Summary


PRSITE20241662
Development - Site
Final Completion
NLV MANSION LLC
DEVELOPMENT COMPLETE
Longview Mansion Parking Lot addition - Storm, Street and Site
04/05/2024
05/28/2024
01/29/2025
Locations
Contacts
NLV MANSION LLC, Address:1125 GRAND BLVD STE 202  
Garrett Cates, Address:520 W Pennway, Phone:(816) 520-9983  
Sunflower Development Group, LLC, Address:Attn: Mark Moberly, Phone:(816) 581-3997  
Olsson Engineering, Address:1301 Burlington, Suite 100, Phone:(816) 361-1177  
Reviews
Review Type Outcome Est. Completion Date Completed
Licensed Contractors Approved 04/10/2024 04/10/2024
Scott Ready
Fees
Paid Fees Amount Paid Owing Date Paid
9110068-Storm Sewer Inspection Fee $1,094.58 $1,094.58 Paid 04/05/2024
9110081-Paved Surface Inspection Fee $3,217.25 $3,217.25 Paid 04/05/2024
9110071-Site Grading Fee $1,240.65 $1,240.65 Paid 04/05/2024
9110073-Right of Way Permit Fee $85.00 $85.00 Paid 04/05/2024
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Erosion Control Inspection Partial 6/12/2024 6/12/2024 06/13/2024
Misc
Informational
06/13/2024
6-12-24 DP. Welch was out and installed silt fence. Crew also has 3 in rock established for a construction entrance.
Grading/Excavation/Fill Inspection Partial 6/12/2024 6/12/2024 06/13/2024
Misc
Informational
06/13/2024
6-13-24 DP. Crew is on site just doing dirt work. Adding and removing dirt where needed. They have been doing a good job of cleaning up.
Grading/Excavation/Fill Inspection Partial 6/20/2024 6/20/2024 06/20/2024
Misc
Informational
06/13/2024
6-13-24 DP. Crew is on site just doing dirt work. Adding and removing dirt where needed. They have been doing a good job of cleaning up. 6-20-24 DP. Crew is onsite still adding and grading dirt. They are getting close to where they start mixing in the chemical stabilization.
Erosion Control Inspection Partial 6/25/2024 6/25/2024 06/25/2024
Misc
Informational
06/13/2024
6-12-24 DP. Welch was out and installed silt fence. Crew also has 3 in rock established for a construction entrance. 6-25-24 DP. ESC is in good working order. Contractor is doing a great job cleaning up and even communicating with the Longview Mansion so they can be cleaned up before any events.
Site Visit Partial 7/1/2024 7/1/2024 07/02/2024
Misc
Informational
07/02/2024
7-1-24 DP. No work for development.
Pavement-Stabilized Subgrade Partial 7/2/2024 7/2/2024 07/03/2024
Misc
Informational
07/03/2024
7-3-24 DP. Crew was onsite stabilizing subgrade.
Pavement-Proof Roll Partial 7/10/2024 7/10/2024 07/11/2024
Misc
Informational
07/11/2024
7-10-24 DP. Met crew on site to proof roll the entire parking lot. 20 ton certified load. passed.
Sanitary Sewer - Manhole Adjustment Partial 7/11/2024 7/11/2024 07/11/2024
Misc
Informational
07/11/2024
7-11-24 DP. Crew added 2 barrel sections to MH 35-016 and reset the cone and ring.
Erosion Control Inspection Partial 07/16/2024
Misc
Informational
06/25/2024
6-12-24 DP. Welch was out and installed silt fence. Crew also has 3 in rock established for a construction entrance. 6-25-24 DP. ESC is in good working order. Contractor is doing a great job cleaning up and even communicating with the Longview Mansion so they can be cleaned up before any events. 7-16-24 DP. ESC is in good working order.
Erosion Control Inspection Partial 7/23/2024 7/23/2024 07/23/2024
Misc
Informational
07/16/2024
6-12-24 DP. Welch was out and installed silt fence. Crew also has 3 in rock established for a construction entrance. 6-25-24 DP. ESC is in good working order. Contractor is doing a great job cleaning up and even communicating with the Longview Mansion so they can be cleaned up before any events. 7-16-24 DP. ESC is in good working order. 7-23-24 DP. ESC is in good working order.
