Permit Application Status

PRSITE20242655


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary


PRSITE20242655
Development - Site
Final Completion
LEES SUMMIT SCHOOL DIST R 7
DEVELOPMENT COMPLETE
LEE'S SUMMIT HIGH SCHOOL - ALTERATIONS TO PARKING LOTS IN PREPARATION OF BLUE PKWY AND M 291 RELOCATION. STOP WORK ORDER generated on 07/30/2024 12:00 AM by username 'Robb Popp'. STOP WORK ORDER removed on 07/31/2024 12:00 AM by username 'Robb Popp'.
05/23/2024
06/20/2024
11/01/2024
Locations
Contacts
LEES SUMMIT SCHOOL DIST R 7, Address:600 MILLER  
WIL-PAV INC, Address:12900 E KENTUCKY RD, Phone:(816) 836-1786  
KAW VALLEY ENGINEERING INC, Address:14700 W 114TH TERR, Phone:(913) 894-5150  
DAN WARD, Address:WIL-PAV, Phone:(816) 935-3422  
DAVID WOOD, Address:KAW VALLEY ENGINEERING, INC, Phone:(913) 894-5150  
Reviews
Review Type Outcome Est. Completion Date Completed
Building Plan Review Approved 07/25/2024 07/29/2024
Joe Frogge
Licensed Contractors Approved 05/23/2024 05/23/2024
Mike Weisenborn
Fees
Paid Fees Amount Paid Owing Date Paid
9110081-Paved Surface Inspection Fee $14,722.79 $14,722.79 Paid 06/07/2024
9110068-Storm Fee $1,304.70 $1,304.70 Paid 06/07/2024
9110071-Site Grading Fee $2,376.30 $2,376.30 Paid 06/07/2024
Outstanding Fees Amount Paid Owing Date Paid
9110080-Not Ready Inspection Fee $75.00 $0.00 $75.00 Not Paid


$75.00    Add Fees to My Cart
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Erosion Control Inspection Partial 06/12/2024
Misc
Informational
06/12/2024
06/11/24 Tuesday Erosion control was installed two weeks ago. Erosion control appears to be functionable.
Pavement-Surface Partial 06/12/2024
Misc
Informational
06/12/2024
06/12/24 Wednesday JMJ (Wil-Pav) Contractor has began the milling of the parking lot on the South East portion of school on 06/10/24 Monday.
Grading/Excavation/Fill Inspection Partial 6/17/2024 6/17/2024 06/17/2024
Misc
Informational
06/17/2024
06/17/24 Monday JMJ Contractor is excavating existing curb, sidewalk, and grass median/parkway for constructure of parking lot .
Grading/Excavation/Fill Inspection Partial 6/18/2024 6/18/2024 06/18/2024
Misc
Informational
06/17/2024
06/17/24 Monday JMJ Contractor is excavating existing curb, sidewalk, and grass median/parkway for constructure of parking lot .
Misc
Informational
06/18/2024
06/18/24 Tuesday JMJ Contractor continued to excavate for new parking lot.
Erosion Control Inspection Partial 6/26/2024 6/26/2024 06/26/2024
Misc
Informational
06/12/2024
06/11/24 Tuesday Erosion control was installed two weeks ago. Erosion control appears to be functionable. 06/26/24 Wednesday JMJ Erosion control was installed two weeks ago. Erosion control appears to be functionable.
Grading/Excavation/Fill Inspection Partial 6/26/2024 6/26/2024 06/26/2024
Misc
Informational
06/18/2024
06/17/24 Monday JMJ Contractor is excavating existing curb, sidewalk, and grass median/parkway for constructure of parking lot .
Misc
Informational
06/18/2024
06/18/24 Tuesday JMJ Contractor continued to excavate for new parking lot. 06/26/24 Wednesday JMJ Contractor continued to excavate and install new base rock.
Grading/Excavation/Fill Inspection Partial 6/28/2024 6/28/2024 06/28/2024
Misc
Informational
06/26/2024
06/17/24 Monday JMJ Contractor is excavating existing curb, sidewalk, and grass median/parkway for constructure of parking lot .
Misc
Informational
06/26/2024
06/18/24 Tuesday JMJ Contractor continued to excavate for new parking lot. 06/26/24 Wednesday JMJ Contractor continued to excavate and install new base rock. 06/28/24 Friday JMJ (Wil-Pav) Contractor continued to excavate for the new parking lot.
