PRRES20240569
Building Permit - Residential
Certificate of Occupancy
NEW SINGLE FAMILY
NEW HOUSE. FINISHED/UNFINISHED BASEMENT. WALK OUT BASEMENT. COVERED DECK. ENGINEERED FLOOR SYSTEM - DEFERRED.
02/09/2024
02/19/2024
08/12/2024
12/05/2024
Locations
Contacts
JFE CONSTRUCTION INC, Address:1314 SW MARKET ST, Phone:(816) 470-0074  
Angie Mendenhall, Address:1314 SW Market Street  
MIKE BRYANT HEATING & COOLING , Address:1711 E 123RD , Phone:(913) 441-7807  
ARROW CIRCLE ELECTRIC, Address:1224 SE CENTURY DR, Phone:(816) 373-4888  
TRI-COUNTY PLUMBING LLC, Address:PO BOX 234, Phone:(816) 720-3222  
JORDAN@JFECONSTRUCTION.COM  
Reviews

There are no reviews for this permit application.

Fees
Paid Fees Amount Paid Owing Date Paid
8331401-Water Tap Fee $3,760.00 $3,760.00 Paid 02/19/2024
8350015-Water Meter Fee $680.46 $680.46 Paid 02/19/2024
8331507-Sanitary Sewer Development Fee $2,159.00 $2,159.00 Paid 02/19/2024
9110073-Right of Way Permit Fee $85.00 $85.00 Paid 02/19/2024
7232302-Residential License Tax Fee $1,022.72 $1,022.72 Paid 02/19/2024
9110078-Valuation Fee New Single Family $1,671.27 $1,671.27 Paid 02/19/2024
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Footing Inspection - Residential Passed 3/25/2024 03/25/2024
Sewer Service Inspection - R Passed 4/5/2024 04/05/2024
Water Service Inspection - R Partial 4/5/2024 04/05/2024
Water Service Inspection - R Passed 4/8/2024 4/8/2024 04/08/2024
Underslab Plumbing Inspection - Residential Passed 4/10/2024 4/10/2024 04/10/2024
Underslab Electrical Inspection - Residential Passed 4/10/2024 4/10/2024 04/10/2024
All Rough Inspection - Residential Partial 5/7/2024 5/7/2024 05/07/2024
Misc
Informational
05/07/2024
- Portal frame OK - Dining Room CSPF OK
Erosion Control Inspection Residential Partial 7/19/2024 07/19/2024
Misc
Informational
07/19/2024
Erosion control was in compliance at the time of the inspection
Electrical Service Inspection Passed 7/19/2024 7/19/2024 07/19/2024
Gas Service Inspection - Residential Failed 7/19/2024 7/19/2024 07/19/2024
Misc
Corrective Action Required
07/19/2024
-No pressure at gauge
All Rough Inspection - Residential Failed 7/19/2024 7/19/2024 07/19/2024
Misc
Informational
05/07/2024
- Portal frame OK - Dining Room CSPF OK
Misc
Corrective Action Required
07/19/2024
-Missing fire blocking at the top of the chase in the master bedroom closet
Gas Service Inspection - Residential Passed 7/24/2024 7/24/2024 07/24/2024
Misc
Resolved
07/24/2024
-No pressure at gauge
All Rough Inspection - Residential Failed 7/24/2024 7/24/2024 07/24/2024
Misc
Resolved
07/24/2024
- Portal frame OK - Dining Room CSPF OK
Misc
Resolved
07/24/2024
-Missing fire blocking at the top of the chase in the master bedroom closet
Misc
Corrective Action Required
07/24/2024
Missing double Lvl above living room. Okay to insulate
Erosion Control Inspection Residential Partial 7/29/2024 7/29/2024 07/29/2024
Misc
Informational
07/19/2024
Erosion control was in compliance at the time of the inspection
All Rough Inspection - Residential Passed 7/29/2024 7/29/2024 07/29/2024
Misc
Resolved
07/29/2024
Missing double Lvl above living room. Okay to insulate
Driveway Inspection Partial 8/23/2024 8/23/2024 08/23/2024
Misc
Informational
08/23/2024
8-23-24 DW was formed, aggregate compacted, need to keep cross slopes throughout driveway approach. Approved to pour.
Sidewalk Inspection Partial 8/23/2024 8/23/2024 08/23/2024
Misc
Informational
08/23/2024
8-23-24 DP. SW was formed, aggregate was compacted and cross slopes were in compliance but conditions can change. Approved to pour.
Driveway Inspection Partial 8/30/2024 8/30/2024 08/26/2024
Misc
Informational
08/23/2024
8-23-24 DW was formed, aggregate compacted, need to keep cross slopes throughout driveway approach. Approved to pour. 8-26-24 Dustin A, DW was not poured if not poured before next rain event it will need another pre pour inspection
Sidewalk Inspection Partial 8/30/2024 8/30/2024 08/26/2024
Misc
Informational
08/23/2024
8-23-24 DP. SW was formed, aggregate was compacted and cross slopes were in compliance but conditions can change. Approved to pour. 8-26-24 Dustin A, Part of Sw was poured, forms still on section poured.
Driveway Inspection Partial 8/28/2024 8/28/2024 08/28/2024
Misc
Informational
08/26/2024
8-23-24 DW was formed, aggregate compacted, need to keep cross slopes throughout driveway approach. Approved to pour. 8-26-24 Dustin A, DW was not poured if not poured before next rain event it will need another pre pour inspection 8-28-24. DW is approved to be poured.
