are all transferred. 10/31/24 Thursday JMJ (Stark Boring-Scott) Contractor transferred to water services to the newly installed private water main. (Benjamin Moore Spectrum Paint, and Box Drop Mattress & Furniture). 11/01/24 Friday JMJ (Stark Boring-Scott) Only on service was transferred and another was exposed but not completed. 11/05/24 Tuesday JMJ (Stark Boring-Scott) Contractor restarted the transferring water service from old water main to the newly installed water main. The contractor had shoring delivered to the site for excavation. The trench or depth and the rains have weaken the sides. 11/06/24 Wednesday JMJ (Stark Boring-Scott) Contractor was able to complete only one water service transfer to the new main. Contractor will continue water transfer tomorrow. 11/08/24 Friday JMJ (Stark Boring-Scott) Contractor continued the transfer of services to the new water main. One on Thursday and One on Friday. 11/12/24 Tuesday JMJ (Stark Boring-Scott) Contractor continued the transfer of services to the new water main. One was completed yesterday service on Veterans day (which was a holiday) contractor message photo of the water service. Contractor installed 5 services today. 11/14/24 Thursday JMJ (Stark Boring-Scott) Contractor continued the transfer of services to the new main. One service was completed today. The contractor did not work yesterday. 11/19/24 Tuesday JMJ (Stark Boring-Scott) Contractor continued the transfer of services to the new main. 11/21/24 Thursday JMJ (Stark Boring-Scott) Yesterday during transferring of services there was a spider tap of three different taps, which resulted in pressure still being on the abandoned copper line. Retail store owners were notified about the circumstance and contractor continued to transfer services today. 11/22/24 Friday JMJ (Stark Boring-Scott) Contractor continued the transfer of 2 services to the new main.
Water Line - Construction Inspection Partial 11/26/2024
Misc
Informational
11/22/2024
09/06/24 Friday JMJ (Stark Boring-Scott) Contractor started yesterday began to excavate site to began installation of waterline. The contractor is planning a night shut for Monday. I will inform water of the shut on the private waterline & the fire hydrants that will effected. 09/10/24 Tuesday JMJ (Stark Boring-Scott) Contractor throttle down water @ Summit Shopping Center @ 1:30AM for a night shut to construct tie-in location. The removal of existing 90 degree bend for a 6"X6" tee 2/90 deg bends with stainless steel all-threads to establish new grade. Water line was flushed after tie-in was completed. The 6" gate was installed after the 90 degree bend on the high side. 09/11/24 Wednesday JMJ (Stark Boring-Scott) Contractor installed approximately 25' of 6" PVC water main 2/45 degree bends used all-threads on the 45 degree point down to obtain space from existing RCP storm pipe. Contractor place steel plates over trench excavation for the water line parking lot area. Backing blocks were poured. 09/12/24 Thursday JMJ (Stark Boring-Scott) Contractor installed approximately 120' of 6" PVC water main. 09/13/24 Friday JMJ (Stark Boring-Scott) Contractor installed approximately 40' of 6" PVC water main. The contractor clean up the construction site and covered excavated trench for water line. 09/16/24 Monday JMJ (Stark Boring-Scott) Contractor installed approximately 100' of 6" PVC water main. The contractor clean up the construction site and covered excavated trench for water line. 09/18/24 Wednesday JMJ (Stark Boring-Scott) Contractor installed approximately 120' of 6" PVC water main. 09/20/24 Friday JMJ (Stark Boring-Scott) Contractor continued 6" PVC water installation with a tee 6"X6" & valve the will run to Freddy's restaurant yesterday it was inspected by (BR).Today contractor cleaned parking lot area and broke through rock. Contractor preparing for weekend rain condition. 09/25/24 Wednesday JMJ (Stark Boring-Scott) Contractor continued to install 6" water main, but ran into heavy rock only 100' for today and yesterday. 