Inspection |
Outcome |
Requested |
Scheduled |
Date Inspected |
Erosion Control Inspection
|
Partial
|
3/22/2024
|
3/22/2024
|
03/22/2024
|
|
Misc
|
Erosion Control Inspection
|
Partial
|
3/27/2024
|
3/27/2024
|
03/27/2024
|
|
Misc
|
Pavement-Curb Construction
|
Partial
|
|
|
03/29/2024
|
|
Misc
|
Pavement-Stabilized Subgrade
|
Partial
|
4/1/2024
|
4/1/2024
|
04/01/2024
|
|
Misc
|
Pavement-Curb Construction
|
Partial
|
4/4/2024
|
4/4/2024
|
04/04/2024
|
|
Misc
|
|
Misc
|
Pavement-Curb Construction
|
Partial
|
4/9/2024
|
4/9/2024
|
04/09/2024
|
|
Misc
|
Pavement-Curb Construction
|
Partial
|
4/10/2024
|
4/10/2024
|
04/10/2024
|
|
Misc
|
Pavement-Curb Construction
|
Partial
|
4/11/2024
|
4/11/2024
|
04/11/2024
|
|
Misc
|
Pavement-Proof Roll
|
Passed
|
4/11/2024
|
4/11/2024
|
04/11/2024
|
|
Misc
|
Site Visit
|
Partial
|
4/12/2024
|
4/12/2024
|
04/12/2024
|
|
Misc
|
Site Visit
|
Partial
|
4/16/2024
|
4/16/2024
|
04/16/2024
|
|
Misc
|
Pavement-Aggregate Base
|
Partial
|
4/17/2024
|
4/17/2024
|
04/17/2024
|
|
Misc
|
Erosion Control Inspection
|
Partial
|
4/18/2024
|
4/18/2024
|
04/18/2024
|
|
Misc
|
Site Visit
|
Partial
|
4/24/2024
|
4/24/2024
|
04/24/2024
|
|
Misc
|
Erosion Control Inspection
|
Partial
|
5/1/2024
|
5/1/2024
|
05/01/2024
|
|
Misc
|
Erosion Control Inspection
|
Partial
|
5/8/2024
|
5/8/2024
|
05/08/2024
|
|
Misc
|
Sanitary Sewer Construction Inspection
|
Partial
|
5/8/2024
|
5/8/2024
|
05/08/2024
|
|
Misc
|
Site Visit
|
Partial
|
5/17/2024
|
5/17/2024
|
05/17/2024
|
|
Misc
|
Water Service Inspection
|
Partial
|
5/22/2024
|
5/22/2024
|
05/22/2024
|
|
Misc
|
Site Visit
|
Partial
|
5/28/2024
|
5/28/2024
|
05/28/2024
|
|
Misc
|
Pavement-Curb Construction
|
Partial
|
6/3/2024
|
6/3/2024
|
06/03/2024
|
|
Misc
|
Pavement-Curb Construction
|
Partial
|
6/4/2024
|
6/4/2024
|
06/04/2024
|
|
Misc
|
Pavement-Surface
|
Partial
|
6/5/2024
|
6/5/2024
|
06/05/2024
|
|
Misc
|
Pavement-Surface
|
Partial
|
6/12/2024
|
6/12/2024
|
06/12/2024
|
|
Misc
|
Pavement-Surface
|
Partial
|
6/14/2024
|
6/14/2024
|
06/14/2024
|
|
Misc
|
Site Visit
|
Partial
|
6/25/2024
|
6/25/2024
|
06/25/2024
|
|
Misc
|
Erosion Control Inspection
|
Partial
|
6/26/2024
|
6/26/2024
|
06/26/2024
|
|
Misc
|
Pavement-Surface
|
Partial
|
6/26/2024
|
6/26/2024
|
06/26/2024
|
|
Misc
|
Sidewalk Inspection
|
Partial
|
6/26/2024
|
6/26/2024
|
06/26/2024
|
|
Misc
|
Sidewalk Inspection
|
Partial
|
6/27/2024
|
6/27/2024
|
06/27/2024
|
|
Misc
|
Site Visit
|
Partial
|
7/1/2024
|
7/1/2024
|
07/01/2024
|
|
Misc
|
|
Misc
|
Site Visit
|
Partial
|
7/9/2024
|
7/9/2024
|
07/09/2024
|
|
Misc
|
|
Misc
|
Sidewalk Inspection
|
Passed
|
7/12/2024
|
7/12/2024
|
07/12/2024
|
|
Misc
|
Site Visit
|
Partial
|
7/31/2024
|
7/31/2024
|
07/31/2024
|
|
Misc
|
|
Misc
|
Site Visit
|
Partial
|
8/9/2024
|
8/9/2024
|
08/09/2024
|
|
Misc
|
|
Misc
|
Site Visit
|
Partial
|
10/22/2024
|
10/22/2024
|
10/22/2024
|
|
Misc
|
|
Misc
|
Verify Final Inspection Status - New Com Development
|
Complete
|
|
|
11/20/2024
|
Final Completion - Planning
|
Passed
|
|
11/22/2024
|
11/22/2024
|
Final Completion - Building Inspections
|
Passed
|
|
11/22/2024
|
11/22/2024
|
Final Completion - Field Engineering
|
Final Completion
|
|
11/22/2024
|
11/22/2024
|
|
Misc
|