Grading/Excavation/Fill Inspection Partial 7/2/2024 7/2/2024 07/02/2024
Misc
Informational
06/28/2024
06/17/24 Monday JMJ Contractor is excavating existing curb, sidewalk, and grass median/parkway for constructure of parking lot .
Misc
Informational
06/28/2024
06/18/24 Tuesday JMJ Contractor continued to excavate for new parking lot. 06/26/24 Wednesday JMJ Contractor continued to excavate and install new base rock. 06/28/24 Friday JMJ (Wil-Pav) Contractor continued to excavate for the new parking lot. 07/02/24 Tuesday JMJ (Wil-Pav) Contractor continued to excavation.
Pavement-Surface Partial 7/2/2024 7/2/2024 07/02/2024
Misc
Informational
06/12/2024
06/12/24 Wednesday JMJ (Wil-Pav) Contractor has began the milling of the parking lot on the South East portion of school on 06/10/24 Monday. 07/02/24 Tuesday JMJ (Wil-Pav) Contractor poured approximately 10 yards of concrete. Contractor has not poured the 10 yards of concrete yet, the time is 3:20PM. Contractor still installing clean gravel rock.
Pavement-Curb Construction Partial 7/9/2024 7/9/2024 07/09/2024
Misc
Informational
07/09/2024
07/03/24 Wednesday JMJ (Wil-Pav) Contractor poured approximately 10 yards of concrete on the South East side of newly constructed parking lot. 07/09/24 talked with GC about need to cover the honey cone that present in the curb that were poured.
Pavement-Curb Construction Partial 7/9/2024 7/9/2024 07/09/2024
Misc
Informational
07/09/2024
07/03/24 Wednesday JMJ (Wil-Pav) Contractor poured approximately 10 yards of concrete on the South East side of newly constructed parking lot. 07/09/24 talked with GC about need to cover the honey cone that present in the curb that were poured. Contractor continues to install forms for curbs for reconstructed parking lot area per project plans.
Grading/Excavation/Fill Inspection Partial 7/9/2024 7/9/2024 07/09/2024
Misc
Informational
07/02/2024
06/17/24 Monday JMJ Contractor is excavating existing curb, sidewalk, and grass median/parkway for constructure of parking lot .
Misc
Informational
07/02/2024
06/18/24 Tuesday JMJ Contractor continued to excavate for new parking lot. 06/26/24 Wednesday JMJ Contractor continued to excavate and install new base rock. 06/28/24 Friday JMJ (Wil-Pav) Contractor continued to excavate for the new parking lot. 07/02/24 Tuesday JMJ (Wil-Pav) Contractor continued to excavation. 07/09/24 Tuseday JMJ (Wil-Pav) Contractor continued to excavation & grading of newly constructed parking lot.
Pavement-Curb Construction Partial 7/10/2024 7/10/2024 07/10/2024
Misc
Informational
07/09/2024
07/03/24 Wednesday JMJ (Wil-Pav) Contractor poured approximately 10 yards of concrete on the South East side of newly constructed parking lot. 07/09/24 Tuesday JMJ (Wil-Pav) Talked with GC about need to cover the honey cone that present in the curb that were poured. Contractor continues to install forms for curbs for reconstructed parking lot area per project plans. 07/10/24 Wednesday JMJ(Wil-Pav) Yesterday contractor manage to pour approximately 20 yards of concrete curbs and islands. Contractor continued pouring curbs for reconstructed parking lot.
Pavement-Curb Construction Partial 7/11/2024 7/11/2024 07/11/2024
Misc
Informational
07/10/2024
07/03/24 Wednesday JMJ (Wil-Pav) Contractor poured approximately 10 yards of concrete on the South East side of newly constructed parking lot. 07/09/24 Tuesday JMJ (Wil-Pav) Talked with GC about need to cover the honey cone that present in the curb that were poured. Contractor continues to install forms for curbs for reconstructed parking lot area per project plans. 07/10/24 Wednesday JMJ(Wil-Pav) Yesterday contractor manage to pour approximately 20 yards of concrete curbs and islands. Contractor continued pouring curbs for reconstructed parking lot. 07/11/24 Thursday JMJ (Wil-Pav) Contractor continue to pour curbs and islands. The forms pulled from the curbs and islands poured earlier in the week.