Sidewalk Inspection Partial 8/28/2024 8/28/2024 08/28/2024
Misc
Informational
08/26/2024
8-23-24 DP. SW was formed, aggregate was compacted and cross slopes were in compliance but conditions can change. Approved to pour. 8-26-24 Dustin A, Part of Sw was poured, forms still on section poured. 8-28-24 DP. SW is approved to be poured. I had the add 2 dowels in the north section since its only a single panel that needs to be poured. I also didn't check cross slopes of SW that is already poured, can do that at time of final.
Driveway Inspection Passed 9/4/2024 9/4/2024 09/04/2024
Misc
Informational
08/28/2024
8-23-24 DW was formed, aggregate compacted, need to keep cross slopes throughout driveway approach. Approved to pour. 8-26-24 Dustin A, DW was not poured if not poured before next rain event it will need another pre pour inspection 8-28-24. DW is approved to be poured. 9-3-2024 Dustin A, DW is poured to city specs and slopes are in compliance. Passed
Sidewalk Inspection Passed 9/4/2024 9/4/2024 09/04/2024
Misc
Informational
08/28/2024
8-23-24 DP. SW was formed, aggregate was compacted and cross slopes were in compliance but conditions can change. Approved to pour. 8-26-24 Dustin A, Part of Sw was poured, forms still on section poured. 8-28-24 DP. SW is approved to be poured. I had the add 2 dowels in the north section since its only a single panel that needs to be poured. I also didn't check cross slopes of SW that is already poured, can do that at time of final. 9-3-2024 Dustin A, SW is poured to city specs and slopes are in compliance. Passed
Plot Plan Inspection Passed 9/30/2024 09/30/2024
Occupancy Inspection - Codes Residential Failed 11/27/2024 11/27/2024 11/27/2024
Miscellaneous Correction
Corrective Action Required
11/27/2024
-Permanent address numbers are not installed -Garage to house self closing door does not fully shut and lock -Fire block all gaps in the sheet rock in garage above overhead garage doors -One deck joist hanger is missing nails Irrigation permit needs to be obtained -Sod, splash pads and sump pump extension are not installed
Occupancy Inspection - Codes Residential Failed 12/3/2024 12/3/2024 12/03/2024
Miscellaneous Correction
Corrective Action Required
11/27/2024
Irrigation permit needs to be obtained Talked to the builder, he stated he wanted. Full CofO
Occupancy Inspection - Codes Residential Full C of O 12/5/2024 12/5/2024 12/05/2024
Miscellaneous Correction
Resolved
12/05/2024
Irrigation permit needs to be obtained Talked to the builder, he stated he wanted. Full CofO
Documents & Images
Date Uploaded File Type Document Name
02/09/2024 HF187 - Permit App
02/09/2024 HF187 - Tax App
02/14/2024 Permit Codes Residential Plan Review
02/16/2024 Approved Plans APPROVED PLANS
02/16/2024 Plot Plan APPROVED PLOT PLAN
02/16/2024 Approved Plans APPROVED JOIST DRAWING
02/16/2024 Permit Codes Residential Plan Review
02/19/2024 Permit DS Building Permit
02/19/2024 Receipt Receipt for transaction:2024-000926
03/22/2024 Approved Plans APPROVED PIER PLAN
03/23/2024 3RD Party Insp Report Wilmoth 2755 SW Heartland Rd LSMO Hook Farms Lot 187 Footing Inspection Report 3-22-24
03/25/2024 Letter INSPECTION SUMMARY
03/25/2024 3RD Party Insp Report 2755 sw heartland rd_pier insp_2024-03-21
04/05/2024 Letter INSPECTION SUMMARY
04/05/2024 Letter INSPECTION SUMMARY
04/08/2024 Letter INSPECTION SUMMARY
04/10/2024 Letter INSPECTION SUMMARY
04/10/2024 Letter INSPECTION SUMMARY
05/07/2024 Letter INSPECTION SUMMARY
05/10/2024 2755 sw heartland rd_all slab insp_2024-04-22
07/19/2024 Letter INSPECTION SUMMARY
07/19/2024 Letter INSPECTION SUMMARY
07/19/2024 Letter INSPECTION SUMMARY
07/19/2024 Letter INSPECTION SUMMARY
07/24/2024 Letter INSPECTION SUMMARY
07/24/2024 Letter INSPECTION SUMMARY
07/29/2024 Letter INSPECTION SUMMARY
07/29/2024 Letter INSPECTION SUMMARY
08/23/2024 Letter INSPECTION SUMMARY
08/23/2024 Letter INSPECTION SUMMARY
08/26/2024 Letter INSPECTION SUMMARY
08/26/2024 Letter INSPECTION SUMMARY
08/26/2024 Letter INSPECTION SUMMARY
08/28/2024 Letter INSPECTION SUMMARY
08/28/2024 Letter INSPECTION SUMMARY
09/04/2024 Letter INSPECTION SUMMARY
09/04/2024 Letter INSPECTION SUMMARY
09/27/2024 Plot Plan APPROVED AS BUILT PLOT PLAN
09/30/2024 Letter INSPECTION SUMMARY
11/27/2024 Letter INSPECTION SUMMARY
12/03/2024 Letter INSPECTION SUMMARY
12/05/2024 Letter Codes Final Certificate of Occupancy
12/05/2024 Letter Field Certificate of Occupancy
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home