Summary
PRSITE20201921
Development - Site
Final Completion
SCHOOL DISTRICT 7 REORGANIZED
DEVELOPMENT COMPLETE
Development for a middle school
07/13/2020
08/28/2020
06/08/2021
Locations
Contacts
SCHOOL DISTRICT 7 REORGANIZED, Address:301 NE TUDOR RD  
DLR GROUP, Address:7290 W 133RD ST, Phone:(913) 897-7811  
Dana Schwartz, Address:DLR Group, Phone:(913) 897-7811  
MCCOWN GORDON CONSTRUCTION LLC, Address:850 MAIN ST, Phone:(816) 960-1111  
Reviews
Review Type Outcome Est. Completion Date Completed
Licensed Contractors Approved 08/21/2020 08/24/2020
Mike Weisenborn
Fees
Paid Fees Amount Paid Owing Date Paid
9110071-Land Disturbance Fee $1,400.00 $1,400.00 Paid 07/16/2020
9110071-Site Grading Fee $51,180.10 $51,180.10 Paid 08/24/2020
$52,580.10
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Erosion Control Inspection Partial 08/28/2020
Misc
Informational
08/28/2020
On Thursday, 8-27-2020. The contractor installed silt and erosion fencing on project and began mass grading for the LSR7 Middle School.
Misc
Informational
08/28/2020
On Thursday, 8-27-2020. The contractor installed silt and erosion fencing on project and began mass grading for the LSR7 Middle School.
Misc
Informational
08/28/2020
On Thursday, 8-27-2020. The contractor installed silt and erosion fencing on project and began mass grading for the LSR7 Middle School.
Misc
Informational
08/28/2020
On Friday 8-28-2020. The contractor continued mass grading on project. Contractor is moving equipment and project office to mobilize for start of project.
Misc
Informational
09/01/2020
On Tuesday 9-01-2020. The contractor removed curb at the project site entrance located at the intersection of Bailey & Country Ln. Contractor placing rock entrance for project.
Storm - Pipe Partial 03/26/2021
Miscellaneous Correction
Corrective Action Required
03/26/2021
Installed approximately 200 feet of storm pipe.
Documents & Images
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home