Pavement-Curb Construction Partial 7/12/2024 7/12/2024 07/12/2024
Misc
Informational
07/11/2024
07/03/24 Wednesday JMJ (Wil-Pav) Contractor poured approximately 10 yards of concrete on the South East side of newly constructed parking lot. 07/09/24 Tuesday JMJ (Wil-Pav) Talked with GC about need to cover the honey cone that present in the curb that were poured. Contractor continues to install forms for curbs for reconstructed parking lot area per project plans. 07/10/24 Wednesday JMJ(Wil-Pav) Yesterday contractor manage to pour approximately 20 yards of concrete curbs and islands. Contractor continued pouring curbs for reconstructed parking lot. 07/11/24 Thursday JMJ (Wil-Pav) Contractor continue to pour curbs and islands. The forms pulled from the curbs and islands poured earlier in the week. 07/12/24 Friday JMJ (Wil-Pav) Contractor constructed forms for curbs on the Northeast side of the school. 20 yards of concrete will arrive around Noon to pour curbs. (Contractor also graded sidewalks and ramps for the Northeast portion of project.)
Sidewalk Inspection Partial 7/15/2024 7/15/2024 07/15/2024
Misc
Informational
07/15/2024
07/15/24 Monday JMJ Contractor began to pour sidewalks . on the Southeast side of school.
Grading/Excavation/Fill Inspection Partial 7/17/2024 7/17/2024 07/17/2024
Misc
Informational
07/09/2024
06/17/24 Monday JMJ Contractor is excavating existing curb, sidewalk, and grass median/parkway for constructure of parking lot .
Misc
Informational
07/09/2024
06/18/24 Tuesday JMJ Contractor continued to excavate for new parking lot. 06/26/24 Wednesday JMJ Contractor continued to excavate and install new base rock. 06/28/24 Friday JMJ (Wil-Pav) Contractor continued to excavate for the new parking lot. 07/02/24 Tuesday JMJ (Wil-Pav) Contractor continued to excavation. 07/09/24 Tuesday JMJ (Wil-Pav) Contractor continued to excavation & grading of newly constructed parking lot. 07/17/24 Wednesday JMJ (Wil-Pav) Contractor continued to grading & compacting parking lot. The contractor began preparing parking lot for base asphalt.
Pavement-Curb Construction Partial 7/22/2024 7/22/2024 07/22/2024
Misc
Informational
07/12/2024
07/03/24 Wednesday JMJ (Wil-Pav) Contractor poured approximately 10 yards of concrete on the South East side of newly constructed parking lot. 07/09/24 Tuesday JMJ (Wil-Pav) Talked with GC about need to cover the honey cone that present in the curb that were poured. Contractor continues to install forms for curbs for reconstructed parking lot area per project plans. 07/10/24 Wednesday JMJ(Wil-Pav) Yesterday contractor manage to pour approximately 20 yards of concrete curbs and islands. Contractor continued pouring curbs for reconstructed parking lot. 07/11/24 Thursday JMJ (Wil-Pav) Contractor continue to pour curbs and islands. The forms pulled from the curbs and islands poured earlier in the week. 07/12/24 Friday JMJ (Wil-Pav) Contractor constructed forms for curbs on the Northeast side of the school. 20 yards of concrete will arrive around Noon to pour curbs. (Contractor also graded sidewalks and ramps for the Northeast portion of project.) 07/22/24 Monday JMJ (Wil-Pav) Contractor finishing curbs connecting to newly installed storm inlets.
Sidewalk Inspection Partial 07/22/2024
Misc
Informational
07/15/2024
07/15/24 Monday JMJ Contractor began to pour sidewalks . on the Southeast side of school. 07/22/24 Monday JMJ Contractor poured newly reconstructed sidewalk on the Southeast of across from the football field.
Pavement-Aggregate Base Partial 7/23/2024 7/23/2024 07/23/2024
Misc
Informational
07/23/2024
07/23/24 Tuesday JMJ Contractor began to lay the base aggregate asphalt for the reconstructed parking lot on the East side of the school. Third partying testing CFS was onsite.
Pavement-Aggregate Base Partial 7/24/2024 7/24/2024 07/24/2024
Misc
Informational
07/24/2024
07/24/24 Wednesday JMJ (Wil-Pav) Contractor laid approximate 1,300 tons of KCMMB A3 yesterday. Today the contractor is installing the second layer of base aggregate.
Grading/Excavation/Fill Inspection Partial 7/25/2024 7/25/2024 07/25/2024
Misc
Informational
07/17/2024
06/17/24 Monday JMJ Contractor is excavating existing curb, sidewalk, and grass median/parkway for constructure of parking lot .