Underground Electrical Inspection - Commercial Passed 7/24/2024 07/24/2024
Site Visit Partial 7/26/2024 7/26/2024 07/26/2024
Misc
Informational
07/02/2024
7-1-24 DP. No work for development. 7-26-24 DP. No work for FEI today. Earl with SB called and said they are planning on asphalting on Monday
Pavement-Surface Partial 7/29/2024 7/29/2024 07/29/2024
Misc
Informational
07/29/2024
7-29-24 DP. SB is onsite laying base asphalt today. They are using type A3
Pavement-Surface Partial 7/29/2024 7/29/2024 07/29/2024
Misc
Informational
07/29/2024
7-29-24 DP. SB is onsite laying base asphalt today. They are using type A3 7-29-24 DP. Superior Bowen finished laying base asphalt today. They laid 25.29 tons of KCMMB type A3 asphalt.
Pavement-Surface Partial 7/30/2024 7/30/2024 07/30/2024
Misc
Informational
07/29/2024
7-29-24 DP. SB is onsite laying base asphalt today. They are using type A3 7-29-24 DP. Superior Bowen finished laying base asphalt today. They laid 25.29 tons of KCMMB type A3 asphalt. 7-30-24 DP. Superior Bowen installed asphalt surface today. They used 18.62 tons of KCMMB type A2 asphalt
Grading/Excavation/Fill Inspection Passed 7/30/2024 7/30/2024 07/30/2024
Misc
Informational
06/20/2024
6-13-24 DP. Crew is on site just doing dirt work. Adding and removing dirt where needed. They have been doing a good job of cleaning up. 6-20-24 DP. Crew is onsite still adding and grading dirt. They are getting close to where they start mixing in the chemical stabilization. 7-30-24 DP. All grading and fill has been complete.
Pavement-Proof Roll Passed 07/30/2024
Misc
Informational
07/11/2024
7-10-24 DP. Met crew on site to proof roll the entire parking lot. 20 ton certified load. passed.
Pavement-Stabilized Subgrade Passed 07/30/2024
Misc
Informational
07/03/2024
7-3-24 DP. Crew was onsite stabilizing subgrade.
Pavement-Surface Passed 7/30/2024 7/30/2024 07/30/2024
Misc
Informational
07/30/2024
7-29-24 DP. SB is onsite laying base asphalt today. They are using type A3 7-29-24 DP. Superior Bowen finished laying base asphalt today. They laid 25.29 tons of KCMMB type A3 asphalt. 7-30-24 DP. Superior Bowen installed asphalt surface today. They used 18.62 tons of KCMMB type A2 asphalt
Sanitary Sewer - Manhole Adjustment Passed 07/30/2024
Misc
Informational
07/11/2024
7-11-24 DP. Crew added 2 barrel sections to MH 35-016 and reset the cone and ring.
Storm Sewer Construction Inspection Passed 7/17/2024 7/17/2024 07/30/2024
Misc
Informational
07/30/2024
7-17-24 DP. SB was on site and installed the BMP. they laid fabric, large rock, the 6" pipe with holes in it, covered it with large rock and backfilled. They also installed 2 clean outs.
Piers/Caissons Inspection - Commercial Passed 8/7/2024 08/07/2024
Underground Electrical Inspection - Commercial Passed 8/7/2024 08/07/2024
Water Line - Coliform Test 1 Partial 08/14/2024
Misc
Informational
08/14/2024
8-14-24 Water sample on 8-6 which failed Had them re do the water testing process and pulled samples number 1 on 8-13 which passed and pulled water samples number 2 on 8-14-24
Erosion Control Inspection Partial 8/20/2024 8/20/2024 08/20/2024
Misc
Informational
07/23/2024
6-12-24 DP. Welch was out and installed silt fence. Crew also has 3 in rock established for a construction entrance. 6-25-24 DP. ESC is in good working order. Contractor is doing a great job cleaning up and even communicating with the Longview Mansion so they can be cleaned up before any events. 7-16-24 DP. ESC is in good working order. 7-23-24 DP. ESC is in good working order. 8-20-24 DP. ESC is in good working order. Contractor has seeded and covered the areas without vegetation.
Site Visit Partial 8/20/2024 8/20/2024 08/20/2024
Misc
Informational
07/26/2024
7-1-24 DP. No work for development. 7-26-24 DP. No work for FEI today. Earl with SB called and said they are planning on asphalting on Monday 8-20-24 DP. Crew stripped the parking lot.
Site Visit Partial 9/17/2024 9/17/2024 09/17/2024
Misc
Informational
08/20/2024
7-1-24 DP. No work for development. 7-26-24 DP. No work for FEI today. Earl with SB called and said they are planning on asphalting on Monday 8-20-24 DP. Crew stripped the parking lot. 9-17-24 NS Site visited it appears that no work today.