09/27/24 Friday JMJ (Stark Boring-Scott) Contractor continued to install 6" water main only 2 stick pipe were laid yesterday. Contractor will install another stick pipe and a 90 degree bend on the water pipe. Contractor will installed the 6''X6" tee as-per project plan. 10/01/24 Monday JMJ (Stark Boring-Scott) Contractor installed only 60' of 6" water main because of breaking heavy rock. 10/02/24 Tuesday JMJ (Stark Boring-Scott) Contractor was able to install two sticks on Monday & two on Tuesday. Contractor continued to to break rock to install the 6" water main. 10/03/24 Wednesday JMJ (Stark Boring-Scott) Contractor installed 170' of 6" water main plus a 6"X6" tee. Contractor backfilled and used a vibration plate to compact excavation trench. Contractor cleaned up area around excavation and used plates. 10/15/24 Tuesday JMJ (Stark Boring-Scott) 2 hour Hydrostatic passed for 6" private waterline. Contractor is chlorinating 6" private waterline. 10/16/24 Wednesday JMJ (Stark Boring-Scott) Contractor plans to de-chlorinated 6" private waterline today @ 3:00PM. 10/23/24 Wednesday JMJ (Stark Boring-Scott) Both bacterial samples passed. 10/30/24 Wednesday JMJ (Stark Boring-Scott) Contractor is doing the water tie-in to the newly installed line. Newly installed private line and the old water main will be active until the water service are all transferred. 10/31/24 Thursday JMJ (Stark Boring-Scott) Contractor transferred to water services to the newly installed private water main. (Benjamin Moore Spectrum Paint, and Box Drop Mattress & Furniture). 11/01/24 Friday JMJ (Stark Boring-Scott) Only on service was transferred and another was exposed but not completed. 11/05/24 Tuesday JMJ (Stark Boring-Scott) Contractor restarted the transferring water service from old water main to the newly installed water main. The contractor had shoring delivered to the site for excavation. The trench or depth and the rains have weaken the sides. 11/06/24 Wednesday JMJ (Stark Boring-Scott) Contractor was able to complete only one water service transfer to the new main. Contractor will continue water transfer tomorrow. 11/08/24 Friday JMJ (Stark Boring-Scott) Contractor continued the transfer of services to the new water main. One on Thursday and One on Friday. 11/12/24 Tuesday JMJ (Stark Boring-Scott) Contractor continued the transfer of services to the new water main. One was completed yesterday service on Veterans day (which was a holiday) contractor message photo of the water service. Contractor installed 5 services today. 11/14/24 Thursday JMJ (Stark Boring-Scott) Contractor continued the transfer of services to the new main. One service was completed today. The contractor did not work yesterday. 11/19/24 Tuesday JMJ (Stark Boring-Scott) Contractor continued the transfer of services to the new main. 11/21/24 Thursday JMJ (Stark Boring-Scott) Yesterday during transferring of services there was a spider tap of three different taps, which resulted in pressure still being on the abandoned copper line. Retail store owners were notified about the circumstance and contractor continued to transfer services today. 11/22/24 Friday JMJ (Stark Boring-Scott) Contractor continued the transfer of 2 services to the new main. 11/25/24 Monday JMJ (Stark Boring-Scott) Contractor completed the transfer of all businesses in the shopping center. Contractor will abandon old main and permanently tie-in newly installed private water main 1:00 am 11/26/24 Tuesday JMJ (Stark Boring-Scott) Contractor was able to complete tie-in of new water main. Contractor is backfilling trenches and cleaning site.
Site Visit Partial 12/3/2024 12/3/2024 12/03/2024
Misc
Informational
10/25/2024
08/21/24 Wednesday JMJ Contractor not on site as of today. 10/25/24 Friday JMJ Contractor not on site as of today. 12/03/24 Tuesday Contractor on site cutting back and squaring cuts for concrete pour.
Pavement-Surface Partial 12/18/2024 12/18/2024 12/18/2024
Misc
Informational
12/18/2024
12/18/24 Wednesday (Stark Boring) Contractor paved parking and pavement-surface.