Misc
Informational
07/17/2024
06/18/24 Tuesday JMJ Contractor continued to excavate for new parking lot. 06/26/24 Wednesday JMJ Contractor continued to excavate and install new base rock. 06/28/24 Friday JMJ (Wil-Pav) Contractor continued to excavate for the new parking lot. 07/02/24 Tuesday JMJ (Wil-Pav) Contractor continued to excavation. 07/09/24 Tuesday JMJ (Wil-Pav) Contractor continued to excavation & grading of newly constructed parking lot. 07/17/24 Wednesday JMJ (Wil-Pav) Contractor continued to grading & compacting parking lot. The contractor began preparing parking lot for base asphalt. 07/25/24 Thursday JMJ (Wil-Pav) Contractor continued to grade for island, & curb. Work onsite consstruction.
Underground Electrical Inspection - Commercial Failed 7/26/2024 07/26/2024
Misc
Corrective Action Required
07/26/2024
NO INSPECTIONS PERFORMED ON UNDERGROUND ELECTRICAL -Expose all unapproved conduit
Piers/Caissons Inspection - Commercial Failed 7/26/2024 07/26/2024
Misc
Corrective Action Required
07/26/2024
-No underground electrical performed. Expose all unapproved conduit -Secure all rebar min 3" from bottom and sides of pier -Complete electrical
Underground Electrical Inspection - Commercial Not Ready 7/26/2024 07/26/2024
Misc
Corrective Action Required
07/26/2024
NO INSPECTIONS PERFORMED ON UNDERGROUND ELECTRICAL -Expose all unapproved conduit
Piers/Caissons Inspection - Commercial Passed 7/26/2024 07/26/2024
Misc
Resolved
07/26/2024
-Secure all rebar min 3" from bottom and sides of pier -Complete electrical
Pavement-Surface Partial 7/29/2024 7/29/2024 07/29/2024
Misc
Informational
07/02/2024
06/12/24 Wednesday JMJ (Wil-Pav) Contractor has began the milling of the parking lot on the South East portion of school on 06/10/24 Monday. 07/02/24 Tuesday JMJ (Wil-Pav) Contractor poured approximately 10 yards of concrete. 07/29/24 Monday JMJ (Wil-Pav) Contractor asphalt the top overlay for the parking lot.
Underground Electrical Inspection - Commercial Failed - Stop Work 07/30/2024
Misc
Corrective Action Required
07/26/2024
NO INSPECTIONS PERFORMED ON UNDERGROUND ELECTRICAL -Expose all unapproved conduit
Underground Electrical Inspection - Commercial Partial 07/31/2024
Misc
Corrective Action Required
07/30/2024
Conduit to (6) light poles approved per letter and photos on permit
Piers/Caissons Inspection - Commercial Partial 8/1/2024 08/01/2024
Miscellaneous Correction
Informational
07/30/2024
(8) piers and ground rods for light poles approved
Piers/Caissons Inspection - Commercial Passed 8/2/2024 08/02/2024
Miscellaneous Correction
Informational
08/01/2024
(13) piers and ground rods for light poles approved
Underground Electrical Inspection - Commercial Failed 08/02/2024
Misc
Corrective Action Required
07/31/2024
Conduit to (8) light poles approved per letter and photos on permit **PROVIDE BORING REPORT FOR REMAINING (5) PIERS AT EAST PARKING LOT -(conduit at "diamonds" witnessed to be 14"-18" depth. Min 24" depth under driving surfaces is required)
Fire Line Construction Inspection Partial 8/12/2024 8/12/2024 08/12/2024
Misc
Informational
08/12/2024
8-12-24 BR Contractor is installing fire hydrant on south east side of building next to parking lot to existing water main doing a live tap.
Grading/Excavation/Fill Inspection Passed 8/20/2024 8/20/2024 10/02/2024
Misc
Informational
07/25/2024
06/17/24 Monday JMJ Contractor is excavating existing curb, sidewalk, and grass median/parkway for constructure of parking lot .
Misc
Informational
07/25/2024
06/18/24 Tuesday JMJ Contractor continued to excavate for new parking lot. 06/26/24 Wednesday JMJ Contractor continued to excavate and install new base rock. 06/28/24 Friday JMJ (Wil-Pav) Contractor continued to excavate for the new parking lot. 07/02/24 Tuesday JMJ (Wil-Pav) Contractor continued to excavation. 07/09/24 Tuesday JMJ (Wil-Pav) Contractor continued to excavation & grading of newly constructed parking lot. 07/17/24 Wednesday JMJ (Wil-Pav) Contractor continued to grading & compacting parking lot. The contractor began preparing parking lot for base asphalt. 07/25/24 Thursday JMJ (Wil-Pav) Contractor continued to grade for island, & curb. Work onsite consstruction.