Site Visit Partial 12/30/2024 12/30/2024 12/31/2024
Misc
Informational
09/17/2024
7-1-24 DP. No work for development. 7-26-24 DP. No work for FEI today. Earl with SB called and said they are planning on asphalting on Monday 8-20-24 DP. Crew stripped the parking lot. 9-17-24 NS Site visited it appears that no work today.\ 12-30-24 DP. No ESC issues at this time
Site Visit Partial 1/15/2025 1/15/2025 01/15/2025
Misc
Informational
12/31/2024
7-1-24 DP. No work for development. 7-26-24 DP. No work for FEI today. Earl with SB called and said they are planning on asphalting on Monday 8-20-24 DP. Crew stripped the parking lot. 9-17-24 NS Site visited it appears that no work today.\ 12-30-24 DP. No ESC issues at this time 1-15-24 DP. Everything is complete for FEI. Just waiting on the contractor to call in for a final.
Final Electrical Inspection - Commercial Passed 1/29/2025 01/29/2025
Final Completion - Building Inspections Passed 1/29/2025 01/29/2025
Site Visit Complete 1/29/2025 1/29/2025 01/29/2025
Misc
Informational
01/15/2025
7-1-24 DP. No work for development. 7-26-24 DP. No work for FEI today. Earl with SB called and said they are planning on asphalting on Monday 8-20-24 DP. Crew stripped the parking lot. 9-17-24 NS Site visited it appears that no work today.\ 12-30-24 DP. No ESC issues at this time 1-15-24 DP. Everything is complete for FEI. Just waiting on the contractor to call in for a final. 1-29-25 DP. All work complete at this location. Advised Brent with SB to remove silt fencing.
Erosion Control Inspection Passed 1/29/2025 1/29/2025 01/29/2025
Misc
Informational
08/20/2024
6-12-24 DP. Welch was out and installed silt fence. Crew also has 3 in rock established for a construction entrance. 6-25-24 DP. ESC is in good working order. Contractor is doing a great job cleaning up and even communicating with the Longview Mansion so they can be cleaned up before any events. 7-16-24 DP. ESC is in good working order. 7-23-24 DP. ESC is in good working order. 8-20-24 DP. ESC is in good working order. Contractor has seeded and covered the areas without vegetation. 1-29-25 DP. Brent with SB is ok to remove silt fencing as project is complete
Final Completion - Field Engineering Final Completion 1/29/2025 01/29/2025
Misc
Informational
01/29/2025
1-29-25 DP. Met onsite for final walk through. All items for FEI have been completed.
Documents & Images
Date Uploaded File Type Document Name
04/05/2024 Receipt Receipt for transaction:2024-002190
04/05/2024 Approved Plans Approved FDP_Longview Mansion Parking Lot Expanson_04052024
05/28/2024 Letter DE-Permit
06/13/2024 Letter INSPECTION SUMMARY
06/13/2024 Letter INSPECTION SUMMARY
06/20/2024 Letter INSPECTION SUMMARY
06/25/2024 Letter INSPECTION SUMMARY
06/26/2024 Approved Plans Approved FDP Rev_Longview Mansion Parking Lot Expansion_06262024
07/02/2024 Letter INSPECTION SUMMARY
07/03/2024 Letter INSPECTION SUMMARY
07/11/2024 Letter INSPECTION SUMMARY
07/11/2024 Letter INSPECTION SUMMARY
07/16/2024 Letter INSPECTION SUMMARY
07/23/2024 Letter INSPECTION SUMMARY
07/24/2024 Letter INSPECTION SUMMARY
07/26/2024 Letter INSPECTION SUMMARY
07/29/2024 Letter INSPECTION SUMMARY
07/29/2024 Letter INSPECTION SUMMARY
07/30/2024 Letter INSPECTION SUMMARY
07/30/2024 Letter INSPECTION SUMMARY
07/30/2024 Letter INSPECTION SUMMARY
07/30/2024 Letter INSPECTION SUMMARY
07/30/2024 Letter INSPECTION SUMMARY
07/30/2024 Letter INSPECTION SUMMARY
07/30/2024 Letter INSPECTION SUMMARY
08/07/2024 Letter INSPECTION SUMMARY
08/07/2024 Letter INSPECTION SUMMARY
08/14/2024 Letter INSPECTION SUMMARY
08/20/2024 Letter INSPECTION SUMMARY
08/20/2024 Letter INSPECTION SUMMARY
09/17/2024 Letter INSPECTION SUMMARY
10/16/2024 Approved Plans Approved Revised FDP Plan Set_PL2024031_10.16.2024_Admin
12/31/2024 Letter INSPECTION SUMMARY
01/15/2025 Letter INSPECTION SUMMARY
01/29/2025 Letter INSPECTION SUMMARY
01/29/2025 Letter INSPECTION SUMMARY
01/29/2025 Letter INSPECTION SUMMARY
03/07/2025 Photograph Longview Mansion Parking Lot - ADA parking stall signs
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home