Water Line - Construction Inspection Passed 01/10/2025
Misc
Informational
11/26/2024
09/06/24 Friday JMJ (Stark Boring-Scott) Contractor started yesterday began to excavate site to began installation of waterline. The contractor is planning a night shut for Monday. I will inform water of the shut on the private waterline & the fire hydrants that will effected. 09/10/24 Tuesday JMJ (Stark Boring-Scott) Contractor throttle down water @ Summit Shopping Center @ 1:30AM for a night shut to construct tie-in location. The removal of existing 90 degree bend for a 6"X6" tee 2/90 deg bends with stainless steel all-threads to establish new grade. Water line was flushed after tie-in was completed. The 6" gate was installed after the 90 degree bend on the high side. 09/11/24 Wednesday JMJ (Stark Boring-Scott) Contractor installed approximately 25' of 6" PVC water main 2/45 degree bends used all-threads on the 45 degree point down to obtain space from existing RCP storm pipe. Contractor place steel plates over trench excavation for the water line parking lot area. Backing blocks were poured. 09/12/24 Thursday JMJ (Stark Boring-Scott) Contractor installed approximately 120' of 6" PVC water main. 09/13/24 Friday JMJ (Stark Boring-Scott) Contractor installed approximately 40' of 6" PVC water main. The contractor clean up the construction site and covered excavated trench for water line. 09/16/24 Monday JMJ (Stark Boring-Scott) Contractor installed approximately 100' of 6" PVC water main. The contractor clean up the construction site and covered excavated trench for water line. 09/18/24 Wednesday JMJ (Stark Boring-Scott) Contractor installed approximately 120' of 6" PVC water main. 09/20/24 Friday JMJ (Stark Boring-Scott) Contractor continued 6" PVC water installation with a tee 6"X6" & valve the will run to Freddy's restaurant yesterday it was inspected by (BR).Today contractor cleaned parking lot area and broke through rock. Contractor preparing for weekend rain condition. 09/25/24 Wednesday JMJ (Stark Boring-Scott) Contractor continued to install 6" water main, but ran into heavy rock only 100' for today and yesterday. 09/27/24 Friday JMJ (Stark Boring-Scott) Contractor continued to install 6" water main only 2 stick pipe were laid yesterday. Contractor will install another stick pipe and a 90 degree bend on the water pipe. Contractor will installed the 6''X6" tee as-per project plan. 10/01/24 Monday JMJ (Stark Boring-Scott) Contractor installed only 60' of 6" water main because of breaking heavy rock. 10/02/24 Tuesday JMJ (Stark Boring-Scott) Contractor was able to install two sticks on Monday & two on Tuesday. Contractor continued to to break rock to install the 6" water main. 10/03/24 Wednesday JMJ (Stark Boring-Scott) Contractor installed 170' of 6" water main plus a 6"X6" tee. Contractor backfilled and used a vibration plate to compact excavation trench. Contractor cleaned up area around excavation and used plates. 10/15/24 Tuesday JMJ (Stark Boring-Scott) 2 hour Hydrostatic passed for 6" private waterline. Contractor is chlorinating 6" private waterline. 10/16/24 Wednesday JMJ (Stark Boring-Scott) Contractor plans to de-chlorinated 6" private waterline today @ 3:00PM. 10/23/24 Wednesday JMJ (Stark Boring-Scott) Both bacterial samples passed. 10/30/24 Wednesday JMJ (Stark Boring-Scott) Contractor is doing the water tie-in to the newly installed line. Newly installed private line and the old water main will be active until the water service are all transferred. 10/31/24 Thursday JMJ (Stark Boring-Scott) Contractor transferred to water services to the newly installed private water main. (Benjamin Moore Spectrum Paint, and Box Drop Mattress & Furniture). 11/01/24 Friday JMJ (Stark Boring-Scott) Only on service was transferred and another was exposed but not completed. 11/05/24 Tuesday JMJ (Stark Boring-Scott) Contractor restarted the transferring water service from old water main to the newly installed water main. The contractor had shoring delivered to the site for excavation. The trench or depth and the rains have weaken the sides. 11/06/24 Wednesday JMJ (Stark Boring-Scott) Contractor was able to complete only one water service transfer to the new main. Contractor will continue water transfer tomorrow. 11/08/24 Friday JMJ (Stark Boring-Scott) Contractor continued the transfer of services to the new water main. One on Thursday and One on Friday. 11/12/24 Tuesday JMJ (Stark Boring-Scott) Contractor continued the transfer of services to the new water main. One was completed yesterday service on Veterans day (which was a holiday) contractor message photo of the water service. Contractor installed 5 services today. 11/14/24 Thursday JMJ (Stark Boring-Scott) Contractor continued the transfer of services to the new main. One service was completed today. The contractor did not work yesterday. 11/19/24 Tuesday JMJ (Stark Boring-Scott) Contractor continued the transfer of services to the new main. 11/21/24 Thursday JMJ (Stark Boring-Scott) Yesterday during transferring of services there was a spider tap of three different taps, which resulted in pressure still being on the abandoned copper line. Retail store owners were notified about the circumstance and contractor continued to transfer services today. 11/22/24 Friday JMJ (Stark Boring-Scott) Contractor continued the transfer of 2 services to the new main. 11/25/24 Monday JMJ (Stark Boring-Scott) Contractor completed the transfer of all businesses in the shopping center. Contractor will abandon old main and permanently tie-in newly installed private water main 1:00 am 11/26/24 Tuesday.