Rough Electrical Inspection - Commercial Failed 10/30/2024 10/30/2024 10/30/2024
Misc
Corrective Action Required
10/30/2024
-1 Hour call ahead was requested. Called at 9:05 am. 10:20 am no contractor on site. Opened one light pole hand hole and copper ground wire not connected. -Complete work per plan and schedule when contractor will be on site with light poles opened for inspection
Rough Electrical Inspection - Commercial Failed 10/31/2024 10/31/2024 10/31/2024
Misc
Corrective Action Required
10/30/2024
-1 Hour call ahead was requested. Called at 9:05 am. 10:20 am no contractor on site. Opened one light pole hand hole and copper ground wire not connected. -Complete work per plan and schedule when contractor will be on site with light poles opened for inspection *10/31/24 -inspection moved to tomorrow by contractor
Rough Electrical Inspection - Commercial Passed 11/1/2024 11/1/2024 11/01/2024
Misc
Resolved
11/01/2024
-1 Hour call ahead was requested. Called at 9:05 am. 10:20 am no contractor on site. Opened one light pole hand hole and copper ground wire not connected. -Complete work per plan and schedule when contractor will be on site with light poles opened for inspection *10/31/24 -inspection moved to tomorrow by contractor
Final Electrical Inspection - Commercial Passed 11/1/2024 11/1/2024 11/01/2024
Final Completion - Field Engineering Final Completion 11/01/2024
Documents & Images
Date Uploaded File Type Document Name
05/23/2024 Activity Document FEE WORKSHEET PHASE I_REV 0_PL2024096
05/29/2024 Approved Plans STAMPED PLAN SET FOR LSHS SE PARKING LOT ALTERATIONS PHASE I_REV 0_PL2024096
06/07/2024 Receipt Receipt for transaction: 2024-004526
06/12/2024 Letter INSPECTION SUMMARY
06/12/2024 Letter INSPECTION SUMMARY
06/17/2024 Letter INSPECTION SUMMARY
06/18/2024 Letter INSPECTION SUMMARY
06/20/2024 Letter DE-Permit
06/26/2024 Letter INSPECTION SUMMARY
06/26/2024 Letter INSPECTION SUMMARY
06/28/2024 Letter INSPECTION SUMMARY
07/02/2024 Letter INSPECTION SUMMARY
07/02/2024 Letter INSPECTION SUMMARY
07/02/2024 Letter INSPECTION SUMMARY
07/05/2024 Approved Plans STAMPED PLAN SET FOR LSHS SE PARKING LOT ALTERATIONS PHASE I_REV 1_PL2024096
07/09/2024 Letter INSPECTION SUMMARY
07/09/2024 Letter INSPECTION SUMMARY
07/09/2024 Letter INSPECTION SUMMARY
07/10/2024 Letter INSPECTION SUMMARY
07/11/2024 Letter INSPECTION SUMMARY
07/12/2024 Letter INSPECTION SUMMARY
07/15/2024 Letter INSPECTION SUMMARY
07/17/2024 Letter INSPECTION SUMMARY
07/22/2024 Letter INSPECTION SUMMARY
07/22/2024 Letter INSPECTION SUMMARY
07/22/2024 Letter INSPECTION SUMMARY
07/24/2024 Plans LIGHT POLE DETAIL_REV 0_PRSITE20242655
07/24/2024 Approved Plans Approved Light Pole Base detail
07/24/2024 Letter INSPECTION SUMMARY
07/24/2024 Letter INSPECTION SUMMARY
07/25/2024 Letter INSPECTION SUMMARY
07/26/2024 Letter INSPECTION SUMMARY
07/26/2024 Letter INSPECTION SUMMARY
07/29/2024 Letter INSPECTION SUMMARY
07/30/2024 Letter Stop Work Order
07/31/2024 Activity Document LSHS East Parking Lot Site Lighting Conduit Documentation from Wil-Pav
07/31/2024 Letter INSPECTION SUMMARY
08/01/2024 Letter INSPECTION SUMMARY
08/02/2024 Letter INSPECTION SUMMARY
08/02/2024 Letter INSPECTION SUMMARY
08/09/2024 Plans Lees Summit HIgh School Parking Lot Bore log
08/12/2024 Letter INSPECTION SUMMARY
10/02/2024 Letter INSPECTION SUMMARY
10/30/2024 Letter INSPECTION SUMMARY
10/31/2024 Letter INSPECTION SUMMARY
11/01/2024 Letter INSPECTION SUMMARY
11/01/2024 Letter INSPECTION SUMMARY
11/01/2024 Letter INSPECTION SUMMARY
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home