Water Line - Hydrostatic Test Passed 10/10/2024 01/10/2025
Water Line - Coliform Test 1 Passed 10/17/2024 01/10/2025
Water Line - Coliform Test 2 Passed 10/21/2024 01/10/2025
Final Completion - Field Engineering Final Completion 1/10/2025 01/10/2025
Documents & Images
Date Uploaded File Type Document Name
08/08/2024 Engineers Estimate Fee worksheet_City of LS_PRSITE20244163
08/08/2024 Stark Boring_bid form_7.2024 (signed)
08/08/2024 Work overview
08/09/2024 Receipt Receipt for transaction:2024-006727
08/09/2024 Letter DE-Permit
08/15/2024 Receipt Receipt for transaction:2024-006930
08/21/2024 Letter INSPECTION SUMMARY
09/06/2024 Letter INSPECTION SUMMARY
09/10/2024 Letter INSPECTION SUMMARY
09/11/2024 Letter INSPECTION SUMMARY
09/12/2024 Letter INSPECTION SUMMARY
09/13/2024 Letter INSPECTION SUMMARY
09/13/2024 Letter INSPECTION SUMMARY
09/16/2024 Letter INSPECTION SUMMARY
09/18/2024 Letter INSPECTION SUMMARY
09/20/2024 Letter INSPECTION SUMMARY
09/25/2024 Letter INSPECTION SUMMARY
09/25/2024 Letter INSPECTION SUMMARY
09/27/2024 Letter INSPECTION SUMMARY
10/01/2024 Letter INSPECTION SUMMARY
10/02/2024 Letter INSPECTION SUMMARY
10/03/2024 Letter INSPECTION SUMMARY
10/03/2024 Letter INSPECTION SUMMARY
10/15/2024 Letter INSPECTION SUMMARY
10/16/2024 Letter INSPECTION SUMMARY
10/23/2024 Letter INSPECTION SUMMARY
10/25/2024 Letter INSPECTION SUMMARY
10/25/2024 Letter INSPECTION SUMMARY
10/25/2024 Letter INSPECTION SUMMARY
10/30/2024 Letter INSPECTION SUMMARY
10/31/2024 Letter INSPECTION SUMMARY
11/04/2024 Letter INSPECTION SUMMARY
11/05/2024 Letter INSPECTION SUMMARY
11/05/2024 Letter INSPECTION SUMMARY
11/06/2024 Letter INSPECTION SUMMARY
11/08/2024 Letter INSPECTION SUMMARY
11/08/2024 Letter INSPECTION SUMMARY
11/12/2024 Letter INSPECTION SUMMARY
11/14/2024 Letter INSPECTION SUMMARY
11/14/2024 Letter INSPECTION SUMMARY
11/19/2024 Letter INSPECTION SUMMARY
11/21/2024 Letter INSPECTION SUMMARY
11/22/2024 Letter INSPECTION SUMMARY
11/26/2024 Letter INSPECTION SUMMARY
11/26/2024 Letter INSPECTION SUMMARY
12/03/2024 Letter INSPECTION SUMMARY
12/18/2024 Letter INSPECTION SUMMARY
01/10/2025 Letter INSPECTION SUMMARY
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home